Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 8

AMG,Inc.

Factored Capital Cost Estimating Tool


This estimating tool allows the user to develop a factored Capital Construction Cost estimate based on known or e
process equipment cost, and will provide estimated values of each construction trade, craft, or discipline.
The factors used in the tool to estimate the overall cost and the trade/craft/discipline estimated costs are based on
years of historical cost profiles of various chemical, agricultural commodity, biotechnology, and mineral processing
construction projects.

The "Factored" method of cost estimation is often attributed to Lang (1948). The fixed capital cost of a project is e
as a function of the total purchase cost of the project's process & utility equipment by the Formula:

Total Construction Cost ($) = Factor x Equipment Cost ($)

Where....

Equipment Cost = the total delivered cost of all the major equipment such as pumps, heat exchangers, process and
vessels/tanks, reactors, columns, centrifuges, etc.

Factor = "Lang" factor, a process or "complexity" based value that can range from as low as 1.5 for a carbon steel b
process with limited piping, instrumentation, and structures, to as high as 4.5 for process involving exotic alloys, ex
complex piping, sterile conditions, heavy, large structures, an complicated instrumentation.

This estimating tool can be used to make a quick budgetary estimate of capital cost in the early stages of project
development, when the preliminary flow-sheets have been developed and the main items of equipment have bee
sized and priced.

This tool is based on a Lang factor of approximately 2.6, which essentially means that the equipment cost is 38% o
project cost. However, the tool incorporates a "Relative Magnitude" adjustment feature where the user can select
"Relative Magnitude" value for each trade or discipline depending on the type and complexity of the project that i
estimated.
The default value for the relative magnitude for each trade/discipline/craft is 3.0. If the value of 3.0 is input for ea
trade/discipline/craft, the estimate will be based on the historically "typical" cost profile indicated in the Estimator

If however, on a particular project there is no process sheetmetal for example, the value would be input at 0, whic
removes sheetmetal cost from the estimate. On the other hand, if the sheetmetal is significant, or more complex t
what might be considered typical, the value could be input at 6.0, which would approximately double estimated sh
cost.

This factor can be any number greater than 0.

Each of these individual relative magnitude adjustments change of the "weighting" of each trade/discipline/craft's
contribution to the total project cost, and consequently adjust the effective Lang factor.

We hope you find this tool useful.


what might be considered typical, the value could be input at 6.0, which would approximately double estimated sh
cost.

This factor can be any number greater than 0.

Each of these individual relative magnitude adjustments change of the "weighting" of each trade/discipline/craft's
contribution to the total project cost, and consequently adjust the effective Lang factor.

We hope you find this tool useful.

The following are the explanations for the column heading utilized in the Estimate Tool

The items in this column represent the Trade/Discipline/Cost Items for which the tool
TRADE/ DISCIPLINE/ values
COST ITEM

The percentages in this column are representative of typical values from AMG's indust
cost database. These values are typical of processes such as Dry Corn to Ethanol, Soyb
TYPICAL % OF TOTAL Processing, Petroleum Oil Blending & Storage, etc.

These are the estimated costs that result from the profile of a typical project as mentio
ESTIMATED COST above
BASED ON TYPICAL
PROFILE

This is the column that contains the Relative Magnitude values discussed above. Thes
can be any value 0 or greater.
RELATIVE MAGNITUDE
3=AVERAGE
0=NONE
6=DOUBLE

These are the costs resulting from the Relative Magnitude value inputs
ESTIMATED COST

This column shows resulting percentage of each Trade/Discipline/Cost Items resulting


Relative Magnitude value inputs
% OF TOTAL

This column shows the difference in cost (New Estimated Cost - Typical Estimated Cost
INCREASE ABOVE from the Relative Magnitude value inputs
TYPICAL

DIFFERENCE
This column shows the Ratio of cost (New Estimated Cost ÷ Typical Estimated Cost) res
INCREASE ABOVE from the Relative Magnitude value inputs
TYPICAL

MULTIPLE
mating Tool
st estimate based on known or estimated
ade, craft, or discipline.
line estimated costs are based on 35+
hnology, and mineral processing facility

fixed capital cost of a project is estimated


nt by the Formula:

ps, heat exchangers, process and storage

as low as 1.5 for a carbon steel based


process involving exotic alloys, extensive
entation.

st in the early stages of project


ain items of equipment have been roughly

hat the equipment cost is 38% of the total


eature where the user can select a
d complexity of the project that is being

If the value of 3.0 is input for each


profile indicated in the Estimator Tool.

value would be input at 0, which


l is significant, or more complex than
proximately double estimated sheetmetal

" of each trade/discipline/craft's


actor.
proximately double estimated sheetmetal

" of each trade/discipline/craft's


actor.

ne/Cost Items for which the tool calculates

typical values from AMG's industrial project


uch as Dry Corn to Ethanol, Soybean

ofile of a typical project as mentioned

de values discussed above. These values

tude value inputs

e/Discipline/Cost Items resulting from the

ted Cost - Typical Estimated Cost) resulting


Cost ÷ Typical Estimated Cost) resulting
ESTIMATED EQUIPMENT COST = $ 1,000,000

RELATIVE
ESTIMATED COST MAGNITUDE
TYPICAL % OF
TRADE/DISCIPLINE/COST ITEM BASED ON 3=AVERAGE
TOTAL
TYPICAL PROFILE 0=NONE
6=DOUBLE

SITE DEVELOPMENT 3.0% $ 78,947 3


BUILDINGS & EQUIPMENT SUPPORTS 15.0% $ 394,737 3
EQUIPMENT 38.0% $ 1,000,000 3
EQUIPMENT INSTALL 4.0% $ 105,263 3
PIPING 8.0% $ 210,526 3
ELECTRICAL 7.0% $ 184,211 3
INSTRUMENTATION 7.0% $ 184,211 3
PROCESS SHEETMETAL 1.5% $ 39,474 3
PAINTING 1.0% $ 26,316 3
PROCESS INSULATION 1.5% $ 39,474 3
CRANE AND EQUIPMENT RENTALS 1.0% $ 26,316 3
ENGINEERING 8.0% $ 210,526 3
CONSTRUCTION MANAGEMENT 3.0% $ 78,947 3
CONSTRUTION GENERAL CONDITIONS 2.0% $ 52,632 3
SUB TOTAL 100.0% $ 2,631,579 42
CONTINGENCY 10.0% $ 263,158
TOTAL 110.0% $ 2,894,737

LANG FACTOR 2.63

USER INPUT VALUES


INCREASE ABOVE TYPICAL
ESTIMATED COST % OF TOTAL

DIFFERENCE MULTIPLE
$ 78,947 3.0% $ - 1.0
$ 394,737 15.0% $ - 1.0
$ 1,000,000 38.0% $ - 1.0
$ 105,263 4.0% $ - 1.0
$ 210,526 8.0% $ - 1.0
$ 184,211 7.0% $ - 1.0
$ 184,211 7.0% $ - 1.0
$ 39,474 1.5% $ - 1.0
$ 26,316 1.0% $ - 1.0
$ 39,474 1.5% $ - 1.0
$ 26,316 1.0% $ - 1.0
$ 210,526 8.0% $ - 1.0
$ 78,947 3.0% $ - 1.0
$ 52,632 2.0% $ - 1.0
$ 2,631,579 100.0% $ - 1.0
$ 263,158 10.0% $ - 1.0
$ 2,894,737 110.0% $ - 1.000

2.63

You might also like