Professional Documents
Culture Documents
700 - Drainage Construction - 178
700 - Drainage Construction - 178
701.1 Description
This work shall consist of the construction of roadside and lead-away surface
drains, unlined or lined, and covered where required, to dimensions, grades and in
positions shown in the Drawings or as directed by the Engineer.
701.2 Materials
The materials used for lining the drains shall meet the requirements of the
following, unless otherwise specified.
Rock out-crops or rock boulders, encountered during excavation for the drain
shall be removed by sledging or b lastingvor by other approved means. Where such
operations are not advisable to be carried out due to site conditions, the drains may be
suitably deviated with the prior approval of the Engineer. Such deviations however,
shall not impair the smooth flow of storm water in the drain and where necessary, they
shall be suitably lined, using concrete or RR masonry as suitable.
All loose and erodible material shall be removed and such pockets shall be
filled back with suitable material approved by the Engineer and compacted as
required. Where necessary, random rubble paving with cement mortar jointing shall be
provided over such excavated and back filled areas, to be flushed with the adjoining
sections.
Where the gradients are steep, due to site conditions, suitable drop structures
and stilling basins shall be constructed as given in Drawings or as directed by the
Engineer.
179
SECOND EDITION. JlINE 2009 Institute for Construction Training and Development (ICT AD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCA/S) 700 - Drainage Construction
Rubble paving with mortar jointing, where specified, shall be carried out
using selected rubble, hammer dressed as necessary, to ensure proper embedment of
the rubble and also to obtain a reasonable smoothness of the surface finish after
jointing with 1:3 cement sand mortar is completed.
(a) Measurement
The excavation for lined and unlined drains shall be measured and as
provided in Section 302.
180
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (lCTAD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCAlS) 700 - Drainage Construction
(b) Payment
The excavation for lined and unlined drains shall be paid as provided \11
Section 301 A.
Payment shall be at the Contract unit rate for the different items of work and
shall include full compensation for all labour, materials, tools and incidentals
necessary for completion of the work.
Note
Refer Sub section 106.6 regarding sub divisions of pay items.
702.1 Description
This work shall consist of construction of subsurface drains (under-drains or
trench drains) and drain outlets using perforated pipes, non-perforated pipes and
granular filter material. The work shall be carried out in accordance with this
Specification and in conformity with the Plans or as directed by the Engineer.
•
702.2 Materials
(a) The non perforated pipes shall be of concrete, PYC or earthen, conforming to
following standards.
Concrete pipes to SLS 452·
PYC pipes to SLS 147
Earthen ware pipes to SLS 449
Geotextiles / filter fabrics to section 1710 & 2000
)81
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (lCT AO)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCA/5) 700 - Drainage Construction
(b) Granular filter material, for bedding and for surrounding the pipe under-
drains, shall be graded aggregate of maximum size 37.5mm conforming to the
requirements of Sub section 1701.1 (b) unless otherwise specified by the Engineer.
(a) Under-drains
Perforated pipes unless otherwise required, shall be laid with the perforations
down and the pipe sections shall be securely jointed by co llar s, mortar joints etc., as
specified or as directed.
Non-perforated pipes of the bell and spigot type when used shall be laid with
the bell end upgrade and the spigot ends entered into the bell ends and spot mortared
to provide for centring of the pipe but open enough to allow the infiltration of water.
After the pipe installation has been approved, granular filter material shall be
placed to a depth as specified so as to completely surround the pipe as shown in the
Drawings or required by the Engineer. If a geo-fabric filter as per the next paragraph
is used as shown in the Drawings, single sized aggregate of nominal maximum size of
37.5 mm, instead of granular filter material can be used with the approval of the
Engineer. The remaining portion of the trench shall then be filled and lightly
compacted in layers of 300mm with either granular or impervious material, as may be
specified.
Trenches for the outlets shall be excavated, to the dimensions required by the
Engineer. The outlet pipes shall be laid on approved compacted bedding in the trench
with their ends firmly jointed as required, On approval of the pipe installation the
trench shall be back filled with approved suitable material and compacted in layers in
accordance with section 305.3(b).
182
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (lCTAD)
STANDARD SPECIFICATIONS FqR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCA/S) 700 - Drainage Construction
(a) Measurement
Excavations and approved soil back fills shall be measured and paid for as
provided for in Section 302.
Perforated and outlet drain pipes shall be measured by the Iinear metre along
the centre line of the pipe for each type and size specified.
The filter fabric shall be measured in Sq.m , by taking the width required to
encircle and overlap the perforated pipe by one and a half times the circumference and
multiplying by the length of the perforated pipes.
(b) Payment
The quantities as determined above will be paid for at the Contract unit price
which shall be full compensation for furnishing and placing of all materials including
all labour, equipment, tools and incidentals necessary to complete the work
prescri bed.
Note
Refer Sub section 106.6 regarding sub divisions of pay items.
703.1 Description
This work shall consist of construction of manholes, catch-pits and inlets for
underground drainage systems in accordance with these Specifications and with the
lines and levels as shown on Drawings or as directed by the Engineer.
The inlets may be of the gully type or side entry type or a combination of
both as shown in the Drawings.
183
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (ICT AD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCAl5) 700 - Drainage Construction
703.2 Materials
All excavations and backfill required for construction shall be carried out 111
Inlets, catch-pits and manholes shall be either, pre-cast and installed or shall
be constructed in-situ.
Irisitu construction of catch pits and manholes shall be carried out using
concrete, rubble masonry, brick masonry or block masonry as specified or instructed
at site .. The Concrete used shall be of class A or B and of grade 20/20. Rubble
masonry, brick or block masonry shall conform to the requirements of Sections 1006
and 1007 respectively.
Pipe ends that are connected to the catchpits or manholes shall be flush on the
inside of the structure wall and project outside sufficiently for proper connection with
the next pipe section.
Pipe end joints of pre-cast concrete manhole sections and pipe to pipe JOInts
shall be made with 1: 1 cement mortar, mastic joint fillers or a combination of these or
any other approved material as may be specified. The completed mortar joint shall be
finished smooth and suitably cured. The mastic joint filler where used shall be applied
in accordance with the manufacturers recommendations or as required by the Engineer,
so as to form a water tight seal.
Metal frames for gully inlets shall be set 111 mortar beds or be otherwise
properly secured as indicated in Drawings.
184
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (ICT AD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCAlS) 700 - Drainage Construction
When grade adjustment of existing structures has to be carried out, the covers
gratings and frames shall be removed as necessary and the walls reconstructed as
required. The cleaned frames shall be reset at the required elevations. Frames, covers
or gratings that are unfit for further use shall be replaced with new units. Upon
completion, each structure shall be cleaned of any accumulation of silt, debris or
foreign matter of any kind and shall be kept clean of such accumulation until final
acceptance of the work.
On resurfacing Contracts the metal frames for gulley inlets shall be adjusted
to grade after the Base course is laid and prior to placing the surface course.
(a) Measurement
All work measured for payment shall be satisfactorily carried out by the
contractor and accepted by the Engineer.
(b) Payment
The accepted quantities of manholes, inlets and catchpits shall be paid for at
the Contract unit price for each complete in place and shall be full compensation for
excavation, bedding, backfill, replacing Pavement where required. Disposal of surplus
material shall, not be measured and paid for separately but shall be included in the
Contract price for each structure unless otherwise specified.
The quantities as determined above will be paid for at the Contract unit price
which shall be full compensation for furnishing and placing of all materials including
all labour, equipment, tools and incidentals necessary to complete the work
prescribed.
Note
Refer Sub section 106.6 regarding sub divisions of pay items.
185
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (lCT AD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCA/S) 700 - Drainage Construction
704.1 Description
The work shall include the furnishing and construction of joints and
connections to other pipes and catchpits and other items as required to complete the
structure in accordance with these Specifications and as shown in the Drawings or as
directed by the Engineer.
704.2 Materials
(a) Concrete pipes and fittings shall meet the requirements of SLS 452.
(c) P'VC pipes and fittings shall meet the requirements of SLS 147.
(d) Cement grout and cement mortar used for jointing of concrete and earthen I
ware pipes shall meet the requirements of the Sub sections 1703.1 & 1703.2
respectively.
(e) Plastic sealing compounds used for jointing of PYC pipes shall meet the
manufacturer's requirements.
(g) Pipe surround material may be pipe bedding material or selected fill material
as shown in Drawings or specified elsewhere in the Contract documents or as required
by the Engineer.
186
SECOND EDITION, JlJNE 2009 Institute for Construction Training and Development (lCTAD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCAlS) 700 - Drainage Construction
Pipes shall be jointed such that the inner surfaces are reasonably flush and
even and the ends are centred as required.
Joints shall be made with cement mortar (I :2), cement-grout, plastic seal ing
compound or by a combination of these types or any other approved material as may
be specified.
Pipes shall be inspected after the jointing operations are over. Any pipe found
to be out of alignment, or damaged shall be re-laid or replaced. Any other defective
work such as leaky joints and defective grouting shall be redone.
The bedding shall be completed so that the pipes bear uniformly at least upto
10 percent of the vertical diameter in concrete or at least 25 percent in granular
material.
(
The pipe surround material as per Sub section 704.2(g) shall be laid in layers
not exceeding 150mm thickness and carefully compacted. The surround shall be taken
up to a height of 300mm above the top of the pipe unless otherwise stated in the
Contract or directed by the Engineer.
187
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (lCT AD)
STANDARD SPECII'ICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCA/S) 700 - Drainage Construction
(a) Measurement
Pipes of different types and sizes shall be measured by the linear metre in
place along centre line of the pipe. The above measurement, unless otherwise
specified, will include excavation, pipe bedding, surround and the backfill upto the
original ground level. Branch connections and elbows may be included in the length
measurement for pipe, or they may be measured by the number of units installed if so
specified.
(I;) Payment
The accepted quantities of pipe shall be paid for at the Contract unit price per
Iinear metre of the type and size of pipe as specified, complete in place.
Excavation and backfill where separately measured, shall be paid for as given
in under Section 305. Pipe bedding and pipe surround where separately measured shall
be paid for at the Contract unit price per Cu.m laid and compacted.
The quantities as determined above shall be paid for at the Contract unit price
which shall be full compensation for furnishing and placing of all materials including
all labour, equipment, tools and incidentals necessary to complete the work
prescri bed.
Note
Refer Sub section 106.6 regarding sub divisions of pay items.
188
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (ICT AD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCAlS) 700 - Drainage Construction
705.1 Description
The double layer shall consist of a layer of large sized aggregate backfill
immediately behind the wall and a layer of graded small aggregate, referred to as the
filter medium placed along the sloping face of the aggregate backfill.
All work shall be carried out in accordance with the Specification and in
conformity with Drawings or as directed by the Engineer.
705.2 Materials
The filter material shall be graded aggregate of 37.5mm maximum size and
conforming approximately to grading requirement given in Sub section 1701.1 (b).
The aggregate and filter medium shall be free of organic material, clay or
other materials which will adversely effect the free drainage of water.
Prior to placement of the larger sized aggregate behind the structure, the soil
layer, on which the aggregate is placed, shall be well compacted and made impervious
either by constructing a clay puddle or by the application of a bituminous binder as
required.
The aggregate backfill shall be placed along the wall and to a stable
configuration as indicated in the Drawings to a width not less than 200 mm or as
instructed. The material shall be hand packed and compacted using a hand tamper.
189
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (lCTAD)
STANDARD SPECIFICAllOIiS f9R CONSTRUCTION AND
DS A '0 BRIDGES (SCA/S)
MAINTENANCE Of RO ..•• 700 - Drainage Construction
(a) Measurement
(b) Payment
This work measured as provided above will be paid for at the unit price per
Cu.m of drainage backfill behind earth retaining structures. The price shaJl be full
compensation for aJl labour, materials, equipment and incidentals required to furnish
and acceptably place the materials.
706.1 Description
The weep-holes may either be cast insitu or consist of pipes embedded in the
structure.
706.2 Materials
The pipes shall be made of concrete, PVC or any other suitable material
approved by the Engineer.
The moulds for cast in-situ weep-holes shall be of timber or similar material
approved by the Engineer.
When pipes are embedded in the earth retam mg structure, they shall be laid
to the slope given in Drawings or required by the Engineer and shall extend from the
rear face to the front face of the structure. They shall be protected from ingress of
materials during construction and shall be cleaned before backfilling is placed behind
the structure.
190
SECOND EDITION, JllNE 2009. Institute for Construction Training and Development (lCT AD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND·BRIIIGES (SCA/S) 700 - Drainage Construction
When the weepholes are cast in situ the moulds used shall be longitudinally
straight, and shall be laid to the required slope in their designated places as the work
proceeds. Where necessary extra cement mortar shall be placed round them and the
moulds worked, loose to facil itate easy removal when the material round them has
sufficiently hardened. If PYC pipes are used as weep-holes at least gauge 600 shall be
obtained.
(a) Measurement
(b) Payment
Payment shall be based on the Contract unit price for the item and shall
include full compensation for all materials, labour, tools, equipment and incidentals
necessary to complete the work to the Specifications.
706( I) Weepholes using pipes (state type and size) linear metre
706(2) Weepholes cast insitu (state type & size) linear metre
Note
Refer Sub section 106.6 regarding sub divisions of pay items.
707.1 Description
All work shall be carried out in accordance with these Specifications and with
Iines and levels and dimensions shown in Drawings or as directed by the Engineer.
191
SECOND EDITION. JUNE 2009 Institute for Construction Training and Development OCTAD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCA/S) 700 - Drainage Construction
707.2 Materials
Materials used for construction of head walls, wingwalls and other ancillary
items shall conform to the requirements given in Section 1106 for R.R masonry, 1107
for brick masonry and 1001 for concrete.
(a) Excavation
The Contractor shall take all necessary precautions to safeguard the stabi Iity
of all trench excavations and ensure that the safety of no person is be placed in
jeopardy by his operations or working methods.
The amount by which the excavation is to exceed the proposed level of the
invert of the culvert shall be sufficient to allow for the type and thickness of bedding
material to be placed as specified or as shown on the Drawings.
Trench when shaped and completed to receive the pipes shall be of sufficient
width, depending on pipe size and other considerations, to provide working space for
satisfactory bedding, laying and jointing of the pipe and for satisfactory compaction of
bedding material and backfill.
When completed, the bottom of the trench shall be well compacted and of
uniform density throughout its full length and width.
192
SECOND EDITION. JlINE 2009 Institute for Construction Training and Development (lCT AD)
STANDARD SPECifICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCA/S) 700 - Drainage Construction
After completing the outlet structure, the culvert units shall be laid in the
normal manner, starting from the lower end and placing successive units firmly
against each other to prevent subsequent movement. The lowest unit shall be securely
cast into the outlet structure.
The granular bedding sha\l be sand or any other selected fill and shall be
accurately shaped by a template to fit the lower part of the pipe. The selected
granular bedding shall surround the pipe upto a height of 100mm above the top of the
pipe. In appropriate circumstances the Engineer may permit compaction of sand
bedding by hydraulic compaction (flooding) subject to approval of trials carried out by
the Contractor.
. Prior to placing of the pipes the soil bed shall be lightly scarified and
moistened to facilitate uniform embedment and where necessary, fresh soil shall be
added so that the pipes when placed are firmly and uniformly bedded into the soil.
193
(
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (lCT AD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND'BRIDGES (SCA/S) 700 - Drainage Construction
707.4 Jointing
Where dowels are required they shall be installed with an approved type of
epoxy-resin grout in holes drilled into the existing structure in accordance with details
shown on the Drawings or as instructed by the Engineer.
New concrete shall be bonded to the old concrete by using a cement paste or
slurry or an approved type of bonding agent.
Each pipe joint shall be sealed to prevent leakage and infiltration of water on
to the bedding, unless shown on the Drawings or specified, jointing and sealing shall
conform to one of the following :-
Abutting ends of adjacent pipes shall be connected with concrete collars and
the space between the pipe and the collar shall be tightly sealed with stiff 1:2 cement
mortar, to uniform thickness round the pipe.
Where a pipe with spigot at one end and socket at the other are jointed with
pipe of the same type and size, the spigot of one pipe shall be inserted into the socket
of the other with the flexible joint ring fitted at the spigot end, and where a mortar
joint is specified, cement mortar of 1: I composition shall be worked into the joint by
hand or by an approved tool.
In jointing pipes with tapered ends, the end with external taper of one pipe
shall be joined with the end with internal taper of the other pipe and the space
between the pipes at the joint shall be patched with 1:2 cement sand mortar. In
addition to this the joint shall be provided with a covering with cement mortar of the
same composition having a minimum width of 100mm and minimum thickness of
25mm placed across, and running continuously round the ·pipe at the joint.
194
SECOND EDITION. JlJNE 2009 Institute for Construction Training and Development (lCT AD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND'BRIDGES (SCAlS) 700 - Drainage Construction
707.5 Backfilling
Backfilling of trenches or around the pipes shall begin at the lower end and
be carried aut in horizontal layers.
The material used far the backfilling of those portions of culverts subject to'
traffic laads shall be selected material af at least Sub-base quality or such lawer
quality as the Engineer may permit.
The backfilling material shall be thoroughly tamped under the flanks af the
culverts to' provide a unifarm bedding to' the Engineer's satisfaction. Adequate caver
over the culvert shall be pravided before the Contractor rautes his construction
equipment across it. Hydraulic compaction af backfilling may be permitted in
appropriate circumstances after successful trials.
Headwalls, wing walls, aprons and other ancillary works shall be constructed
in accordance with the details shawn in the Drawings or as directed by the Engineer.
Rubble masonry or brick masonry for the walls etc., shall conform to' requirements of
Section 1006 or 1007 respectively as specified and concrete for head walls, wing walls
and other ancillary works, if so specified, shall conform to concrete af class B or
Sectian 1001.
(a) Measurement
(i) Cancrete for bedding, encasement, granular aggregate bedding and soil
bedding shall be measured in Cu.m af material laid and compacted. The rate shall
include shuttering, if required and payment for shaping and compacting of stable in-
situ bedding material.
Pipes shall be measured as supplied, laid and jointed in linear metres along .
the centre line of the laid pipes.
195
SECOND EDiTIaN, JUNE 2009 Institute for Construction Training and Development (lCT AD)
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND
MAINTENANCE OF ROADS AND BRIDGES (SCA/S) 700 - Drainage Construction
(ii) The culvert construction shall be measured as linear metres for various
Numbers and sizes of pipes.
(b) Payment
(i ) Payment for bedding and laying of pipes measured as above will be based on
the Contract unit rate for the items which shall include full compensation for all
labour tools, equipment and incidentals necessary. Payment for excavation,
backfilling and dewatering and construction of headwalls etc., shall be as specified in
the respective sections.
(ii) Payment shall be made for full compensation for constructing the culvert
measured as above which will be based on the Contract unit rate for the item which
shall include full compensation for all labour tools, equipment and incidentals
necessary.
Either
196
SECOND EDITION, JUNE 2009 Institute for Construction Training and Development (K'T AD)