Professional Documents
Culture Documents
Final Report of Andode Tuma Power and Telecommunication
Final Report of Andode Tuma Power and Telecommunication
1. Introduction
1.1 Introduction and Purpose
1.2 Contract Data
1.3 Scope of Services and Objectives
1.3.1 Objective of Project
1.3.2 The Scope of Project Services
2. Project Description
2.1 Type of Project
2.2 Location
2.3 Project Back Ground
3. Land use categories, power estimation, and power forecast
3.1 Land use categories
3.2 Power Estimation
3.3 Load Growth Forecast
4. Planning and design of the medium voltage network
4.1 The operation mode of the power supply system
4.2 The selection of equipment
4. 3 Selection of Topology and Hierarchy
4.3.1 The fundamental structure of the power system configuration (topology)
4.3.2 Selection of Topology
4.3.3 Hierarchical Approaches
4.4 Distribution System Remote Monitoring
5. Road Lighting Design
6. Telecommunication Networks
6.1 Overview
6.2 Preferred Telecom Infrastructure for Andode Tuma Project
6.3 Optical Access Network
6.4 Full-Service Optical Access Network
6.5 Introduction
6.6 Optical Fiber
6.7 Optical Access Network Architecture
7. SWOT Analysis Major Finding and their Implications
7.1 SWOT Analysis
7.2 Summary of Major Findings/ Planning Issues & Planning Implications
7.3 Synthesis of Major Finding/planning issue and their implication
List of Figures
Figure 2.1 Location of the Project
Figure 2.2 Small Village nest to condominium
Figure 3.1 Picture Sample of transformer and High Tension
Figure 3.2 Picture for sample transformer and LV electric line
Figure 3.3 Sub-Station –Salo Gora Gelan condominium
Figure 3.4 Gelan condominium Sub-station
Figure 3.5 telecom tower electric utility
Figure 5.1 Typical radial topology
Figure 5.2 Typical Ring topology
Figure 5.3 SCADA block diagram system
Figure 5.4 Nomo solar pole Lighting
List of Tables
Table: 1.1 Project Data for Andode Tuma site
Table: 2.1 Project Description for Power and Telecom
Table: 3.1 Exist telecommunication figures
1. Introduction
1.1 Introduction and Purpose
Shaggar is the recent instituted city which formulated and endorsed by Oromia Regional
government. It has been known that an administration city faces many challenges to fulfil the need
of infrastructure and facilities and housing. To solve the mentioned problem Shaggar city
Administration launched five Neighborhood Development Plans projects for implementation.
The project is aimed at providing the high‐class basic infrastructure development that can
contribute to the regional, national, and international prospect investors creating opportunities to
participate in the diverse impact and export trades and manufacturing activities.
Since, smart city is a place where traditional networks and services are made more flexible,
efficient, and sustainable with the use of information, digital and telecommunication technologies,
to improve its operations for the benefit of its inhabitants. Smart cities are greener, safer, faster
and friendlier. The different components of a smart city include smart infrastructure, smart
transportation, smart energy, smart healthcare, and smart technology. These components are what
makes the cities smart and efficient. Information and communication technology (ICT) are
enabling keys for transforming traditional cities to smart cities.
The purpose of this report is to describe the current status of electric power, street light and telecom
infrastructure level in the area. It illustrates the overall infrastructure accessibility within the
selected site. Type of telecom system, transmission system and power supply and its distribution
mode of the community.
1.2 Contract Data
Project Name Sheger City Administration
The Consultancy services shall be carried following generally accepted standards of professional
practice, following recognized engineering procedures. The Consultant’s scope of work is to
Prepare Neighborhood Development Plan for different five sites, produce detailed engineering
designs for infrastructure and utilities in the NDP including roads, water supply,
sewerage, wastewater treatment plant, power, telecom, and solid waste site. The general scope of
the service covers the following major tasks.
Carry out the necessary field investigation including all field works like site visits, data
collection from the project site.
Carry out preliminary and final design works covering preparation of preliminary design
and final design.
Identifying and evaluating of the existing utilities, and preparing the existing statues and
the proposals.
2. Project Description
2.1 Type of Project
The project has proposed to launch Neighborhood Development Plan which is an action- oriented
development basis to improve the living standard inhabitants significantly.
2.2 Location
The site is located at about 8.8684° latitude 38.8334° longitude.
Region/Zone ECO
Length/Capacity
Climate Classification
a) Administration Center
The Administration Centers include all civic centers such as municipal, sectorial offices and other
civic centers are planned as compact and pedestrian‐friendly systems, which respect the scales of
the planned urban form. The total are coverage of administration center is 37.18 hectare (2.68%).
However, the circulation and green area should be suggested and so the total area consider for
administration building is 70% of the total area. Additionally, the supposed floor area for each
b) Residential
According to data and information collected from our socio-economics, the density of residential
is 120 dwelling/hectare. The Population density within this residential classification is estimated
to be 87,384 and 26400 households. The total area thought for residential is 302 hectare. The
estimated height of the total floor is assumed for residential buildings 10floors.
The power estimation is an essential task and forms the basis for the planning of the power system
There are five methods to estimate power.
1. Load forecast with load increase factors – This method is based
on the existing power system load and the increase in past years and
estimate the future load increase employing exponential increase
functions and trend analyses.
2. Load forecast with economic characteristic data – Load forecast
with economic characteristic data assumes different relations between
economic growth, availability of energy resources, energy
consumption and requirement in general, and growth in population
3. Load forecast with estimated values – Matching existing
settlements based on area, population number, etc. with the new
proposed area.
4. Load forecast with specific loads and degrees of electrification –
More exact planning is possible using development plans from planners
and estimating the power demand based on different types and number
of stories.
5. Load forecast with standardized load curves ‐ Determination of
the system load based on annual energy consumptions of individual
consumer or consumer groups, which can be taken from the service
provider
For this project, we estimated the power demand with “the load forecast with a specific load and
degrees of electrification” method. The method takes into account standard load densities (W/m2)
for different applications. The load densities are taken from IEEE 241‐1991 and NEC standards.
S.No Land Use Cat Total area-m2 Area for Building-m2 Number of floor(max) Total area of Buil
1 Commercial 1,543,710.00 926,226.00 10 9262260
2 Logistic 4,112,284.00 2,467,370.40 1 2467370.4
3 Residential 3,018,180.00 1,810,908.00 10 18109080
4 Service 54,755.00 32,853.00 6 197118
5 Spec Service 73,364.00 44,018.40 buffer zone for PHT 0
Urban
6 Agriculture 2,362.00 0 0
7 administrator 372,180.00 223,308.00 10 2233080
Table 3.2 Estimated used area for different purpose
Table 3.3 Power demand of each block with the next 5 and 10 years forecast
Load Demand in MW
111 Commertial
Logistic
218 Residen
30
Adminstr
30
Electrical Load Prediction is the estimation of future load by the designer. Prediction of
the load is an important and central process in the planning of transmission and
distribution systems. Load estimation perdition is important for the reduction of the
distribution system from problems like
Overloading
Instability in the system
Power cuts and power shortage
Poor reliability and safety issues
For the Andode Tuma project area, the load growth forecast is based on the IEC standard
i.e. the Impact of nominal load growth over time. Typically, some slight growth in kilowatt
demand (Generally 0.5 to 1% per year) will be experienced over time. In this case, we use 1%
for the load forecast. As per this, the additional demand growth over 10 years the demand will
be 407MW. Considering the power factor 0.8, the total capacity requirements for the next 10
years will be 509MVA. The details of the IEEE and NEC standards and the power calculation
and growth forecast for each land functions are annexed in Appendix A, B, and C respectively.
From the above specification, the high tension transmission lines interconnected the sub-
stations which located inside and adjacent to Addis Ababa are categories four types, depend
on its capacity.
1. Transmission line with 500KV…substituted by Pink color
2. Transmission line with 400K……substituted by back ‘’
3. Transmission line with 230KV…..’’ ‘’ ‘’ Red ‘’
4. Transmission line with 132KV…..’’ ‘’ ‘’ Green ‘’
The aim of planning electrical power systems is to fully serve the interests of the consumers
to be supplied with electricity. To determine the configuration of the power system in terms
of technical, operational, and economic criteria, planning principles have to be defined and
used. The reliability of the power supply system (Power station, transmission, and distribution
system, etc.) is influenced by:
The operational mode of the power supply system
The selection of equipment
The fundamental structure of the power system
configuration(topology)
Understandably, 100% security and reliability of electrical power supply cannot be achieved.
In each case, a compromise between supply reliability, the design of the system, the operation
requirements, the interest of consumers, and the expected investment cost are to be
considered. The power system in the Andode Tuma project can be characterized into three
different subsystems according to its tasks.
The high voltage transmission grid – Its major task is the
transportation of electrical energy over long distances (This is
not in our scope)
Distribution systems with 33KV/66KV – This serves as a
network of distribution in urban population centers. Industrial
suppliers and high power demanding customers are provided
directly from the 33KV/66KV line.
LV distribution with 480/220V – This is mainly done for individual
residential customers.
4.1 The operation mode of the power supply system
The mode of operation is the first major element in the architecture of the power network. There
are mainly two modes i.e. overhead and underground. The general understanding is that the
underground cables are laid beneath the ground and the overhead cables are visible overhead. But
apart from this, there are many significant features of both the types of these cables from the
perspectives of electrical power transmission or distribution. In the changed scenario of the power
system design, particularly, the distribution system, the cables, and their characteristics have
become highly selective and the technological advancements have also made the selection of cable
for a particular application more flexible. Several factors are affecting the selection of overhead or
underground transmission
System cost‐ the underground system is more expensive than the overhead
system.
Safety ‐ as the conductors are constantly exposed to the open
atmosphere, there are several concerns related to the safety of the
system and also reliability. The adverse conditions like heavy rain,
wind, snowfall, humid and salty contents in the air could deteriorate
the lifespan of these conductors and raise serious electrical safety
concerns. The underground system is not susceptible to such
environmental problems.
Possibility of expansion – On the possibility of expansion, the
overhead system is more preferable. However, in our case, all our
designs take into consideration future expansion and leave the
necessary space in the underground manholes and PVC ducts.
Fault detection – Fault detection is easier in overhead lines.
The selection of operation mode defines the type of conductor used in our system which is
underground cable. The next step is deciding the voltage level and hence deciding the
subsequent equipment. The voltage levels are selected based on IEC recommended system
voltages as shows in below table and EEP distribution voltage recommendations. The voltage
level of the nearby substations also influences the type of transformers at the substation.
Reliability and operational considerations play an important role in power distribution system
planning and design. Radial distribution system topology is the most common topology worldwide
due to its simplicity in design and operation but it provides the least degree of reliability. On the
other hand, ring distribution systems represent a compromise solution that provides an increased
reliability level at moderate planning cost. Ring topology provides simple structure, low
maintenance cost, flexibility in response to load variability and faults and standardization of cables
cross-sectional areas. Interruption duration of loads after faults is limited to switching duration
only regardless of repair duration. Also, reserve capacity for service restoration is provided by the
same ring. In ring distribution systems, reliability is enhanced compared to radial system because
each load point can be supplied from the two ends of the ring. Ring distribution systems are radially
operated by opening at least one line segment along the ring tour, and the status of open/closed
lines changes in case of fault in a line segment for restoration of power
1) Radial Topology
The radial system is the simplest electrical distribution arrangement, and the least expensive in
terms of equipment initial cost. It’s also the least reliable arrangement since it only uses a single
utility source. The conventional simple radial system receives power at the utility supply voltage
at a single substation and steps the voltage down to the utilization level. The loss of the utility
source, transformer, or the service or distribution equipment will result in a loss of service.
Further, the loads must be shut down in order to perform maintenance on the system. This
arrangement is most commonly used where the need for low initial cost, simplicity, and space
economy outweigh the need for enhanced reliability.
Typical equipment for this system arrangement is a single unit substation consisting of a fused
primary switch, a transformer of sufficient size to supply the loads, and a low voltage switchboard.
The simplest kind of ring‐main system is obtained by connecting the lines ends back to the
feeding station as shown in Fig. 3.6.
Figure -3.6- Typical ring topology
A Ring main typology is selected for the power distribution as it is the most reliable.
From the substations, outgoing circuits are provided to all the nearest loads (manufacturing,
commercial, residential, mixed residential,). In most cases, a single feeder is considered for all the
land use categories/customers. The main distribution element at each customer is the switching
station. The switching stations are the main instruments in utilizing the full benefits of the ring
typology as shown in Fig 4.4. The switching stations are placed closer to the loads.
This will benefit in the following ways:
Reduced losses
Risk containment and mitigation
Will give a chance for future distributed energy resource
After the switching stations, RMUs are provided to the power the transformers at each buildings.
As much as possible, a single RMU is used to feed two adjacent transformers. A total of switching
station and 10 RMUs required for this project.
4.4 Distribution System Remote Monitoring
The control of the substation, monitoring of the status of the switchgear, feeder loads, and
transformer loading, metering, and other parameters can be remotely monitored. The choice of a
SCADA system will impose technical requirements that will need to be incorporated in the
substation and distribution design. A SCADA (supervisory control and data acquisition) is an
automation control system that is used in industries such as energy, oil and gas, water, power, and
many more. The system has a centralized system that monitors and controls entire sites, ranging
from an industrial plant to a complex of plants across the country. A SCADA system works by
operating with signals that communicate via channels to provide the user with remote controls of
any equipment in a given system. It also implements a distributed database, or tag database, that
Human Machine Interface (HMI)
supervisory system
Remote Terminal Units (RTUs)
Programmable Logic Controllers (PLCs)
communication infrastructures
We incorporated the SCADA system in our distribution plan as it fits the technical requirement
and it is already utilized by Ethiopian Electric Power for remote monitoring. The main control
station will be at the substations and each switching station is connected to the control room via
fiber optic cables.
1) General description
The main task of road lighting is to assure proper luminous levels on the roads to enable
the good vision for all road users.
2) Standard Use
The right light levels are determined by the internationally accepted standard Commission
(CIE, International Commission on Illumination). This standard defines the required
lighting for every type of motorized road, with roads classified according to a set of
defining characteristics such as traffic volume and composition, the number of lanes,
usage, weather condition (fog, rain), and type of road surface ( paved, unpaved, cemented,
asphalt).
There may many type of roads on this project. The height and spacing between street pole
is depends on the road design, land use and final city plan layout. Accordingly, the
selection of pole height, planning and design, selection of light fitting and analysis of
parameter shall be done after the work land use and categories with site plan is being
finalized.
However, due to its many advantages, Nomo solar pole lighting is proposed for this
project. It has combines remote centralized control and management of street lights
through solar photovoltaic applications and ZigBee wireless communication technology,
4G communication, cloud computing, Internet of Things and mobile Internet technologies,
with brightness adjustment, active fault alarm, Lamp cable anti-theft, visual remote
control, and other sensor extension applications. Smart solar street lights can greatly
Improve the level of public lighting management, save power resources, reduce operation
and maintenance costs, and increase additional revenue.
Urban street lights serve as the densest urban infrastructure for information gathering and
dissemination. Smart lighting is an important part of the smart city and the best entrance.
Smart solar street lights are an effective support for the city. Low-power smart solar street
light is the perfect embodiment of smart city new energy application.
Nomo intelligent outdoor lighting solution for Smart City comes with an upgrade option
to become a public streetlight Wi-Fi hotspot. Nomo in partnership with one of the most
advanced routers and wireless ISP systems manufacturer is able to provide an easily
installable wireless device which is carrying out the public internet hotspot function for
the street lighting poles. Besides it support usb charger (charged service)
1. LED charger indicator light
2. Non slip pad surface
3. 10w transmitter coil
4. Fanless design for quiet operation
5. Wireless charging chipset control the current flow
6. Thermal protection sensor can dial back power for safer operation
7. Foreign object detection circuit to prevent conductive materials from receiving
the power from the charger.
6.1 Overview
Telecommunication systems play a very important role in the infrastructure of smart cities. An
excess of networked devices interact to provide safe, convenient and environmentally conscious
new services. Residents in smart cities can enjoy their lives using these services, seamlessly and
without being aware of the existence of the networks.
In cities, transportation, distribution, finance, and energy services are connected to networks and
interact to provide more reliable, convenient, and environmentally conscious new services.
Residents in smart cities will have seamless access to these services without needing to know about
the networks on which they are based.
Recognizing the crucial role of telecommunication sector in the entire economic activities and
impact on growth and developments governors in different regime in the last century have been
attempting to expand this service for citizens, though at different scale. A structurally different
communication institution had and has been established all along in telecommunication history of
the country. In our country, recently the responsible institution to render this service is the
Ethiopian Telecommunication Corporation (ETC). This sector structure has stretched down from
national level up to sub areas.
ETC has been monopolistically providing nationwide telecommunications services since 1996.
These are including consisting of:
Telephone Service is calls which including voice, voicemail and conference and data calls, and
supplementary services that including call forwarding and call transfer. It is also messaging and
multi-media services.
The provision of nationwide telephone service to fulfill the waiting demand is current core activity
for ETC and has been accelerated recent years. From a viewpoint of accessibility to the telephone
service, most of the regions except certain areas (including rural areas) have been covered to some
extent by the telephone network
A service available to the public for originating and receiving national and international calls and
access to emergency services through a telephone number or numbers in a national or
international telephone
ETC is providing public payphones in a nationwide basis. Since the start of the public payphone
service, ETC established 935 coin telephones as of 2001, and starting card phone system in early
2002. However, the number of public telephones is insufficient compare with other telecom
communication.
A mobile phone or cellphone is a portable telephone that can make and receive calls over a radio
frequency link while the user is moving within a telephone service area, as opposed to a fixed-
location phone landline phone. The radio frequency link establishes a connection to the switching
systems of a mobile phone operator, which provides access to the public switched telephone
network PSTN. Modern mobile telephone services use a cellular network architecture and
therefore mobile telephones are called cellphones cell phones in North America. In addition
to telephony, digital mobile phones support a variety of other services, such as text
messaging, multimedia messaging, email, Internet access (via LTE, 5G or Wi-Fi), short-range
wireless communications (infrared, Bluetooth), satellite access (navigation, messaging
connectivity), business applications, video games and digital photography. Mobile phones offering
only basic capabilities are known as feature phones; mobile phones which offer greatly advanced
computing capabilities are referred to as smartphones.
In 1999 ETC entered into Mobile-phone Service. In 2001, the service covers urban and suburb
areas of Addis Ababa and metropolitan. Nowadays, compare to other countries, Ethiopia is
massively lagging behind in the development of telecommunications. Under the country code
+251, there were a total of 65.39 million connections in 2021. Among them were 64.50 million
mobile phones, which corresponds to an average of 0.54 per person.
6.2 Preferred Telecom Infrastructure for Andode Tuma Project
Depending on the structure and purpose of use of smart city applications, different network and
communication technologies are used, as well as different network protocols used to connect the
system components that support these applications. A strong network infrastructure is needed to
support different applications in smart city systems. A hierarchical topology structure is also
required in which the operations of the applications can be carried out, as well as the network
protocols suitable for the needs.
Gigaband Solution – Gigabit broadband is an internet connection that offers a speed of 1 gigabit
per second (1Gbps/1GB) or more. The proposed design can accommodate this and has the
following characteristics.
Smart Transportation
Smart Energy and Water
E – Healthcare
Smart Garbage Disposal
Smart Agriculture
Smart Lighting, Smart Parking, Smart Transit, Smart Waste Management, Video Surveil
lance, robotic network, etc
Digital Transformation – This is the result of the gigaband solution. With such an infrastructure
in place, the following things can be achieved.
Broadband
Main Data Centers, Backup data center, Satellite backup
Cloud Network
Big Data
Internet of things (IoT), SCADA, Robotic network
4K / VR / Game online
On‐demand fiber blowing to anywhere in the Andode Tuma project via the adopted flexible micro‐
duct pipe and spare fiber in the feeder network is achievable.
Full‐service optical access network for high‐speed data, voice, and video
Backbone network
• No existing fiber route in the site that cross the Andode Tuma area
• Permanent new fiber route, pipe, and manhole facility design
Based on ITU‐T L.90 recommendation progress on multimedia technologies has led to the active
development of many kinds of broadband services such as data and video communication using
access networks. High‐speed broadband networks must be developed economically to provide
such services to all subscribers. To provide these services in a timely way, it is necessary to
construct optical access networks quickly, efficiently, and cost‐effectively. However, recent
progress in the application of optical plant technology in local access networks has provided
substantial technical and economical experiences in several countries. Considering this, the
network design must take into account planning, construction, maintenance, and operation. Here,
an optical access network is defined as a network of optical fiber cables that extend from a carrier's
central office to the cabinets, buildings, individual homes, apartment blocks, or business offices
for broadband services.
A suitable choice of fiber and splicing technology should be made. Single‐mode fiber, normally
compliant with [ITU‐T G.652] and [ITU‐T G.657], is the most appropriate for a wide range of
telecommunication services in the local distribution network since this fiber benefits from
economy of scale and has long‐term potential utility for future services. With the current usage of
single‐mode fiber, splicing techniques will allow typical splice losses of less than 0.5 dB to be
achieved.
As per ITU-T recommendation, only ITU-T G.657 category A fibers are compatible with ITU-T
with G.652 fibers. Using other fiber types will increase the uncertainty regarding the splice value
and compatibility issue.
[ITU‐T G.984.1] to [ITU‐T G.984.7], [ITU‐T G.985], [ITU‐T G.986] and [ITU‐T G.987.x]. The
calculation of the total network optical loss will take into account [ITU‐T G.982] recommendation
In generally, the following points are provided concerning about the Andode Tuma site.
1. There is no telecom center, telecom tower and fiber transmission line across the
Andode Tuma site. However, only on telecom tower at the border of the project
site built.
2. One medium voltage transmission line–stretched over wooden pole supply for
rural villages- found in near to condominium
3. Three sub-stations are found closer to the project site.
4. Two high tension transmission line have passed over the Andode Tuma site.
b) Planning Assumption
One new transmission sub-station which supplies 509kVA loads is required for
Andode Tuma project
Underground installed optical fiber for telecom transmission system is required
from the nearest switching center.
Table 3 Typical apartment loads