Professional Documents
Culture Documents
R O W of High Voltage Transmission Lines
R O W of High Voltage Transmission Lines
net/publication/349965053
R-O-W-of-High-Voltage-Transmission-lines
CITATION READS
1 1,195
3 authors, including:
SEE PROFILE
All content following this page was uploaded by Mobasher Abdu Alasmari on 11 March 2021.
Abstract—Right of way process of high voltage, 110-132 K.V, MW: The watt (symbol: W) is a derived unit of power in the International
transmission power lines projects is complicated process as it is based System of Units (SI).The unit is defined as 1 joule per second and can be
on more than fifty interrelated steps that involve several departments used to express the rate of energy conversion or transfer with respect to
and governmental agencies to obtain the necessary permits and secure time.
approvals of power lines routes . Permitting process has to be within
time frame of about one to one and a half year which is composing
OHTL: Over head transmission lines , An overhead power line is a
twenty five to thirty percent of project life cycle . Obtaining permits is
structure used in electric power transmission to transmit electrical energy
in accordance with pre-set technical and economical constraints is
along large distances. It consists of one or more bare
more challenging factors to assure constructability and
conductors (commonly multiples of three) suspended by towers.
maintainability of route proposal. This paper will focus on the factors
affecting the R.O.W process of high voltage transmission lines by PI: Points of intersection, the point where two non-parallel lines intersect.
presenting systematic approach entitled; six phases of high voltage More specifically, the point where two tangents to a curved line intersect.
transmission lines R.O.W process. Among the phases is proposing
three routes for transmission lines then its study to select the most cost R.O.W: right of way , used to describe a right belonging to a party to
effective route by utilizing CAD & DEM files .Field portion of the pass over the land of another. it can be simply defined as a right of
process is significant , gathering field data accurately then analyzing passage to another person's land or property. This is a common term often
to converting into profile and route maps is vital phase, this phase has used by land surveyors and civil engineers and is usually associated in land
couple of criteria to make sure the data obtained during site visit is in usage rights.
integration with technical and economical requirements .Also
identifying risks encountered during study of route alternatives along UTM: Universal Transverse Mercator , map projection uses a 2-
with mitigation measures is discussed; risk identification of process dimensional Cartesian coordinate system to give locations on the surface of
will speed up the R.O.W by minimizing permitting duration the Earth. It is used to identify locations independently of vertical position,
particularly at phase five as it is alone consumes 70-80 % of the whole UTM system divides the Earth into sixty zones, each being a six-degree
permitting process duration band of longitude, and uses a secant transverse Mercator projection in each
zone.
Index Terms.
Acquisition process WGS84: The World Geodetic System 1984 (WGS84) is a datum featuring
Electric Networks coordinates that change with time.The system is based on a consistent set
High voltage transmission power lines of constants and model parameters that describe the Earth's size, shape, and
OHTL transmission lines gravity and geomagnetic fields. It is for the Global Positioning System
Overhead transmission line (GPS)
Permitting
Profile maps II. INTRODUCTION
Right of way
Route maps The next five years will witness nearly 30% increase of
Route Selection power demand in kingdom of Saudi Arabia[13]. The larger
Transmission lines survey
R.O.W in Saudi Arabia
annual increase in electrical load resulting from significant
development and growth of all economic sectors, in
I. NOMENCLATURE conjunction with broadening the prospects of internal and
external investment , has led to an increase in the rate of
DEM: digital elevation model is a model or 3D representation of a
terrain's surface .
demand for electricity ; loads have increased over 10 % in
DGN: is the name used for CAD file formats supported by Bentley 2015 compared with 2014 in K.S.A , with the equivalent of
Systems' MicroStation 5776 M.W[13]. To meet the increase demand, Saudi
HV: electrical energy at high voltages,110 to 132 Kilo Volts Electricity Company, SEC, as the sole provider of electric
KMZ: KMZ is a file extension for used by Google Earth. KMZ stands for
energy in the country has expanded its interrelated electric
Keyhole Markup language Zipped. It is a compressed version of
a KML (Keyhole Markup Language) file. network to be capable of transmitting and exchanging energy
between the different regions of Saudi Arabia ; on annual
basis a Saudi Arabia has to have a continuous
unprecedented expansion of the system to supply its growing
*Mobasher Alasmry works for Saudi Electricity Company ,SEC, Jeddah
needs ; for instance, the amount of added overhead network
City, Kingdom of Saudi Arabia ( e-mail: Maasmari1@Ngrid.sa). and underground cables to the existing network measuring
*Khalil Alsayed works for Comets Company, Jeddah City, Kingdom of about 5389 K.M-circular by end of 2015 which represent
Saudi Arabia ( e-mail: Kmsayed@ngrid.sa). nine percent of the existing transmission network .Expansion
*Jaman Al-Zahrani works for Saudi Electricity Company, SEC, Jeddah
City, Kingdom of Saudi Arabia( e-mail: JMZahrani2@se.com.sa).
of the transmission system needs more comprehensive and
*Abdu Abdullah Hobany works for Saudi Electrcity Company, SEC, rigorous planning approach at early stage to avoid negative
Jeddah City , Kingdom of Saudi Arnbia (e-mail: EGSWADV@ngrid.sa). impact on the network system , delay of construction lead to
2
technical solutions and findings new means to Some government agencies lack of clear development
reduce construction cost without impairing plans lead to major changes of connection plan
operation reliability of the system "[2]. Table 03 ( R.O.W risks and mitigation measures)
5. The minimum horizontal distance between the route
center line and other overhead lines or other Risk Impact Suggestion
obstacles (ie. gas, oil, water pipes, building, trees) 1 Difficulties of obtaining Delay obtaining time of Develop a
government authorities rout permits partnership with
shall not be less than given in Table 02. right of way approvals, government sectors
due to restrictions on to be aware of
Table 02(Transmission line clearance to utilities and obstacles ) land use [10] master plans
6. At the crossing of OHL route over other features, the 6 Route passes by Difficult terrains impact change connection
Unavoidable difficult constructability and plan to alternative
following rules shall be applied: terrain maintainability . source substation
i) Where transmission line route cross pipelines, the
angle of intersection is preferably 90 degrees, and if Regarding Public impact on R.O.W , ''The public perception
not possible the angle of intersection shall be of overhead transmission lines has also altered considerably
between 70 to 110 degrees. in the last decades with particular regard to the
ii) Where transmission line route cross overhead environmental ,property values, and alleged health effects
transmission lines and communication lines, the associated with electromagnetic fields''[3]
angle of intersection is preferably 90 degrees, and if
not possible the angle of intersection shall be C. Improvement and suggested practice
between 70 to 110 degrees. Based on the team experience as R.O.W is their sole role in
iii) Where transmission line route cross roads, the the organization , SEC standards and also based on
angle of intersection is preferably 90 degrees, and if technical paper of K.G Matosinho [9] , also our work is
not possible the angle of intersection shall be based on (EPRI-GTC Overhead Electric Transmission line
between 45 to 135 degrees. Where transmission siting methodology) [1] , our suggested practice called; six
line route cross major highways, the angle of phases of high voltage transmission lines R.O.W process.
intersection shall be as near as possible to 90 The suggested systematic process translated into a handy
degrees. checklist to facilitate the permitting procedure.
iv) Where transmission line route cross the railroad
tracks, the angle of intersection is preferably 90 1. Phase I – Proposing three routes/ profiles and preliminary
degrees, and if not possible the angle of study
intersection shall be between 70 to 110 degrees. The three routes proposed shall be located as near as
v) At wadi crossing the route shall be selected possible to major highways, roads for easy accessibility
where a single span is possible. Both banks of the during construction and maintenance phase of the
wadi shall be firm soil, the preference network , Graph no. shows the example of three routes
on map .
B. Challenges to obtain R.O.W of OHTL & improvement
The major challenge at permit stage is to obtain the
necessary approvals within time constraints due to two
critical external factors:
1. Congested Areas
Route selection difficulties increase in crowded areas
such as major cities and industrial zones as other
utilities exist to serve the communities
2. unobtainable approvals of some government agencies
4
Standards:
IV. CONLUSION [13] Saudi Electricity Survey Guidelines , Transmission engineering
Permitting route of high voltage, 132-110 K.V, transmission standard TES-P-122.08,rev .01, December 2011.
[14] Saudi Electricity , Clearance and right of way requirements,
line is complicated as it is composed of at least fifty
Transmission engineering standard TES-P-122.09, Rev. 01,
interrelated steps , however consolidating the fifty steps December 2014
into one handy checklist along with sheet of critical
activities of permitting process in terms of time and Misc.
technical requirements conformity has contributed to [15] SEC, Annual Report. Riyadh , SEC, 2015.
efficiency and effectiveness of permitting process as a result
7
VII. BIOGRAPHIES
Mobasher Alasmry was born in Balasmar City
of Saudi Arabia, on May 13, 1981.He graduated
from King Abdualziz university , engineering
college, Saudi Arabia ; holds B.S of civil
engineering in 2004 and master of engineering
management in 2014.His experience included;
S.Aramco Exxon Mobil Refinery, Saudi
Electricity company , Petrorabigh project in
several departments : quality assurance, project
management and engineering design, handled
several mega projects such as Sr. QC engineer for S.Aramco in Diesel
Hydrotreatment Project , QA engineer for Petrorabigh new refinery
construction team 2007 -2008 , project engineer for design of structures
for heavy sea water pumps in 2010 during working for Saudi Aramco
Exxon Mobil refinery in Yanbu city. He was honored for contribution in
Project management body of Knowledge edition five issued by PMI for
Project Management Professionals