Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

PINNACLE PRIME CONSTRUCTIONS PVT. LTD.

Project :- Electrical Substation Building


Sub :- Project Schedule

Duration
Sl No Particulars Start date Completion date Remarks
in Days

Footing
Mobilization 14 7/1/2022 7/15/2022
Excavation 20 7/10/2022 7/30/2022
PCC 7 7/25/2022 8/1/2022
Reinforcement mat & column 11 7/30/2022 8/10/2022
Shuttering 10 8/2/2022 8/12/2022
Concreting 10 8/4/2022 8/14/2022
Column starter 10 8/5/2022 8/15/2022
Column up to Plinth 11 8/6/2022 8/17/2022
Backfilling 12 8/8/2022 8/20/2022
Floor PCC 5 8/16/2022 8/21/2022
COLUMNS AND WALLS UP TO FIRST SLAB
Column/Retaining Wall reinforcement 11 8/10/2022 8/21/2022
Column/Retaining Wall Shuttering 10 8/12/2022 8/22/2022
Column/Retaining wall Concreting 1st Lift 10 8/15/2022 8/25/2022
Column/Retaining Wall shuttering & concreting 2nd lift 10 8/18/2022 8/28/2022

CELLAR ROOF CONCRETE


Slab & Beam Shuttering 18 8/18/2022 9/5/2022
Slab & Beam Reinforcement 14 8/25/2022 9/8/2022
Slab & Beam Concreting 1 9/10/2022 9/11/2022

GROUND FLOOR ROOF CONCRETE


Column Reinforcement 6 9/12/2022 9/18/2022
Column Shuttering 6 9/14/2022 9/20/2022
Column Concreting 7 9/15/2022 9/22/2022
Slab & Beam Shuttering 12 9/18/2022 9/30/2022
Slab & Beam Reinforcement 7 9/25/2022 10/2/2022
Slab & Beam Concreting 1 10/3/2022 10/4/2022

FIRST FLOOR ROOF CONCRETE


Column Reinforcement 5 10/5/2022 10/10/2022
Column Shuttering 5 10/7/2022 10/12/2022
Column Concreting 4 10/10/2022 10/14/2022
Slab & Beam Shuttering 10 10/10/2022 10/20/2022
Slab & Beam Reinforcement 8 10/14/2022 10/22/2022
Slab & Beam Concreting 1 10/23/2022 10/24/2022

SECOND FLOOR ROOF (TERRACE) CONCRETE


Column Reinforcement 5 10/25/2022 10/30/2022
Column Shuttering 7 10/26/2022 11/2/2022
Column Concreting 7 10/27/2022 11/3/2022
Slab & Beam Shuttering 12 10/29/2022 11/10/2022
Slab & Beam Reinforcement 8 11/4/2022 11/12/2022
Slab & Beam Concreting 1 11/13/2022 11/14/2022

ROAD WORKS & DRAIN WORKS


Drain excavation 40 8/1/2022 9/10/2022
Road formation 31 8/12/2022 9/12/2022
Drain PCC Works 39 8/6/2022 9/14/2022
R/F steel 39 8/8/2022 9/16/2022
Drain bottom slab 36 8/15/2022 9/20/2022
Drain Wall 39 8/20/2022 9/28/2022
Kerb stone fixing 25 9/15/2022 10/10/2022
GSB laying for Road Works 26 10/15/2022 11/10/2022
Reinforcement Works for Road 10 12/10/2022 12/20/2022
Road Concreting Works 10 12/15/2022 12/25/2022

FINISHING WORKS
Block Work
Block Works @ Cellar Floor 19 10/1/2022 10/20/2022
Block Works @ Ground Floor 14 10/16/2022 10/30/2022
Block Works @ First Floor 48 10/10/2022 11/27/2022
Block Works @ Second Floor 14 11/28/2022 12/12/2022
Block Works @ Terrace Floor 15 11/25/2022 12/10/2022

Internal Plastering Work


Plastering Works @ Cellar Floor 9 10/15/2022 10/24/2022
Plastering Works @ Ground Floor 16 10/25/2022 11/10/2022
Plastering Works @ First Floor 15 11/20/2022 12/5/2022
Plastering Works @ Second Floor 12 12/8/2022 12/20/2022
Plastering Works @ Terrace Floor 14 12/1/2022 12/15/2022

External Plastering 27 11/28/2022 12/25/2022

Flooring Works
Cellar Floor 10 10/15/2022 10/25/2022
Ground Floor 15 11/5/2022 11/20/2022
First Floor 15 11/30/2022 12/15/2022
Second Floor 13 12/15/2022 12/28/2022

Waterproofing Works 10 12/10/2022 12/20/2022

Internal Painting Works


Cellar Floor 16 10/20/2022 11/5/2022
Ground Floor 15 11/10/2022 11/25/2022
First Floor 15 12/5/2022 12/20/2022
Second Floor 12 12/18/2022 12/30/2022

External Painting Works 26 12/5/2022 12/31/2022

You might also like