Schedule For Substation Works-HO
Schedule For Substation Works-HO
Duration
Sl No Particulars Start date Completion date Remarks
in Days
Footing
Mobilization 14 7/1/2022 7/15/2022
Excavation 20 7/10/2022 7/30/2022
PCC 7 7/25/2022 8/1/2022
Reinforcement mat & column 11 7/30/2022 8/10/2022
Shuttering 10 8/2/2022 8/12/2022
Concreting 10 8/4/2022 8/14/2022
Column starter 10 8/5/2022 8/15/2022
Column up to Plinth 11 8/6/2022 8/17/2022
Backfilling 12 8/8/2022 8/20/2022
Floor PCC 5 8/16/2022 8/21/2022
COLUMNS AND WALLS UP TO FIRST SLAB
Column/Retaining Wall reinforcement 11 8/10/2022 8/21/2022
Column/Retaining Wall Shuttering 10 8/12/2022 8/22/2022
Column/Retaining wall Concreting 1st Lift 10 8/15/2022 8/25/2022
Column/Retaining Wall shuttering & concreting 2nd lift 10 8/18/2022 8/28/2022
FINISHING WORKS
Block Work
Block Works @ Cellar Floor 19 10/1/2022 10/20/2022
Block Works @ Ground Floor 14 10/16/2022 10/30/2022
Block Works @ First Floor 48 10/10/2022 11/27/2022
Block Works @ Second Floor 14 11/28/2022 12/12/2022
Block Works @ Terrace Floor 15 11/25/2022 12/10/2022
Flooring Works
Cellar Floor 10 10/15/2022 10/25/2022
Ground Floor 15 11/5/2022 11/20/2022
First Floor 15 11/30/2022 12/15/2022
Second Floor 13 12/15/2022 12/28/2022