Construction Project Schedule Template G1 Residential Building
Construction Project Schedule Template G1 Residential Building
Project Owner:
Project Contractor:
Project Start Date: 11/2/2022
Reinf. & Shuttering work will start from one end of the building. Assuming 10 Footings per day. Total 65 footings.
Assuming 5 sets of column shuttering. Duration= (27 Columns/5 lift everyday)= 5.4 days say 6 days
Assumed Backfilling duration=1 day, watering=1 day and compaction=1 day.
Shutt. & Reinf. Work to start after column casting of first two grids.
Shutt. & Reinf. Work to start after column casting of first two grids.
Shutt. & Reinf. Work to start after column casting of first two grids.
Shutt. & Reinf. Work to start after column casting of first two grids.
One blockwork and plaster team will be used for the project. Thus, the first floor to start after ground floor.
One tiling team will be used for the project. Thus, the first floor to start after ground floor.
One plumbing team will be used for the project. Thus, the first floor to start after ground floor.
One carpenter team will be used for the project. Thus, the first floor to start after ground floor.
One painting team will be used for the project. Thus, the first floor to start after ground floor.
New activity added as completion milestone.