Project Name: Construction of

Project Owner:
Project Contractor:
Project Start Date: 11/2/2022

WBS ID Activity Duration Lead Start Date End Date


1 Building Project
A Site Handover to Contractor 0 11/2/2022 11/2/2022
1.1 Structure Work
1.1.1 Foundation
1.1.1.1 Excavation 7 0 11/2/2022 11/9/2022
1.1.1.2 PCC 3 0 11/10/2022 11/13/2022
1.1.1.3 Reinforcement & Shuttering 10 0 11/10/2022 11/20/2022
1.1.1.4 Casting with RCC 3 0 11/21/2022 11/24/2022
1.1.2 Upto Plinth Level
1.1.2.1 Columns & RT Wall up to Plinth Beam Bottom 6 0 11/25/2022 12/1/2022
1.1.2.2 Backfilling & Compaction 3 0 12/2/2022 12/5/2022
1.1.2.3 Plinth Beam Reinf. & Shuttering 7 0 12/6/2022 12/13/2022
1.1.2.4 Casting of Plinth Beam with RCC 1 0 12/14/2022 12/15/2022
1.1.3 Upto Ground Floor Slab
1.1.3.1 Columns & RT Wall up to First Slab 14 0 12/16/2022 12/30/2022
1.1.3.2 Shuttering & Reinforcement of Beams & Slab 14 0 12/16/2022 12/30/2022
1.1.3.3 Casting of First Floor Beams & Slab 2 0 12/31/2022 1/2/2023
1.1.3.4 Curing Period 21 0 1/3/2023 1/24/2023
1.1.3.5 Deshuttering 5 0 1/25/2023 1/30/2023
1.1.4 Upto First Floor Tie Beams
1.1.4.1 Columns up to Tie Beam Bottom 6 0 1/3/2023 1/9/2023
1.1.4.2 Shuttering & Reinforcement of Tie Beams 10 0 1/3/2023 1/13/2023
1.1.4.3 Casting of Tie Beams with RCC 1 0 1/14/2023 1/15/2023
1.1.4.4 Curing Period for Deshuttering 21 0 1/16/2023 2/6/2023
1.1.4.5 Deshuttering 5 0 2/7/2023 2/12/2023
1.1.4 Upto Second Floor Tie Beams
1.1.4.1 Columns up to Tie Beam Bottom 6 0 1/16/2023 1/22/2023
1.1.4.2 Shuttering & Reinforcement of Tie Beams 10 0 1/16/2023 1/26/2023
1.1.4.3 Casting of Tie Beams with RCC 1 0 1/27/2023 1/28/2023
1.1.4.4 Curing Period for Deshuttering 21 0 1/29/2023 2/19/2023
1.1.4.5 Deshuttering 5 0 2/20/2023 2/25/2023
1.1.4 Upto Terrace Floor Tie Beams
1.1.4.1 Columns up to Tie Beam Bottom 8 0 1/29/2023 2/6/2023
1.1.4.2 Shuttering & Reinforcement of Tie Beams 10 0 1/29/2023 2/8/2023
1.1.4.3 Casting of Tie Beams with RCC 1 0 2/9/2023 2/10/2023
1.1.4.4 Curing Period for Deshuttering 21 0 2/11/2023 3/4/2023
1.1.4.5 Deshuttering 5 0 3/5/2023 3/10/2023
1.2 Finishing Work
1.2.1 Blockwork, Plastering, False Ceiling Work & Tiling
1.2.1.1 Plaster for Cellar Floor 15 0 1/31/2023 2/15/2023
1.2.1.2 Blockwork and Plaster for Ground Floor 15 0 2/13/2023 2/28/2023
Blockwork and Plaster for First Floor 15 2/26/2023 3/13/2023
Blockwork and Plaster for Second Floor 15 3/11/2023 3/26/2023
1.2.1.3 False Ceiling Work for First Floor 8 0 3/1/2023 3/9/2023
1.2.1.4 Tiles Work for Ground Floor 10 0 3/10/2023 3/20/2023
1.2.1.5 Tiles Work for First Floor 10 0 3/21/2023 3/31/2023
1.2.2 Plumbing & Sanitary Works
1.2.2.1 Plumbing & Sanitary for Ground Floor 10 0 2/16/2023 2/26/2023
1.2.2.2 Plumbing & Sanitary for First Floor 10 0 2/27/2023 3/9/2023
1.2.4 Doors & Windows Fixing
1.2.4.1 Doors & Windows Fixing for Ground Floor 10 0 2/16/2023 2/26/2023
1.2.4.2 Doors & Windows Fixing for First Floor 10 0 2/27/2023 3/9/2023
1.2.5 Painting and Finishing
1.2.5.1 Painting & Finishing for Ground Floor 15 0 2/28/2023 3/15/2023
1.2.5.2 Painting & Finishing for First Floor 15 0 3/16/2023 3/31/2023
1.2.5.3 Cleaning of Entire Structure 2 0 4/1/2023 4/3/2023
B Handover to Client 0 0 4/4/2023 4/4/2023
Remarks/Assumptions

New acitivity added as start milestone.

Start of work. Excavation to be done by excavator after demarcation by site engineer.

Reinf. & Shuttering work will start from one end of the building. Assuming 10 Footings per day. Total 65 footings.

Assuming 5 sets of column shuttering. Duration= (27 Columns/5 lift everyday)= 5.4 days say 6 days
Assumed Backfilling duration=1 day, watering=1 day and compaction=1 day.

Shutt. & Reinf. Work to start after column casting of first two grids.

New activity added to minimise the deshuttering lead by 21 days

Shutt. & Reinf. Work to start after column casting of first two grids.

New activity added to minimise the deshuttering lead

Shutt. & Reinf. Work to start after column casting of first two grids.

New activity added to minimise the deshuttering lead

Shutt. & Reinf. Work to start after column casting of first two grids.

New activity added to minimise the deshuttering lead

One blockwork and plaster team will be used for the project. Thus, the first floor to start after ground floor.

One tiling team will be used for the project. Thus, the first floor to start after ground floor.

One plumbing team will be used for the project. Thus, the first floor to start after ground floor.

One carpenter team will be used for the project. Thus, the first floor to start after ground floor.

One painting team will be used for the project. Thus, the first floor to start after ground floor.
New activity added as completion milestone.