Monthly Review Meeting-1.11.23-Minutes Abc
Monthly Review Meeting-1.11.23-Minutes Abc
Monthly Review Meeting-1.11.23-Minutes Abc
To
Sir,
Yours faithfully,
t1i:,40v1'
'
'"';--)'
Special Secretary to Govt.
CC:
5. SEs/EEs of all RW Divisions, DGM NBCC Odisha, Bridge & Roof Odisha
for information and necessary action.
The monthly review meeting for the r;;; october'23, was held on 01.11.2023 under the
Chairmanship of the Principal Secretary, R.D. Department, in the Conference Hall of the Department
in presence of Director, Special Secretary, EIC-cum-Special Secretary, Additional Secretary (FE),
Additional Secretary (OE), FA-cum-Additional Secretary, EIC RW, Chief Engineer Bridge & Buildings
and Chief engineer Roads of RW Organisation. The meeting was attended by the CCEs, SEs, EEs and
other field engineers through OSWAN VC from respective Districts. The representatives of Bridge &
Roof and NBCC also attended the meeting from respective district headquarters.
At the outset, Principal Secretarywelcomed all members present in the meeting. He expressed
his disappointment on the overall performance of the Divisions both in financial and physical
achievement during the month of October'23. He also expressed his displeasure for non-achievement
in sectors like tender finalisation, work completion and warned that action will be taken against all
from JE to Chief Engineer for such non-performance.
Further, PrincipalSecretaryinstructed that utmost importance is to be given to Pension and
Promotion matters of the employees pending with RD Department. fu regards Pension matters, there
are two categories of employees i.e. (i) Employees who have retired from RD Department and where
RD Department is the PSA (ii) Employees, who have retired from RD Department but PSA is other
Department like Works/Home etc. Principal Secretary directed that in both categories, the concerned
field offices have to take all necessary steps to send the final pension papers to AG if RD Department
is the PSA. In other cases, pension papers are to be forwarded to the Department which is the PSA for
the retired employee concerned.
For the pension and promotion matters, another linked hindrance is pending Disciplinary
Proceedingcases. Hence, pending DisciplinaryProceedingsareto befinalizedatthe earliest. Principal
Secretary directed the Inquiring Officers to complete the inquiry and submit inquiry reports at the
earliest. He also suggested that while conducting the inquiries, priority should be given to the retired
employees. He expressed that since pension rule has been revised and the provisional pension will
not be continued after 5 months, all pension sanctioning authorities should ensure that no case is left
. beyond 6 months of retirementfor sanction of final pension, failing which the official concerned shall
be taken to task as the retired person shall be liable to be pa id his pension amount with 18% interest.
Additional Secretary (FE) informed that there are t4 cases pending with RD Department for
sanction of final pension in which pension papers have not been received.
Principal Secretary directed that it is the duty of the concerned PSA to collect the pension
papers of those retired persons and the concerned authorities should personally contact those
persons, collect the required papers and dispose allthe cases by end of 3fth Nov. Additional Secretary
(FE)to monitor the same.
Thereafter the meeting was held on the following agenda:
Financial Achievement
As per IFMS, the overall expenditure was 34.38% of the budget provision. As per decision taken in the
reviewmeeting held on 30.09.23,63.55% allotmenthas been givenagainstthe budget provision. In
WAMIS, the overall % of expenditure againstthe allotment was 44.87. However, 22 Divisions have
neither incurred expenditure of Rs.L5crore nor achieved 60% of allotment. Such Divisions are
Balasore-ll -L4.97 (34%1, Dhenkanal-l4.50 (49%1, Karanjia - 1"4.17 134%), Keonjhar- 13.65 (4L%1,
Deogarh- 12.96 (69%|, Bhadrak-ll- 12.88 (32%1, Nayagarh-ll- 12.58 (68%1, Kendrapara - 11.91 (30%1,
Jharsuguda-11.5O (33%), Kendrapara-ll- 11.40 (42%1, Dharmagarh-11.01 (M%1, Nuapada-10.10
(50%1, Kandhamal - 10.80 (32%1, Gajapati-10.69(42%1, Dhenkanal-ll-9.32(5O%l Jeypore-8.82 (38%1,
Khariar- 8.64 {33%1, Bhadrak-8.63(34%), Titilagarh-6.93 (32%1, Kalahandi-6.71{32%1, Samablpur-
5.35(42%1, Kuchinda - 3.52138%l
Principal Secretarv directed that allotment should be 70% of Budset provision bv end of
November. FA-cum-AS to monitor the same. Regarding expenditure against allotment, minimum 70%
of expenditure to be made and amount-wise it must be minimum of Rs.20 Crore bv end of
November'23.
Biiu Setu Yoiana {BSY}
The status of bridge projects under BSY taken up in different years i.e., prior to 2O2L-22, during
2A2I-22, 2022-23 & 2A23-24 were discussed.
A. Bridge proper completed without approach roads
The Chief Engineer, Building & Bridges explained that out of 92 bridges, where bridge proper
has been completed but approach roads not completed, 17 bridges have been completed during last
month & balance 75 are not completed. As per commitment of SEs/EEs, the Division-wise targets are
given below:
Name of R.W. Name of R.W. I TotalNo of Timeline for completion
Circle Division proiects November December Bevond Dec.
Balasore-l 2 2
Balasore-ll 1
a
I
Balasore I
Bhadrak-l I T
Jaleswar 2 t 1
Barioada Karaniia 2 I T
Ganiam-l 2 2
Ganiam-ll 5 5 1 1
Berhampur Mohana 1 L
Phulbani 2 2
Balieuda 3 5
Bhawanipatna 2
Kesinsa L t_
Bhawanipatna
Khariar 2 L 1
Nuapada 1 L
Puri o 3 2 L
Bhubaneswar Nimapara 2 2
Navasarh-l 1
f
Patna sa rh 1 t
Bolangir
Titilaearh 2 2
Cuttack-l 3 2 1
Cuttack Cuttack-ll 5 3 2
4
Japatsinshour 1 I
Kendra para-l 5 2 3
Kendrapara -
Jaipur-l 4 2 t
Jajpur
Jaj pur-l I 4 z 1 1.
a
Keonihar-l 7
Keonjhar
Keonihar-ll 1 1
Sundarearh Jharsusuda 2 2
Ravagada L 1
Gunuour 1 1
Jeypore 1 1
Sunabeda Malkansiri-l 3 3
Malkangiri-ll t 1
Nabaraneaour-l 1 1
Nabarangapur-ll 2 2
TOTAL 75 48 22 5
Principal Secretary directed concerned SEs/ EEs to take needful steps to complete the projects
in all respect within the timeline. All C.C.Es were instructed to closely monitor the above projects for
completion of the same by the above time line.
As on 30.09.2023 As on 31.10.2023
Total no. of Proiects aporoved 1332 L332
Dropped 16 16
Proiect taken up 1315 1315
Completed 1223 L224
tl Oneoine 92 91
lil Tender under process 1 1
Total 1316 1316
2nd time tender for the Bridge over Luna at 5th km on Belar-Nuagaon- Teragaon-Mahakalpada
road has been invited on EPC basis. Technical bid opened on 20.10.2023 & financial bid to be opened
on 10.11.2023.
The bridge projects sanctioned prior to 2027-22 was discussed and it was instructed to take
needful steps to complete the projects at the earliest.
There are 14 bridges continuing for more than 5 years. The District/ Division-wise breakup
along with committed date of c ts bel ow
Date of completion as
No. of
51. No. Name of the District Name of Division per commitment by
Bridges
SE/EE
7 Balasore-l 7 3L.03.2024
Balasore
2 Jaleswar 1 3L.L2.2023
3 Bhadrak Bhadrak-l L 31.L2.2023
4 Navaearh Navagarh-ll 1 30.11.2023
t- 37.12.2023
) Nimapara 2
2- 37.03.2024
Puri 1- 37.72.2023
6 Puri 3 2- 31.05.2024
3- 30.06.2024
7 Bolaneir Patnaga rh 1 Tender stage
8 Jajpur Jaipur-l 1 3t.L2.2023
9 Kendrapara Kendrapara-l L Tender Staee
11 Keonjhar Keonihar-ll 1 31.O3.2024
t2 Malkansiri Malkaneiri-l t 28.02.2024
Total t4
o lt was instructed to complete the bridges within the above timeline positively.
The following Circles and Divisions have highest nos. of slow-moving in that order
G| Slow-moving projects: (sanctioned prior to 2O2'J,-22 & during 2021,-22 taken together)
Circle wise
I Sl. No. Rural Works Circle No. of Slow-moving proiects
1. R.W. Circle, Bhubaneswar L7
2. R.W. Circle, Cuttack 1,0
3. R.W. Circle, Sunabeda 09
4. R.W. Circle, Baripada 08
5. R.W. Circle, Berhampur 08
6. R.W. Circle, Balasore 05
Division wise
I Sl. No. Rural Works Division No. of Slow-moving proiects
1. R.W. Division, Puri 12
2. R.W. Division, Baripada 5
3. R.W. Division, Bhanjanagar 5
4. R.W. Division, Kesinga 4
5. R.W. Division-|, Nayagarh 4
6. R.W. Division-|, Cuttack 4
The CCEs and SEs were instructed to sort out the issues forthwith and ensure that both physical
and financial target are achieved & the projects are completed by December 2023 positively.
H! Month-wise completion plan of bridges under BSY up to March'23:
Prior to 11 2 9 9 5 27 64
202L-22
202L-22 39 16 23 23 31 19 151
2022-23 0 1. z 4 7 2 16
Total 50 19 34 35 M 48 23r
Plan Roads
Review was taken on the following points.
7. Sf ow moving spillover ongoing projects targeted to be completed during 2023-24.
2. Tender /agreement status of projects sanctioned during ZOZZ-23.
3. New Project proposals for 2023-24
4. Pending PCR of completed road projects under RIDF -XX /XXVlll and status of
Reimbursement claim
Vf lll
MMSY- cMRt (rDrB) - zo2t-22
Total roads sanctioned -56
No. of spillover projects {2022-23l. .M
No. of projects completed during 2022-23 -27
No. of projects spillover to 2023-24 -L7
No. of projects completed by September -3
Balance ongoing projects - 14
A target for completion of 6 roads was fixed for month of October and 8 roads in November,
but no work was completed in October. Principalsecretaryinstructed that allthe 14 roads must be
completed during November.
lxl MMSY- cUVDA (Connecting Un-connected Villages in Difficult Areas)-2021-22
Total No. of projects sanctioned - 3g
No. of spillover projects (2022-231 - 15
No. of projects completed during 2022-23 - 10
No. of projects spillover to 2023-24 -5
No. of projects completed by September - NIL
Balance ongoing projects -5
It was targeted for completion of 1 road in October and 4 roads in Nov., but it was found that
no road was completed. Principal Secretary instructed to complete all 5 roads in November.
Month for
Mlonth MMSY MMSY MMS] RIDF TRIP lmpvt. Completion CMRL CUVDA Total
(Sanctioned (sanctioned in LWt (Newly to of rDrB)
prior to during area taken Existin5 incomplete
2021-22) 2021-22], up PR RD road &
roads) road bridses
\ov 2 40 3 3 30 L2 3 L4 5 II2
)ec 10 28 2 a
I 6 5 52
lan-24 80 2 82
:eb-24 1 L
\tlar-24 2 2
)uring
n24-25
fotal L4 L48 5 5 30 20 8 t4 5 249
Other
1.R|DF -XX/XXVlll and status of Reimbursement claim
2. DMF/OMBADC
3. Invoice verification of Bitumen on purchase from HPCL/IOCL.
4. Kalyan Mandap, Deposit Work of H&UD Department.
xxtv Road 93 93 93 0
2018-19 Bridge L7 1 3 13 13 0
xxv Road tu 2 L62 161 1
20L9-20 Bridge
xxvl Road
202U2t Bridge 63 15 48 38 10
Bridges
The superintending Engineers/ Executive Engineers
were instructed to submit the project completion
Report of all completed projects by 15.10.2023 positively
failing which action will be initiated against
the defaulting Divisional Engineers.
Tranche wise details discussed is as follows:
Tranche-XXttl
(i) outof14projects,onlyoneongoingprojectisexpectedtobecompletedwithinMarch
was instructed to monitor the progress properly
2024.ft
so as to complete it within March 2024.
(ii) The construction of Bridge over river Baitarani
uchabali-padampur via uttaraposi road has been
completed. EE to submit pCR by 05.11.2023 positively.
Tranche-XXIV
out of 17 sanctioned projects,3 proiectsare in progress, out
of which 1is expected to be completed
within March 2024 & balance 2 will go beyond March 2024.
The Finance Department may be
feqUgsted fOf extension Tranche-XXIV har,^-,r rr---L
eXtension of Trenrho-Yyn, March .^-,
2O24.
Sl. No. Name of Division Name of the projects Expected date of
completion
H.L. ondge over river Bheden Hirma to
T Jharsuguda
Malda Road 30.06.2024
Lonsrructron of H.L. Bridge over Indravati at
2 Nabarangpur-l 18th km on Kodinga Chirma Nadighat R.D
30.11.2023
road under BSy (Balance Work)
H.L. bridge over Tel nadi on Sandhimunda _
3 Nabarangpur-ll
Kharipokhana road 30.77.2024
Roads
There are 128 PCR pending i.e. Tranche-xxv-2,
xxvlt-43 and XXV|ll-74. The Division-wise
details as follows:
10
r28
Principal Secretary instructed to submit the balance PCRs without further delay.
Further, out of 251 of projects approved in 1*& znd HPc (lst HPc -74 + znd HPC-1771 tor
approvaf under RIDF in current financial Vear 2O23-24,t7t DPRs have been submitted to Govt. for
onward submission to NABARD & remaining 80 DPRs are to be submitted. The PrincipalSecretary
directed to submit the balance DPRs by 15th Nov.
Division wise 80 pending DPRs (MMSY -TRIP-22 & MMSY CMRI-581 to be submitted to NABARD
Govt.
No of DPRs pending for submission
sl.
Name of R.W Division MMSY.
No. MMSY-CMRL Total
TRIP
a
I Anandpur 4 4
2 Angul I 1
3 Balasore-ll 7 1
4 Baripada 2 2
5 Bhadrak-ll 1 I
6 Bhanjanagar 1 L
7 Bhubaneswar t2 L2
8 Boudh 2 2
9 Dhenknal 7 I
10 Dhenknal-ll 3 3
11 Gaiapati 2 1 3
72 Jaipur-ll 5 6
13 Jeypore 7 3 4
t4 Karaniia 1 1
15 Kendrapara-l 2 2
16 Keonjhar-l 3 2 5
t7 Kesinga 2 2
18 Khariar 2 2
19 Navagarh 1 1
20 Nayagarh-ll 2 2
27 Nimaoara 3 3
22 Nuapada 1 1'
23 Puri L t
24 Rairangpur 4 4
25 Rayagada 2 2
26 Sambalpur 4 4
27 Sonepur 4 4
28 Sundargarh 1 2 3
29 Sundargarh-ll 1 I
30 Umerkote 1 L
Total 22 58 80
DMF
Reoort of cEs WAMIS fieures
Total no. of proiects sanctioned 779 1014
11
Total no. of proiects Dropped 257 Nil
Total No. of oroiects Taken uo 454 7474
No. of oroiects comoleted 297 427
No. of proiects ongoing 90 587
No. of works vet to be started 5
It was seen that out of 1014 projects, 791 projects have been mapped by the Divisions. 223
projects are yet to be mapped. Keonjhar District (21), Angul District (721, Koraput (2), Rayagada
{12} Sundarearh (5} are the defaulting districts.
Principal Secretary instucted that the data should be updated in WAMIS and reconciled by
the Divisions by 15th Nov. and CEs are to monitor the same.
3. OMBADC
Report of CEs WAMIS fieures
Total no. of oroiects sanctioned 327 808
Total no. of oroiects Dropped 84 Nil
Total No. of proiects Taken up 243 808
No. of proiects completed t71. 304
No. of proiects ongoing 44 504
No. of works yet to be started 21
It is seen that the report given by CEs is not matching the figures of P&C Department and
the record entered in WAMIS.
Principal Secretary instructed that the data should be updated in WAMIS reconciled by the
Divisions and CEs are to monitor the same.
12
st. Committed date of Total no. Package No.
No. comoletion of Proiects
l. 30.11.2023 8 oR20197, OR19N201, OR25320, OR19LB 32,
oR25LB03, OR23273, OR25LB07 & OR27LB 22
2 3t.12.2023 7 oR20401, OR20400, OR30NBCC523, OR15LB 63,
oR17LB21, OR20LB22 & OR23LB-06
3 oR11267, ORt7478A, OR19N181, OR191225 &
3t.0t.2024 5
OR19LBN51A
4 o R11ADB74, OR24t48, OR20330, OR20287,
28.02.2424 11 o R20404(C), OR2O37, OR19N195, O R20LB-50,
oR20LB-51, OR20LB-52 & OR25LBN269
The Special Secretary also intimated that the completion of the work in 2 Packages (OR-11-
ADB74 & OR-20-404 {C)) has been delayed due to litigation in Hon'ble High Court.
Principalsecretary, R.D. expressed his displeasure over the delay in completion of PMGSY-I
& ll packages. The Principal Secretary reiterated that as the sunset date for completion of PMGSY-I
& ll works is March'2024, all the PlUs are to take necessary steps for completion of all the works by
Feb'2024 so thatthefinalbill can be cleared by March'24. The PlUs will be held responsiblefor non-
completion of the PMGSY-I& llworkswithin the date line. The PIU of Ganjam-ll& Malkangiri-lare
directed to contact the Govt. Advocate for early disposal of the litigation. The Principal Secretary
also directed that CEO, OSRRA to arrange a reyiew meeting with M/s NBCC officialsfor completion
of all incomplete PMGSY works awarded to M/s NBCC ttd. and pending NQM ATRs.
2023-24 r23
4 947 4331.10 r47 239 1346.33 18 708 2984.77
(Spill over)
13
The Special Secretary, R.D. intimated that the target fixed by Govt. of India is 2155 Km. but as
directed by Principal Secretary, RD the target has been fixed for 3200 Km. and accordingly a month
wise target has been communicated to allthe Divisions. The achievement for the month of Oct 2023
is 143.55 Km. against the target of \67.37 Krn. The achievement made during the year 2023-24 is
1-355.41 Km. Principal Secretary expressed his displeasure over the less achievement with respect
to the target and directed to expedite the progress so that the short fall can be compensated in the
month of Nov'23.
5. Payment stotus for maintenonce ol PMGSY works in E-marg and completion of Rl & PE,
ln the financial year 2023-24, as on 01.11.2023 an expenditure of Rs.61.85 Crore (42.58%) has
been made against the target of Rs.145.27 Crore. The percentage of Expenditure in R.W Divisionq
Raygada 113.43%1, Ganjam-ll(16.38%), Ganjam-l(16.59%), Purilt9.34%) and Kesinga(20.$tlo/ol are
miserable.
The percentage of achievement under Rls & PEs are 86.757o & 61.57% respectively in the
month of September-October-2023. The maximum no. of Rls missed by PlUs are R.W. Division
Balasore-ll,Angul, Baliguda, Nuapada and Bargarh. Maximum no. of PEs is pending with R.W. Division,
Mohana, Rairangpur, Bhadrak, Nayagarh-l and Ganjam-ll. Principalsecretary, R.D., directed that the
progress is still slow and instructed allthe PlUs to expedite the Expenditure and complete the Rls
& PEs for the month of September-October-2O23 immediately.
Periodical Maintenance
Status of 5 years Completed PMGSY Roads:
ln the financialyear 2023-24, the provision has been madefor periodical maintenance of 5
year completed PMGSY (POST DLP) for 7437 roads (Length-4442.91Km.)for an amount of Rs.635.64
Cr. The tender for 1363 projects has been invited out of which 1338 projects have been finalized. Out
of baf ance 25 nos., 22 are under court case and 3 are re-tendered. The agreement has been made for
85L projects and for balance 487 projects agreement to be completed within a week. Principal
Secretary, R.D., directed that allthe agreement should be completed within a week positively.
14
BDOs/DRDA/etc. and 134 are pending at field level. All field officers were directed to give utmost
imoportance to CM Jansunani and all pending grievances should be disposed of at the earliest.
2. Mo Sarkar
In was informed that during October, details of L224 visitors have been registered under Mo
Sarkar portal. Three Divisions like BBSR, Kalahandi, Malkangiri-l have not entered any visito/s
detail. Another twenty-two Divisions like Balasore (2), Kesinga (2), Nuapada (2! Jajpur-ll (2), Jajpur
(3), Dharmagarh (6), Khariar (6), Kuchinda (61, Balasore-ll(7), Bargarh (7), Sambalpur (8f, Ray4ada
(8), Cuttack-ll(10), Kendrapara-l{10), Nayagarh (11}, Dhenkanal(11}, Bhadrak-ll(111, Malkangiri{l
(111, Boudh (11), Bhadrak (121, Rairangpur (12), Puri (14) have entered less than 15 visitors' details
Total 7 feedback have been received from the visitors, where action is to be taken by the
Divisions. Out of this one has been addressed by the Nimapara Division. Action for restfollowing 6
ar.e to be taken by the Division : (i) Udayanath Jena-907881,4327- Security and withheld amount of
Rs.23,00,000 pending under PMGSY Package No.OR-17-212 - RW Division Keonjhar. (ii) Samrat Ku
Behera-7008744837- Billamounting to Rs.95 lakhs pending since 11 months- DegreeCollegeOlabhar.
RW Divn-ll, Kendrapara. Deviation pending in O/o ElC, Rural Works. (iii) Arupananda Dhala-
9777598827-EOT for the road i.eBanipanka to Chaliagadia pending in the O/o ElC, Rural Works-
Pending from July'23 (iv) Final Bill of Madhupura Vellora Boxcell bridge on Kanda Gaon Road is
pending for more than 6 months- Balasor Division- Aditya Prasad Das. (v) Final Bill for Model School
Building at Baharaposi, RW Division Deogarh pending for more than 5 yrs. - Buswajit Swain-
9658708542 (vi) Bill pending for construction of Multipurpose Cyclone Shelter. RW Division-ll,
Kendrapara - Basant Kumar Biswal-8328853125. Allthe above feedbacks should be attended with due
sincerity.
3. OSWAS
During, 1st to 30th October, all 80 line offices have started using OSWAS. During the period,
1568 files have been created, 5338 Daks have been diarized, 1437 Daks and 1959 files have been
processed by the Division/Circle offices. However, 18 offices have not used OSWAS and 16 offices
have not processed any file.
4. e-Despatch
Four Offices i.e. Dharmagarh, Karanjia, Mechanical Division BBSR, Electrical Division
Sambalpur have not used e-Despatch.
& any violation to this instruction will attract action against the defaulting officer.
4. The status of approved design ofthe bridges handed over to the Contractors will be an agenda
for discussion in the next review meeting.
5. There will be two project boards in each project, one at starting point and another at end
point.
6. Administrative Expenditure for Building repair work and status of final design/alignment given
to the agency will be added in the agenda for the next monthly review meeting'
7. FA-cum-AS to coordinate with Finance Deptt. and NABARD regarding submission of PCRs, DPRs
and related issues and write to FD/NABARD regarding extension of time for Tranche - XXlll
and Tranche - XlV.
15
8. Grievances received from CMO to be properly monitored and updated by E|C-cum-Special
Secretary, RD Department.
9. Land acquisition processshould startimmediatelyafteraccordanceof A/A. Delayinthe matter
will be viewed seriously.
10. Special Secretary will arrange a meeting with PCCF (Nodal), FE&CC Department for early
disposal of forest diversion/clearance cases.
11. Grievances received through CM Janasunani portal marked to the line offices should be replied
within 7 days with appropriate ATR in the portal.
t2. All Divisions must maintain the visitors' register and enter in WAMIS under Mo Sarkar Module.
13. All Divisions working projects under DMF/OMBADC mustenter the projects being executed in
WAMIS and map the same with the list of P&C Department uploaded in WAMIS.
The meeting ended with vote of thanks to the chair. A /
^","i;i:ffi