PART I.

General Requirements
A.1.1(8) Provision of Field Office for the Engineer (Rental Basis) mos. 5.00 124,133.81 620,669.05 0.4281% 33.33% 1.67 0.1427% 206,889.68
Provision of Furnitures/Fixtures, Equipment & Appliances for the Field
A.1.1(11) lot 1.00 515,686.50 515,686.50 0.3557% 80.00% 0.80 0.2845% 412,549.20
Office for the Engineer
A.1.4(1) Progress Photograph lot 1.00 26,167.05 26,167.05 0.0180% 33.33% 0.33 0.0060% 8,722.35
B.3 Permits and Clearances lot 1.00 150,000.00 150,000.00 0.1035% 100.00% 1.00 0.1035% 150,000.00
B.4(10) Miscellaneous survey and staking lot 1.00 80,644.29 80,644.29 0.0556% 58.33% 0.58 0.0324% 47,039.81
B.5 Project Billboard unit 1.00 17,649.24 17,649.24 0.0122% 100.00% 1.00 0.0122% 17,649.24
B.7 Health and Safety mos. 5.00 92,573.30 462,866.48 0.3192% 33.33% 1.67 0.1064% 154,288.83
B.9 Mobilization/Demobilization lot 1.00 426,951.29 426,951.29 0.2945% 50.00% 0.50 0.1472% 213,475.65
B.23 Staging Area lot 1.00 1,913,186.92 1,913,186.92 1.3195% 100.00% 1.00 1.3195% 1,913,186.92
PART II. EARTHWORKS
100(1) Clearing & Grubbing (with Stripping) sq.m. 97,950.85 30.93 3,029,828.35 2.0896% 95.00% 93,053.31 1.9851% 2,878,336.93
102(1) Roadway Excavation cu.m. 96,956.26 538.95 52,254,116.19 36.0386% 29.72% 28,816.02 10.7109% 15,530,257.60
104(1)a Embankment (from Borrow) cu.m. 17,224.81 734.33 12,648,613.47 8.7235% 65.15% 11,221.96 5.6834% 8,240,571.68
104(1)b Embankment from Roadway Excavation cu.m. 57,776.26 656.76 37,944,886.32 26.1699% 19.35% 11,180.25 5.0641% 7,342,692.57
107(1) Overhaul cu.m 39,180.34 402.92 15,786,685.03 10.8878% 35.50% 13,909.02 3.8652% 5,604,273.18
1010(2)b Backfill & Compaction(from Excavated Foundation) cu.m 1,196.26 461.02 551,498.22 0.3804% - 0.0000% -
803(1)a Structure Excavation cu.m. 1,481.66 622.81 922,799.28 0.6364% 95.00% 1,407.58 0.6046% 876,659.32
PART III. CONCRETE WORKS
804(4) Gravel Bedding cu.m 51.17 2,465.53 126,167.93 0.0870% 78.36% 40.10 0.0682% 98,867.72
900(1)c1 Structural Concrete cu.m. 383.39 9,617.93 3,687,450.85 2.5432% 40.17% 154.00 1.0215% 1,481,161.59
902(1)a Reinforcing Steel (Deformed) Grade 60 kgs 54,603.70 121.15 6,615,145.35 4.5623% 75.00% 40,952.78 3.4218% 4,961,359.02
903(2) Formworks and Falseworks sq.m 1,389.73 1,375.80 1,911,991.51 1.3187% 40.00% 555.89 0.5275% 764,796.60
PART IV. MASONRY WORKS
1046(2)a2 Masonry Works (CHB Non Load Bearing including Reinforcing Steel) sq.m 172.74 1,539.65 265,964.91 0.1834% - - 0.0000% -
1027(1) Cement Plaster Finish sq.m 1,832.68 501.99 919,989.70 0.6345% - 0.0000% -
PART V. STEEL WORKS
SPL1 Steel Fence lm 240.53 14,955.36 3,597,213.73 2.4809% - - 0.0000% -
PART VI. PAINTING WORKS
1032(1)c Painting Works (Steel) sq.m 565.95 916.13 518,484.83 0.3576% - 0.0000% -
TOTAL 144,994,656.30 100.00% 35.11% 50,902,777.89