Professional Documents
Culture Documents
Field Testing of Building Materials
Field Testing of Building Materials
Field Testing is conducted when certain materials or procedures are best done at the
building site.
Contents
Fine Aggregates
Course Aggregates
Cement
Concrete
Bricks
Concrete Blocks
Reinforcement
Tests for Fine Aggregates
Page 1
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Tabulation:
Bulking of Sand
Page 2
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Organic Matters
I – Stage:
Page 3
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
• Pycnometer + Water = W3
Page 4
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Page 5
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Page 6
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Conclusion:
1. For concrete used for wearing surfaces should not be more than 30%
2. For concrete used for other places should not be more than 45%
Page 7
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Bulk Density
Page 8
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Page 9
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Physical Observations
Consistency Test
Soundness Test
Manufacture date
Feel test
Float test
Air Permeability
The time taken for a fixed quantity of air to flow through compacted cement bed of specified
dimension and porosity
Page 10
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Sieve Analysis
Calculation:
Limits:
Consistency Test
Page 11
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
To find out water content required for making cement paste of standard consistency
Standard consistency is the water content of cement paste at which it gives optimum
workable plastic cement paste
The found water content is required for determining,
1. Initial setting time
2. Final setting time
3. Soundness
Procedure:
• 500 gm OPC
Procedure:
• 500 gm OPC
• Add 85% of water from consistency test
• Note the time of water mixing
• Use the plunger in the Vicat Apparatus
• Operate the instrument for every 15 to 5 min interval based on the result
• Note the time at which plunger does not make any impression or 0.5mm impression
from the top
Page 12
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Soundness Test
Procedure:
Procedure:
• Place in boiling water for 30 min & leave it for 3 hrs. reading (d 2)
Procedure:
• Water: (P/4 + 3) %
Page 13
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Compaction Factor
Slump Test
Flow Test
Hardened Concrete Tests:
Stage 1:
Page 14
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Compaction Factor =
Slump Test
Page 15
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Flow Test
Compressive Strength
Page 16
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Cube:
• Fill concrete in 4 layers with 25 strokes
Cylinder:
• Fill concrete in 3/4 layers with 25 strokes
• Keep it aside for 24 hrs
• Release moulds after 24 hrs & immerse it in water
• testing can be done at the age of 3, 7 & 28 days
Hardness test
Page 17
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Page 18
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
• The frog of brick is filled flush with 1:3 mortar and brick is stored under damp jute bags for 24
hours followed by immersion in clean water for three days.
• Load is applied axially at uniform rate till failure. Maximum load at failure divided by average area
of bed face gives compressive strength.
Efflorescence Test
• Brick is immersed in water for 24h. It is then taken out and allowed to dry in shade.
• Nil – No efflorescence
• Serious – Deposits are heavy and powder or flake away the surface
Page 19
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Water Absorption =
Physical Observations
Bend Test
Re-bend Test
Tensile Test
Physical Observation
Weighment Process
Page 20
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Sample: 1 No for each lot (25 M.Tones) length should be more than 0.5mts.
8 0.395
+/- 7mm
10 0.616
12 0.888
+/- 5mm
16 1.578
20 2.466
25 3.853 +/- 3 mm
32 6.313
Bend Test
• Sample bent to 180 Degrees without any transverse crack by mandrel specified
in below Table
Page 21
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Up to and
including 22 3Ø 4Ø 5Ø
mm
Over 22 4Ø 5Ø 6Ø
Re-Bend Test
• bent to an included angle of 135 degree using a mandrel of appropriate diameter &
aged by keeping in boiling water (100 degree) for 30 minutes and then allowed to
cool.
Page 22
Field tests on building materials
36th Batch 12 week Building Construction Supervision & Management
Fe415& Fe 550
Fe 500
<= 10 mm 5Ø 7Ø
Over 10mm 7Ø 8Ø
Tensile Test
Property Grade
Tensile Strength, Min 10% more than 8% more than 6% more than the
the actual 0.2% actual 0.2% actual
proof stress OR proof stress 0.2% proof
485 N/mm.sq OR 545 stress OR 585
whichever is N/mm.sq N/mm.sq.
higher whichever is whichever is
higher higher
Page 23