Professional Documents
Culture Documents
Chapter 2
Chapter 2
Chapter 2
I. PURPOSE
The purpose of this chapter is to describe the water network principles for use by designers
and engineers that are applicable for all properties where the potable water is supplied by
KM. As the principles are the same for KM internal staff and for outside consultants.
II. SCOPE
This chapter summarizes the design criteria for elements of the water system reservoir,
pumping system, and transmission/delivery system including:
■ Service area coverage,
■ Water demand projections,
■ Pipe network design and hydraulic modeling,
■ Typical piping configurations and valving requirements,
■ Reservoir and pumping station design criteria and
■ Safety and security.
This document also presents the current KM guiding principles for the provision of water
network design and a summary and checklist for the preparation of hydraulic network
analyses.
Any deviations from these standards/guidelines outlined in this document must be reviewed
and approved by KM.
Water distribution system infrastructure is generally considered to consist of the pipes, pumps,
valves, storage tanks, reservoirs, meters, fittings, and other hydraulic appurtenances that
connect treatment plants or well supplies to customer taps. The characteristics and typical
features of the basic infrastructure components in the potable water distribution system are
discussed in the following sections.
Design period that is too short must have larger or parallel pipes installed soon after the initial
installation. Conversely, design period that is too long results in excessive costs. Overdesigned
pipelines will have low velocities until the demand is sufficient to require larger flows. This will
result in higher maintenance costs for flushing to keep water quality within acceptable limits.
The ideal design period is based on historical data and projected future events. Experience
has shown the design periods given in Table V-1 typically within acceptable ranges and
therefore can be used. If information is available to justify variance from these values, consult
with KM for guidance.
Water use fluctuates hourly, daily, weekly, and between seasons. These variations are
expressed as ratios to the average day demand, called peaking factors. Flow demands are
estimated from values in Appendix A. The projected water demand or flows should be
presented in various development phase over the chosen design period.
Whole-life cycle costs shall also be used to determine planning horizons and appropriate
phasing of development, taking into account demand growth and changing operating
conditions. The prevailing acceptable discount rate as stipulated by Qatar should be used for
the whole-life cycle costing.
Pumping facilities should be designed for the period associated with full water system build-
out for a specific planned development unless another period is justified and approved by
KM.
A booster pump station (BPS) designed to draw water from a distribution system to supply a
separate high service area directly affects the supplying distribution system. The hydraulic
analysis should include a minimum 48 hour period of simulated operation during which the
peak projected 24 hour flow (PHD) is modeled.
When network analysis determines pumping is required to maintain system integrity, the
following principles should be incorporated into the network design:
■ Duty pumping configurations.
■ Type of drive (variable frequency or fixed speed).
A water system may include multiple pumps designed and operated to provide variable
design flows to its service area.
All pumps including fixed speed and variable speed pumps must be capable of supplying
output required (pressure and flows) to meet the level of service set by the local supply
requirements. The duty pump(s) must have adequate capacity to satisfy the flow and pressure
requirements of the water distribution system under all operational scenarios.
The pumping station peak design flow rate should be achieved with all duty pumps operating
at the design head condition. A minimum of two duty pumps should be provided in each pump
station. As a general guideline, the maximum capacity of any one pump should be limited to
approximately 1.0 m3/s unless this leads to an excessive number of pumps. Table V-2
provides general guidance for the required number of pumping units.
A branch system is comprised of successively smaller pipes that branch off larger pipes and
terminate at the customer’s service. The water can take only one pathway from the source to
the consumer. This type of system is most frequently used in remote areas accessed by only
one travel way.
A looped system consists of connected pipe loops throughout the area to be served and is
most common in municipal areas where travel ways intersect. Multiple paths exist that the
water can follow from the source to the consumer.
Looped systems are more reliable. Line breaks can be isolated without interruption of service
since an alternate flow path is available. Water flow will often reverse direction in the pipe
network because of varying demands. This helps reduce stagnation problems but can increase
transit time for water delivery. Another benefit resulting from multiple flow paths is the
increase in available flow for firefighting. Looped systems also often provide access to
multiple fire hydrants to enhance firefighting efforts.
Most systems are a combination of both looped and branched configurations. Looped systems
are encouraged and should be incorporated whenever possible. When dead-end lines are
unavoidable, flushing hydrants are to be provided at the end of all dead-end lines.
Pipe network design within a District Metered Area (DMA) or individual development should
loop pipes whenever possible and avoid dead-end lines. Connecting points between adjacent
DMAs should be analyzed as both open and closed connections to determine which scenario is
most beneficial for water flows and quality.
These types of hydrants not designed to provide CD required fire flows, such as flush valves,
standpipes, blow-offs, or nonstandard smaller volume hydrants without pumper ports, may be
placed on mains less than 150mm in diameter. Hydrant barrels should be sized to match the
connecting pipe.
Valves for fire hydrants are perpendicular to the water main and in line with the fire hydrant;
no offsets are allowed. Valves in the distribution system should be placed so that pipe sections
can be isolated such that no more than 2 fire hydrants are out of service at any one time in the
event of a main break. Place valves at the connection to the main for all fire services including
hydrants. Typical valving and pipe configurations are presented in the Standard Drawings.
Air inlet and discharge vents for valve chambers should be at least 0.5 m above finished
grade when possible. Vent opening should be downward facing with insect screen. Where it is
not practical to install an air vent above grade, the below-grade chamber must be rated for
appropriate traffic loading in traffic areas and the chamber must drain to daylight.
Hydraulic modeling must verify the need for the control valve function and location. Use of
control valves requires KM approval. This includes:
■ Pressure Reducing
■ Pressure Sustaining
■ Pressure/Surge Relief
■ Flow Control
■ Level Control
V.4.6 Flushing Valves
Install washouts or hydrants at low points and dead-ends using the design standards and
guidelines found in chapter “Main Laying Design Standards”. They should be designed to
achieve a minimum velocity of 0.40 m/s in the main for scouring purposes.
The design consultant prepares the final hydraulic calculations to verify that the final design is
in conformance with the KM standards and guidelines.
It should be emphasized that actual internal pipe diameter instead of nominal size should be
used during hydraulic modeling. Depending on the type of pipe to be used, there can be
marked difference in internal and nominal diameters even as the parameter diameter is a
very sensitive variable in the calculation of pipe frictional head losses.
Conversely, if a minimum velocity of 0.50 m/s is not regularly observed in the pipeline,
sediments can accumulate and tuberculation is likely to form. A minimum velocity of 0.50 m/s
is required to suspend solids and should be observed throughout the pipe network on a
regular basis.
Pipe velocities for both transmission and distribution mains should be within values provided in
Table V-3.
Critical points usually the farthest and highest points in the network are monitored for pressure.
As demand fluctuates, the discharge pressure and flow from each RPS is increased.
For critical customers such as hospitals, consider parallel mains to provide redundancy for
increased reliability of service should repair or maintenance require one main be shut down.
Parallel pipelines should also be considered for pipelines critical to system operation such as
distillate mains, rising mains, primary distribution mains, and reservoir inlets.
Training for water distribution system operators should emphasize issues related to the
mechanical aspects of water delivery (pumps and valves) and safety. System operators are
responsible for ensuring that the operation of the system does not cause degradation of water
quality.
The training should include an understanding of constituents that affect public health, such as
disinfectants, disinfection by-products (DBPs), and metals, and how distribution system
operations affect their concentrations. Distribution system operators should understand the
health related implications of water quality monitoring.
3. General: Determine Determine water demands and apply peaking factors to establish design
Flow Demands flow demand values.
Determine the required project network piping based on the service area
4. Pipe Network: map, customer locations and the design standards and guidelines including
associated fire hydrants and valving.
5a. System Planning:
Prepare the proposed network hydraulic model analysis. If the results of the
Determine
modeling efforts show that a pump station is necessary, proceed to Step 5b.
Requirements
Otherwise, proceed to Step 6.
Network
5b: RPS Planning: Prepare a preliminary RPS station design and the duty points identified in
Determine Pumping the hydraulic model. Provide storage facilities as required and incorporate
Requirement into the piping and pump station networks.
5c: Pump Planning:
Based on the results of the initial modeling, modify the design if needed
Refine Booster
and re-run the model with the revised pump data until a design is created
Pumping
which satisfies the requirements.
Requirement
5d. System Planning:
Determine Surge Perform a transient analysis of the network model to determine the extent
Protection of surge protection required.
Configuration
6. General: Determine
Determine based on each specific project needs which of the monitoring
required monitoring
devices are required.
requirements
Application of fire hydrant criteria should be discussed both with CD and
7. Fire Flow Simulation KM with respect to the specific requirements of the development projects
being designed.
8. Option Analysis & Perform network analysis by setting all criteria and necessary inputs.
Recommendation Consider all options and present recommendations.
9. Prepare Engineer’s
Prepare Engineer’s report.
report
Present the Engineer’s Report to KM for review and approval before
10. Seek KM approval
proceeding.
The KM system has several storage reservoirs coupled with pumping stations to provide
pressure to the distribution system. There are five storage volume components designers must
consider when sizing total storage volume:
1. Operational storage (OS)
2. Equalizing storage (ES)
3. Standby storage (SB)
4. Fire storage (FS)
5. Dead storage (DS)
Figure V-1 illustrates each of these components. Only effective storage volume, as defined in
Section V.5.4, can be used to determine the actual available, or design storage volume. In
KM context, the minimum effective storage volume should not be less than twice the projected
average day demand (ADD) derived at the design year.
If the project is to be phased and two or more storage reservoirs are ultimately required, the
initial or first phase storage reservoir shall include the capacity for the total project (all
Volume
Ground Level
1. ES sizing will require developing a peak day demand (PDD) diurnal curve for the
water distribution system demand. Diurnal demand varies due to water system size,
season, and type of demand (residential, commercial, industrial, and recreational).
After developing the PDD diurnal curve, the design engineer can calculate the required
This fire storage (FS) level depends on the maximum flow rate and duration requirements
needed in the supplying distribution system in accordance with KM fire hydrant guidelines.
The minimum FS volume for water systems served by single or multiple supply sources is the
product of the required flow rate (expressed in liters/min) multiplied by the flow duration
(expressed in minutes) as provided in Equation (4).
VII. RECORDS
Table VII-1provides details on the types of records that should be retained.