MOHAMED RISMIYA-Detailed Estimate (Ground & First FLOOR)
MOHAMED RISMIYA-Detailed Estimate (Ground & First FLOOR)
NAME OF THE
S.
OWNER : MRS.MOHAMED RISMIYA. DIMENSIONS QUANTITY
N DESCRIPTION OF ITEM NOS
L (M) B (M) D (M) (m3)
O
1 Earth Work Excavation In All Soils And Sub Soils 10 1.22 1.22 1.83 27.24
Add Extra 0.76
28.00
2 Sand Filling Using River Sand For Foundation
(A) Foundation For Column 10 1.22 1.22 0.15 2.23
Add Extra 0.77
3.00
(B) Basement Filling
Verandaha 1 4.16 1.83 1.2 9.14
Hall 1 4.16 4.36 1.2 21.77
Kitchen 1 2.75 2.40 1.2 7.92
Bed 1 2.75 2.50 1.2 8.25
Toilet 1 2.75 1.06 1.2 3.50
Add Extra 0.43
51.00
3 P.c.c 1:5:10 Using 40mm Jelly For Foundation
(A) Foundation column 10 1.22 1.22 0.15 2.23
(B) Basement same As Item No2(b) 51.00/1.20x0.10 4.25
Add Extra 0.52
7.00
R.C.C 1:2:4 With 20mm HBG Store Jelly Including
4 Well Curing Etc Complete
(A) Foundation And Basement
For Made Concrete 10 1.22 1.22 0.23 3.42
For Trapezoidal portion 1x10x0.302 3.02
For Column Raising 10 0.23 0.23 1.83 0.97
For Grade Beam In Main Wall Allround 1 28.96 0.23 0.3 2.00
Cross Wall 1 10.52 0.115 0.3 0.36
Add Extra 0.23
10.00
(B) Ground Floor Lintel
For Grade Beam In Main Wall Allround 1 28.96 0.23 0.3 2.00
Cross Wall 1 10.52 0.115 0.3 0.36
Column Raising 10 0.23 0.23 3.05 1.61
W-Window Sunshade 3 1.68 0.6 0.08 0.24
Roof Slab 1 7.6 6.88 0.12 6.27
Add Extra 0.51
11.00
(C) First Floor Lintel
Same As Item No:4(B) 11.00
Total 32.00
5
Brick Work In C:M 1:5 In All Floors With 2nd Class
Chamber Burnt Bricks Including Well Curing Etc Complete
(A) Foundation And Basement
In Main Wall Allround 1 28.96 0.23 1.2 7.99
Cross Wall 1 10.52 0.115 1.2 1.45
Add Extra 0.56
10.00
(B) Ground Floor
In Main Wall Allround 1 28.96 0.23 3.05 20.32
Cross Wall 1 10.52 0.115 3.05 3.69
Add Extra 0.99
25.00
Deduction (Ground Floor)
Column 10 0.23 0.23 3.05 1.61
M.D 2 1.2 0.23 2.1 1.16
Door & Open 2 0.9 0.23 2.1 0.87
Door - 1 1 0.76 0.23 2.1 0.37
Window 3 1.22 0.23 1.37 1.15
Ventilator 1 0.61 0.23 0.61 0.09
Add Extra 0.75
6.00
Total 29.00
(C) First Floor
Same As Item No:5(B) 25.00
Parapet Wall 1 28.96 0.23 0.76 5.06
Add Extra 0.94
31.00
Deduction (First Floor)
Column 10 0.23 0.23 3.05 1.61
M.D 2 1.2 0.23 2.1 1.16
Door 2 0.9 0.23 2.1 0.87
Door -1 1 0.76 0.23 2.1 0.37
Window 3 1.22 0.23 1.37 1.15
Ventilator 1 0.76 0.23 0.61 0.11
Add Extra 0.73
6.00
Total 25.00
Total 54.00
Special Celing Plastering In CM 1:3 / 10mm Thick
6 Ground Floor
(A) Ground Floor
Same As Item No: 2(B) 5.00/1.20 42.50
W-Window Sun Shade 3 1.68 0.6 3.02
Add Extra 0.48
46.00
(B) First Floor
Same As Item No: 6(A) 46.00
Total 92.01
7 Flooring With Granite In CM 1:5 12mm Thick
Including Polishing And Curing Etc Complete
(A) Ground Floor
Same As Item No: (2B) 51.00/1.20 42.50
Add Extra 0.50
43.00
(B) First Floor
Same As Item No: (7A) 43.00
Add Extra 1.00
Total 87.00
Plastering In CM 1:5/12mm Thick In All Floors Etc
8 Complete
Same As Item No: 5 54.00/0.23x2 469.57
Add Extra 0.43
470.00
Weathering course With Lime Mortar sat On Machine
Pressed Tiles In CM 1:3 Including Well Curing Etc
9 Complete
In Over Roof Slab 1 7.6 6.88 52.29
Add Extra 0.71
53.00
10 Supplying Door, Window And Labour Charges
Including Painting Etc Complete ( All Floor )
Ground Floor
M.D 2 1.2 2.1 5.04
Door 2 0.9 2.1 3.78
Door - 1 1 0.76 2.1 1.60
Window 3 1.22 1.37 5.01
Ventilator 1 0.61 0.61 0.37
Add Extra 0.20
16.00
First Floor
M.D 2 1.2 2.1 5.04
Door 2 0.9 2.1 3.78
Door -1 1 0.76 2.1 1.60
Window 3 1.22 1.37 5.01
Ventilator 1 0.76 0.61 0.46
Add Extra 0.11
16.00
Total 32.01
11 White Wash Two Coats
Same As Item No:6 92.01
Same As Item No:8 470.00
562.01
12 Color Washing Outer Same As Item No: 11 562.00x0.40% 224.80
Add Extra 0.20
225.00
13 Color Washing Inner Same As Item No: 11 562.00x0.60% 337.20
Add Extra 0.80
338.00
14 Provision For Staircase Arrangement LS LS
1 Earth Work Excavation In All Soils And Sub Soils 28.00 250.00 m3 7000.00
2 Sand Filling Using River Sand For Foundation
(A) Foundation 3.00 350.00 m3 1050.00
(B) Basement Filling 51.00 350.00 m3 17850.00
3 P.c.c 1:5:10 Using 40mm Jelly For Foundation 7.00 4500.00 m3 31500.00
R.C.C 1:2:4 With 20mm HBG Store Jelly Including
4 32.00 28000.00 m3 896000.00
Well Curing Etc Complete
Brick Work In C:M 1:5 In All Floors With 2nd Class
5 Chamber Burnt Bricks Including Well Curing Etc Comlete
54.00 4500.00 m3 243000.00
FINAL 602000.00
TOTAL 6020000.00
6020000