Professional Documents
Culture Documents
Electricity in Egypt 20201
Electricity in Egypt 20201
Electricity in Egypt 20201
Introduction
• The Egyptian Electricity Holding Company (EEHC) and its affiliated
companies are responsible – by law- to provide continuous and safe
supply of electricity to all types of consumers on economic bases and
according to international performance standards taking into
consideration all the environmental social, and economic determinants.
Primary Priority:
• Luxor 2250 MW Combined Cycle Power Project executed by Aqua Power
on BOO basis, scheduled to operate the 1st module of 750 MW in
December 2023 and the last module of 1500 MW in July 2024.
• Pump & Storage 2400 MW Power Project in Ataqa Mount, Suez,
executed on (EPC +Finance) basis with an initial cost of USD 2.7 billion.
As well, the final decision on the implementation of the above projects will be made after
reviewing the strategy prepared by TARES in light of the low prices of new and renewable
energies and the development of anticipated future loads.
The 9th Five-Year Plan (2022-2027):
Secondary Priority:
• In light of the low prices of new and renewable energies, coordination
has been made with the Emirati investor of the Oyoun Moussa (Coal)
Power Plant to replace the project with new and renewable energy
projects (wind + solar) with capacities of 750 MW in BOO basis.
• Final decision in respect of the execution of a thermal (6x1000) MW
coal-fired power plant in Hamrawein, the Red Sea, on “EPC + Finance”
basis, or part of it, will be made according to the development of future
loads.
• Power Purchase Agreements will be concluded between EETC and
investors for projects to be executed on BOO basis.
As well, the final decision on the implementation of the above projects will be made after
reviewing the strategy prepared by TARES in light of the low prices of new and renewable
energies and the development of anticipated future loads.
Electricity for 2018/2019
Electricity for 2018/2019
Electricity for 2017/2018
Peak load and installed capacity
Load Development
Load Development
Load Development
Load Development
• It is worth mentioning that the installed capacity cannot
be utilized in full due to the ageing of some generating
units, type & quality of fuel used, adverse impact of high
temperatures in Summer on some gaseous units and the
combined cycle units, dependence of hydro power plants
on the amount of irrigation discharged water defined by
the Ministry of Water Resources & Irrigation, as well as
the impact of nonuniformity of wind speed and solar
irradiance on the renewable energy.
Electric Power Production
• Electricity Production Companies:
• In 1967 the 2.1GW High Dam hydro power plants was commissioned,
followed by the commissioning of Aswan 2 power plant in 1985 and
in cooperation with the ministry of Water Research and Public Works;
Isna hydropower plant was commissioned in 1993 and Naga-Hamadi
in year 2008.
Objectives:
1. Management, operation and maintenance of electric power
transmission grids on Extra and High Voltages all over the
country, with the optimal economic usage of those grids.
2. Organization of the energy transmission on extra and high
voltage grids all over the country through the National
Dispatch Center and the Regional Control Centers.
3. Purchase of electric power produced from the power plants
according to the needs and selling it to the consumers on
the Extra and High voltages and to the Electricity
distribution Companies.
4. Co-ordination with the production and companies for
providing electric energy on the various voltages for all uses
with high efficiency.
Electric Power Transmission
Egyptian Electricity Transmission Company (EETC)
Objectives:
5. Co-operation with the Egyptian Electricity Holding
Company in preparing technical and economical studies to
meet the demand on electricity and its stability.
6. Implementation of electric power transmission projects on
Extra and High voltages approved by EEHC management
and in accordance with the time schedules.
7. Implementation of the interconnection projects approved
by EEHC Board of Directors, exchange of electric power
grids interconnected to the Egyptian Grid.
8. Carry out demand forecast for its direct customers as well
as financial and economic forecasts for the company.
Transmission Network Statistics
Transmission Network Statistics
Transmission Network Statistics
Transmission Network Statistics
Transmission Network Statistics
Energy Sold from Egyptian Electricity Transmission Company
International Electrical Interconnection
International Electrical Interconnection
International Electrical Interconnection
International Electrical Interconnection
1. The Egyptian / Saudi Electrical Interconnection Project:
• The project aims to exchange a capacity of 3000 MW between the two
countries through HVDC bipolar transmission technology on 500 kV
Badr Substation in the Arab Republic of Egypt and Medina & Tabuk
Substations in the Kingdom of Saudi Arabia with overhead lines totaling
1450 Km on both sides and a submarine cable of 16 Km crossing the
Aqaba Gulf and to that end.
• Coordination is underway with the Kingdom of Saudi Arabia to conclude
all contracts on the various packages of the Project for both sides by
30.5.2020.
International Electrical Interconnection
2. The Egyptian / Sudanese Electrical Interconnection Project:
• Completing implementation of the Egyptian / Sudanese connecting line
(220 kV with length of about 100 km), and the trial operation of a
capacity of 50 MW is expected to start by the end of this year.
• Completion of the full synchronous interconnection is planned to
transmit a capacity of 240 MW by the end of 2020 after installing the
ineffective power compensator devices for the Sudanese side power
stations.
International Electrical Interconnection
3. The Egyptian / Jordanian Electrical Interconnection Project:
• A study was prepared to raise the current capacity of the Egyptian /
Jordanian connection line to 2000 MW instead of 450 MW, which allows
a possibility for energy exportation to Lebanon, Syria and Iraq via
Jordan; and coordination is underway between the two sides to agree
on the optimal scenario to be executed.
International Electrical Interconnection
4. The Egyptian Electrical Interconnection with GCC Interconnection
Authority
• On 5.11.2019, a Memorandum of Understanding was signed by the Arab
Republic of Egypt with the Kingdom of Jordan on the one part and with
the GCC Interconnection Authority on the other part for interconnecting
the national grid of Egypt with the GCC grid through Jordan.
• The capacity of that interconnection will be determined upon completion
of preparing the technical studies that are being conducted at present
by one of the worldwide reputed consultant firms.
International Electrical Interconnection
5. The Egyptian / Libyan Electrical Interconnection Project:
• The construction of the 500 kV Burj Al-Arab / Marsa Matrouh
transmission line, double-circuit quadconductor, under progress with a
length of about 255 km. It will be operated temporarily with voltage of
220 kV, where it is used to support the Egyptian / Libyan
interconnection and be later powered at its full capacity by expanding
both of Burj Al-Arab and Marsa Matrouh substations up to 500 kV.
International Electrical Interconnection
6. The Egyptian / Cypriot Electrical Interconnection Project:
• A Framework Agreement has been signed with EuroAfrica
Interconnector Co. to transmit a capacity of 2000 MW from West
Burrullus region on the Mediterranean Sea in Egypt to Cyprus and from
there to Greece, thus providing a connection from the Egyptian grid to
the Pan-European electricity grid.
• The electrical interconnection will be implemented using High-voltage
direct current (HVDC) technology.
• A higher joint Steering Committee has been established between Egypt
and Cyprus, as well as a technical committee to implement the
recommendations made by the Steering Committee.
• The Project will be executed in two phases of 1000 MW each. The 1st
phase is scheduled to be completed in July 2021 and the 2nd phase in
July 2022.
International Electrical Interconnection
New & Renewable Energy
Considering the foregoing, the FIT projects (wind and solar) were
tendered in two phases:
A. First Phase
• On 17/09/2014, a Cabinet decree was issued for the First
Phase of the FIT projects.
• In October 2016, Power Purchase Agreements, for solar
cells (PV) with a total capacity of 12 MW, were signed with
6 qualified investors for capacities of more than 500 KW
8MW was connected to the distribution networks by end of
2018.
• In March 2017, the financial closure documents were
accepted for 3 investors in the field of solar energy (Elef,
Infinity, Fas) with a total capacity of 150 MW but Elef was
apologized for the project to become a total capacity of 100
MW.
New & Renewable Energy
Considering the foregoing, the FIT projects (wind and solar) were
tendered in two phases:
B. Second Phase
• On 6/09/2016, the Second Phase of the (FIT) program was
announced.
• Cost Sharing Agreements for Phase B of the (FIT) program
have been signed with 30 investors for solar projects as
well as full agreements for projects.
• On 29/10/2017, the international financing institutions
submitted letters confirming the achievement of financial
closure of (30) projects for electricity production from the
solar energy in Benban region with total capacities of 1365
MW so the total capacity of the two phases is 1465 MW
(almost finished).
Electric Power Distribution
Distribution Company
1. North Cairo Electricity Distribution Company
2. South Cairo Electricity Distribution Company
3. Alexandria Electricity Distribution Company
4. Canal Electricity Distribution Company
5. North Delta Electricity Distribution Company
6. South Delta Electricity Distribution Company
7. El-Behera Electricity Distribution Company
8. Middle Egypt Electricity Distribution Company
9. Upper Egypt Electricity Distribution Company
Electric Power Distribution
Objectives
1. Distributing and selling to customers on medium and low voltages,
electric power purchased from the Egyptian Electricity Transmission
Company and from the Egyptian Electricity production companies on
medium voltage, and also electric power purchased from industrial and
other IPP’s exceeding their needs, provided that the approval of EEHC
Board is obtained.
2. Managing, operating and maintaining medium and low voltage grids in
the company, incompliance with the dispatch centers instructions as to
fit for economic operation requisites.
3. Preparing forecast plan studies on loads and energy for customers of
the company and on economic and financial forecasts for the company.
4. Conducting studies, researches, designs, and implementing electric
projects for different purposes on the medium and low voltages, and
carrying out all associated works.
5. Managing, operating and maintaining isolated units.
Information about Distribution Companies
Information about Distribution Companies
Medium and Low Voltage Network in 2019
Medium and Low Voltage Network in 2019
Number of Customers in Distribution Companies
Energy Sold from Distribution Companies
Number of Customers in Distribution Companies (30-6-2019)
Number of Customers in Distribution Companies (30-6-2019)
Energy Sold from Distribution Companies (30-6-2019)
Energy Sold from Distribution Companies (30-6-2018)
Distribution Transformers Capacities
Distribution Lines and Cables
Smart Services
Smart Services
Smart Services
Smart Services
Development of Customers Services
Smart Meters
Smart Services
Development of Customers Services
Pre-Paid Meters
Smart Services
Improving Energy Efficiency and Rationalizing Consumption
Improving Energy Efficiency and Rationalizing Consumption
Improving Energy Efficiency and Rationalizing Consumption
Improving Energy Efficiency and Rationalizing Consumption
Improving Energy Efficiency and Rationalizing Consumption
Improving Energy Efficiency and Rationalizing Consumption
Improving Energy Efficiency and Rationalizing Consumption
Improving Energy Efficiency and Rationalizing Consumption
• The higher the demand, the greater the electricity generating capacity
required to supply that demand.
• It has a large no. of rate blocks, there are a total of 6 rate blocks.
• The tariff is designed and the charges are based on total monthly
electricity consumption (no charge for peak demand).
Next 150 kWh (201 to 350 kWh) LE 0.305 (45.75 L.E max)
Next 300 kWh (351 to 650 kWh) LE 0.405 (121.5 L.E max)
Next 350 kWh (651 to 1000 kWh) LE 0.71 (248.5 L.E max)
Next 150 kWh (201 to 350 kWh) LE 0.42 (63 L.E max)
Next 300 kWh (351 to 650 kWh) LE 0.55 (165 L.E max)
Next 350 kWh (650 to 1000 kWh) LE 0.95 (332.5 L.E max)
Next 150 kWh (201 to 350 kWh) LE 0.55 (82.5 L.E max)
Next 300 kWh (351 to 650 kWh) LE 0.75 (225 L.E max)
Next 350 kWh (650 to 1000 kWh) LE 1.25 (437.5 L.E max)
Next 150 kWh (201 to 350 kWh) LE 0.7 (105 L.E max)
Next 300 kWh (351 to 650 kWh) LE 0.9 (270 L.E max)
Next 350 kWh (650 to 1000 kWh) LE 1.35 (472.5 L.E max)
Next 150 kWh (201 to 350 kWh) LE 0.82 (123 L.E max)
Next 300 kWh (351 to 650 kWh) LE 1.00 (300 L.E max)
Next 350 kWh (650 to 1000 kWh) LE 1.40 (490 L.E max)
Next 150 kWh (201 to 350 kWh) LE 0.96 (144 L.E max)
Next 300 kWh (351 to 650 kWh) LE 1.18 (354 L.E max)
Next 150 kWh (201 to 350 kWh) LE 1.06 (159 L.E max)
Next 300 kWh (351 to 650 kWh) LE 1.28 (384 L.E max)
Next 150 kWh (201 to 350 kWh) LE 1.11 (166.5 L.E max)
Next 300 kWh (351 to 650 kWh) LE 1.31 (393 L.E max)
Next 150 kWh (201 to 350 kWh) LE 1.19 (166.5 L.E max)
Next 300 kWh (351 to 650 kWh) LE 1.35 (393 L.E max)
Next 150 kWh (201 to 350 kWh) LE 1.23 (184.5 L.E max)
Next 300 kWh (351 to 650 kWh) LE 1.36 (408 L.E max)
•تم افتراض 8ساعات استهالك للثالجات في اليوم نظرا الن التالجات معظمها تفصل عندما تصل لدرجة
التبريد المطلوبة لكن هذا في حاالت التالجات ذات الكفاءة العالية ( ) class Aبينما يزداد االستهالك كلما
قلت درجة ال class
متوسط استهالك االجهزة الكهربائية شهريا
Monthly Electricity Consumption اسم الجهاز
1500W * 0.5hour *30days = 22.5kwh ميكروييف
1500W * 1hour *30days = 45kwh فرن كهربي
550W * 3hour *30days = 49.5kwh مبرد مياه
70W * 10hour *30days = 21kwh مروحة
200W * 4hr * 30days = 24kwh ديب فريزر
2000W * 0.5hour *30days = 30kwh بويلر
1125W * 3hr * 30days = 101.25kwh تكييف 1.5حصان
1680W * 3hr * 30days = 151.875kwh تكييف 2.25حصان
•طبعا االرقام ديه بتختلف من جهاز لجهاز ومدة االستهالك تختلف من أسرة ألسرة وعدد األجهزة ايضا
تختلف واألهم من ده كفاءة األجهزة الن كفاءة الجهاز ممكن تقلل من االستهالك الي ما يقارب من 30او 40
%
متوسط استهالك االجهزة الكهربائية شهريا
Monthly Electricity Consumption اسم الجهاز
6W * 24hours * 30days = 4.32kwh الراوتر
10W * 6hours * 30days = 1.8kwh شاحن الموبايل
100W * 10hours * 30days = 30kwh الالبتوب
200W * 10hours * 30days = 60kwh الكومبيوتر المنزلي
1200W * 0.15hours * 30days = 5.4kwh المكواة
1500W * 0.15hours * 30days = 6.75kwh المكنسة
Table 2
Small industrial Electricity Tariff (less Than 500 kW}:
Private Sector industrial, Agricultural and land
Reclamation Customers
Annual Electricity Consumption
Table 3
Small industrial Electricity Tariff (less Than 500 kW}:
All Other Customers
• This tariff schedule is similar to the residential tariff structure.
Table 5
Large Industrial Customer (500 kW or more)
Motive Power Electricity Consumption Tariff
Impact of Contract Demand on Annual Consumption &
Demand Charges
• Both the demand charge and the consumption charge are
heavily dependent on the billing demand.
• The final element of the industrial tariff is the cost of the power
factor penalty.
• During the early part of 1990, e.g., the fuel adjustment charge was as
high as LE 0.10/kwh (nearly double the actual tariff charges for
consumption.
• This means that nearly two-thirds of the cost of electricity was the fuel
adjustment charge.
• Tariffs for industries in the Free Zone areas are quite simple; they are
made up of a demand charge and a flat rate consumption charge.
• Charges and rates are based primarily on voltage; note that they
increase significantly for lower-voltage supply .
• The contract demand times 0.9 is 7500 kW. This is higher than the
maximum recorded demand of 5200 kW.
• Hence, the annual demand charge is based on 7500 kW.
•The power factor penalty at 0.55 PF is LE 1,397,725 per year. This penalty
can be eliminated if the power factor is increased to 0.9 or above through
the installation of capacitors.
• At a 0.75 power factor, the penalty is computed as:
• The power factor penalty at 0.75 PF is LE 299,513 per year. This penalty
can be eliminated if the power factor is increased to 0.90 or above through
the installation of capacitors.
Sheet 1
7)
For the industrial user in the previous example, the contract
demand is 7500 kW. What would be the savings by renegotiating
the contract demand to 6500 kW? What would be the savings by
renegotiating the contract demand to 5400 kW?
Next 1,000 hr x 5,400 kW = 5,400 ,000 kWh @L.E 0.1207= L.E 651,780
Next 1,000 hr x 5,400 kW = 5,400 ,000 kWh @L.E 0.1037= L.E 559,980