Risk Management Procedure
Risk Management Procedure
SDN BHD
Registration No.: 200101016732 (552489-K)
Table of Content
1.0 OBJECTIVES.............................................................................................................................................3
2.0 SCOPE........................................................................................................................................................3
OSM ENGINEERING
SDN BHD
Registration No.: 200101016732 (552489-K)
List of Tables
Table 1: Likelihood of an occurrence (L).......................................................................................................5
Table 2: Severity cause by an occurrence.......................................................................................................5
Table 3: Risk Matrix........................................................................................................................................6
Table 4: Action Priority Indicator..................................................................................................................6
OSM ENGINEERING
SDN BHD
Registration No.: 200101016732 (552489-K)
1.0 OBJECTIVES
This procedure serves to ensure all safety risk assessment are conducted in a thorough,
formalized and well documented manner. This procedure are applied to all OSM
Engineering’s employees in all kind of work places.
2.0 SCOPE
Hazard identification
Risk assessment
Risk control and recovery
Risk assessment is the full process of estimation and evaluation the level of risk
associated with the identified hazard. The result of this assessment shall be reflected
for any decision making and determine control.
R=L x S
Where,
R-Risk
L-Likelihood
S- Severity
OSM ENGINEERING
SDN BHD
Registration No.: 200101016732 (552489-K)
Severity
Likelihood(L) 1 2 3 4 5
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
COMPANY OSM ENGINEERING SDN BHD LOCATION XXXXXX, KEM PGA DATE & TIME XXXX @ XXXX AM
ASSET GROUP ELECTRICAL WORK DESCRIPTION TO PERFORM ELECTRICAL MAINTENANCE WORK
CONDUCTED BY REVIEWED BY
NOTE
1. JHA Shall be applicable for all electrical maintenance work.
2. Personnel carrying out the work shall be fully familiar with the written Work/Operating Procedures develop for the job.
3. Prior to commencement of work, the task-specific JHA shall be discussed amongst all personnel involved in the execution; and requirements contained shall be fully understood and agreed by all involved
personnel.
Performing outdoor
3. Extreme hot weather Dehydrated Drink plenty of water 1 2 2 First Aid Team Leader
maintenance work
Falling object and Secure tools properly and check toolbox for
Housekeeping and secure Mishandling tools 3 2 6 First Aid Team Leader
hit personnel any sign of damage
tools, equipment and worksite
7.
must in good condition prior
Trip & Fall Aware on the surface to lean on ladder
to leave. Uneven surfaces 3 2 6 First Aid Team Leader
Bodily Injury Application of buddy system
OSM ENGINEERING
SDN BHD
Registration No.: 200101016732 (552489-K)
7.0 CONCLUSION