Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21 Sep '21
Complete 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27
1 MAIN MATRIAL ORDER PLAN ETA JAKARTA 236 days Sat 29/08/20 Tue 13/07/21 18% 18%
6 Generator Kato 4P9.2-3200 IP55 148 days Mon 21/12/20 Tue 13/07/21 13% 13%
7 Dokument for Fabrication 5 wks Mon 21/12/20 Fri 22/01/21 60% 60%
8 Fabrication Process 14 wks Mon 15/03/21 Fri 18/06/21 0% 0%
9 FAT on Workshop 2 days Mon 21/06/21 Tue 22/06/21 0% 8 0%
10 Packing & Preparation for Delivery 1 wk Wed 23/06/21 Tue 29/06/21 0% 9 0%
11 Delivery from USA Air Freight 1 wk Wed 30/06/21 Tue 06/07/21 0% 10 0%
12 Custom Clearence 1 wk Wed 07/07/21 Tue 13/07/21 0% 11 0%
13 Radiator QSK-95 120 days Sat 29/08/20 Tue 02/02/21 95% 95%
16 Deliver to Workshop 2 days Mon 01/02/21 Tue 02/02/21 0% 15 0%
17 LCP & UCP Panel 135 days Mon 02/11/20 Thu 29/04/21 31% 31%
19 Order Matrial & Fabrication 18 wks Mon 14/12/20 Thu 15/04/21 25% 18 25%
20 FAT Panel LCP & UCP / Simulation Test 1 wk Fri 16/04/21 Thu 22/04/21 0% 19 0%
21 Delivery from singapore 1 wk Fri 23/04/21 Thu 29/04/21 0% 20 0%
22 Spring Mounting 2 wks Mon 01/02/21 Fri 12/02/21 0% 0%
23 Junction Box Panel 14 wks Mon 01/02/21 Thu 06/05/21 0% 0%
25 Automatic Damper 35 days Mon 01/02/21 Thu 18/03/21 0% 0%
26 Fabrication 6 wks Mon 01/02/21 Thu 11/03/21 0% 0%
27 Delivery 1 wk Fri 12/03/21 Thu 18/03/21 0% 26 0%
28 Exhaust Muffler 4 wks Fri 26/02/21 Thu 25/03/21 0% 0%
29 Gas & Flame Detector 16 wks Mon 01/02/21 Thu 20/05/21 0% 0%
30 Level Glass & Level Trasmitter 14 wks Mon 01/02/21 Thu 06/05/21 0% 0%
31 Lighting Lamp 10 wks Mon 01/02/21 Thu 08/04/21 0% 0%
33 Water Mist 80 days Mon 01/02/21 Thu 20/05/21 0% 0%
34 Matrial Order Ready Jakarta 16 wks Mon 01/02/21 Thu 20/05/21 0% 0%
38 Skidbase & Fuel Tank Fabrication 109 days Thu 17/09/20 Mon 08/02/21 41% 41%
41 Leak Test Fuel Tank 3 days Thu 21/01/21 Mon 25/01/21 0% 40 0%
42 Painting 10 days Tue 26/01/21 Mon 08/02/21 0% 41 0%
43 Wall Fabrication 113 days Thu 17/09/20 Sat 13/02/21 62% 62%
45 Painting 2 wks Tue 19/01/21 Mon 01/02/21 0% 44 0%
46 Attenuator Fabrication 1 wk Tue 13/10/20 Tue 20/10/20 0%
47 Instaltion 2 wks Mon 01/02/21 Sat 13/02/21 0% 45;46 0%
48 INSTALATION 118 days Mon 15/02/21 Tue 27/07/21 0% 0%
49 Install Spring Mounting to Skidbase 2 days Mon 15/02/21 Tue 16/02/21 0% 42;22 0%
50 Install engine and Radiator 3 days Wed 17/02/21 Fri 19/02/21 0% 49;16;5 0%
51 Install Wall 2 wks Sat 20/02/21 Thu 04/03/21 0% 50 0%
52 Install Automatic Damper 6 days Fri 19/03/21 Fri 26/03/21 0% 51;27 0%
53 Install Wtaer Mist 6 days Fri 21/05/21 Fri 28/05/21 0% 34 0%
54 Install Junction Box Panel 6 days Fri 07/05/21 Fri 14/05/21 0% 51;23 0%
55 Install LCP 2 days Fri 30/04/21 Mon 03/05/21 0% 21 0%
56 Install Muffler 2 days Fri 26/03/21 Mon 29/03/21 0% 28;50 0%
57 Install Accessories Lain-lain 6 days Fri 21/05/21 Fri 28/05/21 0% 29;30;31;47 0%
58 Install Generator KATO 6 days Wed 14/07/21 Wed 21/07/21 0% 12;51 0%
59 Install Wall Sisi Generator 4 days Thu 22/07/21 Tue 27/07/21 0% 58;49;50;51;52;53;54;55;56;57 0%
60 Pulling Cable 3 wks Fri 05/03/21 Thu 25/03/21 0% 51 0%
61 Wirring 2 wks Fri 07/05/21 Thu 20/05/21 0% 21;23;60 0%
62 NGR 90 days Sat 20/02/21 Thu 24/06/21 0% 0%
63 Matrial Order 16 wks Sat 20/02/21 Thu 10/06/21 0% 0%
64 Deliver from Singapore 2 wks Fri 11/06/21 Thu 24/06/21 0% 63 0%
65 FAT EMERGENCY DIESEL GENERATOR PACKAGE 10 days Wed 28/07/21 Tue 10/08/21 0% 0%
66 Preparation for FAT 2 days Wed 28/07/21 Thu 29/07/21 0% 59;61;64 0%
67 Internal test EDG 2 days Fri 30/07/21 Mon 02/08/21 0% 66 0%
68 FAT EDG Package 4 days Tue 03/08/21 Fri 06/08/21 0% 67 0%
69 Closing Punch List 2 days Mon 09/08/21 Tue 10/08/21 0% 68 0%
70 READY FOR DELIVERY 2 days Wed 11/08/21 Thu 12/08/21 0% 0%
71 Packing & Wrapping 1 day Wed 11/08/21 Wed 11/08/21 0% 69 0%
72 Ready for Delivery (Ready in Cikarang) 1 day Thu 12/08/21 Thu 12/08/21 0% 71 0%
73 Delivery to Site 7 days Fri 13/08/21 Mon 23/08/21 0% 72 0%