The document provides a checklist for inspecting a building's fire protection systems. It lists items to verify such as the placement of exhaust pipes and pumps, ensuring valves and gauges are installed correctly, verifying the operation of jockey pumps and fire pumps, checking that all fire cabinets have the proper accessories, and ensuring extinguishers are placed in designated locations. The checklist also includes items like inspecting the fire panel, checking the water level in tanks, and verifying that emergency stops and signage are properly installed. Sign-off is provided by representatives of the contractor, project management consultant, and client.
The document provides a checklist for inspecting a building's fire protection systems. It lists items to verify such as the placement of exhaust pipes and pumps, ensuring valves and gauges are installed correctly, verifying the operation of jockey pumps and fire pumps, checking that all fire cabinets have the proper accessories, and ensuring extinguishers are placed in designated locations. The checklist also includes items like inspecting the fire panel, checking the water level in tanks, and verifying that emergency stops and signage are properly installed. Sign-off is provided by representatives of the contractor, project management consultant, and client.
The document provides a checklist for inspecting a building's fire protection systems. It lists items to verify such as the placement of exhaust pipes and pumps, ensuring valves and gauges are installed correctly, verifying the operation of jockey pumps and fire pumps, checking that all fire cabinets have the proper accessories, and ensuring extinguishers are placed in designated locations. The checklist also includes items like inspecting the fire panel, checking the water level in tanks, and verifying that emergency stops and signage are properly installed. Sign-off is provided by representatives of the contractor, project management consultant, and client.
Exhaust pipe of the diesel engine shall be placed at a good height in
ambience at the out side of the building.
Pumps clean and free of debris
Pressure/Temperature gauges installed Associated valve tags and labeling in place Flow switch shall be provided on the branch pipe of the sprinkler to give indication of bursting of sprinkler bulb.
Verify flow switches installed in correct direction for flow
On detection of bursting of the sprinkler, for quick draining and recovery of fire water, proper drain valve /piping arrangement shall be provided. Air purging valves shall be provided at the highest location of the header lines of the Hydrant and sprinkler systems.
There shall be two independent Jockey pumps for the Hydrant and sprinkler systems.
Check the starting and stopping of pumps wrt set pressure
Verify operation of jockey pumps Verify operation of fire pumps Witness flow/capacity test of fire pump including flow, pressure, speed and amperage readings for combinations of 1,2,3&4 hoses. All the fire cabinets to be checked with accessories check list All the pressure switch calibration report to be submitted All the pumps to be checked for the normal operation Fire water tank to be checked for the water level and overflow mechanism Fire pump pit and pump arrangement to be checked and to be on auto Water transducer panel in the sprinkler system to be functional
Extinguisher of appropriate type to be placed in all the designated location
All the floor isolation valves to be checked for open position
Fire panel inspection to be done as per the panel check list in the electrical check list
Functionality of the mechanical alarm in the installation valve to be checked
Height of the water through from the nozzle at the ground level to be checked.
Starting of the fire DG pump to be checked at the designated pressure.
Emergency stop of the DG is located by the vicinity of the DG Pressure drop of the system to be noted as per time Fire brigade hydrant points to be checked and the connection to be checked for the fire tank and to the system directly
Fire Cabinet keys to handed over
Fire safety sinages to be placed all strategic locations