Professional Documents
Culture Documents
1 Air System Balancing 2023 0823
1 Air System Balancing 2023 0823
Faculty of Engineering
M.Sc.(Eng) in Building Services Engineering
MEBS 6013 Testing & Commissioning
1
K.F. Chan (Mr.) MEBS6013
2
K.F. Chan (Mr.) MEBS6013
3
K.F. Chan (Mr.) MEBS6013
5
K.F. Chan (Mr.) MEBS6013
(I) Principle
The balancing procedure consists of setting the
correct proportional air flow at each branch and
sub-branch without regard to the absolute value.
6
K.F. Chan (Mr.) MEBS6013
Measured flow
%DFR = x100%
Design flow
7
K.F. Chan (Mr.) MEBS6013
8
K.F. Chan (Mr.) MEBS6013
9
K.F. Chan (Mr.) MEBS6013
10
Pre-requisite
❖Ductwork
should have
been properly
leakage tested,
and within
acceptable
leakage limit
(not leak proof).
11
Pre-requisite
❖Air ducts usually need not be cleaned so that the
dirt condition will not be drastically different from the
operational status. However, if dirty air blown out into
space can be a problem, it should then be cleaned
before balancing or be provided with temporary
filtering at air outlets. (If contract requires cleaning of
air ducts before handover, it should be done before
balancing work is carried out)
12
K.F. Chan (Mr.) MEBS6013
12
13
Pre-requisite (Cont’d)
14
K.F. Chan (Mr.) MEBS6013
14
Preliminaries
(2). Walk around the system checking that air
is flowing from each supply terminal or
being extracted from each extract point.
Check fire dampers and
position/temperature control for
completeness of installation before
starting fans.
15
K.F. Chan (Mr.) MEBS6013
15
Preliminaries (Cont’d)
16
K.F. Chan (Mr.) MEBS6013
16
Preliminaries (Cont’d)
(4). Measure the total fan flow rate and
the fan pressure rise after checking
the fan speed. The fan should be
delivering at least 110% of the
design value. If less than this,
open the main damper whilst
ensuring that the design full load
current is not exceeded. If fan flow rate at
this stage is less than the design value, this
indicates a problem with the equipment
installation or the design – this cannot be
solved by balancing alone. 17
K.F. Chan (Mr.) MEBS6013
17
18
K.F. Chan (Mr.) MEBS6013
18
19
K.F. Chan (Mr.) MEBS6013
19
(8). Check the total flow rates in the main branches again
and adjust if necessary to make the most remote (A)
the least favoured.
(9). Sum the main branch flow rates to check that the total
flow rate in the system is not less than 110% of
design. If the total flow has dropped below 110% of
design, adjust the main damper accordingly or
increase the fan speed.
20
K.F. Chan (Mr.) MEBS6013
20
21
Balancing Terminals
(10). Start with the most remote branch and then
sub-branch, i.e. A5 in the above figure.
22
K.F. Chan (Mr.) MEBS6013
22
23
K.F. Chan (Mr.) MEBS6013
23
24
K.F. Chan (Mr.) MEBS6013
24
25
K.F. Chan (Mr.) MEBS6013
25
26
K.F. Chan (Mr.) MEBS6013
26
Balancing Sub-branches
27
K.F. Chan (Mr.) MEBS6013
27
28
K.F. Chan (Mr.) MEBS6013
28
29
K.F. Chan (Mr.) MEBS6013
29
30
K.F. Chan (Mr.) MEBS6013
30
31
K.F. Chan (Mr.) MEBS6013
31
Final Correlation
(17). When the entire duct network is balanced,
measure the total flow in the main duct. If the
flow is higher than the design value, adjust
the main damper.
If the flow is less than the design rating, open
the damper, making sure that the maximum
permissible fan motor current is not exceeded.
If the flow rate is still too low after the damper
has been fully opened, this indicates a fault in
the installation of equipment or the design.
32
K.F. Chan (Mr.) MEBS6013
32
33
34
K.F. Chan (Mr.) MEBS6013
34
35
K.F. Chan (Mr.) MEBS6013
35
(V). Reporting
During construction, it is recommended that formal
reports relating to commissioning are produced
at four key control points.
1)System design is commissionable report;
2)Post installation report;
3)System cleanliness report;
4)System commissionable report
A prime purpose of these reports is to form
“bridges” over the boundaries of responsibilities
between the parties involved.
36
K.F. Chan (Mr.) MEBS6013
36
Documentation
An essential part of each report will be the completed pro forma
checklists utilized as aide-memories for both implementation and
supervision.
Potential disputes will be minimized substantially if reporting forms,
including the use of pro-formas, can be agreed as early as possible.
At the most vulnerable points of potential failure in communication –
i.e. at the design/installation, design/commissioning,
installation/commissioning interfaces – the same pro forma may be
used advantageously by each party for their own requirements within
the same common objective. For example, a design information
checklist may be used :-
•By the designer, to help him complete his tasks
•By the installer, to help satisfy himself that sufficient information is
available to proceed with procurement and installation.
•By the commissioning engineer, to help satisfy himself that the design
is commissionable
•By the head contractor, as a control tool and an important supportive
addendum to the “system design is commissionable” report.
37
K.F. Chan (Mr.) MEBS6013
37
38
39
40
41
42
Preliminaries
1.Determine the required maximum air volume
to be delivered by the supply and return air
fans.
2.If speed control is used, find out the
maximum and minimum allowable speed.
3.Find out the minimum and maximum
operating pressures of the VAV boxes.
43
K.F. Chan (Mr.) MEBS6013
43
Diversity
If a diversity factor has been incorporated into
the system design, this has to be taken into
account in setting up the supply system so that
the fan can be tested at its maximum duty.
This requires that some of the terminal units
need to be closed or set at their minimum flow
rate so that the system is set up for the design
maximum volume flow rate. If there is no
diversity factor, then the test of maximum fan
duty will be made with all the VAV terminal
units set for maximum flow rate.
44
K.F. Chan (Mr.) MEBS6013
44
Diversity (Cont’d)
Where there is a diversity factor, the designer shall specify
how this will be applied. The setting of this diversity pattern
should take into account the following practical factors :-
•The pattern of terminal units set at minimum flow (or closed)
should represent the thermal loading of the air conditioning
system at the peak cooling time;
•It is simpler to set all terminal units on a floor or zone to a
minimum or to shut off an entire branch duct, than to have a
random pattern of reduced settings
•The most searching test for the supply fan and system
performance will normally be if the terminal units closest to
the supply fan are reduced in capacity forcing the maximum
volume flow rates to the most distant terminals. These most
distant terminal units will then have the least static pressure
available for their operation. 45
K.F. Chan (Mr.) MEBS6013
45
Diversity (Cont’d)
Setting the fan duty above its specified duty
means that with limited duct leakage the
required maximum flow rate can be delivered
to the terminals.
46
K.F. Chan (Mr.) MEBS6013
46
47
K.F. Chan (Mr.) MEBS6013
47
48
49
K.F. Chan (Mr.) MEBS6013
49
10.
•Proportion the outlets.
•Verify design volume with the
VAV box on maximum flow.
•Verify minimum flow setting.
50
K.F. Chan (Mr.) MEBS6013
50
51
K.F. Chan (Mr.) MEBS6013
51
52
K.F. Chan (Mr.) MEBS6013
52
53
K.F. Chan (Mr.) MEBS6013
53