NCRTC Contract No: Package XIX/ Lot 1 Part 2: Employer’s Requirements

Section-6B: Particular Specifications Appendix E

Part-2, Section-6B
APPENDIX E
SCHEDULE OF KEY DATES AND COMPLETION DATES
All number refer to days from Commencement Dates of the works

Key Dates for Lot-1: Sarai Kale Khan – Duhai (EPE)


Tentative Date: D is considered asJune’2020
Stage-1: Stage-3:
Sahibabad - Duhai Sarai Kale Khan-
KEY (EPE) including Sahibabad
Description
DATES depot including Jungpura
RSS Traction RSS Traction
Preliminary Design Submission for D+90 D+90 D+90 D+90
KD-1
RSS
Civil Works
Layout Plan
EHV Cable Route
Submission of Preliminary Simulation D+90 D+90 D+90 D+90
KD-2
Study
KD-3 Submission of Final Simulation Study D+120 D+120 D+120 D+120
KD-4 Detailed Design Submission D+150 D+150 D+210 D+210
Earthing Grid at RSS and OHE
HV / EHV Cable, RSS Equipment
Earthing & Bonding
Traction Equipment
ASS at Stations
Submission of Detail Engineering D+180 D+180 D+270 D+270
KD-5
proposals to Engineer for Approval
Technical proposals of major
equipment
Working /Manufacturer’s Drawings
KD-6 Delivery of Major Equipment to Site D+365 D+365 D+850 D+850
Execution of works of RSS, OHE & D+485 D+530 D+1050 D+530
KD-7
ASS
EHV cable laying X X
RSS cum TSS cum AMS X X
Traction Equipment
ASS at Stations
Testing & Commissioning of RSS cum D+500 X D+1100 X
KD-8
TSS cum AMS
D+520 Depot D+1125 D+1155
D+ 550
KD-9 Energisation
Main Line
D+595
Submission of Report by Independent D+625 D+625 D+1185 D+1185
Agency for Verification (Auditing) of
KD-10
design and Detail Engineering
including ROCS
KD-11 Testing & Commissioning of ASS D+530 D+530 D+1100 D+1125
Testing and Commissioning of D+530
KD-12
Traction Equipment
KD-13 Integrated Testing & Commissioning D+560 D+560 D+1185 D+1185

Appendix 1 of 3 Revision-1
NCRTC Contract No: Package XIX/ Lot 1 Part 2: Employer’s Requirements
Section-6B: Particular Specifications Appendix E

KD-14 Commissioning of SCADA System D+500 D+560 D+1185 D+1185


Integrated Testing & Commissioning D+575 D+575 D+1200 D+1200
KD-15 (All Systems) with SCADA System (in
days)
Integrated Testing & Commissioning 01.10.22 to 29.12.22 30.01.24 to 28.04.24
(All Systems) with SCADA System (by
Date)
Trial Run 21.12.22 to 30.03.23 29.04.24 to 31.05.2024
KD-16 Taking over of the system March’2023 May’2024
Revenue Opening Date (ROD) March’2023 May’2024

1. Notes on Key Dates:


A. The achievement of a Key Date shall be subject to the issuing of a notice of no
objection from the Employer’s Representative
B. The achievement of a Key Date shall require completion of all the works specified for
achievement of the Key Date.
C. The achievement of Key Dates shall be read in conjunction with the Interface
Specifications to establish access requirements for Interfacing Contractors.
D. The access and order for completion of the Works shall be coordinated among the
Interfacing Contractors in the development of the Track Related Installation
Programme (TRIP) and Coordinated Installation Programme (CIP).
E. RRTS project comprises of four stages of ROD for complete section of Lot-1&2.

2. ACHIEVEMENT OF COMPLETION

A. KD-9: Submission of Report by Independent Agency for Verification (Auditing) of


design and installation of ROCS
Achievement: After completion of required verification of Design and Detailed
Engineering including the ROCS, the submission of final report by Independent
Agency for Validation.

B. KD 8: Commissioning of RSS-cum-AMS cum TSS


Achievement: Commissioning of Receiving Substation cum Traction Substation after
completion of construction of the substation building, installation of transformers,
installation of all necessary equipment, final finishes and testing in accordance with
the Specification. Completion of cable trough, HT cable laying and connection between
GSS and RSS-cum-TSS, and other associated civil works of the compound.

Appendix 2 of 3 Revision-1
NCRTC Contract No: Package XIX/ Lot 1 Part 2: Employer’s Requirements
Section-6B: Particular Specifications Appendix E

C. KD-10: Commissioning of ASS and power on


Achievement: Commissioning of ASS after completing installation of all equipment and
testing for ASS. Completion of laying 33kV cables, their terminations and connections,
and all other works required to permit power on up to the auxiliary transformer of ASS.
D. KD-11: Commissioning of Traction Equipment
Achievement: Energising 25kV traction on overhead equipment after completing all
OHE installation, earthing and bonding, buried earth cables, safety works and all other
connected works and testing for tracks.

E. KD-13: Commissioning of SCADA System


Achievement: Commissioning of SCADA system after installation of all Control and
Monitoring Equipments at OCC & BCC and performing all the Acceptance tests.

F. KD-14: Completion of Integrated Testing and Commissioning for Revenue Service


Achievement: Completion of integrated testing and commissioning prior to Service
Trial

G. KD-15: Taking Over of the system


Achievement: Satisfactory completion of all the Works and Service Trial and taking
over for Revenue Service.

Appendix 3 of 3 Revision-1