ID Task Task Name Duration Start Finish August January

Mode M T W T F S S M T W T F S S M T W
1 Implantação de Sinalização 145 days? Mon 10/07/23 Fri 26/01/24

2 Analise Preliminar de campo 37 days Mon 10/07/23 Tue 29/08/23

3 Projeto 43 days Mon 10/07/23 Wed 06/09/23

4 Implantação de Placas Doutor 30 days Mon 11/09/23 Fri 20/10/23

5 Implantação de Placas Campo Grande 36 days Mon 23/10/23 Mon 11/12/23

6 Implantação de Placas Dicão Leste 34 days Tue 12/12/23 Fri 26/01/24

10

11

12

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Thu 21/09/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish August January
Mode M T W T F S S M T W T F S S M T W
13

14

15

16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Thu 21/09/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2