6.1.1 Analiza Cijene
6.1.1 Analiza Cijene
6.1.1 Analiza Cijene
faktor 3
€/m2 0,84
ZEMLJANI RADOVI
GA 2 SKIDANJE HUMUSA DOZEROM m2
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
faktor 3
€/m2 2,53
ZEMLJANI RADOVI
GA 3 STROJNI ŠIROKI ISKOP U ZEMLJI I. KATEGORIJE m3
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
faktor 3
€/m3 5,55
ZEMLJANI RADOVI
GA 4 ISKOP TRAKASTIH TEMELJA I TEMELJA SAMACA m3
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
faktor 3
€/m3 5,96
ZEMLJANI RADOVI
GA 5 NASIPAVANJE TAMPONSKOG SLOJA ŠLJUNKA d=15 cm m3
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
Šljunak m³ 1 20 20,00
20,00 0,58 4,18
faktor 3
€/m3 25,93
ZEMLJANI RADOVI
GA 6 RAZASTIRANJE, PLANIRANJE I NABIJANJE TAMPONSKOG SLOJA ŠLJUNKA/ISKOPA m2
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
Vibrovaljak 49,88
m3/h h 0,02 30 0,60
3
Dozer 19,90 m /h h 0,0502513 50 2,51
faktor 3
ZEMLJANI RADOVI
GA 7 ZATRPAVANJE TEMELJA I VANJSKIH PODRUMSKIH ZIDOVA MATERIJALOM IZ ISKOPA m3
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
Vibrovaljak 49,88
m3/h h 0,0200481 30 0,601
Bager 50,48 m3/h h 0,0198098 50 0,990
Kamion 11,97 m3/h h 0,0835422 50 4,177
faktor 3
€/m3 8,24
ZEMLJANI RADOVI
GA 8 IZRADA SLOJA UVALJANOG ŠLJUNKA NA RAVNOM KROVU m3
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
proračun Šljunak m3 1 20 20
Toranjska dizalica
3,43 m3/h h 0,29 20 5,83
20 1,45772595 5,83
faktor 3
€/m3 70,20
ZEMLJANI RADOVI
GA 9 TRANSPORT VIŠKA ZEMLJE IZ ISKOPA NA DEPONIJU m3
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
Utovarivač 50,48
0,99
m3/h h 0,0198 50
Kamion kiper 11,97
4,18
m3/h h 0,0835 50
faktor 3
€/m3 15,92
ZIDARSKI RADOVI
PA 1 SPRAVLJANJE PRODUŽNOG MORTA 1:2:6 m3
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA MATERIJAL RAD STROJ
R II h 0,55 5 2,75
R II h 1,88 5 9,40
R II h 0,21 5 1,05
faktor 0
€/m3 67,76
ZIDARSKI RADOVI
PA 2 DOVOZ MATERIJALA ZA IZRADU MORTA m3
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA MATERIJAL RAD STROJ
faktor 0
€/m3 13,23
ZIDARSKI RADOVI
GA 10 ZIDANJE PARAPETNIH ZIDOVA D=30cm PRODUŽENIM MORTOM 1:2:6 m3
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
Blok opeka
35x20x20 kom 72 0,8 57,60
faktor 3
€/m3 246,45
ZIDARSKI RADOVI
GA 11 ZIDANJE ZIDA OKO OKNA LIFTA D=12cm PRODUŽENIM MORTOM 1:2:6 m2
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
faktor 3
€/m2 57,92
ZIDARSKI RADOVI
GA 12 ZIDANJE ZIDA ZA ZAŠTITU VERTIKALNE HI D=6cm PRODUŽENIM MORTOM 1:2:6 m2
faktor 3
€/m2 42,28
TESARSKI RADOVI
PA 3 DOVOZ OPLATE IZ CENTRALNOG POGONA m3
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
faktor 3
€/m3 34,62
TESARSKI RADOVI
GA 13 OPLATA TRAKASTIH TEMELJA, AB ZIDOVA - 24 mm m2
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
faktor 3
€/m2 22,39
TESARSKI RADOVI
GA 14 OPLATA TEMELJA SAMACA, STUPOVA, SERKLAŽA, GREDA - 24mm m2
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
faktor 3
€/m2 29,44
TESARSKI RADOVI
GA 15 OPLATA RAVNE AB PLOČE I KOSE PRILAZNE RAMPE - 24 mm m2
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
Čišćenje i vađenje
R II 0,14 5 0,70
čavala
faktor 3
€/m2 19,67
BETONSKI RADOVI
GA 16 BETONIRANJE PODLOŽNOG I PADNOG BETONA -C12/15 m3
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
faktor 3
€/m3 82,41
BETONSKI RADOVI
GA 17 BETONIRANJE TEMELJA, ZIDOVA I RAMPE- C25/30 m3
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
faktor 3
€/m3 99,86
Ugradba BV 1 7 7,00
B III 1 6,00 6,00
R II 0,15 5 0,75
faktor 3
€/m3 119,64
ARMIRAČKI RADOVI
PA 4 DOVOZ ARMATURE IZ CENTRALNOG POGONA t
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
faktor 3
€/t 0,53
ARMIRAČKI RADOVI
GA 19 ARMIRANJE 4- 12 mm, SREDNJE SLOŽENA t
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
Postavljanje i
A IV (h) 11 6 66,00
vezivanje
A III (h) 11 6 66,00
faktor 3
€/kg 1,13
ARMIRAČKI RADOVI
GA 20 ARMIRANJE 14mm>, SREDNJE SLOŽENA t
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
Postavljanje i
6
vezivanje A IV 11 66,00
A III 11 6 66,00
faktor 3
€/kg 1,13
IZOLATERSKI RADOVI
GA 21 POSTAVLJANJE HORIZONTALNE HIDROIZOLACIJE PODRUMA I KROVA m2
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
RV h 0,0597 7 0,42
R III h 0,0594 6 0,36
RII h 0,0088 5 0,04
faktor 3
€/m2 5,89
IZOLATERSKI RADOVI
GA 22 POSTAVLJANJE VERTIKALNE HIDROIZOLACIJE PODRUMA m2
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
RV h 0,08955 7 0,63
R III h 0,0885 6 0,53
RII h 0,0132 5 0,07
faktor 3
€/m2 7,23
IZOLATERSKI RADOVI
GA 23 POSTAVLJANJE TERMOIZOLACIJE KROVA m2
MATERIJAL RAD STROJ
GRAĐ NORMA OPIS RADOVA JED. MJERA KOLIČINA JED. CIJENA
M R S
RV h 0,0044 7 0,03
RII h 0,0088 6 0,05
RII
faktor 3
€/m2 7,80