MS - Rainy Season Drainage Construction-1115
MS - Rainy Season Drainage Construction-1115
MS - Rainy Season Drainage Construction-1115
Document #
Rainy Season Drainage 00001
Document No : 1003-CHI-00000-GCX-30Y-00001
Revision : 000
Date of Issue : 17 NOVEMBER 2023
中国港湾工程沙特阿拉伯有限责任公司
China Harbour Engineering Arabia Co. Ltd.
Director
Checked By Mr Chen Ruiqing 15-11-23
Construction
Deputy Project
Confirmed By Mr Li Lin 15-11-23
Director
Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001
NOTE: This document and all its contents is the property of CHEC. It is confidential and is given to
you. Neither this document nor any information concerning it may be copied, exhibited or furnished to
others without the consent of CHEC
Table of Contents
Table of Contents.................................................................................................................................. 2
1 PURPOSE.......................................................................................................................................... 3
2 SCOPE OF WORK............................................................................................................................ 3
3 DESCRIPTION OF WORKS.............................................................................................................. 3
4 CONSTRUCTION RESOURCES....................................................................................................... 3
4.1 Main Construction Equipment’s............................................................................................... 3
4.2 Manpower................................................................................................................................ 4
5 ORGANISATION RESPONSIBILITY and SUPERVISION.................................................................4
6 METHODOLOGY............................................................................................................................... 5
6.1 Construction Process............................................................................................................... 5
6.2 Make Embankment.................................................................................................................. 5
6.3 make a water storage point...................................................................................................... 7
6.4 installation water pump............................................................................................................ 7
7 SAFETY AND ENVIRONMENT......................................................................................................... 7
8 QUALITY ASSURANCE..................................................................................................................... 8
Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001
1 PURPOSE
The purpose of this method statement is to explain the rainy season drainage construction for
Mukaab project.
2 SCOPE OF WORK
Rainy season drainage construction of Mukaab project.
3 DESCRIPTION OF WORKS
Construction of rainy season drainage contains the following items:
Make the embankment.
Make water storage point
Installation water pump
4 CONSTRUCTION RESOURCES
4.2 Manpower
Table: 4.2 -1 Manpower’s
Sr No Description Quantity Remarks
1 Construction Director 1
2 Site engineer 1
3 QC Inspector 1
4 HSE Manager 1
5 HSE officer 1
6 Surveyor 1
7 Electrician 1
8 Equipment operator 12
9 Labor 4
Organization Chart
Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001
6 METHODOLOGY
During Zone B, Zone C, Zone D are high point and Zone E near finish, so, an embankment which is
1 meter in width and 1.5 meters in height is planned to be built around Zone A only. The
embankment to prevent water accumulation in Zone A, 4 water pump to take out Zone A inside rain
water to drainage channel.
Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001
According to the weather forecast, when the rainfall is not heavy, water storage points are set up in
the depression near the backfill area, and drainage ditches are built around the Zone A to gather the
rainwater to water storage point.
When unusually heavy rains hit the site, the contractor intends to deal with it in the following ways:
(1) Find a professional drainage subcontractor for assistance.
(2) Use the water pump to take the water from storage point to the existing culvert location.
(3) The client needs to coordinate the water pumping out of plot A.
(3) AII personnel involved should wear complete personal protective equipment (PPE) in accordance
with safe work requirements.
(4) All the work shall comply with the approved safety management plan. Risk assessment shall be
submitted for approval before work commence.
(5) If the weather condition turns bad, (sand storms, wind storms, rains, flooding and hailstorms),
there should be immediate coordination with CHEC Safety Department and Construction
Management in cases where the works will be stopped. If necessary night observation or monitoring
will be carried out, adequate lighting must be prepared by the Construction Manager.
8 QUALITY ASSURANCE
(1)The depth of water storage points should meet the requirements of the method statement.
(2)The width and slope of the drainage ditch meet the requirements of the method statement.