MS - Rainy Season Drainage Construction-1115

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 8

Method Statement for 1003-CHI-00000-GCX-30Y-

Document #
Rainy Season Drainage 00001

Construction REVISION 000

ISSUED BY CHEC ISSUED DATE 26-Nov-23 1/8

METHOD STATEMENT FOR


RAINY SEASON DRAINAGE CONSTRUCTION

Document No : 1003-CHI-00000-GCX-30Y-00001

Revision : 000
Date of Issue : 17 NOVEMBER 2023

中国港湾工程沙特阿拉伯有限责任公司
China Harbour Engineering Arabia Co. Ltd.

Name Title Date Signature

Prepared By Mr Rongqi Lyu Design Manager 15-11-23

Director
Checked By Mr Chen Ruiqing 15-11-23
Construction

Deputy Project
Confirmed By Mr Li Lin 15-11-23
Director
Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001

Construction REVISION 000

ISSUED BY CHEC ISSUED DATE 26-Nov-23 2/8

NOTE: This document and all its contents is the property of CHEC. It is confidential and is given to
you. Neither this document nor any information concerning it may be copied, exhibited or furnished to
others without the consent of CHEC

Table of Contents
Table of Contents.................................................................................................................................. 2
1 PURPOSE.......................................................................................................................................... 3
2 SCOPE OF WORK............................................................................................................................ 3
3 DESCRIPTION OF WORKS.............................................................................................................. 3
4 CONSTRUCTION RESOURCES....................................................................................................... 3
4.1 Main Construction Equipment’s............................................................................................... 3
4.2 Manpower................................................................................................................................ 4
5 ORGANISATION RESPONSIBILITY and SUPERVISION.................................................................4
6 METHODOLOGY............................................................................................................................... 5
6.1 Construction Process............................................................................................................... 5
6.2 Make Embankment.................................................................................................................. 5
6.3 make a water storage point...................................................................................................... 7
6.4 installation water pump............................................................................................................ 7
7 SAFETY AND ENVIRONMENT......................................................................................................... 7
8 QUALITY ASSURANCE..................................................................................................................... 8
Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001

Construction REVISION 000

ISSUED BY CHEC ISSUED DATE 26-Nov-23 3/8

1 PURPOSE
The purpose of this method statement is to explain the rainy season drainage construction for
Mukaab project.

2 SCOPE OF WORK
Rainy season drainage construction of Mukaab project.

3 DESCRIPTION OF WORKS
Construction of rainy season drainage contains the following items:
 Make the embankment.
 Make water storage point
 Installation water pump

4 CONSTRUCTION RESOURCES

4.1 Main Construction Equipment’s


Table: 4.1-1 Equipment’s
Sr No Description Quantity Remarks
1 Excavator 10 Make the embankment
2 Water pump 4 Dewater
3 Bulldozer 2 Make the embankment
4 Survey Equipment’s 1 Layout Setting
Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001

Construction REVISION 000

ISSUED BY CHEC ISSUED DATE 26-Nov-23 4/8

4.2 Manpower
Table: 4.2 -1 Manpower’s
Sr No Description Quantity Remarks
1 Construction Director 1
2 Site engineer 1
3 QC Inspector 1
4 HSE Manager 1
5 HSE officer 1
6 Surveyor 1
7 Electrician 1
8 Equipment operator 12
9 Labor 4

5 ORGANISATION RESPONSIBILITY and SUPERVISION

Organization Chart
Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001

Construction REVISION 000

ISSUED BY CHEC ISSUED DATE 26-Nov-23 5/8

6 METHODOLOGY

6.1 Construction Process

Fig 6.1-1 Construction process of rainy season drainage

6.2 Make Embankment

During Zone B, Zone C, Zone D are high point and Zone E near finish, so, an embankment which is
1 meter in width and 1.5 meters in height is planned to be built around Zone A only. The
embankment to prevent water accumulation in Zone A, 4 water pump to take out Zone A inside rain
water to drainage channel.
Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001

Construction REVISION 000

ISSUED BY CHEC ISSUED DATE 26-Nov-23 6/8

Fig 6.2-1 embankment location and water pump plan

Fig 6.2-2 embankment build


Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001

Construction REVISION 000

ISSUED BY CHEC ISSUED DATE 26-Nov-23 7/8

6.3 Make a water storage point (normal rain)

According to the weather forecast, when the rainfall is not heavy, water storage points are set up in
the depression near the backfill area, and drainage ditches are built around the Zone A to gather the
rainwater to water storage point.

Fig 6.3-1 drainage drawing


6.4 Heavy rains

When unusually heavy rains hit the site, the contractor intends to deal with it in the following ways:
(1) Find a professional drainage subcontractor for assistance.
(2) Use the water pump to take the water from storage point to the existing culvert location.
(3) The client needs to coordinate the water pumping out of plot A.

7 SAFETY AND ENVIRONMENT


(1) Pay attention to Oil spillage from equipment, check the equipment every day before work starts,
ensuring the equipment can work properly.
(2) Maintain a distance of more than 30 meters between personnel and equipment.
Method Statement for 1003-CHI-00000-GCX-30Y-
Document #
Rainy Season Drainage 00001

Construction REVISION 000

ISSUED BY CHEC ISSUED DATE 26-Nov-23 8/8

(3) AII personnel involved should wear complete personal protective equipment (PPE) in accordance
with safe work requirements.
(4) All the work shall comply with the approved safety management plan. Risk assessment shall be
submitted for approval before work commence.
(5) If the weather condition turns bad, (sand storms, wind storms, rains, flooding and hailstorms),
there should be immediate coordination with CHEC Safety Department and Construction
Management in cases where the works will be stopped. If necessary night observation or monitoring
will be carried out, adequate lighting must be prepared by the Construction Manager.

8 QUALITY ASSURANCE
(1)The depth of water storage points should meet the requirements of the method statement.
(2)The width and slope of the drainage ditch meet the requirements of the method statement.