Professional Documents
Culture Documents
Lesson 3
Lesson 3
Lession-3
How to consider for Abutment Design
H
② ③ ④
⑥
H = H/3
③‘
Load Combination
Table C-3.2. General Load Combinations
Design of Abutments Design of Pie1's Load Situations
a) Dead loads + live loads a) Dead loads + live loads Under ordinary
+ earth pressure b)Dead loads + effects of temperature change conditions
b) Dead loads + earth pressure c)Dead loads + live loads + effects of temperature change
c) Dead Loads + earth pressure + d) Loads + seismic effects Under earthquake
seismic effect condition
e) Dead loads + wind loads Extreme wind
situation
Page 4
Property of Materials
275
100
160
160
160
160
160
Yield strength fy (N/mm2) 235 295 345 275
Page 5
Page 7
4
200
2
Weight of Pavement
1,300
1,500
1,000
1
Weight of Card 600
Example:
Section No H B unit wt Wd (kN)
1 girder 3 1.3 0.6 24.5 57.33
2 slab 1 0.2 4.8 24.5 23.52
3 pavement 1 0.05 4.2 22.5 4.725
4 curb 2 0.3 0.3 24.5 4.41
5 handrail post 0.6 0.825 0.15 24.5 1.819
6 handrail 2 0.1 0.15 24.5 0.735
7 handrail deflector 2 0.15 0.075 24.5 0.55125
8 handrail deflector 2 0.25 0.075 24.5 0.91875
Sum = 94.009125
Span Length =18m
Point Load (mid) W =1692.2kN
Dead Load Reaction, Rd =846. 1kN Page 8
(2) Live Load (AASHTO HL-93 Load)
1.Truck Load HS-20 and Tandem Load 2.Tandem Load
Page 9
The design lane load shall consist of a load of 0.64 klf (9.3 kN/m) uniformly distributed in the
longitudinal direction. In transverse direction, the design lane load shall be assumed to be
uniformly distributed over a 10.0’ (3m) width (9.3/3m =3.1 kN/m2).Impact factor or dynamic load
allowance is applied only for trucks and tandems, not for lane loading.
Page 10
(4) Inertia force in a simple girder bridge
In a simple girder bridge, the inertia force acting from the superstructure onto the
substructure in the longitudinal direction of the bridge axis shall be calculated as follows as
shown in Fig 2.3.
Where,
H-EQ :Horizontal force on the abutment due to earthquake
Rd-FIX : Vertical reaction of the abutment due to W
kh : Design horizontal seismic coefficient of the design vibration unit containing girder
H-FR : Superstructure inertia force on the abutment due to expansion of girder
fs : Coefficient of static friction when the support is movable Page 11
(5) Example
1)HS-20 L=18m
L-4.3 , L-8.6 8.6m
ℓ1= ℓ2=
L L FR = FR =
FF =
RL =(1.00x FR +A1x FR +A2 x FF) x
(number of lane)×(multiple presence factor) ℓ2
ℓ1
Truck Load,RL = 273.64×1×1.2=328.4 kN
2)Tandem
RA = {110+(18-1.2)/18×110}×1×1.2=255.2
RL
3)Lane Load
110kN 110kN
Lane Load = 167.4 ×1×1.2 = 100.4kN 1.2
7
Earth
9 Rd 846.1 1 846.1
n
10 RL 328.4 1 328.4
Page 13
a
A t A
A t
2
a
A
A
A
At bottom, z=H At bottom, z=H
1 H
PA K A t H 2 , y
2 3 A A
1 2
MA H y K A t H 3 A A
6
For earth pressure calculation, Coulomb's, Rankin's, Terzaghi's and many other earth
pressure formulae have been proposed.
Coulomb's earth pressure formula is said to give a value that is relatively close to the
measured value for active and passive earth pressure.
Page 14
Coefficient of Earth Pressure
There are many equations for earth pressure, Japanese standard
use follows equation;
cos 2
KA 2
sin sin
cos cos2 cos 1
cos cos
STATIC
φ-α-θ 20 25 30 35 20 25 30 35 q
α+δ+θ 20 25 30 35 6.667 8.333 10 11.667
φ+δ 40 50 60 70 26.667 33.333 40 46.667
α-β 0 0 0 0 0 0 0 0
Ka 0.427 0.355 0.297 0.250 0.458 0.377 0.308 0.251 ,
kh 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 PA
δ(°) 10 12.5 15 17.5 0 0 0 0
H
α(°) 0 0 0 0 0 0 0 0
EARTHQUAKE
β(°) 0 0 0 0 0 0 0 0
θ=tan-1(kh) (°) 11.31 11.31 11.31 11.31 11.31 11.31 11.31 11.31
φ-α-θ 8.69 13.69 18.69 23.69 8.69 13.69 18.69 23.69
α+δ+θ 21.31 23.81 26.31 28.81 11.31 11.31 11.31 11.31
φ+δ 30 37.5 45 52.5 20 25 30 35
α-β 0 0 0 0 0 0 0 0
Ka 0.648 0.539 0.452 0.380 0.672 0.564 0.473 0.396 Page 15
Stability calculation
Gravity-type Soil &
Sectional φ/3 0
abutment Concrete
calculation of wall
Stability calculation Soil & Soil φ φ/2
Reversed
T-type abutment Sectional Soil &
φ/3 0
calculation of wall Concrete Page 16
Earth Pressure considering Presence of Water
【Case1】 【 Case2】
Retained earth is allowed to drain Retained earth is not allowed to drain
Gravel
Drain Drain pA-1
H
H
pipe ▽ Water Table
Hw
pA pA-2 pw
KA: Coefficient of Active Earth Pressure
■Active Erath Pressure ■Effective Active Erath Pressure
pA K A t H pA 1 K A t H H w
PA
1 1
p A H K A t H 2 pA 2 pA 1 K A sat w Hw
2 2
1 1
PA pA 1 H H w pA 1 pA 2 H w
2 2
GS e
sat w
1 e
Approximately sat w t 9 kN m3
■Water Pressure
pw w H w
1
Pw w H w2
2 Page 17
Eight-Japan Engineering Consultants Inc. (EJEC)
Water flow
Pressure
▽H.W.L
▽ Residual Water Table
HW
HR
Surcharge on
Heel
Ordinary
Condition
Exclude
Surcharge on
Heel
Earth Quake
Page 19
1 1 2
P p H K H
A
2 A
2 A t
PA
PA
pA1 pA2
KA: Coefficient of Active Earth Pressure KA= 0.297
■ Active Erath Pressure
pA K A t H
1 1
PA p A H K A t H 2
2 2
Example;
δ = 30Ka ,KA =0.297 , γt = 20 (kN/m3) , B= 4.91 m
PA1 = ½ ×20.0 ×0.297×(5.6)2×4.91 =457.03 kN
PA1-H = PA1×cos δ = 395.8 kN
PA1-V = PA1×sin δ = 228.52 kN
■ Earth Pressure by surcharged load
Example;
q=10 (kN/m2)
PA2 = 0.297×5.6×10.0 ×4.91 = 81.61 kN
PA1-H = PA2×cos δ = 70.68 kN
PA2-V = PA2×sin δ = 40.81 kN Page 20
1.5 Buoyancy and Water Pressure
Water Height hw-f = 1 m (Assume according to the death of pile cap high ) * water level at river side
Water Height hw-b = 3.5 m *residual water level at embankment
H1 =2.1
▽ pa1
PA-2
pa2
yu1
H2 =3.5
yu2
yw-f
▽ pw w H w
Pw 1
H2=3.5m
Pw w H w2
Pw 2
yw-b
yw-f
1 1
Pw b w H w b 2 B yw b H w b
2 3
1 1
Pw f w H w f 2 B yw f H w f
2 3
Buoyancy
VF・x
VF (kN) x (m)
(kN・m)
2 Breast Wall 0.00 × 1.2 × 4.91 × 9.80 = 0 1.200 0
8 Soil on Toe 0.00 × 0.60 × 4.91 × 9.80 = 0 0.300 0
Cap-1 1.00 × 1.80 × 4.91 × 9.80 = 86.56 0.900 77.9
3
Cap-2 1.00 × 1.80 × 4.91 × 9.80 = 86.56 2.700 233.71
4 Back Fill 2.50 × 1.8 × 4.91 × 9.80 = 216.4 2.700 584.28
Total 389.52 0 895.89
H=5.6
pA
Coef: of Active Earth Pressure KA: =0.452
Page 23
PA-1
H1 =4.6
PA-2
yu1
▽
H2 =1
yu2
H1
pa1 Ka t H1 y u1
3
H2
pa 2 K a t H1 t 9 H 2 H 2 2 p a1 p a 2
yu 2
3 p a1 p a 2
1
PA 1 pa1 H1B
2
1
PA 2 pa1 pa 2 H 2 B
2
Page 24
■ Buoyancy and Water Pressure
Hw-b=1m
Pw-f Pw-f
yw-f yw-b
1 1
Pw b w H w b2 B yw b H w b
2 3
1 1
Pw w H w f 2 B yw f H w f
f
2 3
Buoyancy
VF・x
VF (kN) x (m)
(kN・m)
2 Breast Wall 0.00 × 1.20 × 4.91 × 9.8 = 0 1.200 0
Page 26
1.7 Load for Computing Stability
① Dead + Live Load
V = 3378.0 (kN)
H = 466.5 (kN)
Mo = 6022.9 - 936.9 = 5086.0 (kN・m)
eo = Mo/V = 1.506 (m)
e = b/2-eo = 0.294 (m)
M = e×V =993.1 (kN・m)
① Ground horizontal
resistance:kH・D
③ Friction resistance
around pile ②Vertical Resistance: Kv
(Downward)
=UΣfiℓi
③Friction resistance
around pile
(Upward)
=UΣfiℓi
Page 29
Average N=12
5.5m
17m
Average N=14 3m
?? Page 30
Computing Model for Pile Foundation
FRAME MODEL
DISPACEMENT MODEL
【Merit】
Vo
Mo The force acting on the pile head can
Ho be accurately analyzed without using
structural analysis software.
Page 31
Page 32
Coefficient of subgrade reaction KH (2)
-3/4
Page 33
Page 34
Coefficient of subgrade reaction KH (4)
Page 35
HO
O
kH D 26976 0.8
4
4EI
4
4 502750
0.322 m 1
1/β = 3.106 (m)
Page 36
Compute Coefficient of subgrade reaction KH
2) Second time
1/β = 3.106 (m)
2.1 9 3.106 2.1 12
AverageN value 9.97
3.106
E O 2800 9.97 27916
HO
O
4 H
4
1
1/β = 3.116(m) 3.116 ok Repeat until almost equal
Page 37
Correction KH by μ
If the distance between adjacent pile centers was shorter than 2.5 times the pile diameter
Because the footing width has to be short due to site restrictions.
In such cases, group pile action has to be fully examined in accordance with the
provisions in Sec. 12.4.4 in JRA.
1D 2.5D
2.5D 1D
Where,
μ : modification coefficient for the coefficient of
horizontal subgrade reaction
L: distance between adjacent pile centers (m)
D: pile diameter (m), equal to the diameter of the soil
cement column in cases of steel pipe soil cement In Case of Bore Pile
pile. Page 38
(2.4) Spring Constants (Axial Spring Constant Kv )
The coefficient of horizontal subgrade reaction to be used in the design of piles
shall be evaluated either by fully reviewing the results of geotechnical investigations
and soil tests, or by back-calculating the load-displacement curve obtained from
horizontal loading tests.
Page 39
Corrected KH by μ, and Kv
1) Corrected KH by μ
Ap E p 0.5027× 2.5×107
Kv = a = 0.5088× = 376,138(kN / m)
L 17.0
Page 40
(2.4.2)Radial Spring Constant K (Normal Time & During Earthquake)
Page 41
Coefficient of Matrix
Page 42
Reference (about Frame Model)
The same coefficient kH, Kv as displacement method are used in
Frame Model.
Page 43
Page 44
Example
1) Friction: UΣfi・Li
Example:Soil Condition and Shaft Resistance
a
u
s s
*The factor of safety for the bearing pile can be used in a friction pile if the pile
satisfies reliable conditions regarding bearing capacity.
u
i
i
(12.4.3)
a
u
(Japanese Standard )
where,
Pa : axial allowable pull-out force of pile at pile head (kN)
N : safety factor shown in Table-12.4.3
Pu : ultimate pull-out force of pile
Normal Time : a
Earthquake : a
Page 47
(Japanese Standard )
Front low Back low Front low Back low Front low Back low Front low Back low
δxi (m) 2.128E-03 2.128E-03 3.091E-03 3.091E-03 4.277E-03 4.277E-03 4.257E-03 4.257E-03
δyi (m) 2.040E-03 9.540E-04 2.113E-03 5.002E-04 2.828E-03 -2.913E-04 2.747E-03 -3.655E-04
αi (rad) 5.430E-04 5.430E-04 8.065E-04 8.065E-04 1.560E-03 1.560E-03 1.556E-03 1.556E-03
Page 48
Check Bearing Capacity of Pile
【Check Stability 】
Page 51
・Shear Strength
d0 D2
4
d= do-Δc
Ps = Sc + Ss Eq:(5.2.1)
Sc =τa1bd Eq:(5.2.1)
w
sy
s
Page 52
Requirement on Re-ba in RC Pile
D20 in Myanmar
Page 53
Minimum spacing 100mm
Re-bar cage
Mmax=196.1(kN・m)
ℓa=40φ+0.1m
L ≥ 5.0 +2×0.8+0.1 = 6.7→
L=5 m
ℓa=40φ=0.8m
1/2Mmax=98.05 (kN・m)
Φ: Re-bar
diameter
D20
Page 54
Detail Drawing for Bore RC Pile
Page 55
PA1 H=4.601(m)
yu-2=2.301(m)
yu-1=1.534(m)
O pa
V (kN)
V・x H H・y
x (m) y (m)
height width depth unit weight (kN・m) (kN) (kN・m)
1 Parapet Wall 1.742 × 0.4 × 4.91 × 24.5 × = 83.77 1.0 83.77 16.75 3.73 62.49
2 Breast Wall 2.859 × 1.2 × 4.91 × 24.5 × = 412.46 0.600 247.48 82.49 1.4295 117.92
Pressure
3 Pa2
Reaction
During
Normal Time Dead Loading
Earthquak
M kN・m/m 163.899 415.256 115.508
N kN//m 356.301 273.554 114.911
S kN/m 78.166 189.316 78.17
2
Concrete Ec (N/mm ) 2.500E+04
n=Es/Ec 15
c=40+12+20/2
concrete cover Specifeid
=62 mm (center)
(mm)
Round c (mm) 70.0
Re-bar schedule
pitch in meter 150 nos in meter 6.667
2
Diameter (mm) D16 as (mm ) 201.0
2
As(mm /m) 1340.1 d1 (mm) 1130
e=M/N 460.002 1518.004 1005.195
c=d1-B/2 530 530 530
Neutral axis x(mm) 597.808 265.860 314.223
2
σc N/mm 1.27 4.05 1.10
2
σs N/mm 16.9 197.3 42.6
2
τm N/mm 0.069 0.168 0.069
Check Ductility ( φMn≧φrMcr ) by AASHTO Page 57
Content Requirement
Front side As1
Longitudinal re-bar
Back side As2 Minimum ≧1/2 As1
Front side Ab1 Ab1 ≧ 1/3 As1
Lateral re-bar
Back side Ab2 Ab2 ≧ 1/3 As2
Vertical h ≦ 600mm
Intermediate tie AT
Horizontal w ≦ 1000mm
Page 58
4. Design Pile Cap
Critical section for shear
AASHTO(5.13.3.6.1)
Verification of Pile Cap Footing
• One-way action, with a critical section extending in a plane across the entire width and located
at a distance taken.
• Two-way action, with a critical section perpendicul3I to the plane of the slab and located so that
its perimeter, b 0' is a minimum but not closer than 0.5d~ to the perimeter of the concentrated
load or reaction area
• Where the slab thickness is not constant, critical sections located at a distance not closer than
O.5d~ from the face of any change in the slab thickness and located such that the perimeter, bo'
is a minimum
O.5d
=
Page 59
hc/2=0.5
(1.1.2) Shear
F (kN)
unit
height width Depth
weight
Reaction F = 0
Footing 1.000 × 0.1 × 4.9 × -24.5= -12.022
Sum -12.022
Page 60
(1.2) Include Buoyancy
F (kN)
x(m) M=F・x(kN・m)
unit
height width depth
weight
Sum -12.984
(1.2.2) Shear
F (kN)
Reaction F = 0
Sum -7.213
Page 61
(2)Heel
1.7M ≤ Mcr OK OK OK OK
Page 64
Content Requirement
Tension side Main re-bar As1-T
(lower side) distribution Ab1-T ≧1/3 As1-T
Toe
Compression side Main re-bar As2-T ≧1/2 As1-T
(upper side) distribution Ab2-T ≧1/3 As2-T
Tension side Main re-bar As1-R
(upper side) distribution Ab1-R ≧1/3 As1-R
Rear
Compression side Main re-bar As2-R ≧1/2 As1-R
(lower side) distribution Ab2-R ≧1/3 As2-R
Stirrup Both side AKN Distribution pitch
Page 65
(Intermediate tie) Toe and Rear AT-R ≦d (effective height of cap)
"Sidewalk or the like" here includes, besides sidewalks, portions ordinarily not loaded with vehicle loads such
as shoulders. "No sidewalk or the like is provided" may be thought of as a sidewalk or the like less than 1 m
in width.
Give consideration to wall thickness and arrangement of reinforcements to ensure adequate transfer of
forces. The connected portions make structural weak points and therefore are desirably provided with a
haunch.
In a wing wall of the parallel type, the main horizontal reinforcements must be anchored in the direction of the
lateral reinforcements (horizontal bars) in the parapet.
Therefore, it is necessary to add reinforcing bars in the parapet if the wall thickness or the amount of
horizontal reinforcements of the parapet is smaller than the wing wall.
Page 66
Wing Wall Design ( 8.4.4) Japan Standard
Page 67
Page 68
1.Calculation of Member Force
Ultimate Limit , α₁=1 ,α₂=1.75
Serviceability Limit , α₁=1 ,α₂=1
L1=4.5m
a● e
h=0.9m
●
h2=3.7m
h3=2.34m
H=5.5m
b●
h1=1.8m
● f
h4=3.16m
b● ●
’
● 45
● ●
c c d
°
’
b2=2.7m
b1=1.8m
Page 69
h=0.9m
6 2
h3=2.34m
MD
1
1
α 1K'A γ t b3 h3 2h3h 3h2 2 K ' A qb3 h3 2h
2 2 2
H=5.5m
24 6
h1=1.8m
h4=3.16m
Example:
● f
45°
PD-1 = 1/6×0.3038 ×20 ×2.7 ×(5.476 +2.106 +0.900 ) = 23.189 kN/m
Page 70
L1=4.5m
(1.2) a-b section
p1 1 K ' A z
a● e●
h=0.9m
p2
h2=3.7m
2 K ' A q
h4=3.16m h3=2.34m
1
PA 1 ' b1 p 1 z , P A 2 ' b1 p 2 z
2
H=5.5m
PA 1 P A 1 ' PD 1 , PA 2 P A 2 ' PD 2
b●
h1=1.8m
1 1
M A 1 ' b1 P A 1 ' , M A 2 ' b PA 2 ' ● f
2 2
M A 1 M A 1 ' M PD 1 b1
D 1
45°
M A 2 M A 2 ' M D 1 PD 2 b 1
Example:
b2=2.7m
PA-1‘ = ½ ×1.800 ×(0.3038 × 20 × 3.700 ) × 3.700 = 74.858 kN/m b1=1.8m
L1=4.5m
(1.3) b-b' section
a● e
pi 1 1 K A' h 2 , pi 2 2 K A 'q
h=0.9m
●
h2=3.7m
h3=2.34m
h
p j 1 1 K A ' h2 1 , p j 2 2 K A ' q
2
H=5.5m
b● pi
pk 1 1 K A 'H , pk 2 2 K A ' q
h1=1.8m
h4=3.16m
● f
PB 1 pi 1 b1 (kN / m), PB 2 pi 2 b1 (kN / m) b’● ● pj
1 1 45° pk
MB PB 1 b1 (kN m / m), M B 2 PB 2 b1 ( kN m / m)
2 2
Example:
b1=1.8m b2=2.7m
PB-1 = 0.3038 × 20 × 3.700 ×1.800 = 40.64 kN/m
α1 α2 α1 α2
Sum Sum
1.00 1.75 1.00 1.00
h=0.9m
h2=3.7m
b b
PB ' 1 p j 1 1 , PB ' 2 p j 2 1
h4=3.16m h3=2.34m
2 2
1 1
H=5.5m
b● pi
M B ' 1 b1 PB ' 1 , M B ' 2 b1 PB ' 2
h1=1.8m
4 4
● f
b’ ● ● pj
Example: ●
45°
c
PB'-1 = 0.3038 × 20 × (3.700 +1/2×1.800 ) × 1.800 /2 = 25.153 kN/m
b1=1.8m b2=2.7m
PB'-2 = 0.3038 ×10 ×1.800 /2 = 2.734 kN/m
α1 α2 α1 α2
Sum Sum
1.00 1.75 1.00 1.00
Page 73
h3=2.34m
Example:
pi-1 = 0.3038 × 20 ×3.700 = 22.480 kN/m
H=5.5m
b● pi
h1=1.8m
b’● ● pj
pk-1 = 0.3038 × 20 × 5.500 = 33.416 kN/m
pk-2 = 0.3038 × 10 = 3.038 kN/m ● 45°
● ● pk
c c’ d
Pc-1 = ½ × (22.480 + 33.416 )× 1.800 = 50.307 kN/m
Pc-2 = ½ × (3.038 +3.038 ) ×1.800 = 5.468 kN/m b1=1.8m b2=2.7m
α1 α2 α1 α2
Sum Sum
1.25 1.75 1.00 1.00
p j 1 pk 1 h1 / 2, p j 2 pk 2 h1 / 2
1 1
PC ' 1 PC ' 2
2 2
M C ' 1 2 p j 1 pk 1 h1 / 2 , 2 p j 2 pk 2 h1 / 2
1 2 1 2
MC 2 L1=4.5m
6 6
Example: a● e
h=0.9m
●
h2=3.7m
pj-1 = 0.3038 × 20 × 4.600 = 27.948 kN/m
h3=2.34m
pj-2 = 0.3038 × 10 = 3.038 kN/m
H=5.5m
b● pi
PC'-1 = ½ × (27.948 + 33.416 ) × 1.800 /2 = 27.614
h1=1.8m
● f
h4=3.16m
b’● ● pj
PC'-2 = ½ × (3.038 + 3.038 ) × 1.800 /2 = 2.734
● 45°
● ● pk
c c’ d
MC'-1 = 1/6 ×(2 × 27.948 + 33.416 ) × 0.81 =1 2.057
MC'-2 = 1/6×(2 × 3.038 + 3.038 ) × 0.81 =1.230 b1=1.8m b2=2.7m
α1 α2 α1 α2
Sum Sum
1.00 1.75 1.00 1.00
as (mm ) 2
201.1 201.1 201.1 201.1 201.1 201.1 < τa1
Pitch (mm/m) 300 150 150 300 150 300
2
As (mm /m) 663.6 1347.4 1347.4 663.6 1347.4 663.6
Page 76
3.Ultimate Condition
1 .1 f y A a
z (1 )d
f cu bd
Wing Wall
(iii) Check Shear (AASHTO 5.8.2.9)
V
v
bd
Parapet Wall
1
0.27 100As 3
vc fcu 13
m bd
Reinforcing bar As2
v < vc (OK)
Example:
e - f section a' - b section b - b' section b' - c section c' - d section c - c' section
D A B B' C C'
Remarks OK NG OK OK OK OK
Page 78
Detail Drawing of Abutment (1)
Page 79
Page 80
Detail Drawing of Abutment (3)
Page 81
Page 82
Thank you for your kind attention