Professional Documents
Culture Documents
DOH Calinan Pipes
DOH Calinan Pipes
A. DIRECT COST
I. GENERAL REQUIREMENTS ₱ ₱
a Mobilization/Demobilization lot 1.00 30,000.00 30,000.00 - 30,000.00
b Temporary Facilities lot 1.00 50,000.00 50,000.00 - 50,000.00
c Project Billboard/Info Board lot 1.00 1,600.00 1,600.00 - 1,600.00
d Safety and Health lot 1.00 20,000.00 20,000.00 - 20,000.00
e Mat'ls Testing for Concrete, CHB & Steel Bars lot 1.00 10,000.00 10,000.00 - 10,000.00
f. Permits (Building, Occupancy) lot 1.00 50,000.00 50,000.00 - 50,000.00
Total Direct Cost 161,600.00 - 161,600.00
III. EARTHWORKS ₱ ₱ ₱
a. Excavation works (refer to actual & plan for the affected area) cu.m 93.00
Embankment (elevation of 0.6m from the natural grade line to finish floor
b.
line)
Mountain Mix (in place) cu.m 442.00 - - 250.00 110,500.00
Earthfill to the ff.areas:
c. Gravel bedding for footing,wall footing, & slab on fill cu.m 201.00
F1,F2 cu.m 17.00 73.50 1,249.50 1,624.35 2,873.85
FTB, WF, Zocallo cu.m 29.00 73.50 2,131.50 2,770.95 4,902.45
Slab on fill cu.m 155.00 73.50 11,392.50 14,810.25 26,202.75
Total Direct Cost 14,773.50 21,705.55 214,229.05
Materials:
10mm thk x 4' x 8' Ordinary Plywood shts. 43.00 450.00 19,350.00 25,155.00 44,505.00
Asstd. Coco Lumber bd.ft 2,500.00 35.00 87,500.00 113,750.00 201,250.00
Asstd. Common Wire Nails kgs. 40.00 90.00 3,600.00 4,680.00 8,280.00
Labor Cost
Total Direct Cost 110,450.00 143,585.00 254,035.00
Page 1 of 18
PROJECT : Construction of Calinan Super Health Center
LOCATION : Brgy. Tamayong, Calinan, Davao City
SUBJECT : DETAILED ESTIMATE
Estimated Wall Area to be plastered (w/ 16mm thk bothsides) sq.m 1,344.00
150mm thk CHB, machine made (exterior walls) pcs. 3,412.00 20.00 68,240.00 88,712.00 156,952.00
100mm thk CHB, machine made (interior walls including end
pcs. 5,652.00 18.00 101,736.00 132,256.80 233,992.80
walls/spandrel)
Portland Cement (including mortar) bags 948.00 270.00 255,960.00 332,748.00 588,708.00
Washed Sand (including mortar) cu.m. 55.75 1,500.00 83,625.00 108,712.50 192,337.50
10mm dia. x 6m Deformed Bar lgths 634.00 136.00 86,224.00 112,091.20 198,315.20
No. 16 GI Tie Wire kg 33.00 90.00 2,970.00 3,861.00 6,831.00
Labor Cost
Total Direct Cost 598,755.00 778,381.50 1,377,136.50
VII.A CEILING
a. Installation of fiber cement board on furring ceiling system (interior) sq.m 360.00 187.50 67,500.00 87,750.00 155,250.00
Labor Cost
Total Direct Cost 94,279.77 122,563.70 216,843.47
6mm x 50mm x 50mm x 3/16" Angle bar ( top,bottom & web chord ) lghts. 85.00 1,488.10 126,488.50 164,435.05 290,923.55
4.5mm x 25mm x 6m Flat bar ( steel facia frame ) lghts. 60.00 167.90 10,074.00 13,096.20 23,170.20
16mm plain round bar Sag Rod with turnbuckle cross bracing lghts. 15.00 625.60 9,384.00 12,199.20 21,583.20
12mm plain round bar Sag Rod lghts. 22.00 348.45 7,665.90 9,965.67 17,631.57
1.5 mm x 50mm x 100mm Cee Steel Purlins (painted w/ red oxide) lghts. 98.00 412.85 40,459.30 52,597.09 93,056.39
Welding Rod 3/32" diam. kgs. 70.00 51.00 3,570.00 4,641.00 8,211.00
Red Oxide gals. 20.00 589.95 11,799.00 15,338.70 27,137.70
Paint brush & other accessories lot 1.00 5,000.00 5,000.00 6,500.00 11,500.00
Miscellaneous (teckscrew, rubber washer, cleats, etc.) lot 1.00 5,000.00 5,000.00 6,500.00 11,500.00
Equipment Rental
eqpt-
1 unit - Welding Machine 30.00 850.00 25,500.00 33,150.00 58,650.00
days
Stainless Steel Railing 38mm diameter #304 with end caps at the Ramp,
c. lot 1.00 12,500.00 12,500.00 16,250.00 28,750.00
Porch, Landings & Step-ups.
Labor Cost
Total Direct Cost 257,440.70 334,672.91 592,113.61
0.4mm thk x 1.013m x Long Span Pre-painted Rib Type G.I Roofing. ln.m 499.04 - - -
Page 2 of 18
PROJECT : Construction of Calinan Super Health Center
LOCATION : Brgy. Tamayong, Calinan, Davao City
SUBJECT : DETAILED ESTIMATE
X. DOORS ₱ - ₱
D-1 Double Swing Glass Door with transom (2.650mW x 2.65mH), (50mm
x 100mm Analok Aluminum Frame Door Jamb, 50mm x 50mm Analok
Aluminum Door Frame, 50mm x 100mm Analok Aluminum Frame Door w/ unit 2.00 - - -
6mm thk. Clear Glass) with aluminum handrail, overhead concealed door
closer, includes hardware accessories and installation.
D-1a Double Swing Hollow Core Steel Door Type with 6mm. thk. transom
glass (1.60mW x 2.65mH), Steel door jamb, Top and bottom heavy duty
pivot hinges, Lever type heavy duty door handle with chrome finish, 150 x unit 4.00 - - -
400mm stainless steel kick plate (back to back) and (600 x 300 x 6mm) thk.
viewing glass (verify plan).
D-2 Double Swing Glass Door with transom and side fixed glass (2.65mW x
2.65mH), (50mm x 100mm Analok Aluminum Frame Door Jamb, 50mm x
50mm Analok Aluminum Door Frame, 50mm x 100mm Analok Aluminum unit 3.00 - - -
Frame Door w/ 6mm thk. Clear Glass) with aluminum handrail, overhead
concealed door closer, includes hardware accessories and installation.
D-2a Double Swing Hollow Core Steel Door Type with 6mm. Thk. Transom
glass (1.3mW x 2.65mH). Steel door jamb, Tap and bottom heavy duty pivot
hinges. Lever type heavy duty door handle with chrome finish, 150 x 400mm unit 1.00 - - -
stainless steel hand push plate (back to back), 800 x 400mm stainless kick
plate (back to back) and (600 x 300 x 6mm) thk. viewing glass (Verify plan)
D-3 Single Swing Glass Door with transom (0.90mW x 2.65mH), (50mm x
100mm Analok Aluminum Frame Door Jamb, 50mm x 50mm Analok
Aluminum Door Frame, 50mm x 100mm Analok Aluminum Frame Door w/ unit 5.00 - - -
6mm thk. Clear Glass) with aluminum handrail, overhead concealed door
closer, includes hardware accessories and installation.
D-4 Single Swing Hollow Core Steel Door Type with 6mm thk transom glass
(0.8mW x 2.65mH), Steel door jamb, Top and bottom heavy duty pivot
units 2.00 - - -
hinges, Lever type heavy duty handle with chrome finish, 800 x 400mm
stainless steel kick plate (back to back). Verify plan
D-4a Flush door type single swing door with viewing glass & transom
(0.8mW x 2.15mH), 50mm x 150mm door jamb kiln dried solid wood,
50mm x 150mm flush door frame, KD Solid Wood, 100mm x 100mm ball
bearing door hinges, stainless (see image), 6mm thick clear glass, with lever units 2.00 - - -
type door handle satin chrome finish, 6mm thick marine plywood(grade2),
12mm x 50mm solid wood moulding (front only), includes complete
hardware accessories and installation.
D-5 PVC with louver type swing door, (0.80mW x 2.150mH), with heavy
duty lever type door handle chrome finish, door hinges, includes complete units 4.00 - - -
hardware accessories and installation. Verify plan
D-6 PVC with louver type swing door, (1.00mW x 2.150mH), with lever
type door handle chrome finish, door hinges, includes complete hardware units 1.00 - - -
accessories and installation.
D-7 PVC with louver type swing door, (0.60mW x 2.150mH), with lever
type door handle chrome finish, door hinges, includes complete hardware units 1.00 - - -
accessories and installation.
Page 3 of 18
PROJECT : Construction of Calinan Super Health Center
LOCATION : Brgy. Tamayong, Calinan, Davao City
SUBJECT : DETAILED ESTIMATE
D-8 Single Swing Steel Door Type (0.90mW x 2.15mH) with lever type door
handle chrome finish, door hinges with paint finished includes complete units 2.00 - - -
hardware accessories and installation. Verify plan
D-9 Single Swing Grill Door Type (0.80mW x 2.15mH) with steel door
handle with paint finish, cylindrical door hinges includes complete hardware units 1.00 - - -
accessories and installation. Verify plan
XI. WINDOWS ₱ - ₱
a. Installation of Ceramic Tiles at the entire floor sq.m. 183.41 708.88 130,016.94 169,022.02 299,038.96
Page 4 of 18
PROJECT : Construction of Calinan Super Health Center
LOCATION : Brgy. Tamayong, Calinan, Davao City
SUBJECT : DETAILED ESTIMATE
c. Installation of Ceramic Tiles at proposed Comfort Room for floor & walls sq.m. 66.81 352.84 23,571.68 30,643.18 54,214.86
d. Installation of Ceramic Tiles at the porch, fire exit, landing / step-up sq.m. 38.19 579.43 22,128.34 28,766.84 50,895.18
Application of epoxy counter top finish with cove wall with seamless
f. sq.m. 27.97 650.00 18,181.87 23,636.43 41,818.30
connection (400m height splash board)
Note: Plain Cement Rough Finish Painted Color Gray with PWD Logo
(Color: Blue) for Ramp
600mm x 600mm Granite Tiles pcs
400mm x 400mm Glazed Ceramic Tiles for interior and non-skid for landing
pcs
and step-up
a. Waterline system
Materials required:
40mm DN x 4 mtrs. PPR pipes, PN-16
le. 4.00 - - -
( distribution pipe to building )
32mm DN x 4 mtrs. PPR pipes, PN-16
le. 4.00 - - -
( distribution pipe to building )
25mm DN x 4 mtrs. PPR pipes, PN-16 le. 6.00 - - -
20mm DN x 4 mtrs. PPR pipes, PN-16 le. 10.00 - - -
1-1/4" ø Brass Check valve (MAIN) pc. 1.00 - - -
1-1/4" ø Brass Gate valve (MAIN) pc. 1.00 - - -
1" ø PPR Gate valve pc. 1.00 - - -
3/4" ø PPR Gate valve pc. 2.00 - - -
1/2" ø PPR Gate valve pc. 4.00 - - -
1" PPR female adapter ( for urinal ) pc. 1.00 - - -
1/2" PPR female adapter pc. 29.00 - - -
1/2" S/S 2-way angle valve pc. 5.00 - - -
1/2" S/S 1-way angle valve pc. 19.00 - - -
1/2" heavy duty wall faucet pc. 6.00 - - -
1/2" Bidet with hose and accessories pc. 6.00 - - -
1/2" s/s flexible plumbing hose pc. 14.00 - - -
1/2" Hose bibb (for outside the building) pc. 1.00 - - -
Shower single S/S with complete accessories. set. 2.00 - - -
4"ø S/S floor drain pc. 5.00 - - -
6"ø S/S floor drain pc. 1.00 - - -
PPR fittings and accessories. lot. 1.00 - - -
Sub-Total -
Stainless Steel Deep Sink w/ side drain (minimum size 600mmL x 400mmW
x 300mmD) gauge 16 with complete accessories including S/S steel wall set. 7.00 2,687.00 18,809.00 24,451.70 43,260.70
mount faucet. (for lavolatory)
Single sink counter drain stainless steel (minimum size 600mmL x 400mmW
x 150mmD) gauge 16 with complete accessories including S/S steel wall set. 7.00 1,150.00 8,050.00 10,465.00 18,515.00
mount faucet.
Page 5 of 18
PROJECT : Construction of Calinan Super Health Center
LOCATION : Brgy. Tamayong, Calinan, Davao City
SUBJECT : DETAILED ESTIMATE
wall hung Lavatory with S/S faucet and complete accessories. set. 5.00 1,148.51 5,742.55 7,465.32 13,207.87
Flash tank watercloset, Soap, tissue holder, 1-1/2" grab bar with complete
set. 5.00 7,850.00 39,250.00 51,025.00 90,275.00
accessories.
wall hung Urinal with complete accessories. set. 1.00 1,957.00 1,957.00 2,544.10 4,501.10
S/s bathroom towel holder. set. 2.00 1,200.00 2,400.00 3,120.00 5,520.00
Faucet at the Janitorial Closet & CR. set. 5.00 850.00 4,250.00 5,525.00 9,775.00
Sub-Total 188,642.67
Sub-Total
Total Direct Cost - - 188,642.67
Page 6 of 18
PROJECT : Construction of Calinan Super Health Center
LOCATION : Brgy. Tamayong, Calinan, Davao City
SUBJECT : DETAILED ESTIMATE
- - -
INSTALLATION OF PANELBOARD & BOXES : - - -
175 AT MCCB 3P 240 VAC Automatic Transfer Switch ,can be operated in manual
mode , oven baked & powder finish & epoxy primer coated.
Assy. 1.00 - - -
DISTRIBUTION PANEL 1 - - -
200 AT MCCB, 3Phase, 3Pole 240 VAC 18 kaic " Industrial Type" THJK
Unit 1.00 - - -
or approved equal
125 AT MCCB, 1Phase, 2Pole 240 VAC 18 kaic " Industrial Type" TQD or
Unit 1.00 - - -
approved equal
30 AT MCCB, 1Phase, 2Pole 240 VAC 18 kaic " Industrial Type" TQD or
Unit 1.00 - - -
approved equal
40 AT MCCB, 1Phase, 2Pole 240 VAC 18 kaic " Industrial Type" TQD or
Unit 1.00 - - -
approved equal
70 AT MCCB, 1Phase, 2Pole 240 VAC 18 kaic " Industrial Type" TQD or
Unit 1.00 6,000.00 6,000.00 7,800.00 13,800.00
approved equal
- - -
Page 7 of 18
PROJECT : Construction of Calinan Super Health Center
LOCATION : Brgy. Tamayong, Calinan, Davao City
SUBJECT : DETAILED ESTIMATE
1 x 1.20 m box or batten type Louminaire w/ 18 WATTS Led tube set 55.00 368.00 20,240.00 26,312.00 46,552.00
Square Type 150 mm X 150 mm 11 Watts Led Panel Recessed Type set 32.00 402.50 12,880.00 16,744.00 29,624.00
3 Prong Universal 2 Gang convenience Outlet w/ Grounding. set 68.00 334.40 22,739.20 29,560.96 52,300.16
3 Prong Universal 1 Gang convenience Outlet w/ Grounding. (ACU outlet) set 9.00 340.80 3,067.20 3,987.36 7,054.56
weatherproof cover plate for convenience outlet 2gang 3 prong (for CO-2) set 13.00 941.60 12,240.80 15,913.04 28,153.84
Twin head Emergency lamp set 15.00 1,725.00 25,875.00 33,637.50 59,512.50
300 mm X 300 mm ceiling mounted exhaust fan - 15W (for T&B & EE
set 6.00 1,200.00 7,200.00 9,360.00 16,560.00
room)
CEILING FAN BLADE/OPEN FAN TYPE - LOBBY (w/ remote control or
set 2.00 8,700.00 17,400.00 22,620.00 40,020.00
switch control, 60W)
Nema- 3R enclosure w/ 30AT circuit breaker (for condensing uint of split
set 3.00 2,500.00 7,500.00 9,750.00 17,250.00
type acu)
SWITCHES - - -
1 Gang " Flush Type " Switch set 19.00 - - -
2 Gang " Flush Type " Switch set 10.00 - - -
3 Gang " Flush Type " Switch set 5.00 - - -
F1 Junction Box Pc. 121 - - -
f1 Utility Box Pc. 111.00 - - -
BRANCH CIRCUIT LINE - - -
5.5 mm 2 Thw Cu Wire roll. 6.00 - - -
3.5 mm 2 Thw Cu Wire roll. 15.00 - - -
20 mm Ø PVC Pipe pc. 150.00 - - -
- - -
DESCRIPTION - - -
Page 8 of 18
PROJECT : Construction of Calinan Super Health Center
LOCATION : Brgy. Tamayong, Calinan, Davao City
SUBJECT : DETAILED ESTIMATE
• Fire Hose Cabinet, complete set, 1-1/2" x 100 ft. fire hose, single jacket,
set 1.00 11,200.00 11,200.00 14,560.00 25,760.00
aluminum frame, included complete accessories.
. Consumables Materials
• Welding rod, paint red oxide intenational red, paint thinner, teflon tape, 4'
lot. 1.00 5,000.00 5,000.00 6,500.00 11,500.00
grinding cutting disc and others.
• Sealant, bolts nuts, hangers and supports, including full threaded rod, bolts
lot. 1.00 5,000.00 5,000.00 6,500.00 11,500.00
and nuts, angle bars, pipe sleeve, expansion bolts and others…
b. EXHAUST SYSTEM
Materials required:
4" Ø x 3m PVC Series-1000 le. 10.00 1,040.00 10,400.00 13,520.00 23,920.00
3" Ø x 3m PVC Series-1000 le. 3.00 721.20 2,163.60 2,812.68 4,976.28
159-194 cfm, 490 rpm, 25watts ceiling mounted type exhaust fan pcs. 5.00 1,150.00 5,750.00 7,475.00 13,225.00
60-90 cfm, 980 rpm, 13watts ceiling mounted type exhaust fan pcs. 3.00 950.00 2,850.00 3,705.00 6,555.00
150mm x 150mm wall type, paint finish exhaust grill or vent grill set 2.00 549.63 1,099.26 1,429.04 2,528.30
Consumables Materials
• Sealant, bolts nuts, hangers and supports, including full threaded rod, bolts
lot. 1.00 10,000.00 10,000.00 13,000.00 23,000.00
and nuts, angle bars, pipe sleeve, expansion bolts and others…
Labor
Supply & Install Fire Extinguisher (Lab./Records/Pharmacy/ Recovery
c.
Room)
10lbs CO2 with Wall Hanger set 4.00 2,800.00 11,200.00 14,560.00 25,760.00
Total Direct Cost 95,431.19 124,060.55 219,491.74
a. Surface preparation & painting of the entire SHC sq.m 2,284.80 91.03 207,985.34 270,380.94 478,366.28
Wooden Surface Area (Jambs, Ceiling, gable, cabinets, doors & window
b. sq.m 346.96 20.92 7,258.40 9,435.92 16,694.32
grills)
Flat Latex gal.
Semi-Gloss Latex gal.
Flat Wall Enamel gal.
Semi-Gloss Enamel gal.
Concrete Neutralizer gal.
Tinting Color pint
Polymer Body Filler gal.
Paint Thinner gal.
Paint Putty / Cast gal.
Paint Roller w/ Tray set
Paint Brush pc.
Masking Tape pc.
Waste Cotton kg. `
Assorted Sand Paper pc.
Total Direct Cost 495,060.60
Name:
In capacity of:
Signed:
Duly Authorized to Sign on behalf of:
Page 9 of 18
Republic of the Philippines
Department of Health
DAVAO CENTER FOR HEALTH DEVELOPMENT
J.P Laurel Ave,. Bajada, Davao City
A. DIRECT COST
I. GENERAL REQUIREMENTS 1.49% 161,600.00
II. SITE WORKS 0.45% 49,097.49
III. EARTHWORKS 1.97% 214,229.05
IV. FORMWORKS & SCAFFOLDINGS 2.34% 254,035.00
V. REINFORCED CONCRETE WORKS 28.62% 3,108,762.11
VI. MASONRY WORKS 12.68% 1,377,136.50
VII. CARPENTRY WORKS 2.00% 216,843.47
VIII. STEEL WORKS 5.45% 592,113.61
IX. TINSMITHRY WORKS 0.00% -
X. DOORS 0.00% -
XI. WINDOWS 0.00% -
XII. TILE WORKS & OTHER FINISHES 6.05% 656,873.97
XIII. PLUMBING WORKS 1.74% 188,642.67
XIV. ELECTRICAL WORKS 10.60% 1,151,117.94
XV. MECHANICAL WORKS 2.02% 219,491.74
XVI. PAINTING WORKS 4.56% 495,060.60
B. INDIRECT COST
1 Overhead Expenses & Supervision 173,700.08
2 Contingencies 173,700.08
3 Miscellaneous 173,700.08
4 Contractor's Profit 868,500.42
5 Taxes (12% of [ ( A.1-6 + B.1-4 ) ]) 786,535.30
Name :
In the Capacity of:
Signed:
a. Provision of formworks and scaffolding must be a fixed connection and should have enough and proper bracing for safety purposes.
b. Use assorted sizes of coco lumber and ordinary 5mm thk x 4' x 8' plywood for formworks and scaffoldings.
c. Use coco lumber for batterboard and stakes.
V. REINFORCED CONCRETE WORKS
a. Concrete Works
− Total volume of foundation and slab gravel bedding is approximately 102cu.m.
− Total volume of Footing, Column, Pedestal, Ledge, Lintel & Roof Beam, Slab, Ramp and Countertop sink is approximately
156.80cu.m.
− Pouring of concrete must be clean and free from any organic materials.
− Use 3/4" gravel for gravel bedding with minimum 100mm thick.
− Provide concrete for Footings, Columns, Wall Footings, Slab-on-fill, as indicated in the drawings.
− Pouring of concrete shall be clean and free from any organic materials.
− Minimum compressive strength of concrete is 3500Psi.
b. STEEL REINFORCING BARS
− Provide the required steel reinforcement whether or not indicated in the drawings for the construction of new structural
components described above.
− All deformed reinforced bars shall be graded 40 with a minimum steel yield stress of 280 MPa based on laboratory test. .
c. Secure and submit laboratory testing results for concrete and steel reinforcement.
VI. MASONRY WORKS
Construction of CHB wall partitions, counters, ramps, landing (both interior & extrior); plain plaster finish * using class B mixture
a.
(including sink counter & porch )
− Total Area of CHB Walls is approximately 672sq.m
−Use 100mm and 150mm thk. Machine made CHB on ProposedCHB Wallswith minimum compressive strength of CHB is 350Psi.
− Minimum of 16mm thick for plastering of walls and exposed concrete structure, smooth finish
− Total Area of plastering on CHB Walls is approximately 1344sq.m
VII. CARPENTRY WORKS
vii.a. Installation of fiber cement board on furring ceiling system (interior)
vii.a. Installation of fiber cement board on furring ceiling system with vents (exterior eaves and gable)
Total area covered is approximately 484sq.m
- Use 4.5mm thk fiber cement board as ceiling cover sheets with wooden ventilation (along the perimeter of the eaves)
- Use Aluminum metal furring for ceiling joist spaced at 0.6m bothways on center.
Page 11 of 18
- Provide aluminum carrying channel spaced at 0.6 m on center.
− Use 4.5mm THK, 4' x 8' Fiber Cement Board
− Use 400mm x 400mm sp. of metal furring and 1000mm Carrying Channel
- Provide aluminum wall angle every wall side.
- Use carrying channel as hanger instead of hanger rod.
- Use approved equivalent fastener to fixed connection.
- All ceiling joist shall be fixed and properly alligned before installtion of ceiling
sheets.
- Use Kiln Dried Good Lumber (2" x 2" & 2" x 4") for supports & studs
VIII. STEELWORKS
viii. Fabrication & Installation of steel trusses, struts, & fascia frame
Fabrication and installation of steel framings/purlins in preparation for the installation of roofing sheets
Fabrication and installation of stainless steel railing 38mm diameter #304 with end caps at the ramp, porch, landings & step-ups.
− Use 6mm x 50mm x 50mm x 3/16" Angle bar ( top,bottom & web chord )
− Use 25mm x 6m angle bar ( steel facia frame )
− Use 1.5 mm x 50mm x 100mm cee steel purlins (painted w/ red oxide)
− Use 16mm x 6.0m plain round bar sag rod with cross bracing and 10mm dia. X 300mm turn buckle at both ends.
− All connection must be fixed, alligned and welded properly.
− All steel must be painted with steel primer before installation to avoid corrosion.
X. DOORS
vi.a. Installation of New Doors ( See door schedule and details )
Quantity: 2 unit
D-1 Double Swing Glass Door with transom (2.650mW x 2.65mH), (50mm x 100mm Analok Aluminum Frame Door Jamb, 50mm x
50mm Analok Aluminum Door Frame, 50mm x 100mm Analok Aluminum Frame Door w/ 6mm thk. Clear Glass) with aluminum
handrail, overhead concealed door closer, includes hardware accessories and installation.
Quantity: 4 units
D-1a Double Swing Hollow Core Steel Door Type with 6mm. thk. transom glass (1.60mW x 2.65mH), Steel door jamb, Top and
bottom heavy duty pivot hinges, Lever type heavy duty door handle with chrome finish, 150 x 400mm stainless steel kick plate (back
to back) and (600 x 300 x 6mm) thk. viewing glass (verify plan).
Quantity: 3 units
D-2 Double Swing Glass Door with transom and side fixed glass (2.65mW x 2.65mH), (50mm x 100mm Analok Aluminum Frame
Door Jamb, 50mm x 50mm Analok Aluminum Door Frame, 50mm x 100mm Analok Aluminum Frame Door w/ 6mm thk. Clear
Glass) with aluminum handrail, overhead concealed door closer, includes hardware accessories and installation.
Quantity: 1 unit
D-2a Double Swing Hollow Core Steel Door Type with 6mm. Thk. Transom glass (1.3mW x 2.65mH). Steel door jamb, Tap and
bottom heavy duty pivot hinges. Lever type heavy duty door handle with chrome finish, 150 x 400mm stainless steel hand push plate
(back to back), 800 x 400mm stainless kick plate (back to back) and (600 x 300 x 6mm) thk. viewing glass (Verify plan)
Quantity: 5 units
D-3 Single Swing Glass Door with transom (0.90mW x 2.65mH), (50mm x 100mm Analok Aluminum Frame Door Jamb, 50mm x
50mm Analok Aluminum Door Frame, 50mm x 100mm Analok Aluminum Frame Door w/ 6mm thk. Clear Glass) with aluminum
handrail, overhead concealed door closer, includes hardware accessories and installation.
Quantity: 2 units
D-4 Single Swing Hollow Core Steel Door Type with 6mm thk transom glass (0.8mW x 2.65mH), Steel door jamb, Top and bottom
heavy duty pivot hinges, Lever type heavy duty handle with chrome finish, 800 x 400mm stainless steel kick plate (back to back).
Verify plan
Page 12 of 18
Quantity: 2 units
D-4a Flush door type single swing door with viewing glass & transom (0.8mW x 2.15mH), 50mm x 150mm door jamb kiln dried solid
wood, 50mm x 150mm flush door frame, KD Solid Wood, 100mm x 100mm ball bearing door hinges, stainless (see image), 6mm
thick clear glass, with lever type door handle satin chrome finish, 6mm thick marine plywood(grade2), 12mm x 50mm solid wood
moulding (front only), includes complete hardware accessories and installation.
Quantity: 4 units
D-5 PVC with louver type swing door, (0.80mW x 2.150mH), with heavy duty lever type door handle chrome finish, door hinges,
includes complete hardware accessories and installation. Verify plan
Quantity: 1 unit
D-6 PVC with louver type swing door, (1.00mW x 2.150mH), with lever type door handle chrome finish, door hinges, includes
complete hardware accessories and installation.
Quantity: 1 unit
D-7 PVC with louver type swing door, (0.60mW x 2.150mH), with lever type door handle chrome finish, door hinges, includes
complete hardware accessories and installation.
Quantity: 2 units
D-8 Single Swing Steel Door Type (0.90mW x 2.15mH) with lever type door handle chrome finish, door hinges with paint finished
includes complete hardware accessories and installation. Verify plan
Quantity: 1 unit
D-9 Single Swing Grill Door Type (0.80mW x 2.15mH) with steel door handle with paint finish, cylindrical door hinges includes
complete hardware accessories and installation. Verify plan
XI. WINDOWS
vi.a. Installation of Windows with complete accessories. See drawing details
Quantity: 1 unit
W-1, (1.65mW x 2.350mH ), Fixed type Aluminum Window , 50mm x 100mm analok aluminum frame with snap-on for glass holding
frame,6mm thk. Clear Glass window includes window lock, analok finish aluminum aluminum frame, with hardware accessories and
installation (see plan)
Quantity: 2 unit
W-2, (1.65mW x 1.750mH ), Aluminum Window with transom, 50mm x 100mm analok aluminum frame with snap-on for glass
holding frame,6mm thk. Clear Glass window includes window lock, analok finish aluminum aluminum frame, with hardware
accessories and installation (see plan)
Quantity: 3 units
W-3, (1.6mW x 0.650mH ), Casement Type, Aluminum High Window Type, 50mm x 100mm analok aluminum frame, 6mm thk.
Clear Glass window, analok finish aluminum frame with hardware accessories and installation. (Verify plan)
Quantity: 7 units
W-4, (1.60mW x 1.750mH ), Casement Type, Aluminum Window with transom, 50mm x 100mm analok aluminum frame with snap-
on for glass holding frame,6mm thk. Clear Glass window includes window lock, analok finish aluminum aluminum frame, with
hardware accessories and installation (see plan)
Quantity: 2 units
W-5 , (1.10mW x 1.650mH ), Aluminum Window with transaction window and transaction counter , 50mm x 100mm analok
aluminum frame with snap-on for glass holding frame,6mm thk. Clear Glass window includes window lock, analok finish aluminum
aluminum frame, with hardware accessories and installation (see plan)
Quantity: 1 unit
W-6 , (1.30mW x 1.650mH ), Aluminum Window with transaction window and transaction counter , 50mm x 100mm analok
aluminum frame with snap-on for glass holding frame,6mm thk. Clear Glass window includes window lock, analok finish aluminum
aluminum frame, with hardware accessories and installation (see plan)
Quantity: 1 unit
W-7 , (2.350mW x 1.600mH ), Aluminum Window with transaction window and transaction counter , 50mm x 100mm analok
aluminum frame with snap-on for glass holding frame,6mm thk. Clear Glass window includes window lock, analok finish aluminum
aluminum frame, with hardware accessories and installation (see plan)
Quantity: 1 unit
W-8, (0.80mW x 1.750mH ), Aluminum Fixed Window with transom, 50mm x 100mm analok aluminum frame with snap-on for glass
holding frame,6mm thk. Clear Glass window includes window lock, analok finish aluminum aluminum frame, with hardware
accessories and installation (see plan)
Quantity: 7 units
Page 13 of 18
W-9, (0.80mW x 0.65mH ), Aluminum casement type window, 50mm x 100mm analok aluminum frame with snap-on for glass
holding frame,6mm thk. Clear Glass window includes window lock, analok finish aluminum aluminum frame, with hardware
accessories and installation (see plan)
Application of Monolithic Seamless Chemical resistant Vinyl Flooring with integral Cove base & on Laboratory counter-top coves
Page 14 of 18
1.) Supply & Installation of Main Service Entry conductor , from Service point to main breaker inside 25 mm Ø RSC Pipe. Supply
and installation of OUTDOOR NEMA 3R ENCLOSURE WITH 60AT ACB 240 VAC FOR OUTDOOR MAIN DISCONNECT
2. ) Supply & Installation of Wires( BRANCH CKT LINES ) for ligthing fixtures , Convenience Outlet t inside 20 mm Ø PVC Pipe
Conduit & fittings . Note : Rough ins ( wires inside 20 mm Ø PVC Pipe & fittings ) should be provided for CEILING FAN locations
3.) Supply & Installation of Lighting fixtures (ensure proper installation lighting fixture should be properly fixed to ceiling)
4.) Supply & Installation of Outlets: Provide Grounding Conductor per Convenience Outlet(including range ,ref ,acu outlet)
fixtures, note : consider proper elevation refer to plan legend/symbols
5. ) Supply & Installation of SWITCHES (refer to plan for proper switching location )
6. ) Supply & Installation of Panelbard , Boxes , Breakers & Automatic Transfer Switch
Note : provide Grounding
Bus for ckt home run of branch circuit grounding conductors
7. ) Supply & Installation of Electrical Boxes and Misc
OTHER CONSIDERATIONS :
- Supply & Installation of Grounding conductor for convenience outlets and Ceiling fans , ACU outlets to be tapped to Grounding
Bus of Panel Board and Supply and installation of Grounding conductor from Panel Board Grounding Bus to Grounding Lug
* Consider Proper Conduit runs Avoid excessive bends on PVC pipe and fittings
XV. MECHANICAL WORKS
1.) Supply & installation of schedule 40 BI pipes and fittings for the proposed dry stand pipe.
2. ) Supply & installation of 2.5" x 2.5" x 2.5" diameter Fire Department Connection / Siamese Twin, brass, W/ chain & Cap with
65mmØ blind flange with bolts and nuts
− Provide sealant, bolts nuts, hangers and supports, including full threaded rod, bolts and nuts, angle bars, pipe sleeve, expansion
bolts and others.
− Use threading machine for the ends of the pipes.
− All joints must be fixed and properly alligned before testing and commissioning.
OTHER CONSIDERATIONS :
- Provide and apply the minimum stanards for the installation based on the Fire Code of the Philippines, National Pipe Standard,
National Fire Protection Association (NFPA 13), Plumbing Code of the Philippines, Uniform Plumbing Code and American Society
for Testing and Materials (ASTM).
XVI. PAINTING WORKS
Priming & Painting of Interior & Exterior Walls, Doors, Windows, and Jambs, Roofing and Ceiling
Total area covered = 2,631.76 sq.m
- Includes putting of Neutralizer, putty, filler, epoxy adhesive and primer on all surfaces required for Surface preparation.
- Use Semi-Gloss latex Paint for Concrete Surfaces with a minimum of two ( 2) coats.
- Use Flat latex Paint for Exterior and Interior Ceiling with a minimum of two ( 2) coats.
- Use Gloss Enamel Paint for Wooden and Steel Surfaces with a minimum of two ( 2) coats.
- Use Body Filler and Non-sag epoxy to holes and cracks.
- Use approved tinting color for the suggested color by the End-user.
- Use approved equivalent accessories for painting requirements as per standard specification.
- All painted surfaces shall be clean and smoth.
III. .
Miscellaneous incidental materials not specifically mentioned herein or in other section of this specification but are required to
complete the work, for which there are no detailed drawings, shall be provided and installed in accordance with standard practice of
the trades as approved by the project engineer.
The contractor shall be responsible for protecting the structure during construction and to leave the building '' broom and clean "
ready for full occupancy by the end users.
________________________________
CONTRACTOR/BIDDER
Page 15 of 18
Page 16 of 18
Project: CONSTRUCTION OF CALINAN SUPER HEALTH CENTER
Location: Brgy. Tamayong, Calinan,Davao City
Cash Flow and Payment Schedule
DESCRIPTION 1st QUARTER 2nd QUARTER 3rd QUARTER 4th QUARTER
Submitted by:
Renato C Ramos
General Manager
Villaram Builders
Project: Construction of Rizal Municipal Police Station Building ( Type "BC")
Location : Brgy. Pauli 2, Rizal, Laguna
ITEM RATE/DAY
Project Manager 1,500.00
Project Engineer 1,500.00
Materials Engineer 1,000.00
Registered Electrical Engineer 1,000.00
Construction Safety Officer 700.00
Civil/Site Engineer 1,000.00
Foreman 800.00
Submitted by:
RENATO C. RAMOS
General Manager/ Villaram Builders