Professional Documents
Culture Documents
10-2023 - Midor Project Cementitious Fireproofing Progress Report.
10-2023 - Midor Project Cementitious Fireproofing Progress Report.
10-2023 - Midor Project Cementitious Fireproofing Progress Report.
Project Manager
osama kheadry
Client: Petrojet
Project: Midor Project Cementitious Fireproofing
Job ID: 4290321053237 & 4290321053383
Dry bond 540 250.00 250.00 42.96 14% 48.97 12,243.60 - - - 12,243.60
Wire mesh 50*50*1.5 mm 1,500.00 150.00 1,350.00 16.40 14% 18.70 28,044.00 - - 2,804.40 25,239.60
Isolatek MII From El Nasr project 50.00 50.00 - 444.92 444.92 22,246.00 - - 22,246.00 -
Isolatek MII New Ordar 0.00 950.00 200.00 550.00 200.00 840.00 840.00 - 798,000.00 168,000.00 462,000.00 168,000.00
Jotashield colourlast Glossy 370.00 370.00 101.80 14% 116.05 42,939.24 - - - 42,939.24
SikaCryl-621 987 144.00 57.00 87.00 250.00 14% 285.00 41,040.00 - - 16,245.00 24,795.00
0.00 - - - - - - -
0.00 - - - - - - -
0.00 - - - - - - -
0.00 - - - - - - -
0.00 - - - - - - -
Contract # 1 8,570.00 8,929,612.17 3,863,316.69 1,393,047.21 14,185,976.08 9,771.47 17,299,960.08 - - - 9,771.47 17,299,960.08
Contract # 2 EGP 740.00 6,309,021.48 2,520,006.20 887,648.86 9,716,676.54 580.00 5,815,178.42 319.00 296.38 1,228,254.98 899.00 7,043,433.39
GRAND TOTAL 9,310.00 15,238,633.65 6,383,322.89 2,280,696.07 23,902,652.62 10,351.47 23,115,138.49 319.00 296.38 1,228,254.98 10,670.47 24,343,393.47
Data Unit Previous Current Cumulative
Denisty kg/m3 736 736 736
Weight kg/Bag 22.6 22.6 22.6
Volume m3/Bag 0.031 0.031 0.031
Thickness mm 0.04 0.04 0.04
Theo. m2 0.77 0.77 0.77
Theo.material Bag 30026.0 696.9 30723.0
m3 529 9 538
Area
m2 9,822 310 10,132
Material Bag 26,650 600 27,250 (6,231.87) (3,801,441.41)
Loses % -11.2% -14% -11.3%
24,600
TyssenKrupp Xervon - Egypt
System
Total contract Total contract UNIT PRICE
DESCRIPTION PRICE (EGP) PRICE (EGP)
Area (m2) Amount (EGP) PRICE (EGP) (EGP)
PREVIOUS CURRENT CUMULATIVE Application Supply PREVIOUS CURRENT CUMULATIVE PREVIOUS CURRENT CUMULATIVE PREVIOUS CURRENT CUMULATIVE PREVIOUS CURRENT CUMULATIVE PREVIOUS CURRENT CUMULATIVE PREVIOUS NET PREVIOUS NET
Scaffolding
1.1 1,250.00 1,431,250.00 Steel Structure 6m height + scaf 484.45 - 484.45 1,145.00 357.17 190.29 597.54 173,030.35 - 173,030.35 92,185.95 - 92,185.95 289,476.50 - 289,476.50 554,692.80 - 554,692.80 563,488.85 563,488.85 (8,796.05) (8,796.05) (7.68) (7.68)
1.2 875.00 1,028,125.00 Steel Structure 6-12m height +scaf 1,002.25 - 1,002.25 1,175.00 387.17 190.29 597.54 388,041.19 - 388,041.19 190,718.82 - 190,718.82 598,883.23 - 598,883.23 1,177,643.24 - 1,177,643.24 1,072,281.50 1,072,281.50 105,361.74 105,361.74 89.67 89.67
1.3 1,600.00 1,909,696.00 Steel Structure >12m height +scaf 1,179.60 - 1,179.60 1,193.56 405.73 190.29 597.54 478,600.32 - 478,600.32 224,467.41 - 224,467.41 704,858.43 - 704,858.43 1,407,926.16 - 1,407,926.16 1,418,080.57 1,418,080.57 (10,154.41) (10,154.41) (8.51) (8.51)
1.4 425.00 358,394.00 Steel Structure 6m height 1,422.48 - 1,422.48 843.28 245.74 - 597.54 349,562.08 - 349,562.08 - - - 849,988.43 - 849,988.43 1,199,550.51 - 1,199,550.51 1,234,966.69 1,234,966.69 (35,416.19) (35,416.19) (42.00) (42.00)
1.5 600.00 505,968.00 Steel Structure 6-12m height 1,959.99 - 1,959.99 843.28 245.74 - 597.54 481,648.67 - 481,648.67 - - - 1,171,167.65 - 1,171,167.65 1,652,816.32 - 1,652,816.32 1,687,934.55 1,687,934.55 (35,118.23) (35,118.23) (41.64) (41.64)
1.6 575.00 484,886.00 Steel Structure >12m height 768.82 - 768.82 843.28 245.74 - 597.54 188,929.84 - 188,929.84 - - - 459,398.17 - 459,398.17 648,328.01 - 648,328.01 683,090.53 683,090.53 (34,762.52) (34,762.52) (41.22) (41.22)
1.7 1,300.00 1,488,500.00 Equipment 6m+scaf 394.24 - 394.24 1,145.00 306.81 118.93 719.26 120,956.64 - 120,956.64 46,887.84 - 46,887.84 283,562.26 - 283,562.26 451,406.74 - 451,406.74 455,927.55 455,927.55 (4,520.81) (4,520.81) (3.95) (3.95)
1.8 165.00 193,875.00 Equipment > 6m+scaf 32.66 - 32.66 1,175.00 336.81 118.93 719.26 10,999.97 - 10,999.97 3,884.24 - 3,884.24 23,490.63 - 23,490.63 38,374.85 - 38,374.85 40,901.75 40,901.75 (2,526.90) (2,526.90) (2.15) (2.15)
1.9 400.00 389,340.00 Equipment 6 m 1,799.77 - 1,799.77 973.35 254.09 - 719.26 457,302.51 - 457,302.51 - - - 1,294,499.20 - 1,294,499.20 1,751,801.71 - 1,751,801.71 1,775,039.99 1,775,039.99 (23,238.29) (23,238.29) (23.87) (23.87)
1.10 110.00 105,774.90 Equipment >6m 69.25 - 69.25 961.59 242.33 - 719.26 16,781.74 - 16,781.74 - - - 49,809.89 - 49,809.89 66,591.62 - 66,591.62 69,446.03 69,446.03 (2,854.41) (2,854.41) (2.97) (2.97)
1.11 42.50 778,600.00 Steel Box Section 6m +Scaf 34.81 - 34.81 18,320.00 2,427.11 1,646.01 14,246.88 84,481.14 - 84,481.14 57,293.44 - 57,293.44 495,896.31 - 495,896.31 637,670.90 - 637,670.90 641,566.40 641,566.40 (3,895.50) (3,895.50) (0.21) (0.21)
1.12 75.00 1,491,750.00 Steel Box Section 6m-12m+Scaf 30.20 - 30.20 19,890.00 3,997.11 1,646.01 14,246.88 120,705.48 - 120,705.48 49,706.73 - 49,706.73 430,230.43 - 430,230.43 600,642.64 - 600,642.64 603,064.80 603,064.80 (2,422.16) (2,422.16) (0.12) (0.12)
1.13 82.50 1,766,992.42 Steel Box Section >12m+Scaf 136.07 - 136.07 21,418.09 5,525.20 1,646.01 14,246.88 751,835.54 - 751,835.54 223,979.87 - 223,979.87 1,938,630.15 - 1,938,630.15 2,914,445.56 - 2,914,445.56 2,945,201.56 2,945,201.56 (30,756.00) (30,756.00) (1.44) (1.44)
1.14 12.50 208,000.00 Steel Box Section 6m 136.71 - 136.71 16,640.00 2,393.12 - 14,246.88 327,156.23 - 327,156.23 - - - 1,947,647.71 - 1,947,647.71 2,274,803.94 - 2,274,803.94 2,287,334.40 2,287,334.40 (12,530.46) (12,530.46) (0.75) (0.75)
1.15 22.50 397,800.00 Steel Box Section 6m-12m 70.79 - 70.79 17,680.00 3,433.12 - 14,246.88 243,045.50 - 243,045.50 - - - 1,008,598.49 - 1,008,598.49 1,251,643.99 - 1,251,643.99 1,267,479.20 1,267,479.20 (15,835.21) (15,835.21) (0.90) (0.90)
1.16 25.00 465,324.75 Steel Box Section >12m 36.08 - 36.08 18,612.99 4,366.11 - 14,246.88 157,544.38 - 157,544.38 - - - 514,076.74 - 514,076.74 671,621.11 - 671,621.11 692,589.36 692,589.36 (20,968.25) (20,968.25) (1.13) (1.13)
2.2 850.00 994,500.00 Steel Structure 6-12m height +scaf - - - 1,170.00 382.17 190.29 597.54 - - - - - - - - - - - - 124,827.30 124,827.30 (124,827.30) (124,827.30) (106.69) (106.69)
2.8 160.00 187,200.00 Equipment > 6m+scaf - - - 1,170.00 331.81 118.93 719.26 - - - - - - - - - - - - - - - - - -
Extra work Metal lath apllication (m2) 980.00 - 980.00 120.00 120.00 - - 117,600.00 - 117,600.00 - - - - - - 117,600.00 - 117,600.00 100,303.20 100,303.20 17,296.80 17,296.80 144.14 144.14
Extra work Metal lath apllication (m3) 58.00 - 58.00 1,200.00 1,200.00 - - 69,600.00 - 69,600.00 - - - - - - 69,600.00 - 69,600.00 43,536.00 43,536.00 26,064.00 26,064.00 21.72 21.72
Extra work for Repair work per point 110.00 113.00 223.00 900.00 900.00 - - 99,000.00 101,700.00 200,700.00 - - - - - - 99,000.00 101,700.00 200,700.00 - 200,700.00 200,700.00 99,000.00 - 110.00 -
3.1 450.00 44,586.00 Steel Structure 6-12m height +scaf - - - 99.08 23.00 18.08 58.00 - - - - - - - - - - - - - - - - - -
3.2 15.00 1,508.85 Steel Structure >12m height +scaf - - - 100.59 23.00 19.59 58.00 - - - - - - - - - - - - - - - - - -
3.3 150.00 12,163.50 Steel Structure 6-12m height 481.56 288.02 769.58 81.09 23.00 - 58.09 11,075.96 6,624.42 17,700.38 - - - 27,974.04 16,730.98 44,705.02 39,050.00 23,355.40 62,405.40 53,517.78 53,517.78 (14,467.78) 8,887.62 (178.42) 109.60
3.4 5.00 405.45 Steel Structure >12m height - - - 81.09 23.00 - 58.09 - - - - - - - - - - - - - - - - - -
3.5 75.00 163,538.25 Steel Box Section 6m-12m+Scaf - - - 2,180.51 561.00 217.28 1,402.23 - - - - - - - - - - - - - - - - - -
3.6 15.00 33,458.40 Steel Box Section >12m+Scaf - - - 2,230.56 561.00 267.33 1,402.23 - - - - - - - - - - - - - - - - - -
3.7 25.00 49,080.75 Steel Box Section 6m-12m 76.00 8.36 84.36 1,963.23 561.00 - 1,402.23 42,635.69 4,688.31 47,324.00 - - - 106,568.71 11,718.51 118,287.22 149,204.40 16,406.82 165,611.22 148,086.44 148,086.44 1,117.96 17,524.78 0.57 8.93
3.8 5.00 9,816.15 Steel Box Section >12m - - - 1,963.23 561.00 - 1,402.23 - - - - - - - - - - - - - - - - - -
8,570.00 14,185,976.08 Total Contract # 1 10,706.17 113.00 10,819.17 4,636,821.57 101,700.00 4,738,521.57 889,124.30 - 889,124.30 12,060,214.21 - 12,060,214.21 17,586,160.08 101,700.00 17,687,860.08 17,707,060.23 200,700.00 17,907,760.23 (120,900.15) (219,900.15)
740.00 9,751,277.85 Total Contract # 2 EGP 557.56 296.38 853.94 1,659,153.07 349,450.15 2,008,603.21 - - - 4,156,025.35 878,804.83 5,034,830.18 5,815,178.42 1,228,254.98 7,043,433.39 6,227,645.08 - 6,227,645.08 (412,466.66) 815,788.31
9,310.00 23,937,253.93 TOTALS EGP 11,263.73 409.38 11,673.10 6,295,974.64 451,150.15 6,747,124.78 889,124.30 - 889,124.30 16,216,239.56 878,804.83 17,095,044.39 23,401,338.49 1,329,954.98 24,731,293.47 23,934,705.31 200,700.00 24,135,405.31 (533,366.82) 595,888.16
314,557.35
5/
Indirect Direct Subcontractor
Month Painting (m2) Medical fees
Manpower Manpower Application
CONSUMABLE
Accommodation Transportation Personnel Supply S
DIESEL
5763.5
Application Scaffolding Total
Over Head Total Cost Supply Revenue
Revenue Revenue Valuation
4,947,758.09
29,801,208.63
Margin %
Margin %
(28,495.14) -39%
(17,853.59) -12%
(20,084.21) -8%
47,290.25 9%
143,504.82 17%
58,476.08 12%
150,752.70 17%
(71,169.61) -9%
152,889.56 12%
104,868.58 7%
(267,439.81) -16%
(211,253.06) -12%
(37,765.06) -3%
(885,396.65) -53%
41,891.21 5%
(487,150.90) -39%
(487,504.52) -43%
(228,745.40) -25%
950,885.24 31% ### 857,427.27 997,952.40
1,511,764.39 55% ### 824,116.78 505,838.20
505,838.20 38%
- 0 525,424.69 33,310.49 492,114.20
- 0
- 0
- 0
- 0
- 0
- 0
- 0 17,000,000.00
- 0 2,210,000.00
925,303.06 3.74%
EPC Project
Productivity
Average No. of coats/1m2 sand
Blasting area Painting area Blasting
m2 0
Personnel 252,339.00 0
Material 503,899.40 0
Equipment - 0
General 67,878.38 0
Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22 Nov-22 Dec-22 Jan-23 Feb-23 Mar-23
Actual Cash In 2,837,195 1,255,065 1,128,203 1,456,393 4,801,931
Actual cash in Accumalative - - 2,837,195 2,837,195 2,837,195 2,837,195 2,837,195 4,092,260 4,092,260 5,220,462 5,220,462 6,676,855 6,676,855 ###
Social insurance 16,885
Materiales
Actual Cash out 101,142 155,573 277,160 438,289 653,920 419,330 812,575 851,678 1,108,771 1,408,808 1,901,230 1,993,281 1,358,072 2,565,182
Actual Cash out Accum 101,142 256,715 533,874 972,163 1,626,083 2,045,413 2,857,988 3,709,666 4,818,437 6,227,245 8,128,475 ### ### ###
Actual Net Cash (101,142) (256,715) 2,303,321 1,865,032 1,211,112 791,782 (20,793) 382,594 (726,177) (1,006,782) (2,908,013) (3,444,901) (4,802,973) (2,566,225)
25,000,000
20,000,000
15,000,000
10,000,000
5,000,000
-
Oct-21 Feb-22 May-22 Aug-22 Dec-22 Mar-23 Jun-23 Oct-23 Jan-24
Contractual
Difference
Advance Performance Witholding Other Expected
Actual
Description Invoice Issued Date Retention Social insurance Stamp fees Receipt
Amount % Payment Bond Tax Deduction Amount % Receiving
1 Progress 01/03/2022 To 30/06/2022 18/Jul/22 1,876,166.18 13.2% 187,616.62 375,233.24 42,557.00 15,694.74 1,255,064.59 8.8% 9/1/2022 9/19/2022 45 63 18
2 Against Materiales 1 18/Aug/22 1,611,718.00 11.4% 161,171.80 322,343.60 1,128,202.60 8.0% 10/2/2022 11/6/2022 45 80 35
3 Progress 01/07/2022 To 20/10/2022 14/Nov/22 2,098,251.14 14.8% 209,825.11 419,650.23 12,382.74 1,456,393.06 10.3% 12/29/2022 1/17/2023 45 64 19
4 Progress 21/10/2022 To 25/12/2022 1/Jan/23 3,304,653.52 23.3% 330,465.35 660,930.70 5,744.48 2,307,512.98 16.3% 2/15/2023 3/8/2023 45 66 21
5 Against Materiales 2 25/Jan/23 3,563,453.86 25.1% 356,345.39 712,690.77 2,494,417.70 17.6% 3/11/2023 3/22/2023 45 56 11
6 Progress 26/12/2022 To 10/03/2023 15/Mar/23 1,656,250.25 11.7% 165,625.03 331,250.05 2,790.17 1,156,585.01 8.2% 4/29/2023 7/12/2023 45 119 74
7 Metal Lath Erection Invoice # 01 21/Jun/23 143,839.20 0.0% 14,383.92 129,455.28 0.0% 8/5/2023 11/27/2023 45 159 114
8 Progress 11/03/2023 To 04/07/2023 10/Jul/23 2,778,971.23 19.6% 277,897.12 15,096.62 177,324.70 2,308,652.79 0.0% 8/24/2023 11/27/2023 45 140 95
9 Progress 05/07/2023 To 09/09/2023 12/Sep/23 673,756.84 0.0% 67,375.68 606,381.15 0.0% 10/27/2023 11/27/2023 45 76 31
10 Progress 26/07/2023 To 23/09/2023 USD 24/Sep/23 6,227,554.27 622,755.43 224,191.95 5,380,606.89 11/9/2023 11/27/2023 46 64 18
11 FP Repair Invoice # 01 23/Oct/23 200,700.00 20,070.00 180,630.00 12/7/2023 11/27/2023 45 35 (10)
0.0% - 0.0% 45 - (45)
Total 23,991,475.28 169.12% 2,413,531 2,837,195 177,325 224,192 - 42,557 36,612 18,260,062.84 128.72% 91