This weekly report details the surveying and dredging progress made by the Lot 3 contractor on Route 21 from November 15th to November 21st. It shows that there was no surveying, surveying progress, total surveying completed, or dredging progress during this period. A note explains that dyke construction activities were ongoing on Route 21 instead.
Original Description:
Original Title
5th Weekly Report on Survey and Dredging Progress of Lot 3 Contractor
This weekly report details the surveying and dredging progress made by the Lot 3 contractor on Route 21 from November 15th to November 21st. It shows that there was no surveying, surveying progress, total surveying completed, or dredging progress during this period. A note explains that dyke construction activities were ongoing on Route 21 instead.
This weekly report details the surveying and dredging progress made by the Lot 3 contractor on Route 21 from November 15th to November 21st. It shows that there was no surveying, surveying progress, total surveying completed, or dredging progress during this period. A note explains that dyke construction activities were ongoing on Route 21 instead.
Weekly Report on Survey and Dredging Progress of the Lot 3 Contractor
Route No Date Surveying Surveying Total Chainage (km) Dredging
Progress Progress (km) Progress (Chainage) (km) (m) Route 21 15.11.23 No Activity - No Activity - 16.11.23 No Activity - No Activity - 17.11.23 No Activity - - No Activity - 18.11.23 No Activity - No Activity - 19.11.23 No Activity - No Activity - 20.11.23 No Activity - No Activity - 21.11.23 No Activity - No Activity - N.B. Dyke Construction activities are ongoing on Route 21.