Weekly Report on Survey and Dredging Progress of the Lot 2 Contractor

Route No Date Surveying Surveying Dredging Cutting Total


Progress Progress Progress Length Dredged
(Chainage) (km) (Chainage) (m) Progress
(m)
Route 9 15.11.2023 No Activity - 05+769 to 05+785 16
08+104 to 08+116 12
07+082 to 07+093 11
16.11.2023 No Activity - 05+785 to 05+804 19
08+116 to 08+134 18
17.11.2023 No Activity - No Activity -
184
18.11.2023 No Activity - 07+093 to 07+114 21
08+134 to 08+139 5
19.11.2023 No Activity - 07+114 to 07+125 11
20.11.2023 No Activity - 07+125 to 07+135 10
05+804 to 05+811 7
21.11.2023 No Activity - 05+811 to 05+838 27
07+135 to 07+150 15
08+139 to 08+151 12