Professional Documents
Culture Documents
SHK-ME-ET-M81-0002 Material Handling Report Rev 0 Comment NZM
SHK-ME-ET-M81-0002 Material Handling Report Rev 0 Comment NZM
Revision Revision
Prepared Checked Approved
Number Status
AA PT CCC
AFC (Approved For
0
Construction)
12-October-21 12-October-21 12-October-21
Revision History
Hold List
CONTENTS
1.0 INTRODUCTION ........................................................................................................ 5
1.0 INTRODUCTION
Purpose
The purpose of this Material Handling report is to establish the main parameters and limiting
conditions for each type of material handling operation, enable safe and efficient handling of
all materials, supplies, components and equipment required for the MEG operations and
maintenance.
Scope
This report covers for all equipment and parts, above 25 kg in weight that will require
maintenance and its frequency or overhaul at some point during the 30 years’ service life and
define the minimum resources and devices to be provided in order to fulfill the handling needs
within MEG Regeneration & Reclamation Package.
Project Overview
The Shwe Project is a multiple gas-condensate field integrated development within Blocks A-
1 and A-3, located in the Bay of Bengal, offshore Myanmar. The Shwe development is being
undertaken by a consortium (the Company) of five companies: POSCO INTERNATIONAL
Corporation (PIC), Myanma Oil and Gas Enterprise (MOGE), Oil and Natural Gas Corporation
Videsh Limited (OVL), Gas Authority of India (GAIL) and Korea Gas Corporation (KOGAS).
The Shwe development area consists of three major field areas: the central Shwe field, the
northern Shwe Phyu field and southerly Mya field. The central Shwe field is approximately 70
km from Sittwe, mainland Myanmar, and 105 km from Kyaukphyu on Ramree Island. The
water depth varies from 90m at Shwe Phyu in the north to approximately 950m at the southern
extremity of the Mya field. The central Shwe field is in approximately 140m water depth, with
the existing SHP located in 111m water depth.
Phase 1 of the Shwe development consisted of a single, centrally located Shwe drilling and
production platform (SHP) at the Shwe field, with a multiphase subsea tieback from the Mya
North field area. Export specification gas is exported from the SHP facility via an export
pipeline to an onshore gas terminal at Kyaukphyu. The Phase 1 facilities are designed for a
peak wellhead gas flowrate of 640 MMscfd and commenced gas production in mid-2013.
In Phase 2, the development is currently being undertaken to expand the production of raw
gas to include the Shwe Subsea & Shwe Phyu fields and both fields are planned to start-up
in 2Q 2022.
LP compression is planned as part of Phase 3, to support ongoing production from the
existing and new fields and meet the required contracted quota.
Definitions
Abbreviations Descriptions
COMPANY or PIC POSCO INTERNATIONAL CORPORATION
CONTRACTOR or HHI HYUNDAI HEAVY INDUSTRIES CO., LTD
SUPPLIER The party who supplies goods or services and awarded by CONTRACTOR
International Standard
Length 46.0 m
Width 8.0 m
Height 31.8 m
In Material Handling Philosophy chapter 7, the table is the Handling Matrix to define general
principle and the requirement for permanent or temporary install local handling, depending on the
weight of loads and the frequency of handling operation.
In Zone H2, local maintenance handling for load greater 1000kg where the handling operations are
expected to be rarely happen. Permanent structure such as monorail and lifting devices such as
beam claim, trolley hoist might be used. Otherwise portable device should be used.
In Zone H3, local maintenance handling for load greater 25kg to.1000kg. Portable material
handling might be used such as A-frame, jib crane and high lift pallet truck. Optionally, permanent
structure should be used.
In Zone H4/H5, local maintenance handling for load less than 25kg, for daily and weekly operation,
mobile lifting like portable jib crane might be used. Otherwise, it can carry manually
In the philosophy, the further table is for Mobile Transfer Equipment according to weight and
frequency.
Chain hoist
Chain pulley blocks suspended from A‐frame, Pad‐eye and Beam‐clamp etc. are
used for vertical lifting of materials. The hand chain shall engage positively and with
free movement over the hand chain sprocket / wheel. Load chain and hand chain
shall be made of corrosion resistant, non‐sparking material. Hook‐on type Hoist and
appurtenances shall be designed to withstand all stresses imposed under normal
operating conditions while handling loads within rated capacity.
Chain Hoist shall be in accordance to international code & standard, and certification
as required.
Refer to Table 6.1, item 2 for detail.
Fixed Pad‐‐eye
Beam‐‐Clamp
Deck trolley
Floor trolley is used for horizontal transport of materials from its location to Laydown
area. Manual floor trolley is used for handling weights up to 2MT. For capacities above
2MT air driven floor trolley shall be used.
Refer to Table 6.1, item 10 for detail.
Special trolley for salt bin to carry salt bin to laydown area prior deck crane to pick up.
Refer to Table 6.1, item 5 for detail.
Fixed Swing Davit is used for shifting of materials between different levels (i.e.) from
elevated platform to weather deck.
Refer to Table 6.1, item 6 for detail.
Monorail
Monorails with trolley hoist are used for the vertical lifting and horizontal transportation
of items / materials and to lower this to deck below for further transportation via a
Floor Trolley to process deck laydown area.
Refer to Table 6.1, item 7 for detail.
Trolley hoist
Trolley hoist are used over the monorail for horizontal and vertical transportation of
items to process deck level. Hand chain operated hoist can be used for items 500kg
and less, however it is recommended to use power operated trolley / hoist assembly
for items above 500kg. Rack and pinion type trolley / hoist combination to be used.
Refer to Table 6.1, item 8 for detail.
Pedestal Crane
Jib Crane can be used for limited space area and medium size of handling items.
Refer to Table 6.1, item 11 for detail.
Portable Pulling Post complete with trifor use for pulling bundle and salt bin
horizontally to move the item on the deck floor.
Refer to Table 6.1, item 12 for detail.
Sl. SWL
No. DESCRIPTION (T)
7 Monorail 0.5‐5.0
25MT@R20m
9 Deck Crane
3MT@R40m
12 Tirfor 0.5-1.0
FGJFLJGFLG
1T 2T
0.6T
2T
4T
0.6T 1T
1T
4T 0.6T
4T 1T
0.6T
0.6T
0.6T 2T
0.6T
0.6T
0.6T
2T
0.6T
0.6T
0.6T
0.6T 0.6T
0.6T
0.6T
0.6T
0.6T
0.6T
Figure 8.1.5(a)
Figure 8.1.5(a)
0.6T
0.6T
3T
0.6T
0.6T
0.6T
Deck trolley
Monorail beam
Pulling post
Jib crane
Demounted A-Frame
Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1(a)).
2) Attach trolley hoist 1T at monorail and hook up pump suction and unbolt the spool flange.
Lower down the spool on the floor. Same method using for discharge spool. Precaution
to be taken care to support existing pipeline properly and use temporary pipe support if
necessary.
3) Provide Portable Drop Object Protection Housing to cover motor before lifting the pump.
4) Dismantle the pump, hook and lift up the pump toward motor side and lower down on the
deck trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same methods for another pumps.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)
P-1911A P-1911B
P-1911B
P-1911A
Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1(a)).
2) Attached trolley hoist 1T at monorail and hook up pump suction and unbolt the spool
flange. Lower down the spool on the floor. Same method using for discharge spool.
Precaution to be taken care to support existing pipeline properly and use temporary pipe
support if necessary.
3) Provide Portable Drop Object Protection Cover before lifting the pump/motor if
necessary.
4) Dismantle the pump, hook and lift up the pump toward deck trolley and lower down on
the trolley.
5) For motor, use trolley hoist at motor monorail beam, hook up and dismantle the motor,
lift up direct to the deck trolley nearby.
6) Same methods for another pumps.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1(a)).
2) Attached trolley hoist 1T at monorail and hook up pump suction spool and unbolt the
spool flange. Lower down the spool on the floor. Same method using for discharge spool.
Precaution to be taken care to support existing pipeline properly and use temporary pipe
support if necessary.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump.
4) Dismantle the pump, hook and lift up the pump toward motor side and lower down onto
the trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same methods for another pumps.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)
P-1915B
P-1919B P-1915A
P-1919A
Lifting Method
1) Locate Safety container 2T (as shown in Picture 1).
2) Attached trolley hoist 1T at monorail and hook at the bundle. Install tirfor 0.5T at pulling
post to pulling bundle completely from vessel
3) Pull the bundle by using pulling post toward special trolley and lower down onto the
trolley.
Transfer Method
1) Move trolley to laydown area for deck crane to pick up (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)
E-1919
E-1919
Lifting Method
1) Attached trolley hoist at monorail beam 5T
2) Put salt bin on Safety Container 6T.
3) Hook the salt bin lug and lift up and suspend the bin a bit to allow some load to monorail
so that pulling the bin smoother. Use pulling post complete with tirfor 1T to move bin to
another monorail.
Transfer Method
1) Transfer bin manually via monorail to laydown area. Use portable pulling post complete
with tirfor 1T to move the bin to laydown area.
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)
SALT BINS
Lifting Method
1) Install trolley hoist 0.5MT at monorail beam on the top of vertical valves. Locate deck
trolley near to valves (as shown in Picture 1(b)).
2) Hook the removal spool on top of valves, unbolt both sides and remove the spool and put
on the floor/safe area. Precaution to be taken care to support existing pipeline properly
and use temporary pipe support if necessary.
3) Hook valves at valve lug and unbolt the valve and lower down the valve onto the deck
trolley
4) Same method for other vertical valves.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)
P-1911A P-1911B
M-124 M-144
Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1).
2) Attached trolley hoist 2T at monorail and hook up pump suction and unbolt the spool
flange. Lower down the spool on the floor. Same method using for discharge spool.
Precaution to be taken care to support existing pipeline properly and use temporary pipe
support if necessary.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump.
4) Dismantle the pump, hook and lift up the pump toward motor side and lower down on the
trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same methods for another pumps..
Transfer Method
1) Move deck trolley to laydown area near to davit arm.(as shown in Picture 2(a))
2) Lower down motor/pump to deck trolley at Cellar Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
P-1920B
P-1920A
*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.
Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1).
2) Attach beam clamp complete with chain hoist 1T at beam on the top of pump. Hook up
pump suction spool and unbolt the spool flange. Lower down the spool on the floor. Same
method using for discharge spool. Precaution to be taken care to support existing pipeline
properly and use temporary pipe support if necessary
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump
4) Dismantle the pump, hook and lift up the pump toward deck trolley and lower down onto
the trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same methods for another pumps.
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down motor/pump to deck trolley at Cellar Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
P-1912A P-1912B
*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.
Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1).
2) Attach beam clamp complete with chain hoist 1T at beam on the top of pump. Hook up
pump suction spool and unbolt the spool flange. Lower down the spool on the floor. Same
method using for discharge spool.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump.
4) Dismantle the pump, hook and lift up the pump toward deck trolley and lower down onto
the trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same methods for another pumps.
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down motor/pump to deck trolley at Cellar Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
P-1910A P-1910B
*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.
Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1).
2) Attach beam clamp complete with chain hoist 1T at beam on the top of pump. Hook up
pump suction spool and unbolt the spool flange. Lower down the spool on the floor. Same
method using for discharge spool.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump.
4) Dismantle the pump, hook and lift up the pump toward deck trolley and lower down on
the trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down motor/pump to deck trolley at Cellar Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
A-1913
*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.
Lifting Method
1) Install chain hoist 0.5T at davit arm and hook up the motor conveyor, unbolt and dismantle
it.
2) Lift up the motor and turn davit arm to drop zone area and lower down it on deck trolley
at Cellar Deck slowly.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
M-1911
Lifting Method
1) Locate portable jib crane complete with chain hoist 0.5T and Deck Trolley 2T (as shown
in Picture 1).
2) Hook up pump suction spool and unbolt the spool flange. Lower down the spool on the
floor. Same method using for discharge spool.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump to
protect motor from drop object.
4) Dismantle the pump, hook up the pump and lift up the pump toward deck trolley and lower
down onto the trolley.
5) For motor, hook up the motor, dismantle and lift up direct to the deck trolley nearby.
6) Same method uses for accessories
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)
A-1911 P-1914B
P-1914A
Lifting Method
1) Locate Jib Crane complete chain hoist 0.5Tand Deck Trolley 2T (as shown in Picture 1).
2) Lift the bundle up and push it towards to deck trolley and lower it down.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Coalescer VTA 50
V-1917
Lifting Method
1) Locate A-frame complete with chain hoist 0.5Tand Deck Trolley 2T (as shown in Picture
1).
2) Hook up pump suction spool and unbolt the spool flange. Lower down the spool on the
floor. Same method using for discharge spool.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump.
4) Dismantle the pump, hook up the pump and lift up the pump toward deck trolley and lower
down onto the trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same method uses for another pump.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)
A-1910
Lifting Method
1) Attach beam clamp complete with chain hoist 0.5MT at beam on the top of vertical valves.
Locate deck trolley near to valves (as shown in Picture 1(b)).
2) Hook the removal spool on top of valves, unbolt flange both sides and remove the spool
and put on the floor.
3) Hook valves at valve lug and unbolt the valve flange and lower down the valve onto the
deck trolley.
4) Same methods for other vertical valves.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)
M81-154
M81-147
Lifting Method
1) Attach beam clamp complete with chain hoist 0.5T to beam on top of valve and Deck
Trolley 2T at nearest items to be handled (example as shown in Picture 1).
2) Hook up the valve and unbolt the valve flange. Lift the valve up and push it towards to
deck trolley and lower it down on the trolley.
3) Same method uses for another valves.
Transfer Method
1) Move deck trolley to laydown area near to davit arm.(as shown)
2) Lower down items to deck trolley at Main Deck
3) Move trolley to main SHK platform using the route (as shown).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)
1) Attach beam clamp complete with chain hoist 0.5MT at monorail beam on the top of
vertical valves. Locate deck trolley near to valves.
2) Hook the top removal spool, unbolt both sides and lower it on the floor.
3) Hook valves at valve lug and unbolt the valve and lower down the valve on the deck
trolley.
4) Same method for other vertical valves.
1) Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down items to deck trolley at Upper Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
M81-161
M81-158
Lifting Method
1) Attach beam clamp complete with chain hoist 0.5Tand Deck Trolley 2T at nearest items
to be handled (as shown in Picture 1).
2) For PSV, unbolt PSV flange, dismantle and lift the items up and push it slowly towards to
deck trolley and lower it down.
3) For valve at PSV inlet, once PSV completely dismantled. Hook up the reducer spool,
unbolt flange and lower it down on the floor. Then hook up the valve at valve lug, unbolt,
dismantle and lower it down on the deck trolley.
4) For vertical valve at PSV outlet. Hook up the top removal spool, unbolt and lower it down
on the floor. Then hook up the vertical valve at valve lug, unbolt, dismantle and lower it
down on the deck troll
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Lifting Method
1) Wherever location that beam clamp cannot be used, attach jib crane complete with chain
hoist 0.5T and Deck Trolley 2T at nearest items to be handled (example as shown in
Picture 1).
2) Same method uses for handling PSV, valve and vertical valve that describe in handling
for PSV.
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down items to deck trolley at PSV Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
Lifting Method
1) Handling and removal of motor/cooler accessories shall be included in cooler package.
Vendor to provide
2) Lift the items up and push it towards to deck trolley 2T and lower it down.
3) Same method uses for another items.
4) For handling removal bundle, barge crane with minimum Crane 20T capacity to be use
since deck crane cannot reach the bundle. Proper lifting arrangement for removal bundle
study detail shall be provided prior to lifting the bundle.
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down items to deck trolley at PSV Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
E-1913
Cooler Bundle
Lifting Method
1) Attach beam clamp complete with chain hoist 0.5T to top support beam and locate deck
Trolley 2T at nearest items to be handled.
2) For PSV, unbolt PSV flane, dismantle and lift the items up and push it slowly towards to
deck trolley and lower it down (as shown in Picture 1)
3) For valve at PSV inlet, once PSV completely dismantled. Hook up the reducer spool,
unbolt and lower it down on the floor. Then hook up the valve at valve lug, unbolt,
dismantle and lower it down on the deck trolley (as shown in Picture 1, item 1)
4) For vertical valve at PSV outlet. Hook up the top removal spool, unbolt and lower it down
on the floor. Then hook up the vertical valve at valve lug, unbolt, dismantle and lower it
down on the deck trolley (as shown in Picture 1, item 2)
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a)).
2) Lower down items to deck trolley at Upper Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
Lifting Method
1) Attach beam clamp complete with chain hoist 0.5T to top support beam and locate deck
Trolley 2T at nearest items to be handled.
2) For PSV, unbolt PSV flange, dismantle and lift the items up and push it slowly towards to
deck trolley and lower it down (as shown in Picture 1)
3) For valve at PSV inlet, once PSV completely dismantled. Hook up the reducer spool,
unbolt and lower it down on the floor. Then hook up the valve at valve lug, unbolt,
dismantle and lower it down on the deck trolley (as shown in Picture 1, item 1)
4) For vertical valve at PSV outlet. Hook up the top removal spool, unbolt it and lower it
down on the floor. Then hook up the vertical valve at valve lug, unbolt, dismantle and
lower it down on the deck trolley (as shown in Picture 1, item 2)
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down items to deck trolley at Upper Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
PSV -19613B
PSV -19613A
Lifting Method
1) Attach beam clamp complete with chain hoist 0.5T to top support beam and Deck Trolley
2T at nearest items to be handled.
2) For PSV, unbolt PSV flange, dismantle and lift the items up and push it slowly towards to
deck trolley and lower it down (as shown in Picture 1)
3) For valve at PSV inlet, once PSV completely dismantled. Hook up the reducer spool,
unbolt and lower it down on the floor. Then hook up the valve at valve lug, unbolt,
dismantle and lower it down on the deck trolley (as shown in Picture 1, item 1)
4) For vertical valve at PSV outlet. Hook up the top removal spool, unbolt both side and
lower it down on the floor. Then hook up the vertical valve at valve lug, unbolt, dismantle
and lower it down on the deck trolley(as shown in Picture 1, item 2)
5) .
Transfer Method
1) Move deck trolley to laydown area near to davit arm.(as shown in Picture 2(a))
2) Lower down items to deck trolley at PSV Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
4) Optional, the items can be directly picked up by deck crane at PSV Deck
PSV -19661B
PSV -19661B
Lifting Method
1) Attach beam clamp complete with chain hoist 0.5T to top support beam and Deck Trolley
2T at nearest items to be handled.
2) For PSV, unbolt PSV flange, dismantle and lift the items up and push it slowly towards to
deck trolley and lower it down (as shown in Picture 1)
3) For valve at PSV inlet, once PSV completely dismantled. Hook up the removal spool,
unbolt and lower it down on the floor. Then hook up the valve at valve lug, unbolt,
dismantle and lower it down on the deck trolley (as shown in Picture 1, item 1)
4) For vertical valve at PSV outlet. Hook up the top removal spool, unbolt both side and
lower it down on the floor. Then hook up the vertical valve at valve lug, unbolt, dismantle
and lower it down on the deck trolley (as shown in Picture 1, item 2)
5) .
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down items to deck trolley at PSV Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
4) Optional, the items can be directly picked up by deck crane at PSV Deck
PSV -19605
39 E-1910 Rich MEG Pre-heater (spiral type) Platform (Main Deck) NA (in situ cleaning) NA NA NA
1) Attach trolley hoist 1T at monorail lift up bundle
MONORAIL,
and lower down onto Deck Trolley
40 E-1919 Heating Medium Electrical Heater Cellar Deck bundle 1000 0.6 x 0.6 x 4.2 SPECIAL TROLLEY
2) Special Trolley bring bundle to laydown area
DECK CRANE
for Deck Crane to pick up.
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
41 M-1912 Centrifuge Lube Oil Skid Mezzanine Deck motor, pump, cooler fan 60 Varies DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform
42 E-1911 MEG Flash Column Heater (Spiral type) Main Deck NA (in situ cleaning) NA - NA
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
BEAM CLAMP on maintenance item.
DECK TROLLEY, 2) Remove maintenance items and slowly lower
43 E-1912 Lean meg cooler PSV/Cooler Deck motor, gear and accessories 150 Varies
DECK CRANE down onto Deck Trolley.
2) Deck Trolley brings items to laydown area
3) Deck Crane picks items up from laydown area
to SHK main platform
Piping
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
52 M81-802 8"-DH-19861-A13X-PP Main Deck 4" Manual Valve 150# WNRF 45 0.3 x 0.3 x 0.4 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform
InstrumentActuated Valve
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
91 8"-GL-19971-A16X-EB2 8"-GL-19971-A16X-E Main Deck 8" Actuated Valve 150# WNRF 250 0.7 x 0.7 x 1.2 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform