Download as pdf or txt
Download as pdf or txt
You are on page 1of 82

FINAL

(Few comments are not implemented, see NOV response or CRS)

PROJECT / JOB TITLE : SHWE PROJECT PHASE 3 DEVELOPMENT


DOCUMENT TITLE : MECHANICAL AND MATERIAL HANDLING REPORT

DOCUMENT NUMBER : SHK-ME-ET-M81-0002

ITEM /PO NO. : A-1091/Q553-C5J0-1503910-001


MEG RECLAMATION AND REGENERATION PACKAGE
EQUIPMENT :
AND PACKAGE (1Q-51)

Contractor Documentation Status

Revision Revision
Prepared Checked Approved
Number Status

AA PT CCC
AFC (Approved For
0
Construction)
12-October-21 12-October-21 12-October-21

STRICTLY CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Revision History

Revision Date Section Page(s) Brief Description of Change Author of


Number (s) Change

A 20-August-21 All All IFC AA

0 12-October-21 All All Incorporated IFC Comments AA

Hold List

Hold No. Section Hold Item Hold Description

REVISION 0 SHK-ME-ET-M81-0002 Page 2 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

CONTENTS
1.0 INTRODUCTION ........................................................................................................ 5

2.0 APPLICABLE STANDARDS ...................................................................................... 9

3.0 MEG RECLAMATION AND REGENERATION PACKAGE CONFIGURATION ....... 10

4.0 Material handling principles ................................................................................... 11


5.0 MATERIAL HANDLING EQUIPMENTS ................................................................... 13

6.0 REGISTER MATERIAL HANDLING APPLIANCES ................................................. 16


7.0 MATERIAL HANDLING WAYS ................................................................................ 17

8.0 MATERIAL HANDLING METHODS ......................................................................... 24

REVISION 0 SHK-ME-ET-M81-0002 Page 3 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

APPENDIX A - MATERIAL HANDLING LIST ........................................................................ 71

REVISION 0 SHK-ME-ET-M81-0002 Page 4 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

1.0 INTRODUCTION

Purpose

The purpose of this Material Handling report is to establish the main parameters and limiting
conditions for each type of material handling operation, enable safe and efficient handling of
all materials, supplies, components and equipment required for the MEG operations and
maintenance.
Scope

This report covers for all equipment and parts, above 25 kg in weight that will require
maintenance and its frequency or overhaul at some point during the 30 years’ service life and
define the minimum resources and devices to be provided in order to fulfill the handling needs
within MEG Regeneration & Reclamation Package.

Project Overview

The Shwe Project is a multiple gas-condensate field integrated development within Blocks A-
1 and A-3, located in the Bay of Bengal, offshore Myanmar. The Shwe development is being
undertaken by a consortium (the Company) of five companies: POSCO INTERNATIONAL
Corporation (PIC), Myanma Oil and Gas Enterprise (MOGE), Oil and Natural Gas Corporation
Videsh Limited (OVL), Gas Authority of India (GAIL) and Korea Gas Corporation (KOGAS).

REVISION 0 SHK-ME-ET-M81-0002 Page 5 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Figure 1 Location of Blocks A-1 and A-3, Offshore Myanmar

The Shwe development area consists of three major field areas: the central Shwe field, the
northern Shwe Phyu field and southerly Mya field. The central Shwe field is approximately 70
km from Sittwe, mainland Myanmar, and 105 km from Kyaukphyu on Ramree Island. The
water depth varies from 90m at Shwe Phyu in the north to approximately 950m at the southern
extremity of the Mya field. The central Shwe field is in approximately 140m water depth, with
the existing SHP located in 111m water depth.

REVISION 0 SHK-ME-ET-M81-0002 Page 6 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Phase 1 of the Shwe development consisted of a single, centrally located Shwe drilling and
production platform (SHP) at the Shwe field, with a multiphase subsea tieback from the Mya
North field area. Export specification gas is exported from the SHP facility via an export
pipeline to an onshore gas terminal at Kyaukphyu. The Phase 1 facilities are designed for a
peak wellhead gas flowrate of 640 MMscfd and commenced gas production in mid-2013.
In Phase 2, the development is currently being undertaken to expand the production of raw
gas to include the Shwe Subsea & Shwe Phyu fields and both fields are planned to start-up
in 2Q 2022.
LP compression is planned as part of Phase 3, to support ongoing production from the
existing and new fields and meet the required contracted quota.

Definitions

Abbreviations Descriptions
COMPANY or PIC POSCO INTERNATIONAL CORPORATION
CONTRACTOR or HHI HYUNDAI HEAVY INDUSTRIES CO., LTD

PROJECT or CONTRACT EPCIC Services for SHWE Project Phase 3 Development

REVISION 0 SHK-ME-ET-M81-0002 Page 7 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

SUB-CONTRACTOR Third Party who is providing subcontracting or Engineering Subcontractor.

SUPPLIER The party who supplies goods or services and awarded by CONTRACTOR

REVISION 0 SHK-ME-ET-M81-0002 Page 8 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

2.0 APPLICABLE STANDARDS

COMPANY Standard Specifications and Document Reference

No. Document No. Description

1 SHK-ME-EP-803-1003 SHK -Mechanical Handling Philosophy

2 SHP-ME-ET-303-0001 SHP-Mechanical Handling Report

3 SHK-ME-ET-303-1004 SHK-Maintenance Philosophy

4 SHK-PI-ET-303-1003 SHK-Layout Philosophy

5 SHK-ME-ED-303-1011 DS-Material Handling Equipment

International Standard

No. Document No. Description

1 L23 (4th Edition) Manual Handling Operation Regulation 1992

REVISION 0 SHK-ME-ET-M81-0002 Page 9 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

3.0 MEG RECLAMATION AND REGENERATION PACKAGE


CONFIGURATION

MEG Reclamation and Regeneration Package Configuration

Description Data Unit

Length 46.0 m
Width 8.0 m
Height 31.8 m

REVISION 0 SHK-ME-ET-M81-0002 Page 10 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

4.0 MATERIAL HANDLING PRINCIPLES

In Material Handling Philosophy chapter 7, the table is the Handling Matrix to define general
principle and the requirement for permanent or temporary install local handling, depending on the
weight of loads and the frequency of handling operation.

Table 4.1: Selection of Handling Equipment


In Zone H1, local maintenance handling for load greater 1000 kg where the handling operations
are expected to be frequent as in workshop or operational area. Power and permanent handling
equipment to be used

In Zone H2, local maintenance handling for load greater 1000kg where the handling operations are
expected to be rarely happen. Permanent structure such as monorail and lifting devices such as
beam claim, trolley hoist might be used. Otherwise portable device should be used.

In Zone H3, local maintenance handling for load greater 25kg to.1000kg. Portable material
handling might be used such as A-frame, jib crane and high lift pallet truck. Optionally, permanent
structure should be used.

In Zone H4/H5, local maintenance handling for load less than 25kg, for daily and weekly operation,
mobile lifting like portable jib crane might be used. Otherwise, it can carry manually

REVISION 0 SHK-ME-ET-M81-0002 Page 11 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

In the philosophy, the further table is for Mobile Transfer Equipment according to weight and
frequency.

Table 4.2: Selection of Transfer Mobile Equipment


For above transfer, it depends on the weight and frequent operation, but the type of
trolley is different.
All equipment and parts, above 25 kg in weight that will require maintenance and its
frequency or overhaul at some point during the 30 years’ service life will be identify
and handled manually and transferred to final material laydown area for maintenance.
The selection, design, sizing, capacities and locations of monorail, pad-eyes, lifting
appliance, transportation, removal clearance shall be finalized during detail design.
All handling and lifting means presented in this document are being designed to
enable transfer loads from their original location to the transfer or final laydown area
and back.
Specific handling and required tools shall be determined by material handling study
during the Detail Engineering Phase.
The following parameters were considered to identify type of methodology, appliance
to handle the specific equipment
a) Safety
b) Human Factor and Ergonomics study to comply to international code ISO 26800
c) Module Layout and final Layout drawing
d) Periodic mainternance Requirements, unforeseen failure, vendor
recommendation and service life

REVISION 0 SHK-ME-ET-M81-0002 Page 12 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

5.0 MATERIAL HANDLING EQUIPMENTS

Demounted A‐‐Frame type Gantry

A‐Frame / Gantry consist of portable parts such as standard A‐frame (1 nos.)


connected by a Cross bar and the same shall be assembled at the required handling
location. A trolley with hook will run over the cross bar.
A‐frames / Gantries shall be used along with the chain pulley block for lifting the
materials.
Refer to Table 6.1, item 1 for detail.

Chain hoist

Chain pulley blocks suspended from A‐frame, Pad‐eye and Beam‐clamp etc. are
used for vertical lifting of materials. The hand chain shall engage positively and with
free movement over the hand chain sprocket / wheel. Load chain and hand chain
shall be made of corrosion resistant, non‐sparking material. Hook‐on type Hoist and
appurtenances shall be designed to withstand all stresses imposed under normal
operating conditions while handling loads within rated capacity.
Chain Hoist shall be in accordance to international code & standard, and certification
as required.
Refer to Table 6.1, item 2 for detail.

Fixed Pad‐‐eye

Welded pad‐eyes are permanently welded to overhead beams of the respective


handling equipment’s for vertical lifting. Each pad‐eye shall be identified with its SWL
capacity. Chain pulley block is used along with the pad‐eye for vertical lifting and
further horizontal transport shall be carried by Floor trolley. Pad‐eyes are
recommended up to 2MT capacity.
Fixed Pad Eye shall be in accordance to international code & standard, and
certification as required.
Refer to Table 6.1, item 3 for detail.

Beam‐‐Clamp

Beam‐clamps are temporarily fixed to overhead beams of the respective handling


equipment’s. Chain pulley is suspended from the beam‐clamp for vertical lifting of the
material and floor trolley for further shifting of the materials. Beam‐clamps are
recommended up to 2MT.
Beam Clamp shall be in accordance to international code & standard, and certification
as required.
REVISION 0 SHK-ME-ET-M81-0002 Page 13 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Refer to Table 6.1, item 4 for detail.

Deck trolley

Floor trolley is used for horizontal transport of materials from its location to Laydown
area. Manual floor trolley is used for handling weights up to 2MT. For capacities above
2MT air driven floor trolley shall be used.
Refer to Table 6.1, item 10 for detail.
Special trolley for salt bin to carry salt bin to laydown area prior deck crane to pick up.
Refer to Table 6.1, item 5 for detail.

Manual Davit Arm

Fixed Swing Davit is used for shifting of materials between different levels (i.e.) from
elevated platform to weather deck.
Refer to Table 6.1, item 6 for detail.

Monorail

Monorails with trolley hoist are used for the vertical lifting and horizontal transportation
of items / materials and to lower this to deck below for further transportation via a
Floor Trolley to process deck laydown area.
Refer to Table 6.1, item 7 for detail.

Trolley hoist

Trolley hoist are used over the monorail for horizontal and vertical transportation of
items to process deck level. Hand chain operated hoist can be used for items 500kg
and less, however it is recommended to use power operated trolley / hoist assembly
for items above 500kg. Rack and pinion type trolley / hoist combination to be used.
Refer to Table 6.1, item 8 for detail.

Pedestal Crane

A 25MT@R20m with 3MT@R40m(auxiliary hoist), M-7310 capacity pedestal crane


at SHK South-West side of platform, is servicing MEG module maintenance items to
Laydown area
Portable Jib Crane

Jib Crane can be used for limited space area and medium size of handling items.
Refer to Table 6.1, item 11 for detail.

REVISION 0 SHK-ME-ET-M81-0002 Page 14 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Portable Pulling Post and Tirfor

Portable Pulling Post complete with trifor use for pulling bundle and salt bin
horizontally to move the item on the deck floor.
Refer to Table 6.1, item 12 for detail.

REVISION 0 SHK-ME-ET-M81-0002 Page 15 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

6.0 REGISTER MATERIAL HANDLING APPLIANCES


To be read in conjunction with Material Handling Register Appendix A. Note 1: Scope of supply
for below items to be confirmed.

Sl. SWL
No. DESCRIPTION (T)

1 Demounted A-frame 0.5‐2.0

2 Chain hoist 0.5‐2.0

3 Fixed Pad Eye 0.5‐2.0

4 Beam Clamp 0.5‐2.0

5 Deck trolley @ every level Trolley 2.0

6 Manual Davit Arm 0.5‐2.0

7 Monorail 0.5‐5.0

8 Trolley Hoist 0.5‐5.0

25MT@R20m
9 Deck Crane
3MT@R40m

10 Deck Trolley for Salt Bin 6.0

11 Portable Jib Crane 0.5

12 Tirfor 0.5-1.0

Table 6.1: Registered Material Handling Appliance


Note:
1. Chain hoist shall be supplied with 360° swivel hook.
2. Chain hoist shall be used with Swing Davit.
3. Floor trolley wheel size shall be sufficient for travelling on grating floor/plate.

REVISION 0 SHK-ME-ET-M81-0002 Page 16 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

7.0 MATERIAL HANDLING WAYS


Main Handling Ways are shown on the figures below. Dimension of handling ways shall be
determined by the largest component to be transferred.
In any case it cannot be lower than 0.75m width and 2.1m height. The handlings to allow the
transportation of loads to a lifting/laydown area. As a general the below principle to apply for
transfer of deck trolley from MEG platform to main SHK platform.

Together, it shows the maximum loading for transfer routing.

The legends that used in this chapter as below:


Transfer Route

Maximum Load on the


Transfer Route (Example
1T
1T)

Direction for deck trolley to


SHK Platform Laydown
Area

REVISION 0 SHK-ME-ET-M81-0002 Page 17 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Handling Way at Cellar Cellar Deck

FGJFLJGFLG

Figure 7.1.1: Handling way – Cellar Deck at SHK Platform

1T 2T
0.6T
2T
4T
0.6T 1T
1T
4T 0.6T
4T 1T
0.6T

Figure 7.1.2: Handling way -Cellar Deck at MEG Platform

REVISION 0 SHK-ME-ET-M81-0002 Page 18 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

0.6T
0.6T 2T

0.6T
0.6T
0.6T

2T

Figure 7.1.3: Handling way -Mezzanine Deck at MEG Platform

REVISION 0 SHK-ME-ET-M81-0002 Page 19 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Handling Way at Main Deck

Figure 7.2.1: Handling way – Main Deck at SHK Platform

0.6T

0.6T
0.6T

0.6T 0.6T

0.6T

Figure 7.2.2: Handling way – Main Deck at MEG Platform

REVISION 0 SHK-ME-ET-M81-0002 Page 20 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

0.6T

0.6T
0.6T

0.6T

Figure 7.2.3: Handling way – Main Deck Platform at MEG Platform

REVISION 0 SHK-ME-ET-M81-0002 Page 21 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Handling at Upper Deck

Figure 8.1.5(a)

Figure 8.1.5(a)

Figure 7.3.1: Handling way – Upper Deck at SHK Platform

0.6T
0.6T

3T
0.6T

Figure 7.3.1: Handling way – Upper Deck at MEG Platform

REVISION 0 SHK-ME-ET-M81-0002 Page 22 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Handling at Cooler Deck

Figure 7.4.1: Handling way – Cooler Deck at SHK Platform

0.6T

0.6T

Figure 7.4.1: Handling way – Cooler Deck at MEG Platform

REVISION 0 SHK-ME-ET-M81-0002 Page 23 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.0 MATERIAL HANDLING METHODS


This chapter describes detail of lifting and transfer method for each equipment in the
MEG package.
The legends that used in this chapter as below:
Lay down area

Deck trolley

Deck trolley for another


equipment in same location

Beam clamp/trolley hoist

Special trolley for electrical


heater bundle

Monorail beam

Deck trolley route

Pulling post

Jib crane

Demounted A-Frame

Portable Drop Object


Protection Housing

REVISION 0 SHK-ME-ET-M81-0002 Page 24 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Handling methods at Cellar Deck

8.1.1 Handling for pumps P-1911A/B

Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1(a)).
2) Attach trolley hoist 1T at monorail and hook up pump suction and unbolt the spool flange.
Lower down the spool on the floor. Same method using for discharge spool. Precaution
to be taken care to support existing pipeline properly and use temporary pipe support if
necessary.
3) Provide Portable Drop Object Protection Housing to cover motor before lifting the pump.
4) Dismantle the pump, hook and lift up the pump toward motor side and lower down on the
deck trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same methods for another pumps.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)

Pump 0.6 x 0.8 x 1.2 550

Motor 0.6 x 0.8 x 1.2 358

P-1911A P-1911B

Picture 1(a): Lifting Method Picture 1(b): Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 25 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

P-1911B
P-1911A

Picture 2: Lifting Method


*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.

REVISION 0 SHK-ME-ET-M81-0002 Page 26 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.1.2 Handling for pumps P-1913A/B and P-1916A/B

Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1(a)).
2) Attached trolley hoist 1T at monorail and hook up pump suction and unbolt the spool
flange. Lower down the spool on the floor. Same method using for discharge spool.
Precaution to be taken care to support existing pipeline properly and use temporary pipe
support if necessary.
3) Provide Portable Drop Object Protection Cover before lifting the pump/motor if
necessary.
4) Dismantle the pump, hook and lift up the pump toward deck trolley and lower down on
the trolley.
5) For motor, use trolley hoist at motor monorail beam, hook up and dismantle the motor,
lift up direct to the deck trolley nearby.
6) Same methods for another pumps.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)

Pump 0.5 x 0.7 x 1.2 380

Motor 0.5 x 0.7 x 1.2 318

P-1916A P-1916B P-1913A P-1913B

Picture 1(a):Lifting Method Picture 1(b):Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 27 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2: Lifting Method


*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.

REVISION 0 SHK-ME-ET-M81-0002 Page 28 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.1.3 Handling for pumps P-1915A/B and P-1919A/B

Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1(a)).
2) Attached trolley hoist 1T at monorail and hook up pump suction spool and unbolt the
spool flange. Lower down the spool on the floor. Same method using for discharge spool.
Precaution to be taken care to support existing pipeline properly and use temporary pipe
support if necessary.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump.
4) Dismantle the pump, hook and lift up the pump toward motor side and lower down onto
the trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same methods for another pumps.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)

motor 1.6 x 1.6 x 2.0 180

pump 1.6 x 1.6 x 2.0 115

P-1915B
P-1919B P-1915A

P-1919A

Picture 1(a):Lifting Method

Picture 1(b):Lifting Method


REVISION 0 SHK-ME-ET-M81-0002 Page 29 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2: Lifting Method


*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.

REVISION 0 SHK-ME-ET-M81-0002 Page 30 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.1.4 Handling for bundle E-1919

Lifting Method
1) Locate Safety container 2T (as shown in Picture 1).
2) Attached trolley hoist 1T at monorail and hook at the bundle. Install tirfor 0.5T at pulling
post to pulling bundle completely from vessel
3) Pull the bundle by using pulling post toward special trolley and lower down onto the
trolley.
Transfer Method
1) Move trolley to laydown area for deck crane to pick up (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)

Electrical Heater Bundle 0.6 x 0.6 x 4.2 1000

E-1919

E-1919

Picture 1:Lifting Method

Picture 2: Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 31 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.1.5 Handling for Salt Bins

Lifting Method
1) Attached trolley hoist at monorail beam 5T
2) Put salt bin on Safety Container 6T.
3) Hook the salt bin lug and lift up and suspend the bin a bit to allow some load to monorail
so that pulling the bin smoother. Use pulling post complete with tirfor 1T to move bin to
another monorail.
Transfer Method
1) Transfer bin manually via monorail to laydown area. Use portable pulling post complete
with tirfor 1T to move the bin to laydown area.
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)

Salt Bin (Filled with Salt) 1.6 x 1.6 x 1.5 3800

SALT BINS

Picture 1:Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 32 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.1.6 Handling for Vertical Valves M81-144/124

Lifting Method
1) Install trolley hoist 0.5MT at monorail beam on the top of vertical valves. Locate deck
trolley near to valves (as shown in Picture 1(b)).
2) Hook the removal spool on top of valves, unbolt both sides and remove the spool and put
on the floor/safe area. Precaution to be taken care to support existing pipeline properly
and use temporary pipe support if necessary.
3) Hook valves at valve lug and unbolt the valve and lower down the valve onto the deck
trolley
4) Same method for other vertical valves.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)

Valves 0.6 x 0.6 x 0.8 282

P-1911A P-1911B

M-124 M-144

Picture 1(a):Lifting Method Picture 1(b):Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 33 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2: Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 34 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Handling methods at Mezzanine Deck

8.2.1 Handling for pumps P-1920A/B

Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1).
2) Attached trolley hoist 2T at monorail and hook up pump suction and unbolt the spool
flange. Lower down the spool on the floor. Same method using for discharge spool.
Precaution to be taken care to support existing pipeline properly and use temporary pipe
support if necessary.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump.
4) Dismantle the pump, hook and lift up the pump toward motor side and lower down on the
trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same methods for another pumps..
Transfer Method
1) Move deck trolley to laydown area near to davit arm.(as shown in Picture 2(a))
2) Lower down motor/pump to deck trolley at Cellar Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)

motor 1.6 x 1.6 x 2.0 690

pump 1.6 x 1.6 x 2.0 1300

P-1920B
P-1920A

Picture 1:Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 35 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on Picture 2(b): Transfer Method on


Mezzanine Deck Cellar Deck

*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.

REVISION 0 SHK-ME-ET-M81-0002 Page 36 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.2.2 Handling for pumps P-1912A/B

Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1).
2) Attach beam clamp complete with chain hoist 1T at beam on the top of pump. Hook up
pump suction spool and unbolt the spool flange. Lower down the spool on the floor. Same
method using for discharge spool. Precaution to be taken care to support existing pipeline
properly and use temporary pipe support if necessary
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump
4) Dismantle the pump, hook and lift up the pump toward deck trolley and lower down onto
the trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same methods for another pumps.
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down motor/pump to deck trolley at Cellar Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)

motor 0.4 x 0.7 x 1.0 400

pump 0.4 x 0.7 x 1.0 330

P-1912A P-1912B

Picture 1: Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 37 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on Picture 2(b): Transfer Method on


Mezzanine Deck Cellar Deck

*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.

REVISION 0 SHK-ME-ET-M81-0002 Page 38 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.2.3 Handling for pumps P-1910A/B

Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1).
2) Attach beam clamp complete with chain hoist 1T at beam on the top of pump. Hook up
pump suction spool and unbolt the spool flange. Lower down the spool on the floor. Same
method using for discharge spool.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump.
4) Dismantle the pump, hook and lift up the pump toward deck trolley and lower down onto
the trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same methods for another pumps.
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down motor/pump to deck trolley at Cellar Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)

motor 0.4 x 0.7 x 1.0 400

pump 0.4 x 0.7 x 1.0 330

P-1910A P-1910B

Picture 1:Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 39 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on Picture 2(b): Transfer Method on


Mezzanine Deck Cellar Deck

*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.

REVISION 0 SHK-ME-ET-M81-0002 Page 40 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.2.4 Handling pumps in package A-1913

Lifting Method
1) Locate Deck Trolley 2T (as shown in Picture 1).
2) Attach beam clamp complete with chain hoist 1T at beam on the top of pump. Hook up
pump suction spool and unbolt the spool flange. Lower down the spool on the floor. Same
method using for discharge spool.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump.
4) Dismantle the pump, hook and lift up the pump toward deck trolley and lower down on
the trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down motor/pump to deck trolley at Cellar Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)

motor 0.5 x 0.3 x 0.8 <150

pump 0.5 x 0.3 x 0.8 <150

A-1913

Picture 1:Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 41 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on Picture 2(b): Transfer Method on


Mezzanine Deck Cellar Deck

*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.

REVISION 0 SHK-ME-ET-M81-0002 Page 42 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.2.5 Handling Motor for package M-1911A

Lifting Method
1) Install chain hoist 0.5T at davit arm and hook up the motor conveyor, unbolt and dismantle
it.
2) Lift up the motor and turn davit arm to drop zone area and lower down it on deck trolley
at Cellar Deck slowly.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)

motor 0.5 x 0.3 x 0.8 <150

M-1911

Picture 1:Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 43 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2: Transfer Method on Cellar Deck

REVISION 0 SHK-ME-ET-M81-0002 Page 44 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Handling methods at Main Deck

8.3.1 Handling pumps in Package A-1911

Lifting Method
1) Locate portable jib crane complete with chain hoist 0.5T and Deck Trolley 2T (as shown
in Picture 1).
2) Hook up pump suction spool and unbolt the spool flange. Lower down the spool on the
floor. Same method using for discharge spool.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump to
protect motor from drop object.
4) Dismantle the pump, hook up the pump and lift up the pump toward deck trolley and lower
down onto the trolley.
5) For motor, hook up the motor, dismantle and lift up direct to the deck trolley nearby.
6) Same method uses for accessories
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)

motor 0.5 x 0.3 x 1.0 120

pump 0.5 x 0.3 x 1.0 90

A-1911 P-1914B

P-1914A

Picture 1:Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 45 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2: Transfer Method


*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.

REVISION 0 SHK-ME-ET-M81-0002 Page 46 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.3.2 Handling for coalescer for V-1917

Lifting Method
1) Locate Jib Crane complete chain hoist 0.5Tand Deck Trolley 2T (as shown in Picture 1).
2) Lift the bundle up and push it towards to deck trolley and lower it down.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)

Coalescer VTA 50

V-1917

Picture 1: Lifting Method

Picture 2: Transfer Method

REVISION 0 SHK-ME-ET-M81-0002 Page 47 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.3.3 Handling pump in Package A-1910

Lifting Method
1) Locate A-frame complete with chain hoist 0.5Tand Deck Trolley 2T (as shown in Picture
1).
2) Hook up pump suction spool and unbolt the spool flange. Lower down the spool on the
floor. Same method using for discharge spool.
3) Provide Portable Drop Object Protection Cover to cover motor before lifting the pump.
4) Dismantle the pump, hook up the pump and lift up the pump toward deck trolley and lower
down onto the trolley.
5) For motor, dismantle the motor, hook and lift up direct to the deck trolley nearby.
6) Same method uses for another pump.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)

motor 0.8 x 0.36 x 1.2 180

pump 0.8 x 0.6 x 1.2 150

A-1910

Picture 1: Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 48 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2: Transfer Method


*Note: Drop Object Protection Cover shall be design for full drop load at minimum 1m, detail shall be done
during detail engineering.

REVISION 0 SHK-ME-ET-M81-0002 Page 49 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.3.4 Handling for Vertical valves M81-147/154

Lifting Method
1) Attach beam clamp complete with chain hoist 0.5MT at beam on the top of vertical valves.
Locate deck trolley near to valves (as shown in Picture 1(b)).
2) Hook the removal spool on top of valves, unbolt flange both sides and remove the spool
and put on the floor.
3) Hook valves at valve lug and unbolt the valve flange and lower down the valve onto the
deck trolley.
4) Same methods for other vertical valves.
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)

Valves 0.5 x 0.5 x 0.5 77

M81-154

M81-147

Picture 1(a):Lifting Method Picture 1(b):Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 50 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2: Transfer Method

REVISION 0 SHK-ME-ET-M81-0002 Page 51 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Handling methods at Main Deck Platform

8.4.1 Handling for Valves

Lifting Method
1) Attach beam clamp complete with chain hoist 0.5T to beam on top of valve and Deck
Trolley 2T at nearest items to be handled (example as shown in Picture 1).
2) Hook up the valve and unbolt the valve flange. Lift the valve up and push it towards to
deck trolley and lower it down on the trolley.
3) Same method uses for another valves.
Transfer Method
1) Move deck trolley to laydown area near to davit arm.(as shown)
2) Lower down items to deck trolley at Main Deck
3) Move trolley to main SHK platform using the route (as shown).
Part to Handles Maximum Dimensions Maximum Weights
(L m x W m x H m) (kg)

Valves and PSVS 0.6 x 0.5 x 1.5 350

Picture 1: Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 52 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on Picture 2(b): Transfer Method on


Main Deck Platform Main Deck

REVISION 0 SHK-ME-ET-M81-0002 Page 53 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.4.2 Handling for Vertical Valves M51-158/161

1) Attach beam clamp complete with chain hoist 0.5MT at monorail beam on the top of
vertical valves. Locate deck trolley near to valves.
2) Hook the top removal spool, unbolt both sides and lower it on the floor.
3) Hook valves at valve lug and unbolt the valve and lower down the valve on the deck
trolley.
4) Same method for other vertical valves.
1) Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down items to deck trolley at Upper Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)
Valves 0.5 x 0.5 x 0.5 114

M81-161
M81-158

Picture 1:Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 54 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on Picture 2(b): Transfer Method on


Main Deck Platform Main Deck

REVISION 0 SHK-ME-ET-M81-0002 Page 55 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Handling methods at Upper Deck

8.5.1 Handling for Manual Valves and PSVs

Lifting Method
1) Attach beam clamp complete with chain hoist 0.5Tand Deck Trolley 2T at nearest items
to be handled (as shown in Picture 1).
2) For PSV, unbolt PSV flange, dismantle and lift the items up and push it slowly towards to
deck trolley and lower it down.
3) For valve at PSV inlet, once PSV completely dismantled. Hook up the reducer spool,
unbolt flange and lower it down on the floor. Then hook up the valve at valve lug, unbolt,
dismantle and lower it down on the deck trolley.
4) For vertical valve at PSV outlet. Hook up the top removal spool, unbolt and lower it down
on the floor. Then hook up the vertical valve at valve lug, unbolt, dismantle and lower it
down on the deck troll
Transfer Method
1) Move trolley to main SHK platform using the route (as shown in Picture 2).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)

Valves and PSVS 0.5 x 0.5 x 0.5 114

Picture 1: Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 56 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2: Transfer Method

REVISION 0 SHK-ME-ET-M81-0002 Page 57 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.5.2 Handling for pumps Tote Tank/Salt Bin

Lifting and Transfer Method


1) Deck Crane is used to lift and transfer the tote tank/Salt Bin

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)
Alkalinity Tote Tank 2 x 2 x 2.5 1800

Salt Bin 1.6 x 1.6 x 1.5 3800

Oxygen Scavenger/Antifoam Tote Tank 1.2 x 1.0 x 1.2 1200 (estimated)

Picture 1: Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 58 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Handling methods at PSV Deck Platform

8.6.1 Handling for Valves and PSVs

Lifting Method
1) Wherever location that beam clamp cannot be used, attach jib crane complete with chain
hoist 0.5T and Deck Trolley 2T at nearest items to be handled (example as shown in
Picture 1).
2) Same method uses for handling PSV, valve and vertical valve that describe in handling
for PSV.
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down items to deck trolley at PSV Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)
Valves and PSVs 0.5 x 0.5 x 0.5 114

Picture 1: Lifting Method

Picture 2(a):: Transfer Method on PSV Deck

REVISION 0 SHK-ME-ET-M81-0002 Page 59 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(b): Transfer Method on Upper Deck

REVISION 0 SHK-ME-ET-M81-0002 Page 60 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.6.2 Handling for Motor and Cooler Accessories E-1913

Lifting Method
1) Handling and removal of motor/cooler accessories shall be included in cooler package.
Vendor to provide
2) Lift the items up and push it towards to deck trolley 2T and lower it down.
3) Same method uses for another items.
4) For handling removal bundle, barge crane with minimum Crane 20T capacity to be use
since deck crane cannot reach the bundle. Proper lifting arrangement for removal bundle
study detail shall be provided prior to lifting the bundle.
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down items to deck trolley at PSV Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)

Motor and Cooler Accessories 0.5 x 0.5 x 0.5 330

Cooler Bundle 8.0 x 4.0 x 1.5 15000/bay (estimated)

E-1913

Cooler Bundle

Motor and Accessories


under bundle

Picture 1: Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 61 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on PSV Deck

Picture 2(b): Transfer Method on Upper Deck

REVISION 0 SHK-ME-ET-M81-0002 Page 62 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.6.3 Handling for PSV-19603A/B, removal spool and vertical valves

Lifting Method
1) Attach beam clamp complete with chain hoist 0.5T to top support beam and locate deck
Trolley 2T at nearest items to be handled.
2) For PSV, unbolt PSV flane, dismantle and lift the items up and push it slowly towards to
deck trolley and lower it down (as shown in Picture 1)
3) For valve at PSV inlet, once PSV completely dismantled. Hook up the reducer spool,
unbolt and lower it down on the floor. Then hook up the valve at valve lug, unbolt,
dismantle and lower it down on the deck trolley (as shown in Picture 1, item 1)
4) For vertical valve at PSV outlet. Hook up the top removal spool, unbolt and lower it down
on the floor. Then hook up the vertical valve at valve lug, unbolt, dismantle and lower it
down on the deck trolley (as shown in Picture 1, item 2)
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a)).
2) Lower down items to deck trolley at Upper Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)
Valves and PSVs 0.5 x 0.5 x 0.5 114

PSV -19603A PSV -19603B

Picture 1: Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 63 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on PSV Deck

Picture 2(b): Transfer Method on Upper Deck

REVISION 0 SHK-ME-ET-M81-0002 Page 64 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.6.4 Handling for PSV-19613A/B, removal spool and vertical valves

Lifting Method
1) Attach beam clamp complete with chain hoist 0.5T to top support beam and locate deck
Trolley 2T at nearest items to be handled.
2) For PSV, unbolt PSV flange, dismantle and lift the items up and push it slowly towards to
deck trolley and lower it down (as shown in Picture 1)
3) For valve at PSV inlet, once PSV completely dismantled. Hook up the reducer spool,
unbolt and lower it down on the floor. Then hook up the valve at valve lug, unbolt,
dismantle and lower it down on the deck trolley (as shown in Picture 1, item 1)
4) For vertical valve at PSV outlet. Hook up the top removal spool, unbolt it and lower it
down on the floor. Then hook up the vertical valve at valve lug, unbolt, dismantle and
lower it down on the deck trolley (as shown in Picture 1, item 2)
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down items to deck trolley at Upper Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)
Valves and PSVs 0.5 x 0.5 x 1.1 120 (estimated)

PSV -19613B

PSV -19613A

Picture 1:Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 65 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on PSV Deck

Picture 2(b): Transfer Method on Upper Deck

REVISION 0 SHK-ME-ET-M81-0002 Page 66 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.6.5 Handling for PSV-19661A/B, removal spool and vertical valves

Lifting Method
1) Attach beam clamp complete with chain hoist 0.5T to top support beam and Deck Trolley
2T at nearest items to be handled.
2) For PSV, unbolt PSV flange, dismantle and lift the items up and push it slowly towards to
deck trolley and lower it down (as shown in Picture 1)
3) For valve at PSV inlet, once PSV completely dismantled. Hook up the reducer spool,
unbolt and lower it down on the floor. Then hook up the valve at valve lug, unbolt,
dismantle and lower it down on the deck trolley (as shown in Picture 1, item 1)
4) For vertical valve at PSV outlet. Hook up the top removal spool, unbolt both side and
lower it down on the floor. Then hook up the vertical valve at valve lug, unbolt, dismantle
and lower it down on the deck trolley(as shown in Picture 1, item 2)
5) .
Transfer Method
1) Move deck trolley to laydown area near to davit arm.(as shown in Picture 2(a))
2) Lower down items to deck trolley at PSV Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
4) Optional, the items can be directly picked up by deck crane at PSV Deck

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)
Valves and PSVs 0.5 x 0.5 x 0.5 114

PSV -19661B

PSV -19661B

Picture 1:Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 67 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on PSV Deck

Picture 2(b):: Transfer Method on Upper Deck

REVISION 0 SHK-ME-ET-M81-0002 Page 68 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

8.6.6 Handling for PSV-19605, removal spool and vertical valves

Lifting Method
1) Attach beam clamp complete with chain hoist 0.5T to top support beam and Deck Trolley
2T at nearest items to be handled.
2) For PSV, unbolt PSV flange, dismantle and lift the items up and push it slowly towards to
deck trolley and lower it down (as shown in Picture 1)
3) For valve at PSV inlet, once PSV completely dismantled. Hook up the removal spool,
unbolt and lower it down on the floor. Then hook up the valve at valve lug, unbolt,
dismantle and lower it down on the deck trolley (as shown in Picture 1, item 1)
4) For vertical valve at PSV outlet. Hook up the top removal spool, unbolt both side and
lower it down on the floor. Then hook up the vertical valve at valve lug, unbolt, dismantle
and lower it down on the deck trolley (as shown in Picture 1, item 2)
5) .
Transfer Method
1) Move deck trolley to laydown area near to davit arm (as shown in Picture 2(a))
2) Lower down items to deck trolley at PSV Deck
3) Move trolley to main SHK platform using the route (as shown in Picture 2(b)).
4) Optional, the items can be directly picked up by deck crane at PSV Deck

Part to Handles Maximum Dimensions Maximum Weights


(L m x W m x H m) (kg)
Valves and PSVs 0.5 x 0.5 x 0.5 114

PSV -19605

Picture 1:Lifting Method

REVISION 0 SHK-ME-ET-M81-0002 Page 69 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

Picture 2(a): Transfer Method on PSV Deck

Picture 2(b): Transfer Method on Upper Deck

REVISION 0 SHK-ME-ET-M81-0002 Page 70 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


MECHANICAL AND MATERIAL HANDLING REPORT

APPENDIX A - MATERIAL HANDLING LIST

REVISION 0 SHK-ME-ET-M81-0002 Page 71 of 71

CONFIDENTIAL – Do Not Disclose Without Authorisation


APPENDIX A - Material Handling Register

Equipment Package Description


Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

Equipment Package Description

1 V-1910 Rich MEG Flash Drum Upper Deck NA NA - NA


2 V-1912 Rich MEG Degasser Main Deck NA NA - NA
3 C-1911 MEG Flash & Distillation Column Main/Upper Deck internal 20 TBA

4 V-1913 Reflux Drum Main Deck NA NA - NA

5 V-1915 Recovered MEG Surge Drum Mezzanine Deck NA NA - NA

6 V-1919 Heating Medium Expansion Drum Platform (Main Deck) NA NA - NA

1) Item is replaced manually


7 S-1916A/B Rich MEG Filter Upper Deck filter 20 MANUAL
JIB CRANE, 1) Locate Jib crane 0.5T to lift up items
8 V-1917 Rich MEG Coalescer Main Deck internal 50
DECK TROLLEY 2) Deck Trolley 0.5T brings items to client site.
1) Item is replaced manually
9 S-1920A/B Lean MEG Filters Upper Deck filter 20 MANUAL
10 V-1920 Lean MEG Injection Drum Main Deck NA NA - NA

11 V-1921 MEG Drain Drum Cellar Deck NA NA - NA

1) Attach trolley hoist 1T at monorail to lift up


pump/motor and lower down onto Deck Trolley
MONORAIL,
12 P-1911A/B MEG Flash Column Pump Cellar Deck pump 550 0.6 x 0.8 x 1.2 (Precaution: Avoid motor from drop object)
DECK TROLLEY
2) Deck Trolley bring bundle to SHK main
platform
1) Attach trolley hoist 1T at monorail to lift up
pump/motor and lower down onto Deck Trolley
MONORAIL,
13 P-1911A/B MEG Flash Column Pump Cellar Deck motor 358 0.6 x 0.8 x 1.2 (Precaution: Avoid motor from drop object)
DECK TROLLEY
2) Deck Trolley bring bundle to SHK main
platform

1) Attached trolley hoist 0.5T at monorail to lift up


MONORAIL
14 P-1916A/B Rich MEG Degasser Pump Cellar Deck pump 120 0.5 x 0.7 x 1.2 item and lower down onto deck trolley
DECK TROLLEY
2) Deck trolley bring item to SHK main platform.

1) Attached trolley hoist 0.5T at monorail to lift up


MONORAIL
15 P-1916A/B Rich MEG Degasser Pump Cellar Deck motor 74 0.5 x 0.7 x 1.2 item and lower down onto deck trolley
DECK TROLLEY
2) Deck trolley bring item to SHK main platform.

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
16 P-1912A/B Lean MEG Product Pump Mezzanine Deck pump 330 0.4 x 0.7 x 1.0 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
17 P-1912A/B Lean MEG Product Pump Mezzanine Deck motor 400 0.4 x 0.7 x 1.0 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

1) Attached trolley hoist 0.5T at monorail to lift up


MONORAIL
18 P-1913A/B Reflux Pump Cellar Deck pump 120 0.5 x 0.7 x 1.2 item and lower down onto deck trolley
DECK TROLLEY
2) Deck trolley bring item to SHK main platform.

1) Attached trolley hoist 0.5T at monorail to lift up


MONORAIL
19 P-1913A/B Reflux Pump Cellar Deck motor 74 0.5 x 0.7 x 1.2 item and lower down onto deck trolley
DECK TROLLEY
2) Deck trolley bring item to SHK main platform.

1) Attached trolley hoist 0.5T at monorail to lift up


MONORAIL
20 P-1915A/B Recovered MEG Return Pump Cellar Deck pump 180 0.5 x 0.7 x 1.2 item and lower down onto deck trolley
DECK TROLLEY
2) Deck trolley bring item to SHK main platform.

1) Attached trolley hoist 0.5T at monorail to lift up


MONORAIL
21 P-1915A/B Recovered MEG Return Pump Cellar Deck motor 118 0.5 x 0.7 x 1.2 item and lower down onto deck trolley
DECK TROLLEY
2) Deck trolley bring item to SHK main platform.
Equipment Package Description
Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

1) Attached trolley hoist 0.5T at monorail to lift up


MONORAIL
22 P-1919A/B Heating Medium Pump Cellar Deck pump 180 0.5 x 0.7 x 1.2 item and lower down onto deck trolley
DECK TROLLEY
2) Deck trolley bring item to SHK main platform.

1) Attached trolley hoist 0.5T at monorail to lift up


MONORAIL
23 P-1919A/B Heating Medium Pump Cellar Deck motor 115 1.6 x 1.6 x 2.0 item and lower down onto deck trolley
DECK TROLLEY
2) Deck trolley bring item to SHK main platform.

1) Attach beam clamp complete with chain hoist


2T at beam on top of pump.
BEAM CLAMP 2) Lift up pump/motor to lower down onto Deck
24 P-1920A/B Lean MEG Injection Pump Mezzanine Deck pump 1600 1.6 x 1.6 x 2.0 DECK TROLLEY Trolley 2T and bring to near laydowm area
DAVIT ARM 3) Drop down onto Deck Trolley 2T by Davit Arm
2T at Cellar Deck and bring to SHK Platform

1) Attach beam clamp complete with chain hoist


2T at beam on top of pump.
BEAM CLAMP
2) Lift up pump/motor to lower down onto Deck
25 P-1920A/B Lean MEG Injection Pump Mezzanine Deck Motor 1400 1.6 x 1.6 x 2.0 DECK TROLLEY
Trolley 2T and bring to near laydowm area
DAVIT ARM
3) Drop down onto Deck Trolley 2T by Davit Arm
2T at Cellar Deck and bring to SHK Platform.

1) Beam clamp to lift up item and lower down


BEAM CLAMP
26 P-1921A/B MEG Drain Drum Pump Cellar Deck pump 80 0.5 x 0.3 x 0.8 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Beam clamp to lift up item and lower down


BEAM CLAMP
27 P-1921A/B MEG Drain Drum Pump Cellar Deck motor 50 0.5 x 0.7 x 1.2 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
28 P-1910A/B Rich MEG Condensate Pump Mezzanine Deck pump 30 0.4 x 0.7 x 1.0 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
29 P-1910A/B Rich MEG Condensate Pump Mezzanine Deck motor 12 0.4 x 0.7 x 1.0 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

1) Attach chain hoist 0.5T at A-frame to lift up


A-1910 MEG Centrifuge Package A-FRAME, items
30 Main Deck motor 180 0.8 x 0.36 x 1.2
(M1910) (MEG Centrifuge) DECK TROLLEY 2) Deck Trolley 0.5T brings items to SHK
Platform.
1) Attach chain hoist 0.5T at A-frame to lift up
A-1910 MEG Centrifuge Package A-FRAME, items
31 Main Deck pump 150 0.8 x 0.6 x 1.2
(M1910) (MEG Centrifuge) DECK TROLLEY 2) Deck Trolley 0.5T brings items to SHK
Platform.
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
32 M-1911A Screw Conveyor Mezzanine Deck motor 50 0.5 x 0.3 x 1.0 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

1) Attach trolley hoist 1T at monorail beam brings


items along to Cellar Deck Laydown Area
MONORAIL,
33 TBA Salt Bin Cellar Deck Bin 3800 1.6x1.6x1.5 2) Deck Crane picks up items to SHK main
DECK CRANE
platform

MEG Vacuum Pump Package (consist of


JIB CRANE, 1) Jib crane to lift up items
34 A-1911 Vacuum Pump, Vacumm Pump Scrubber and Main Deck pump 90 0.5 x 0.3 x 0.8
DECK TROLLEY 2) Deck Trolley brings items to client site.
Liquid Ring Cooler)
MEG Vacuum Pump Package (consist of
JIB CRANE, 1) Jib crane to lift up items
35 A-1911 Vacuum Pump, Vacumm Pump Scrubber and Main Deck motor 120 0.8 x 0.36 x 1.2
DECK TROLLEY 2) Deck Trolley brings items to client site.
Liquid Ring Cooler)
Chemical Injection Package 1) Attach chain hoist 0.5T at A-frame to lift up
A-1912 (Alkalinity Tank A-FRAME, items
36 Main Deck pump package 150 0.8 x 0.6 x 1.2
Oxygen Scavenger Tank DECK TROLLEY 2) Deck Trolley 0.5T brings items to SHK
Antifoam Tank) Platform.
Equipment Package Description
Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
37 A-1913 High Purity Nitrogen Package Mezzanine Deck motor <150 0.5 x 0.3 x 0.8 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
38 A-1913 High Purity Nitrogen Package Mezzanine Deck Pump <150 0.5 x 0.3 x 0.8 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

39 E-1910 Rich MEG Pre-heater (spiral type) Platform (Main Deck) NA (in situ cleaning) NA NA NA
1) Attach trolley hoist 1T at monorail lift up bundle
MONORAIL,
and lower down onto Deck Trolley
40 E-1919 Heating Medium Electrical Heater Cellar Deck bundle 1000 0.6 x 0.6 x 4.2 SPECIAL TROLLEY
2) Special Trolley bring bundle to laydown area
DECK CRANE
for Deck Crane to pick up.
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
41 M-1912 Centrifuge Lube Oil Skid Mezzanine Deck motor, pump, cooler fan 60 Varies DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

42 E-1911 MEG Flash Column Heater (Spiral type) Main Deck NA (in situ cleaning) NA - NA
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
BEAM CLAMP on maintenance item.
DECK TROLLEY, 2) Remove maintenance items and slowly lower
43 E-1912 Lean meg cooler PSV/Cooler Deck motor, gear and accessories 150 Varies
DECK CRANE down onto Deck Trolley.
2) Deck Trolley brings items to laydown area
3) Deck Crane picks items up from laydown area
to SHK main platform

1) Vendor to provide lifting device for removal


motor/accessories. location. Hook on
VENDOR maintenance item.
DECK TROLLEY, 2) Lower down onto Deck Trolley 0.5T.
44 E-1913 MEG Liquid Ring Cooler PSV/Cooler Deck motor, gear and accessories 330 0.5 x 0.5 x 0.5
DAVIT ARM 2) Deck Trolley brings items to laydown area near
to Davit Arm
3) Lower down the item onto deck trolley at PSV
deck and transfer to main SHK Platform

1) Batch crane with minimum Crane 20T capacity


to be use since deck crane cannot reach the
BATCH CRANE
45 E-1913 MEG Liquid Ring Cooler PSV/Cooler Deck Heater Bundle 15000/bay 8.0 x 4.0 x 1.5 bundle. lifting arrangement for bundle study detail
shall be made prior lifting the bundle.

1) Deck crane picks item up from laydown area to


46 TBA Tote Tank Upper Deck Tank 1800 2x2x2 DECK CRANE
SHK Platform
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
47 P-1924A/B Lean MEG Booster Pump Mezzanine Deck pump 300 0.5 x 0.7 x 1.2 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
BEAM CLAMP
2) Lift up pump/motor to lower down onto Deck
48 P-1924A/B Lean MEG Booster Pump Mezzanine Deck motor 27 0.5 x 0.3 x 1.0 DECK TROLLEY
Trolley 0.5T and bring to near laydowm area
DAVIT ARM
3) Drop down onto Deck Trolley 0.5T by Davit
Arm 0.5T at Cellar Deck and bring to SHK
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
49 E-1914 Platform (Main Deck) motor, gear and accessories 120 Varies down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
Equipment Package Description
Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

50 V-1921 Rich MEG Drain Tank Cellar Deck NA


51 V-1921 Rich MEG Drain Tank Cellar Deck NA

Piping
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
52 M81-802 8"-DH-19861-A13X-PP Main Deck 4" Manual Valve 150# WNRF 45 0.3 x 0.3 x 0.4 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Install beam clamp complete chain hoist on


bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
53 M81-078 4"-GL-19746-A13X-E Platform (Main Deck) 4" Manual Valve 150# WNRF 45 0.3 x 0.3 x 0.4 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
54 M81-076 4"-GL-19746-A13X-E Main Deck 4" Manual Valve 150# WNRF 45 0.3 x 0.3 x 0.4 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
55 M81-081 4"-GL-19746-A13X-E Main Deck 4" Manual Valve 150# WNRF 45 0.3 x 0.3 x 0.4 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up valve to lower down onto Deck Trolley
BEAM CLAMP
0.5T and bring to near laydowm area
56 M81-424 4"-GL-19886-A13X-E Mezzanine Deck 4" Manual Valve 150# WNRF 45 0.3 x 0.3 x 0.4 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up valve to lower down onto Deck Trolley
BEAM CLAMP
0.5T and bring to near laydowm area
57 M81-432 4"-GL-19886-A13X-E Mezzanine Deck 4" Manual Valve 150# WNRF 45 0.3 x 0.3 x 0.4 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

1) Install beam clamp complete chain hoist on


bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
58 M81-431 4"-GL-19886-A13X-E Platform (Main Deck) 4" Manual Valve 300# WNRF 82 0.4 x 0.4 x 0.5 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
59 M81-019 4"-GL-19892-B13X-IH Platform (Main Deck) 4" Manual Valve 300# WNRF 82 0.4 x 0.4 x 0.5 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
60 M81-054 4"-GL-19892-B13X-IH Platform (Main Deck) 4" Manual Valve 300# WNRF 82 0.4 x 0.4 x 0.5 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
Equipment Package Description
Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

1) Install beam clamp complete chain hoist on


bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
61 M81-020 4"-GL-19892-B13X-IH Platform (Main Deck) 4" Manual Valve 300# WNRF 82 0.4 x 0.4 x 0.5 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
62 M81-143 8"-GL-19730-A16X-E Platform (Main Deck) 6" Manual Valve 300# WNRF 82 0.5 x 0.5 x 0.5 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
63 FV-19003 8"-GL-19730-A16X-E Platform (Main Deck) 6" Manual Valve 300# WNRF 82 0.5 x 0.5 x 0.5 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
64 M81-162 6"-GL-19752-B16X-E Platform (Main Deck) 6" Manual Valve 300# WNRF 82 0.5 x 0.5 x 0.5 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
65 M81-162 6"-GL-19752-B16X-E Platform (Main Deck) 6" Manual Valve 300# WNRF 82 0.5 x 0.5 x 0.5 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
66 M81-154 6"-GL-19756-B16X-E Main Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
67 M81-147 6"-GL-19756-B16X-E Main Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Beam clamp to lift up item and lower down


BEAM CLAMP
68 M81-119 8"-GL-19774-A16X-E Cellar Deck 8" Manual Valve 150# WNRF 157 0.7 x 0.7 x 0.8 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Beam clamp to lift up item and lower down


BEAM CLAMP
INSTRUMENT
69 1 of BRANCH 8"-GL-19774-A16X-EB2
8"-GL-19774-A16X-E Cellar Deck 8" Manual Valve 150# WNRF 157 0.7 x 0.7 x 0.8 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
70 M81-757 6"-HM-19711-B13X-IH Main Deck 6" Manual Valve 300# WNRF 82 0.6 x 0.6 x 0.7 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
71 SDV-19404 6"-HM-19711-B13X-IH Main Deck 6" Manual Valve 300# WNRF 82 0.6 x 0.6 x 0.7 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform
Equipment Package Description
Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
72 M81-161 6"-HM-19750-B13X-IH Platform (Main Deck) 6" Manual Valve 150# WNRF 144 0.5 x 0.5 x 0.5 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
73 M81-158 6"-HM-19750-B13X-IH Platform (Main Deck) 6" Manual Valve 150# WNRF 144 0.5 x 0.5 x 0.5 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Install beam clamp complete chain hoist on


bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
INSTRUMENT
74 1 of BRANCH 6"-HM-19750-B13X-IHB1
6"-HM-19750-B13X-IH Platform (Main Deck) 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform

1) Beam clamp to lift up item and lower down


BEAM CLAMP
75 M81-502 6"-HM-19766-A13X-IH Cellar Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Beam clamp to lift up item and lower down


BEAM CLAMP
76 M81-517 6"-HM-19823-A13X-IH Cellar Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Beam clamp to lift up item and lower down


BEAM CLAMP
77 M81-517 6"-HM-19823-A13X-IH Cellar Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Beam clamp to lift up item and lower down


BEAM CLAMP
78 M81-694 6"-HM-19889-A13X-IH Cellar Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Beam clamp to lift up item and lower down


BEAM CLAMP
79 M81-493 6"-HM-19890-A13X-IH Cellar Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Beam clamp to lift up item and lower down


BEAM CLAMP
80 M81-698 6"-HM-19890-A13X-IH Cellar Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Beam clamp to lift up item and lower down


BEAM CLAMP
81 M81-525 6"-HM-19906-A13X-IH Cellar Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Beam clamp to lift up item and lower down


BEAM CLAMP
82 M81-525 6"-HM-19906-A13X-IH Cellar Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to SHK main platform.

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
83 M81-056 6"-PG-19719-A13X PSV/Cooler Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
84 PSV-19001A 6"-PG-19719-A13X PSV/Cooler Deck 6" PSV Valve 150# WNRF 93 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
Equipment Package Description
Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
85 M81-064 6"-PG-19720-A13X PSV/Cooler Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
86 PSV-19001B 6"-PG-19720-A13X PSV/Cooler Deck 6" PSV Valve 150# WNRF 93 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
87 M81-063 8"-VH-19717-A13X PSV/Cooler Deck 8" Manual Valve 150# WNRF 157 0.7 x 0.7 x 0.8 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
88 M81-065 8"-VH-19718-A13X PSV/Cooler Deck 8" Manual Valve 150# WNRF 157 0.7 x 0.7 x 0.8 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
89 M81-039 6"-VT-19506-A13X PSV/Cooler Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Attach beam clamp complete with chain hoist
BEAM CLAMP 0.5T at beam on top of the valve.
90 M81-300 6"-VT-19563-A13X Main Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5
DECK TROLLEY 2) Remove spool using the beam clamp
3) Hook to the valve and remove valve and lower

InstrumentActuated Valve
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
91 8"-GL-19971-A16X-EB2 8"-GL-19971-A16X-E Main Deck 8" Actuated Valve 150# WNRF 250 0.7 x 0.7 x 1.2 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Install beam clamp complete chain hoist on


bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
92 6"-VT-19598-A13XB1 6"-VT-19598-A13X Platform (Main Deck) 8" Actuated Valve 150# WNRF 160 0.7 x 0.7 x 1.2 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
93 FV-19003 8"-GL-19730-A16X-E Platform (Main Deck) 8" Actuated Flow Control Valve 150# WNRF 350 0.7 x 0.7 x 1.2 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
94 PV-19021 2"-PG-19781-A13X Platform (Main Deck) 2" Actuated Pressure Control Valve 150# WNRF 90 0.3 x0.3 x 0,6 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Install beam clamp complete chain hoist on
bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
95 2"-PG-19781-A13X 2"-PG-19781-A13XB1 Platform (Main Deck) 2" Actuated Pressure Control Valve 150# WNRF 52 0.3 x0.3 x 0,6 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
Equipment Package Description
Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

1) Beam clamp to lift up item and lower down


BEAM CLAMP
96 SDV-19405 2"-GL-19722-A13X Upper Deck 8" Actuated Valve 150# WNRF 90 0.7 x 0.7 x 1.2 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to client site.
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of pump.
2) Lift up PSV to lower down onto Deck Trolley
BEAM CLAMP
0.5T and bring to near laydowm area
97 PV-19002 2"-PG-19729-A13X PSV/Cooler Deck 2" Actuated Pressure Control Valve 150# WNRF 90 0.3 x0.3 x 0,6 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Upper Deck and bring to SHK
Platform

1) Install beam clamp complete chain hoist on


bottom structure frame at suitable location. Hook
on maintenance item.
BEAM CLAMP
2) Remove maintenance items and slowly lower
DECK TROLLEY,
98 6"-HM-19750-B13X-IHB1 6"-HM-19750-B13X-IH Platform (Main Deck) 6" Actuated Valve 300# WNRF 160 down onto Deck Trolley.
DAVIT ARM
2) Deck Trolley brings items to davit arm area
3) Davit arm bring down the items onto Deck
Trolley at main deck and bring them to main SHK
platform
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
99 M81-124 10"-GL-19778-A16X-E Cellar Deck 10" Manual Valve 150# WNRF 282 0.6 x 0.6 x 0.8 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
100 M81-144 10"-GL-19775-A16X-E Cellar Deck 10" Manual Valve 150# WNRF 282 0.6 x 0.6 x 0.8 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of the valve.
2) Remove spool using the beam clamp
BEAM CLAMP
101 M81-164 10"-GL-19743-A13X-E Main Deck 10" Manual Valve 150# WNRF 282 0.6 x 0.6 x 0.8 3) Hook to the valve and remove valve and lower
DECK TROLLEY
down onto Deck Trolley
4) Deck trolley bring to SHK Platform

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up valve to lower down onto Deck Trolley
BEAM CLAMP
0.5T and bring to near laydowm area
102 M81-435 4"-GL-19885-A13X-E Mezzanine Deck 4" Manual Valve 150# WNRF 45 0.3 x 0.3 x 0.4 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
103 M81-046 4"-GL-19813-B13X-IH PSV/Cooler Deck 4" Manual Valve 300# WNRF 82 0.4 x 0.4 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
104 M81-044 4"-GL-19813-B13X-IH PSV/Cooler Deck 4" Manual Valve 300# WNRF 82 0.4 x 0.4 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
105 M81-742 3"-GL-19955-GA3X Upper Deck 3" Manual Valve 1500# WNRF 70 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
106 M81-114 3"-GL-19955-GA3X Upper Deck 3" Manual Valve 1500# WNRF 70 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
107 M81-136 3"-GL-19955-GA3X Upper Deck 3" Manual Valve 1500# WNRF 70 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
108 M81-510 3"-GL-19950-GA3X Upper Deck 3" Manual Valve 1500# WNRF 70 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
Equipment Package Description
Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
109 M81-508 3"-GL-19950-GA3X Upper Deck 3" Manual Valve 1500# WNRF 70 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of pump.
JIB CRANE 2) Lift up PSV to lower down onto Deck Trolley
DECK TROLLEY, 0.5T and bring to near laydowm area
110 PSV-19661B 3"-GL-19941-GA3X PSV/Cooler Deck 3" Pressure Safety Valve 1500# WNRF 100 0.5 x 0.5 x 1.0
DECK CRANE 3) Drop down onto Deck Trolley 0.5T by Davit
Arm 0.5T at Upper Deck and bring to SHK
Platform

1) A-frame to lift valve and lower down onto Deck


JIB CRANE
Trolley.
DECK TROLLEY,
111 M81-620 3"-GL-19941-GA3X PSV/Cooler Deck 3" Manual Valve 1500# WNRF 70 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) A-frame to lift valve and lower down onto Deck
JIB CRANE
Trolley.
DECK TROLLEY,
112 M81-619 3"-GL-19941-GA3X PSV/Cooler Deck 3" Manual Valve 1500# WNRF 70 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Attach beam clamp complete with chain hoist
0.5T at beam on top of pump.
JIB CRANE 2) Lift up PSV to lower down onto Deck Trolley
DECK TROLLEY, 0.5T and bring to near laydowm area
113 PSV-19661A 3"-GL-19940-GA3X PSV/Cooler Deck 3" Pressure Safety Valve 1500# WNRF 68 0.5 x 0.5 x 1.0
DECK CRANE 3) Drop down onto Deck Trolley 0.5T by Davit
Arm 0.5T at Upper Deck and bring to SHK
Platform

1) A-frame to lift valve and lower down onto Deck


JIB CRANE
Trolley.
DECK TROLLEY,
114 M81-615 3"-GL-19940-GA3X PSV/Cooler Deck 3" Manual Valve 1500# WNRF 70 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) A-frame to lift valve and lower down onto Deck
JIB CRANE
Trolley.
DECK TROLLEY,
115 M81-616 3"-GL-19940-GA3X PSV/Cooler Deck 3" Manual Valve 1500# WNRF 70 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
JIB CRANE
1) Beam clamp to lift up item and lower down
DECK TROLLEY,
116 PSV-19038 6"-PG-19982-A13X Upper Deck 6" PSV Valve 150# WNRF 114 0.5 x 0.5 x 0.5 onto Deck Trolley
DECK CRANE
2) Deck Trolley bring item to client site.

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up PSV to lower down onto Deck Trolley
BEAM CLAMP
0.5T and bring to near laydowm area
117 PSV-19603A/B 6"-PG-19982-A13X Upper Deck 6" PSV Valve 150# WNRF 114 0.5 x 0.5 x 0.5 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Upper Deck and bring to SHK
Platform

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
118 M81-780 6"-PG-19982-A13X Upper Deck 6" Manual Valve 150# WNRF 114 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Beam clamp to lift up item and lower down
BEAM CLAMP
119 PSV-19609A 3"-PW-19792-A40XN Upper Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to client site.
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
120 M81-331 3"-PW-19792-A40XN Upper Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
121 M81-135 3"-PW-19792-A40XN Upper Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Beam clamp to lift up item and lower down
BEAM CLAMP
122 PSV-19609B 3"-PW-19792-A40XN Upper Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 onto Deck Trolley
DECK TROLLEY
2) Deck Trolley bring item to client site.
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
123 M81-318 3"-PW-19792-A40XN Upper Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
Equipment Package Description
Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
124 M81-319 3"-PW-19792-A40XN Upper Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
125 M81-232 3"-PW-19792-A40XN PSV/Cooler Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
126 M81-233 3"-PW-19792-A40XN PSV/Cooler Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
127 M81-238 3"-PW-19792-A40XN PSV/Cooler Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
128 PSV-19635A 3"-PW-19792-A40XN PSV/Cooler Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
129 PSV-19635B 3"-PW-19793-A40XN PSV/Cooler Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
130 M81-237 3"-PW-19793-A40XN PSV/Cooler Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
131 M81-236 3"-PW-19793-A40XN PSV/Cooler Deck 3" Manual Valve 150# WNRF 25 0.2 x 0.2 x 0.3 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
132 PSV-19613A 6"-PW-19739-A50XN-PP PSV/Cooler Deck 6" Manual Valve 150# WNRF 114 0.5 x 0.5 x 1.1 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
133 M81-104 6"-PW-19739-A50XN-PP PSV/Cooler Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
134 PSV-19613B 6"-PW-19740-A50XN-PP PSV/Cooler Deck 6" Manual Valve 150# WNRF 114 0.5 x 0.5 x 1.1 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
135 M81-100 6"-PW-19740-A50XN-PP PSV/Cooler Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform

1) Batch crane with minimum Crane 20T capacity


to be use since deck crane cannot reach the
BATCH CRANE
136 REMOVAL SPOOL 14"-PW-19737-A40X-PP PSV/Cooler Deck 6" Removal Spool 150# WNRF 320 0.6 x 0.6 x 1.5 bundle. lifting arrangement for bundle study detail
shall be made prior lifting the bundle.

1) Jib Crane complete with chain hoist 0.5T to lift


JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
137 M81-103 6"-VL-19741-A40X PSV/Cooler Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Jib Crane complete with chain hoist 0.5T to lift
JIB CRANE
valve and lower down onto Deck Trolley.
DECK TROLLEY,
138 M81-107 6"-VL-19742-A40X PSV/Cooler Deck 6" Manual Valve 150# WNRF 77 0.5 x 0.5 x 0.5 2) Deck Trolley brings items to laydown area
DECK CRANE
3) Deck Crane picks items up from laydown area
to SHK main platform
1) Attach beam clamp complete with chain hoist
BEAM CLAMP 0.5T at beam on top of pump.
139 P-1910A Rich MEG Condensate Pump Mezzanine Deck pump 300 0.5 x 0.7 x 1.2 DECK TROLLEY 2) Lift up pump/motor to lower down onto Deck
DAVIT ARM Trolley 0.5T and bring to near laydowm area
3) Drop down onto Deck Trolley 0.5T by Davit
Equipment Package Description
Item No Tagging Approx.
Line Number Service Maintenance Component
Area Maintenance Item component Volume Handling Method Description of Material Handling Method
DutySpare Weight (Kg.)
Lm x Wm x Hm

1) Attach beam clamp complete with chain hoist


0.5T at beam on top of pump.
2) Lift up pump/motor to lower down onto Deck
BEAM CLAMP
Trolley 0.5T and bring to near laydowm area
140 P-1910A Rich MEG Condensate Pump Mezzanine Deck Motor 192 0.8 x 0.36 x 1.2 DECK TROLLEY
3) Drop down onto Deck Trolley 0.5T by Davit
DAVIT ARM
Arm 0.5T at Cellar Deck and bring to SHK
Platform

You might also like