CPWA-23

PROJECT DIVISION
SONAPUR PROJECT SUB DIVISION-II

COMPUTERIZED
MEASUREMENT BOOK
CMB No.COM/ITBP/SO's Mess/PD/

Name of work :- Construction of 45 Nos. SO's suites (ASI


Accomodation ) for 33rd bn, ITBP at Karchia Sonapur
(Assam) including water supply, sanitary installation &
internal electrical installation.

Agency Name M/s Khatri Enterprises

Agreement No. 04/CE/EE/PD/2020-21

Serial No. of Bill:- 5th RA Bill


C.P.W.A-23

5TH RUNNING ACCOUNT BILL


Project Division, C.P.W.D., Bamunimaidam,Guwahati
Sonapur Project Sub-Division:-II ,C.P.W.D,Sonapur

Measurement Book
CMB No.COM/ITBP/SO's Mess/PD/

Name of Work : : Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd
bn, ITBP at Karchia Sonapur (Assam) including water supply,
sanitary installation & internal electrical installation.

Agreement No. : 04/CE/EE/PD/2020-21

Agency Name : M/s Khatri Enterprises

Estimated Cost : Rs.59,040,588.00

Tendered amount : Rs.56,885,607.00

Time allowed : 12 (Twevels) Months

Date of start (Stip.) : 10.08.2020

Date of Completion (Stip.) : 09.08.2021

Actual Date of start : 10.08.2020

Actual Date of Completion : In Progress

Page No:(i)
Issued by : Executive Engineer, PD, CPWD, Bamunimaidam,Guwahati. on

Dated Initial of The Clerk in-charge

Issued to Shri G. Patar, Assistant Engineer , SPSDII,Sonapur on

When this book change hands, the transfer expressed in similar terms, should be recorded under the
dated initial of both the relieving and Relieved Officer, below the last entry of measurement made by the
Relived Officer

Dated initial of Sub-Division officer

Date of First entry: 15.05.2023

Date of Last entry: 15.07.2021

Assistant Engineer
Sonapur Project Sub Division:-II
C.P.W.D, Sonapur

Measurement Book
CMB No.COM/ITBP/SO's Mess/PD/

No.: Docketed in Divisional office Measurement Book vide


Page -1 to 3

Name & designation of Officer :


Shri G. Patar, Assistant Engineer , SPSDII,Sonapur

Date of First entry: 15.05.2023

Date of Last entry: 15.07.2021

Page No. (ii)


Certified that the Measurement book contains ( 1 to 3 Pages

Signature of Officer Receiving the Measurement book

Yearly check in the division office vide instruction No.2 Dated


initial of
Particular Date Divisional
Accounta
nt

Project Division-V, C.P.W.D., Bamunimaidam, Guwahati.


Sonapur Projcet Sub-Division:-II, C.P.W.D., Sonapur

Measurement Book

Central PWD code Para 37, Central P.W.A Code Para 208 to 211 and 220 to 223)

NOTE

Officer and subordinate using this book are expected to keep themselves fully conversant with the above
and the other subsidiary rules, as correct up to the date of measurement

CMB No.COM/ITBP/SO's Mess/PD/

Page No.(iii)
Page II - By Divisional Accountant
s
Calculation Selected Defect
Revie
by Divisional Officer discrepancies Dated initial of
wed Dated Divisional Divisional
for re-check etc noticed
gener Initial Accountant Officer
ally Pages

Page No.(iv)
REVIEW NOTES
By Superior Officer of the Department

Pages recording
Value of Dated initials and
measurements Resualt of the
Date measurements designation of the
subjected to test- check exercised
checked Checking Officer
check

30.08.2023 page no-1 to 12 863178.00 satisfactory

11.09.2023 page no-21 to 23 667963.00 satisfactory

03.10.2023 page no -26 to 29 299638.00 satisfactory

05.10.2023 page no- 30 to 34 314976.00 satisfactory

Assistant Engineer Executive Engineer


Sonapur Project Sub Division:-II Project Division
CPWD,Sonapur CPWD,Guwahati

Page No. (V)


RECORD ENTRY OF MEASUREMENT

Date of Measurement:
Item No:- 3.4 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in
position and binding all complete above plinth level.
Item No:- 3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more.
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
Reinforcement of R/H Side 2nd floor slab Beam Re-inforcement
Long Direction
SB-02 (C8-C9-C10-C11-C12 ) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 18.55 = --- --- --- 55.65 --- ---
Bottom Main Bar 16 mm 1 x 3 x 18.55 = --- --- --- 55.65 --- ---
Top Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Bottom Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Top Extra Bar at C9 16 mm 1 x 1 x 2.60 = --- --- --- 2.60 --- ---
Stirrup
(C8-C9) 10 mm 1 x 22 x 1.42 = --- 31.24 --- --- --- ---
(C9-C10) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 16 x 1.38 = 22.08 --- --- --- --- ---
(C10-C11) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 16 x 1.38 = 22.08 --- --- --- --- ---
(C11-C12) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 16 x 1.38 = 22.08 --- --- --- --- ---
Spacer Pin 16 mm 1 x 2 x 0.16 = --- --- --- 0.32 --- ---
SB-03 (C13-C14 ) (230 X 500)
Top Main Bar 16 mm 1 x 2 x 3.18 = --- --- --- 6.36 --- ---
Bottom Main Bar 16 mm 1 x 2 x 3.18 = --- --- --- 6.36 --- ---
Stirrup
(C13-C14) 10 mm 1 x 12 x 1.42 = --- 17.04 --- --- --- ---
SB-04 (C8-C9 ) (230 X 500) (Lift Bam)
Top Main Bar 12 mm 1 x 2 x 3.72 = --- --- 7.44 --- --- ---
Bottom Main Bar 12 mm 1 x 2 x 3.72 = --- --- 7.44 --- --- ---
Stirrup
(C8-C9) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 4 x 1.38 = 5.52 --- --- --- --- ---
SB-05 (C8-C9 ) (230 X 500) (Lift Bam)
Top Main Bar 12 mm 1 x 2 x 3.72 = --- --- 7.44 --- --- ---
Bottom Main Bar 12 mm 1 x 2 x 3.72 = --- --- 7.44 --- --- ---
Stirrup
(C8-C9) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 4 x 1.38 = 5.52 --- --- --- --- ---
SB-07 (C7-C8) (230 X 500)
Top Main Bar 16 mm 1 x 2 x 4.23 = --- --- --- 8.46 --- ---
Bottom Main Bar 16 mm 1 x 2 x 4.23 = --- --- --- 8.46 --- ---
Extra Bar bottom mid spam 16 mm 1 x 1 x 1.95 = --- --- --- 1.95 --- ---
Stirrup 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 6 x 1.38 = 8.28 --- --- --- --- ---
Spacer Pin 16 mm 1 x 4 x 0.16 = --- --- --- 0.64 --- ---
SB-08 (SB 27- SB 28) (230 X 500)
Top Main Bar 16 mm 1 x 2 x 3.70 = --- --- --- 7.40 --- ---
Bottom Main Bar 16 mm 1 x 2 x 3.70 = --- --- --- 7.40 --- ---
Stirrup 10 mm 1 x 21 x 1.42 = --- 29.82 --- --- --- ---
B/F = 85.56 248.50 29.76 166.05 0.00 0.00

Sign by Contractor Checked by JE Checked by AE


Page no- 1
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 85.56 248.50 29.76 166.05 0.00 0.00
SB-10 (C21-C22-C23-C24-C25-C26) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 26.60 = --- --- --- 79.80 --- ---
Bottom Main Bar 16 mm 1 x 3 x 26.60 = --- --- --- 79.80 --- ---
Top Extra Bar at C22 12 mm 1 x 1 x 2.61 = --- --- 2.61 --- --- ---
Top Extra Bar at C23 12 mm 1 x 1 x 2.60 = --- --- 2.60 --- --- ---
Top Extra Bar at C24 12 mm 1 x 1 x 2.88 = --- --- 2.88 --- --- ---
Top Extra Bar at C25 12 mm 1 x 1 x 3.18 = --- --- 3.18 --- --- ---
Top Extra Bar at C26 16 mm 1 x 1 x 2.05 = --- --- --- 2.05 --- ---
Stirrup
(C21-C22) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 23 x 1.38 = 31.74 --- --- --- --- ---
(C22-C23) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 16 x 1.38 = 22.08 --- --- --- --- ---
(C23-C24) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 15 x 1.38 = 20.70 --- --- --- --- ---
(C24-C25) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 14 x 1.38 = 19.32 --- --- --- --- ---
(C25-C26) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 15 x 1.38 = 20.70 --- --- --- --- ---
Top Lap 16 mm 1 x 6 x 0.80 = --- --- --- 4.80 --- ---
Bottom Lap 16 mm 1 x 6 x 0.80 = --- --- --- 4.80 --- ---
Spacer Pin 16 mm 1 x 18 x 0.16 = --- --- --- 2.88 --- ---
SB-12 (C33-C34-C35-C36-C37-C38) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 26.60 = --- --- --- 79.80 --- ---
Bottom Main Bar 16 mm 1 x 3 x 26.60 = --- --- --- 79.80 --- ---
Top Extra Bar at C33 16 mm 1 x 3 x 2.25 = --- --- --- 6.75 --- ---
Top Extra Bar at C34 16 mm 1 x 3 x 2.65 = --- --- --- 7.95 --- ---
Bottom mid span(C33-C34) 16 mm 1 x 2 x 4.65 = --- --- --- 9.30 --- ---
Top Extra Bar at C37 16 mm 1 x 1 x 2.70 = --- --- --- 2.70 --- ---
Top Lap 16 mm 1 x 6 x 0.80 = --- --- --- 4.80 --- ---
Bottom Lap 16 mm 1 x 6 x 0.80 = --- --- --- 4.80 --- ---
Spacer Pin 20 mm 1 x 10 x 0.16 = --- --- --- --- 1.60 ---
Stirrup
C33-C34 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 23 x 1.38 = 31.74 --- --- --- --- ---
C34-C35 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 16 x 1.38 = 22.08 --- --- --- --- ---
C35-C36 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 15 x 1.38 = 20.70 --- --- --- --- ---
C36-C37 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 15 x 1.38 = 20.70 --- --- --- --- ---
C37-C38 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 15 x 1.38 = 20.70 --- --- --- --- ---
SB-14 (C45-C46-C47-C48-C49-C50) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 26.60 = --- --- --- 79.80 --- ---
Bottom Main Bar 16 mm 1 x 3 x 26.60 = --- --- --- 79.80 --- ---
Top Extra Bar at C45 2nd
16 mm 1 x 2 x 2.10 = --- --- --- 4.20 --- ---
Layer
Top Extra Bar at C46 2nd
16 mm 1 x 3 x 2.70 = --- --- --- 8.10 --- ---
Layer
Bottom mid span(C45-C46) 16 mm 1 x 2 x 4.65 = --- --- --- 9.30 --- ---
Top Lap 16 mm 1 x 6 x 0.80 = --- --- --- 4.80 --- ---
Bottom Lap 16 mm 1 x 6 x 0.80 = --- --- --- 4.80 --- ---
Spacer Pin 20 mm 1 x 10 x 0.16 = --- --- --- --- 1.60 ---
Stirrup
C45-C46 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 20 x 1.38 = 27.60 --- --- --- --- ---
B/F = 343.62 560.90 41.03 726.88 3.20 0.00

Sign by Contractor Checked by JE Checked by AE

Page no- 2
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 343.62 560.90 41.03 726.88 3.20 0.00
C46-C47 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 15 x 1.38 = 20.70 --- --- --- --- ---
C47-C48 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 15 x 1.38 = 20.70 --- --- --- --- ---
C48-C49 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 15 x 1.38 = 20.70 --- --- --- --- ---
C49-C50 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 13 x 1.38 = 17.94 --- --- --- --- ---
SB-30 (SB24-C9-SB31) (230 X 500)
Top Main Bar 12 mm 1 x 3 x 3.95 = --- --- 11.85 --- --- ---
Bottom Main Bar 12 mm 1 x 3 x 3.95 = --- --- 11.85 --- --- ---
Stirrup 10 mm 1 x 14 x 1.42 = --- 19.88 --- --- --- ---
8 mm 1 x 9 x 1.38 = 12.42 --- --- --- --- ---
SB-30 (SB-31-C11-SB31) (230 X 500)
Top Main Bar 12 mm 1 x 3 x 7.00 = --- --- 21.00 --- --- ---
Bottom Main Bar 12 mm 1 x 3 x 7.00 = --- --- 21.00 --- --- ---
Stirrup 10 mm 1 x 29 x 1.42 = --- 41.18 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
Lap 12 mm 1 x 3 x 0.60 = --- --- 1.80 --- --- ---
SB-30 (SB-31-C47-SB31) (230 X 500)
Top Main Bar 12 mm 1 x 3 x 7.00 = --- --- 21.00 --- --- ---
Bottom Main Bar 12 mm 1 x 3 x 7.00 = --- --- 21.00 --- --- ---
Stirrup 10 mm 1 x 28 x 1.42 = --- 39.76 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
SB-30 (SB-31-C49-SB31) (230 X 500)
Top Main Bar 12 mm 1 x 3 x 7.00 = --- --- 21.00 --- --- ---
Bottom Main Bar 12 mm 1 x 3 x 7.00 = --- --- 21.00 --- --- ---
Stirrup 10 mm 1 x 28 x 1.42 = --- 39.76 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
SB-33 (C9-C10-C11-C12 ) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 15.60 = --- --- --- 46.80 --- ---
Bottom Main Bar 16 mm 1 x 3 x 15.60 = --- --- --- 46.80 --- ---
Top Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Bottom Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Stirrup
C9-C10 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 16 x 1.38 = 22.08 --- --- --- --- ---
C10-C11 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
C11-C12 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
SB-35 (C46-C47-C48-C49-C50 ) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 20.37 = --- --- --- 61.11 --- ---
Bottom Main Bar 16 mm 1 x 3 x 20.37 = --- --- --- 61.11 --- ---
Top Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Bottom Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Stirrup
C46-C47 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 16 x 1.38 = 22.08 --- --- --- --- ---

C47-C48 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---


8 mm 1 x 16 x 1.38 = 22.08 --- --- --- --- ---
C48-C49 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 16 x 1.38 = 22.08 --- --- --- --- ---
C49-C50 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 16 x 1.38 = 22.08 --- --- --- --- ---
B/F = 663.78 1013.88 192.53 952.30 3.20 0.00

Sign by Contractor Checked by JE Checked by AE

Page no- 3
Steel (TMT Bars)
Particulars Dia No. Length
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 663.78 1013.88 192.53 952.30 3.20 0.00
SB-21 (C7-C21-C33-C45) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 15.12 = --- --- --- 45.36 --- ---
Bottom Main Bar 16 mm 1 x 3 x 15.12 = --- --- --- 45.36 --- ---
Top Extra Bar at C45 12 mm 1 x 1 x 2.15 = --- --- 2.15 --- --- ---
Top Extra Bar at C33 16 mm 1 x 1 x 2.61 = --- --- --- 2.61 --- ---
Top Extra Bar at C21 20 mm 1 x 1 x 2.52 = --- --- --- --- 2.52 ---
Top Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Bottom Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Spacer Pin 20 mm 1 x 10 x 0.16 = --- --- --- --- 1.60 ---
Stirrup
C7-C21 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 12 x 1.38 = 16.56 --- --- --- --- ---
C21-C33 10 mm 1 x 17 x 1.42 = --- 24.14 --- --- --- ---
C33-C45 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 20 x 1.38 = 27.60 --- --- --- --- ---
SB-22 (SB12-SB14 ) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 7.00 = --- --- --- 21.00 --- ---
Bottom Main Bar 16 mm 1 x 3 x 7.00 = --- --- --- 21.00 --- ---
Bottom mid span 12 mm 1 x 2 x 4.15 = --- --- 8.30 --- --- ---
Spacer Pin 16 mm 1 x 4 x 0.16 = --- --- --- 0.64 --- ---
Stirrup 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 25 x 1.38 = 34.50 --- --- --- --- ---
SB-23 (C8-SB 10 ) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 7.20 = --- --- --- 21.60 --- ---
Bottom Main Bar 16 mm 1 x 3 x 7.20 = --- --- --- 21.60 --- ---
Top Lap 16 mm 1 x 1 x 0.80 = --- --- --- 0.80 --- ---
Bottom Lap 16 mm 1 x 1 x 0.80 = --- --- --- 0.80 --- ---
Stirrup 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 24 x 1.38 = 33.12 --- --- --- --- ---
SB-24 (C9-C22-C34-C46) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 15.94 = --- --- --- 47.82 --- ---
Bottom Main Bar 16 mm 1 x 3 x 15.94 = --- --- --- 47.82 --- ---
Top Extra Bar at C46 12 mm 1 x 1 x 2.54 = --- --- 2.54 --- --- ---
Top Extra Bar at C34 16 mm 1 x 1 x 2.60 = --- --- --- 2.60 --- ---

Top Extra Bar at C22 16 mm 1 x 1 x 2.60 = --- --- --- 2.60 --- ---
Bottom Extra Bar at mid
12 mm 1 x 1 x 4.50 = --- --- 4.50 --- --- ---
span C22-C9
Top Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Bottom Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Stirrup
C9-C22 10 mm 1 x 21 x 1.42 = --- 29.82 --- --- --- ---
8 mm 1 x 21 x 1.38 = 28.98 --- --- --- --- ---
C22-C34 10 mm 1 x 16 x 1.42 = --- 22.72 --- --- --- ---
C34-C46 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 21 x 1.38 = 28.98 --- --- --- --- ---
SB-25 (C10-C23-C35-C47) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 15.94 = --- --- --- 47.82 --- ---
Bottom Main Bar 16 mm 1 x 3 x 15.94 = --- --- --- 47.82 --- ---
Top Extra Bar at C35 12 mm 1 x 2 x 2.45 = --- --- 4.90 --- --- ---
Top Extra Bar at C23 12 mm 1 x 2 x 2.35 = --- --- 4.70 --- --- ---
Top Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
B/F = 833.52 1232.56 219.62 1341.55 7.32 0.00

Sign by Contractor Checked by JE Checked by AE

Page no- 4
Steel (TMT Bars)
Particulars Dia No. Length
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 833.52 1232.56 219.62 1341.55 7.32 0.00
Bottom Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Spacer Pin 20 mm 1 x 6 x 0.16 = --- --- --- --- 0.96 ---
Stirrup
C10-C23 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 22 x 1.38 = 30.36 --- --- --- --- ---
C23-C35 10 mm 1 x 16 x 1.42 = --- 22.72 --- --- --- ---
C35-C47 10 mm 1 x 24 x 1.42 = --- 34.08 --- --- --- ---
8 mm 1 x 21 x 1.38 = 28.98 --- --- --- --- ---
SB-26 (C11-C24-C36-C48) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 15.94 = --- --- --- 47.82 --- ---
Bottom Main Bar 16 mm 1 x 3 x 15.94 = --- --- --- 47.82 --- ---
Top Extra Bar at C24 12 mm 1 x 2 x 2.86 = --- --- 5.72 --- --- ---
Top Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Bottom Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Spacer Pin 20 mm 1 x 4 x 0.16 = --- --- --- --- 0.64 ---
Stirrup
C11-C24 10 mm 1 x 24 x 1.42 = --- 34.08 --- --- --- ---
8 mm 1 x 22 x 1.38 = 30.36 --- --- --- --- ---
C24-C36 10 mm 1 x 16 x 1.42 = --- 22.72 --- --- --- ---
C36-C48 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 21 x 1.38 = 28.98 --- --- --- --- ---
SB-27 (C12-C25-C37-C49) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 15.94 = --- --- --- 47.82 --- ---
Bottom Main Bar 16 mm 1 x 3 x 15.94 = --- --- --- 47.82 --- ---
Top Extra Bar at C49 16 mm 1 x 1 x 2.54 = --- --- --- 2.54 --- ---
Top Extra Bar at C25 16 mm 1 x 1 x 2.60 = --- --- --- 2.60 --- ---
Top Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Bottom Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Spacer Pin 16 mm 1 x 6 x 0.16 = --- --- --- 0.96 --- ---
Stirrup
C12-C25 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 21 x 1.38 = 28.98 --- --- --- --- ---
C25-C37 10 mm 1 x 16 x 1.42 = --- 22.72 --- --- --- ---
C37-C49 10 mm 1 x 24 x 1.42 = --- 34.08 --- --- --- ---
8 mm 1 x 20 x 1.38 = 27.60 --- --- --- --- ---
SB-28 (C13-SB10) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 7.25 = --- --- --- 21.75 --- ---
Bottom Main Bar 16 mm 1 x 3 x 7.25 = --- --- --- 21.75 --- ---
Bottom Extra bar 12 mm 1 x 1 x 4.20 = --- --- 4.20 --- --- ---
Spacer Pin 16 mm 1 x 4 x 0.16 = --- --- --- 0.64 --- ---
Top Lap 16 mm 1 x 1 x 0.80 = --- --- --- 0.80 --- ---
Bottom Lap 16 mm 1 x 1 x 0.80 = --- --- --- 0.80 --- ---
m
Stirrup 10 1 x 20 x 1.42 = --- 28.4 --- --- --- ---
m
m
8 1 x 22 x 1.38 = 30.36 --- --- --- --- ---
m
B/F = 1039.14 1516.56 229.54 1596.67 8.92 0.00

Sign by Contractor Checked by JE Checked by AE


Page no- 5
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 1039.14 1516.56 229.54 1596.67 8.92 0.00
SB-29 (C14-C26-C38-C50) (230 X 500)
Top Main Bar 16 mm 1 x 3 x 15.12 = --- --- --- 45.36 --- ---
Bottom Main Bar 16 mm 1 x 3 x 15.12 = --- --- --- 45.36 --- ---
Top Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Bottom Lap 16 mm 1 x 3 x 0.80 = --- --- --- 2.40 --- ---
Stirrup
C14-C26 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 22 x 1.38 = 30.36 --- --- --- --- ---
C26-C38 10 mm 1 x 16 x 1.42 = --- 22.72 --- --- --- ---
C38-C50 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 21 x 1.38 = 28.98 --- --- --- --- ---
SB-31 (C9-C11) (C10-C11) (C11-C12) (C46-C47) (C47-C48) (C48-C49) (C49-C50) (230 X 500)
Top Main Bar 12 mm 7 x 3 x 4.20 = --- --- 88.20 --- --- ---
Bottom Main Bar 12 mm 7 x 3 x 4.20 = --- --- 88.20 --- --- ---
Stirrup
10 mm 7 x 18 x 1.42 = --- 178.92 --- --- --- ---
8 mm 7 x 7 x 1.38 = 67.62 --- --- --- --- ---
Total (In M) = 1166.10 1775.00 405.94 1692.19 8.92 0.00
0.395 0.616 0.888 1.579 2.467 3.850
Total Weight (In KG) = 460.61 1093.40 360.47 2671.97 22.01 0.00

C/O TCMB / P - 4608.46 Kg


Sign by Contractor Checked by JE Checked by AE

Page no- 6

Date of Measurement:
Item No:- 3.4 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in
position and binding all complete above plinth level.
Item No:- 3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more.
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
Measurement Of R/H Side 2nd Floor Slab Reinforcement
Long Direction
(C21-C33-C35)to(C26-C38-C50)
Bottom bar 10 mm 1 x 39 x 25.56 = --- 996.84 --- --- --- ---
Crank bar 10 mm 1 x 6 x 25.76 = --- 154.56 --- --- --- ---
Crank bar 10 mm 1 x 4 x 26.16 = --- 104.64 --- --- --- ---
Top bar 10 mm 1 x 27 x 25.56 = --- 690.12 --- --- --- ---
10 mm 1 x 3 x 25.96 = --- 77.88 --- --- --- ---
Extra top
At (C33-C45) 10 mm 1 x 9 x 1.05 = --- 9.45 --- --- --- ---
At SB22 10 mm 1 x 9 x 1.50 = --- 13.50 --- --- --- ---
At SB24 10 mm 1 x 5 x 2.15 = --- 10.75 --- --- --- ---
At SB25 10 mm 1 x 5 x 2.55 = --- 12.75 --- --- --- ---
At SB26 10 mm 1 x 5 x 2.55 = --- 12.75 --- --- --- ---
At SB27 10 mm 1 x 5 x 2.55 = --- 12.75 --- --- --- ---
At SB29 10 mm 1 x 5 x 1.10 = --- 5.50 --- --- --- ---
(C21-SB07)TO(C26-SB08)
Bottom bar 10 mm 1 x 10 x 25.56 = --- 255.60 --- --- --- ---
10 mm 1 x 1 x 17.56 = --- 17.56 --- --- --- ---
Crank bar 10 mm 1 x 1 x 22.70 = --- 22.70 --- --- --- ---
10 mm 1 x 1 x 25.86 = --- 25.86 --- --- --- ---
10 mm 1 x 1 x 17.86 = --- 17.86 --- --- --- ---
Top bar 10 mm 1 x 7 x 25.56 = --- 178.92 --- --- --- ---
(SB24-SB27) near lift to staire case
Bottom bar 10 mm 1 x 15 x 14.95 = --- 224.25 --- --- --- ---
Crank bar 10 mm 1 x 1 x 15.25 = --- 15.25 --- --- --- ---
Top bar 10 mm 1 x 11 x 14.95 = --- 164.45 --- --- --- ---
Extra top
10 mm 1 x 4 x 4.76 = --- 19.04 --- --- --- ---
10 mm 1 x 4 x 3.40 = --- 13.60 --- --- --- ---
(C9-C12)TO(C49-C46)
Bottom bar 10 mm 1 x 63 x 14.23 = --- 896.49 --- --- --- ---
Crank bar 10 mm 1 x 23 x 14.43 = --- 331.89 --- --- --- ---
Top bar 10 mm 1 x 45 x 14.23 = --- 640.35 --- --- --- ---
Extra top
(SB14-SB35) 10 mm 1 x 17 x 3.40 = --- 57.80 --- --- --- ---
(SB12-SB10) 10 mm 1 x 17 x 3.80 = --- 64.60 --- --- --- ---
(SB02-SB33) 10 mm 1 x 17 x 3.85 = --- 65.45 --- --- --- ---
(SB02-SB04)
Bottom bar 10 mm 1 x 15 x 2.30 = --- 34.50 --- --- --- ---
Top bar 10 mm 1 x 15 x 2.30 = --- 34.50 --- --- --- ---
B/F = 0.00 5182.16 0.00 0.00 0.00 0.00
Sign by Contractor Checked by JE Checked by AE

Page no- 7
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 0.00 5182.16 0.00 0.00 0.00 0.00
(SB05-SB14)
Bottom bar 10 mm 1 x 13 x 10.10 = --- 131.30 --- --- --- ---
Top bar 10 mm 1 x 8 x 10.10 = --- 80.80 --- --- --- ---
Crank bar 10 mm 1 x 6 x 10.20 = --- 61.20 --- --- --- ---
Extra top
10 mm 1 x 4 x 5.53 = --- 22.12 --- --- --- ---
10 mm 1 x 4 x 1.53 = --- 6.12 --- --- --- ---
(SB07-SB14)
Bottom bar 10 mm 1 x 15 x 9.60 = --- 144.00 --- --- --- ---
Top bar 10 mm 1 x 12 x 9.60 = --- 115.20 --- --- --- ---
Crank bar 10 mm 1 x 4 x 9.70 = --- 38.80 --- --- --- ---
Extra top
10 mm 1 x 3 x 4.95 = --- 14.85 --- --- --- ---
10 mm 1 x 3 x 1.53 = --- 4.59 --- --- --- ---
Extra top
(SB21-SB24) 10 mm 1 x 2 x 7.60 = --- 15.20 --- --- --- ---
(SB23-SB24) 10 mm 1 x 1 x 4.51 = --- 4.51 --- --- --- ---
At SB24 10 mm 1 x 2 x 1.85 = --- 3.70 --- --- --- ---
At SB25 10 mm 1 x 5 x 2.53 = --- 12.65 --- --- --- ---
At SB26 10 mm 1 x 5 x 2.53 = --- 12.65 --- --- --- ---
At SB27 10 mm 1 x 2 x 6.26 = --- 12.52 --- --- --- ---
10 mm 1 x 3 x 1.44 = --- 4.32 --- --- --- ---
(SB23-SB27)
Bottom bar 10 mm 1 x 13 x 17.50 = --- 227.50 --- --- --- ---
Top bar 10 mm 1 x 13 x 17.50 = --- 227.50 --- --- --- ---
(SB28-SB29)
Bottom bar 10 mm 1 x 28 x 2.26 = --- 63.28 --- --- --- ---
Top bar 10 mm 1 x 28 x 2.26 = --- 63.28 --- --- --- ---
Short Direction
(C13-C14)TO (C50-SB31)
Bottom bar 10 mm 1 x 11 x 14.23 = --- 156.53 --- --- --- ---
Crank bar 10 mm 1 x 5 x 14.38 = --- 71.90 --- --- --- ---
Top bar 10 mm 1 x 6 x 14.23 = --- 85.38 --- --- --- ---
Extra top
(SB3-SB12) 10 mm 1 x 3 x 9.30 = --- 27.90 --- --- --- ---
(SB14-SB35) 10 mm 1 x 3 x 3.40 = --- 10.20 --- --- --- ---
(SB08-SB14)
Bottom bar 10 mm 1 x 11 x 9.80 = --- 107.80 --- --- --- ---
Corridor area 10 mm 1 x 33 x 2.32 = --- 76.56 --- --- --- ---
Crank bar 10 mm 1 x 4 x 9.90 = --- 39.60 --- --- --- ---
Top bar 10 mm 1 x 6 x 9.80 = --- 58.80 --- --- --- ---
Slab projection
C9 Area
Top & Bottom 10 mm 2 x 28 x 1.61 = --- 90.16 --- --- --- ---
Binder 10 mm 2 x 6 x 5.50 = --- 66.00 --- --- --- ---
B/F = 0.00 7239.08 0.00 0.00 0.00 0.00
Sign by Contractor Checked by JE Checked by AE

Page no- 8
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 0.00 7239.08 0.00 0.00 0.00 0.00
C11 Area
Top & Bottom 10 mm 2 x 46 x 1.61 = --- 148.12 --- --- --- ---
Binder 10 mm 2 x 6 x 8.20 = --- 98.40 --- --- --- ---
C47 Area
Top & Bottom 10 mm 2 x 47 x 1.61 = --- 151.34 --- --- --- ---
Binder 10 mm 2 x 6 x 8.20 = --- 98.40 --- --- --- ---
C49 Area
Top & Bottom 10 mm 2 x 48 x 1.61 = --- 154.56 --- --- --- ---
Binder 10 mm 2 x 6 x 8.20 = --- 98.40 --- --- --- ---
Laping 10 mm 1 x 390 x 0.50 = --- 195.00 --- --- --- ---
Chair 10 mm 1 x 225 x 1.47 = --- 330.75 --- --- --- ---
Reinforcement of 1st floor Stair Case Re-inforcement
Stair case 4th Flight upto slab (C7-C8)
Bottom main upto slab 12 mm 1 x 13 x 4.19 = --- --- 54.47 --- --- ---
Lap 12 mm 1 x 13 x 0.60 = --- --- 7.80 --- --- ---
Top extra bar 12 mm 1 x 12 x 1.37 = --- --- 16.44 --- --- ---
Middle bar 12 mm 1 x 13 x 1.00 = --- --- 13.00 --- --- ---
Slab to 4th flight 12 mm 1 x 12 x 2.70 = --- --- 32.40 --- --- ---
12 mm 1 x 13 x 2.30 = --- --- 29.90 --- --- ---
Binder 10 mm 1 x 45 x 1.46 = --- 65.70 --- --- --- ---
Slab to 5th flight 12 mm 1 x 12 x 1.60 = --- --- 19.20 --- --- ---
12 mm 1 x 12 x 1.60 = --- --- 19.20 --- --- ---
12 mm 1 x 12 x 0.80 = --- --- 9.60 --- --- ---
Chair 10 mm 1 x 6 x 1.39 = --- 8.34 --- --- --- ---
Stair case 4th Flight (C12-C13)
Bottom barupto slab 12 mm 1 x 10 x 4.25 = --- --- 42.50 --- --- ---
Lap 12 mm 1 x 10 x 0.60 = --- --- 6.00 --- --- ---
Top extra bar 12 mm 1 x 10 x 1.37 = --- --- 13.70 --- --- ---
Middle bar 12 mm 1 x 10 x 1.00 = --- --- 10.00 --- --- ---
Slab upto 4th flight 12 mm 1 x 10 x 2.90 = --- --- 29.00 --- --- ---
12 mm 1 x 10 x 2.43 = --- --- 24.30 --- --- ---
Binder 10 mm 1 x 41 x 1.14 = --- 46.74 --- --- --- ---
Chair 10 mm 1 x 7 x 1.39 = --- 9.73 --- --- --- ---

Total (In m) = 0.00 8644.56 327.51 0.00 0.00 0.00


0.395 0.616 0.888 1.579 2.467 3.850
Total Weight (In Kg) 0.00 5325.05 290.83 0.00 0.00 0.00

C/O TCMB / P - 5615.88 kg


Sign by Contractor Checked by JE Checked by AE

Page no- 9
Item No:- 3.4 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in
position and binding all complete above plinth level.
Item No:- 3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more.
Measurement for Stirrup For Column and Beam Junction at 2nd Floor Slab of R/H side
C7 10 mm 1 x 4 x 1.78 = --- 7.12 --- --- --- ---
C8 10 mm 1 x 4 x 1.78 = --- 7.12 --- --- --- ---
C9 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C10 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C11 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C12 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C13 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C14 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C21 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C22 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C23 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C24 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C25 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C26 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C33 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C34 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C35 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C36 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C37 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C38 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C45 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C46 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C47 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C48 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C49 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C50 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
Total (In m) = 0.00 165.92 0.00 0.00 0.00 0.00
0.395 0.616 0.888 1.579 2.467 3.850
Total Weight (In Kg) 0.00 102.21 0.00 0.00 0.00 0.00

C/O TCMB / P - 102.21 Kg


Sign by Contractor Checked by JE Checked by AE

Page no- 10

Item No:- 3.4 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in
position and binding all complete above plinth level.
Item No:- 3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more.
Reinforcement of Column L/H Side From 3rd floor upto roof slab
C4
Vertical Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 8 x 1.00 = --- --- --- --- 8.00 ---
Stirrups 10 mm 1 x 24 x 1.58 = --- 37.92 --- --- --- ---
10 mm 1 x 24 x 0.62 = --- 14.88 --- --- --- ---
Link
10 mm 1 x 24 x 0.47 = --- 11.28 --- --- --- ---
C5
Vertical Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 8 x 1.00 = --- --- --- --- 8.00 ---
Stirrups 10 mm 1 x 24 x 1.58 = --- 37.92 --- --- --- ---
10 mm 1 x 24 x 0.62 = --- 14.88 --- --- --- ---
Link
10 mm 1 x 24 x 0.47 = --- 11.28 --- --- --- ---
C6
Vertical Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
16 mm 1 x 4 x 3.30 = --- --- --- 13.20 --- ---
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
16 mm 1 x 4 x 0.80 = --- --- --- 3.20 --- ---
Stirrups 10 mm 1 x 24 x 1.58 = --- 37.92 --- --- --- ---
10 mm 1 x 24 x 0.62 = --- 14.88 --- --- --- ---
Link
10 mm 1 x 24 x 0.47 = --- 11.28 --- --- --- ---
C18
Vertical Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
Stirrups 10 mm 1 x 24 x 1.58 = --- 37.92 --- --- --- ---
10 mm 1 x 24 x 0.62 = --- 14.88 --- --- --- ---
Link
10 mm 1 x 24 x 0.47 = --- 11.28 --- --- --- ---
C19
Vertical Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
Stirrups 10 mm 1 x 24 x 1.58 = --- 37.92 --- --- --- ---
10 mm 1 x 24 x 0.62 = --- 14.88 --- --- --- ---
Link
10 mm 1 x 24 x 0.47 = --- 11.28 --- --- --- ---
C20
Vertical Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
16 mm 1 x 4 x 3.30 = --- --- --- 13.20 --- ---
B/F = 0.00 320.40 0.00 29.60 133.60 36.40

Sign by Contractor Checked by JE Checked by AE

Page no- 11
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 0.00 320.40 0.00 29.60 133.60 36.40
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
16 mm 1 x 4 x 0.80 = --- --- --- 3.20 --- ---
Stirrups 10 mm 1 x 24 x 1.58 = --- 37.92 --- --- --- ---
10 mm 1 x 24 x 0.62 = --- 14.88 --- --- --- ---
Link
10 mm 1 x 24 x 0.47 = --- 11.28 --- --- --- ---
C30
Vertical Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
Stirrups 10 mm 1 x 24 x 1.58 = --- 37.92 --- --- --- ---
10 mm 1 x 24 x 0.62 = --- 14.88 --- --- --- ---
Link
10 mm 1 x 24 x 0.47 = --- 11.28 --- --- --- ---
C31
Vertical Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
Stirrups 10 mm 1 x 24 x 1.58 = --- 37.92 --- --- --- ---
10 mm 1 x 24 x 0.62 = --- 14.88 --- --- --- ---
Link
10 mm 1 x 24 x 0.47 = --- 11.28 --- --- --- ---
C32
Vertical Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
16 mm 1 x 4 x 3.30 = --- --- --- 13.20 --- ---
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
16 mm 1 x 4 x 0.80 = --- --- --- 3.20 --- ---
Stirrups 10 mm 1 x 24 x 1.58 = --- 37.92 --- --- --- ---
10 mm 1 x 24 x 0.62 = --- 14.88 --- --- --- ---
Link
10 mm 1 x 24 x 0.47 = --- 11.28 --- --- --- ---
C42
Vertical Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 8 x 1.00 = --- --- --- --- 8.00 ---
Stirrups 10 mm 1 x 23 x 1.58 = --- 36.34 --- --- --- ---
10 mm 1 x 23 x 0.62 = --- 14.26 --- --- --- ---
Link
10 mm 1 x 23 x 0.47 = --- 10.81 --- --- --- ---
C43
Vertical Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 8 x 1.00 = --- --- --- --- 8.00 ---
Stirrups 10 mm 1 x 23 x 1.58 = --- 36.34 --- --- --- ---
10 mm 1 x 23 x 0.62 = --- 14.26 --- --- --- ---
Link
10 mm 1 x 23 x 0.47 = --- 10.81 --- --- --- ---
C44
Vertical Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
16 mm 1 x 4 x 3.30 = --- --- --- 13.20 --- ---
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
16 mm 1 x 4 x 0.80 = --- --- --- 3.20 --- ---
Stirrups 10 mm 1 x 23 x 1.58 = --- 36.34 --- --- --- ---
10 mm 1 x 23 x 0.62 = --- 14.26 --- --- --- ---
Link
10 mm 1 x 23 x 0.47 = --- 10.81 --- --- --- ---
TOTAL = 0.00 760.95 0.00 65.60 275.20 72.80
Provisional Weight considered for Measurements 0.395 0.616 0.888 1.579 2.467 3.850
Weight in Kg 0.00 468.75 0.00 103.58 678.92 280.28
Total (in Kg) 1531.53
C/O TCMB / P -

Sign by Contractor Checked by JE Checked by AE

Page no- 12
Date of Measurement
Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and Removal of form for
3.2.6 : Column, Pillars, piers, Abustments, posts and struts
Particular Nos x Nos x L x B x H = Quantity Unit
ASOS Mess R/H Side Column Shuttering From 2.4 mt upto 2nd floor slab

C7 1 x 2 x( 0.35 + 0.60 )x 0.75 = 1.43 sqm

C8 1 x 2 x( 0.35 + 0.60 )x 0.75 = 1.43 sqm

C9 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C10 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C11 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C12 1 x 2 x( 0.35 + 0.60 )x 0.75 = 1.43 sqm

C13 1 x 2 x( 0.35 + 0.60 )x 0.75 = 1.43 sqm

C14 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C21 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C22 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C23 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C24 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C25 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C26 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C33 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C34 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C35 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C36 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C37 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C38 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C45 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C46 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C47 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C48 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C49 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

C50 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm

Total Quantity = 33.88 Sqm


C/O TCMB -

Sign by Contractor Checked by JE Checked by AE

Page no- 13
Date of Measurement
Providing and laying in position machine batched and machine mixed design mix M-25
grade cement concrete for reinforcd cement concrete work , using coarse aggregate as well
as fine aggregate derived from natural source and cement cocrete as per approved design
mix , including pimping of con crete to site laying but excluding the cost of centering ,
Agreement No. 3.6 : shuttering,finishing and reinforecd , including admixture in recommended proportion as per
IS: 9103 to accelerated, retard setting of concrete , improve workability without impairing
strength and durability as per direction of Engineer-in-Charge.

3.6.2 : All works above plinth level upto floor V level


Particular Nos x Nos x L x B x H = Quantity Unit

ASOS Mess R/H Side Column R.C.C From 2.4 mt upto 2nd floor
C7 1 x 1 x 0.35 x 0.60 x 0.90 = 0.19 Cum
C8 1 x 1 x 0.35 x 0.60 x 0.90 = 0.19 Cum
C9 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C10 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C11 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C12 1 x 1 x 0.35 x 0.60 x 0.90 = 0.19 Cum
C13 1 x 1 x 0.35 x 0.60 x 0.90 = 0.19 Cum
C14 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C21 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C22 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C23 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C24 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C25 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C26 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C33 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C34 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C35 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C36 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C37 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C38 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C45 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C46 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C47 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C48 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C49 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C50 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
Total Quantity = 4.28 Cum

C/O TCMB -

Sign by Contractor Checked by JE Checked by AE


Page no- 14
Date of Measurement 6/8/2023
Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and Removal of form for
3.2.3 : Suspendd floors, roofs, landing, balconies and access platform
Particular Nos x Nos x L x B x H = Quantity Unit
2nd floor R.H.S slab Shuttering
S1 1 x 1 x 2.57 x 1.85 x - = 4.74 Sqm
S2 1 x 1 x 2.77 x 1.19 x - = 3.28 Sqm
S3 1 x 1 x 1.62 x 2.51 x - = 4.05 Sqm
S4 1 x 1 x 2.50 x 1.63 x - = 4.07 Sqm
S5 1 x 1 x 1.19 x 2.79 x - = 3.32 Sqm
S6 1 x 1 x 2.80 x 1.21 x - = 3.38 Sqm
S7 1 x 1 x 1.63 x 2.47 x - = 4.03 Sqm
S8 1 x 1 x 5.91 x 1.86 x - = 10.99 Sqm
S9 1 x 1 x 2.77 x 1.09 x - = 3.02 Sqm
S10 1 x 1 x 2.79 x 1.07 x - = 2.99 Sqm
S11 1 x 1 x 2.80 x 1.08 x - = 3.00 Sqm
S12 1 x 1 x 3.07 x 1.15 x - = 3.53 Sqm
S13 1 x 1 x 2.57 x 1.78 x - = 4.57 Sqm
S14 1 x 1 x 4.61 x 3.19 x - = 14.71 Sqm
S15 1 x 1 x 4.61 x 3.19 x - = 14.71 Sqm
S16 1 x 1 x 4.65 x 3.19 x - = 14.83 Sqm
S17 1 x 1 x 2.52 x 1.40 x - = 3.52 Sqm
S18 1 x 1 x 5.91 x 1.80 x - = 10.60 Sqm
S19 1 x 1 x 4.61 x 1.80 x - = 8.27 Sqm
S20 1 x 1 x 4.64 x 1.80 x - = 8.33 Sqm
S21 1 x 1 x 4.63 x 1.80 x - = 8.31 Sqm
S22 1 x 1 x 4.65 x 1.80 x - = 8.35 Sqm
S23 1 x 1 x 4.59 x 3.20 x - = 14.69 Sqm
S24 1 x 1 x 4.64 x 3.20 x - = 14.83 Sqm
S25 1 x 1 x 4.65 x 3.20 x - = 14.88 Sqm
S26 1 x 1 x 4.65 x 3.20 x - = 14.88 Sqm
S27 1 x 1 x 2.31 x 1.62 x - = 3.73 Sqm
S28 1 x 1 x 2.73 x 1.12 x - = 3.06 Sqm
S29 1 x 1 x 2.78 x 1.12 x - = 3.11 Sqm
S30 1 x 1 x 2.31 x 1.63 x - = 3.76 Sqm
S31 1 x 1 x 2.31 x 1.62 x - = 3.73 Sqm
S32 1 x 1 x 2.80 x 1.09 x - = 3.05 Sqm
S33 1 x 1 x 2.80 x 1.09 x - = 3.05 Sqm
S34 1 x 1 x 2.31 x 1.62 x - = 3.73 Sqm
S35 1 x 1 x 2.75 x 0.98 x - = 2.70 Sqm
S36 1 x 1 x 2.78 x 0.97 x - = 2.70 Sqm
S37 1 x 1 x 2.80 x 0.96 x - = 2.68 Sqm
S38 1 x 1 x 2.80 x 0.96 x - = 2.68 Sqm
S39 1 x 1 x 5.91 x 5.89 x - = 34.81 Sqm
Slab Projection Bottom of Beam
C46-C47-C48 1 x 1 x 7.45 x 1.20 x - = 8.94 Sqm
C48-C49-C50 1 x 1 x 6.79 x 1.20 x - = 8.15 Sqm
C9-C10 1 x 1 x 4.55 x 0.98 x - = 4.46 Sqm
C10-C11-C12 1 x 1 x 7.48 x 0.98 x - = 7.33 Sqm

Total Quantity = 307.55 Sqm


C/O TCMB -
Sign by Contractor Checked by JE Checked by AE

Page no- 15
Agreement No. 3.2.8 : Edges of slabs and breaks in floors and wallsfor
3.2.8.1 : Under 20 cm wide
Particular Nos x Nos x L x B x H = Quantity Unit
Slab edge shuttering L.H.S 1st Floor Slab
Chajja Portion
C46-C47-C48 1 x 1 x 7.45 x - x - = 7.45 mtr
1 x 2 x 1.20 x - x - = 2.40 mtr
C48-C49-C50 1 x 1 x 6.79 x - x - = 6.79 mtr
1 x 2 x 1.20 x - x - = 2.40 mtr
C9-C10 1 x 1 x 4.55 x - x - = 4.55 mtr
1 x 2 x 0.98 x - x - = 1.96 mtr
C10-C11-C12 1 x 1 x 7.48 x - x - = 7.48 mtr
1 x 2 x 0.98 x - x - = 1.96 mtr

Total Quantity = 34.99 mtr


C/O TCMB -
Date of Measurement

Extra for additional height in centering, shuttering where ever required with adequate
bracing, propping etc., including cost of de-shuttering and decentering at all levels, over a
E/S-3 : height of 3.5 m, for every additional height of 1 metre or part thereof (Plan area to be
measured).Suspended floors, roofs, landing, beams and balconies (Plan area to be
measured)
Particular Nos x Nos x L x B x H = Quantity Unit
ASOS mess R/H side 2nd floor slab
Entrance lobby
For height from 3.5 mt upto 4.5 mt=4.50-3.50=1.00=1 times
Bottom of slab 1 X 1 X 5.700 X 5.220 X - = 29.75 Sqm
For height from 3.5 mt upto 5.5 mt=5.50-3.50=2.00=2 times
Bottom of slab 1 X 2 X 5.700 X 5.220 X - = 59.51 Sqm
For height from 3.5 mt upto 6.45 mt=6.45-3.50=2.95=3 times
Bottom of slab 1 X 3 X 5.700 X 5.220 X - = 89.26 Sqm
Total Quantity = 178.52 Sqm
C/O TCMB -

Sign by Contractor Checked by JE Checked by AE


Page no- 16
Date of Measurement
Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and Removal of form for
3.2.5 : Lintels, beams, plinth beams, girders, bressuments and cantilvers
Particular Nos x Nos x L x B x H = Quantity Unit
Beam Shuttering of 2nd Floor slab R.H.S
SB-02 (C8-C9)
Side 1 X 1 X 2.390 X - X 0.500 = 1.20 Sqm
1 X 1 X 2.390 X - X 0.350 = 0.84 Sqm
Bottom 1 X 1 X 2.390 X 0.230 X - = 0.55 Sqm
SB-02 (C9-C10)
Side 1 X 1 X 4.590 X - X 0.500 = 2.30 Sqm
1 X 1 X 4.590 X - X 0.350 = 1.61 Sqm
Bottom 1 X 1 X 4.590 X 0.230 X - = 1.06 Sqm
SB-02 (C10-C11)
Side 1 X 1 X 4.560 X - X 0.500 = 2.28 Sqm
1 X 1 X 4.560 X - X 0.350 = 1.60 Sqm
Bottom 1 X 1 X 4.560 X 0.230 X - = 1.05 Sqm
SB-02 (C11-C12)
Side 1 X 1 X 4.500 X - X 0.500 = 2.25 Sqm
1 X 1 X 4.500 X - X 0.350 = 1.58 Sqm
Bottom 1 X 1 X 4.500 X 0.230 X - = 1.04 Sqm
SB-03 (C13-C14)
Side 1 X 1 X 1.690 X - X 0.500 = 0.85 Sqm
1 X 1 X 1.690 X - X 0.350 = 0.59 Sqm
Bottom 1 X 1 X 1.690 X 0.230 X - = 0.39 Sqm
SB-04 (C8-C9)
Side 1 X 1 X 2.600 X - X 0.500 = 1.30 Sqm
1 X 1 X 2.600 X - X 0.350 = 0.91 Sqm
Bottom 1 X 1 X 2.600 X 0.230 X - = 0.60 Sqm
SB-05 (C8-C9)
Side 1 X 1 X 2.600 X - X 0.500 = 1.30 Sqm
1 X 1 X 2.600 X - X 0.350 = 0.91 Sqm
Bottom 1 X 1 X 2.600 X 0.230 X - = 0.60 Sqm
SB-07 (C7-C8)
Side 1 X 2 X 3.070 X - X 0.300 = 1.84 Sqm
Bottom 1 X 1 X 3.070 X 0.250 X - = 0.77 Sqm
SB-08 (C12-C13)
Side 1 X 2 X 2.530 X - X 0.300 = 1.52 Sqm
Bottom 1 X 1 X 2.530 X 0.250 X - = 0.63 Sqm
SB-10 (C21-C22)
Side 1 X 2 X 5.700 X - X 0.350 = 3.99 Sqm
Bottom 1 X 1 X 5.700 X 0.230 X - = 1.31 Sqm
SB-10 (C22-C23)
Side 1 X 2 X 4.580 X - X 0.350 = 3.21 Sqm
Bottom 1 X 1 X 4.580 X 0.230 X - = 1.05 Sqm
SB-10 (C23-C24)
Side 1 X 2 X 4.550 X - X 0.350 = 3.19 Sqm
Bottom 1 X 1 X 4.550 X 0.230 X - = 1.05 Sqm
B/F = 43.37 Sqm

Sign by Contractor Checked by JE Checked by AE

Page no- 17
Particular Nos x Nos x L x B x H = Quantity Unit
SB-10 (C24-C25) C/O = 43.37 Sqm
Side 1 X 2 X 4.500 X - X 0.350 = 3.15 Sqm
Bottom 1 X 1 X 4.580 X 0.230 X - = 1.05 Sqm
SB-10 (C25-C26)
Side 1 X 2 X 4.550 X - X 0.350 = 3.19 Sqm
Bottom 1 X 1 X 4.550 X 0.230 X - = 1.05 Sqm
SB-12 (C33-C34)
Side 1 X 2 X 5.700 X - X 0.350 = 3.99 Sqm
Bottom 1 X 1 X 5.700 X 0.230 X - = 1.31 Sqm
SB-12 (C34-C35)
Side 1 X 2 X 4.580 X - X 0.350 = 3.21 Sqm
Bottom 1 X 1 X 4.580 X 0.230 X - = 1.05 Sqm
SB-12 (C35-C36)
Side 1 X 2 X 4.550 X - X 0.350 = 3.19 Sqm
Bottom 1 X 1 X 4.550 X 0.230 X - = 1.05 Sqm
SB-12 (C36-C37)
Side 1 X 2 X 4.500 X - X 0.350 = 3.15 Sqm
Bottom 1 X 1 X 4.580 X 0.230 X - = 1.05 Sqm
SB-12 (C37-C38)
Side 1 X 2 X 4.550 X - X 0.350 = 3.19 Sqm
Bottom 1 X 1 X 4.550 X 0.230 X - = 1.05 Sqm
SB-14 (C45-C46)
Side 1 X 2 X 5.700 X - X 0.500 = 5.70 Sqm
Bottom 1 X 1 X 5.700 X 0.230 X - = 1.31 Sqm
SB-14 (C46-C47)
Side 1 X 1 X 4.580 X - X 0.500 = 2.29 Sqm
1 X 1 X 4.580 X - X 0.350 = 1.60 Sqm
Bottom 1 X 1 X 4.580 X 0.230 X - = 1.05 Sqm
SB-14 (C47-C48)
Side 1 X 1 X 4.550 X - 0.500 = 2.28 Sqm
1 X 1 X 4.550 X - 0.350 = 1.59 Sqm
Bottom 1 X 1 X 4.550 X 0.230 - = 1.05 Sqm
SB-14 (C48-C49)
Side 1 X 1 X 4.500 X - 0.500 = 2.25 Sqm
1 X 1 X 4.500 X - 0.350 = 1.58 Sqm
Bottom 1 X 1 X 4.580 X 0.230 - = 1.05 Sqm
SB-14 (C49-C50)
Side 1 X 1 X 4.550 X - 0.500 = 2.28 Sqm
1 X 1 X 4.550 X - 0.350 = 1.59 Sqm
Bottom 1 X 1 X 4.550 X 0.230 X - = 1.05 Sqm
SB-30 (C9-SB31) (SB31-C11) (C11-SB31) (SB31-C47)(C47-SB31)(SB31-C49)(C49-SB31)
Side 7 X 2 X 2.800 X - 0.350 = 13.72 Sqm
Bottom 7 X 1 X 2.800 X 0.230 X - = 4.51 Sqm
B/F = 118.95 Sqm

Sign by Contractor Checked by JE Checked by AE


Page no- 18
Particular Nos x Nos x L x B x H = Quantity Unit
C/O = 118.95 Sqm
SB-31(SB02- SB33)
Side 3 X 2 X 2.500 X - 0.350 = 5.25 Sqm
Bottom 3 X 1 X 2.500 X 0.230 X - = 1.73 Sqm
SB-31(SB35- SB14)
Side 4 X 2 X 2.500 X - 0.350 = 7.00 Sqm
Bottom 4 X 1 X 2.500 X 0.230 X - = 2.30 Sqm
SB-33 (C9-C10)
Side 1 X 2 X 4.620 X - 0.350 = 3.23 Sqm
Bottom 1 X 1 X 4..62 X 0.230 - = 0.23 Sqm
SB-33 (C10-C11)
Side 1 X 2 X 4.620 X - 0.350 = 3.23 Sqm
Bottom 1 X 1 X 4.620 X 0.230 - = 1.06 Sqm
SB-33 (C11-C12)
Side 1 X 2 X 4.680 X - 0.350 = 3.28 Sqm
Bottom 1 X 1 X 4.680 X 0.230 X - = 1.08 Sqm
SB-35 (C46-C47)
Side 1 X 2 X 4.620 X - 0.350 = 3.23 Sqm
Bottom 1 X 1 X 4..62 X 0.230 - = 0.23 Sqm
SB-35 (C47-C48)
Side 1 X 2 X 4.620 X - 0.350 = 3.23 Sqm
Bottom 1 X 1 X 4.620 X 0.230 - = 1.06 Sqm
SB-35 (C48-C49)
Side 1 X 2 X 4.680 X - 0.350 = 3.28 Sqm
Bottom 1 X 1 X 4.680 X 0.230 X - = 1.08 Sqm
SB-35 (C49-C50)
Side 1 X 2 X 4.670 X - 0.350 = 3.27 Sqm
Bottom 1 X 1 X 4.670 X 0.230 X - = 1.07 Sqm
SB-21 (C7-C21)
Side 1 X 2 X 5.440 X - 0.500 = 5.44 Sqm
Bottom 1 X 1 X 5.440 X 0.230 - = 1.25 Sqm
SB-21 (C21-C33)
Side 1 X 1 X 1.800 X - 0.500 = 0.90 Sqm
1 X 1 X 1.800 X - 0.350 = 0.63 Sqm
Bottom 1 X 1 X 1.800 X 0.230 - = 0.41 Sqm
SB-21 (C33-C45)
Side 1 X 2 X 5.220 X - 0.500 = 5.22 Sqm
Bottom 1 X 1 X 5.220 X 0.230 X - = 1.20 Sqm
SB-22 (SB12-SB14)
Side 1 X 2 X 5.760 X - 0.350 = 4.03 Sqm
Bottom 1 X 1 X 5.760 X 0.230 X - = 1.32 Sqm
SB-23(FB 10-C8)
Side 1 X 2 X 6.250 X - 0.500 = 6.25 Sqm
Bottom 1 X 1 X 6.250 X 0.230 X - = 1.44 Sqm
B/F = 191.88 Sqm
Sign by Contractor Checked by JE Checked by AE

Page no- 19
Particular Nos x Nos x L x B x H = Quantity Unit
C/O = 191.88 Sqm
SB-24 (C9-C22)
Side 1 X 2 X 5.440 X - 0.500 = 5.44 Sqm
Bottom 1 X 1 X 5.440 X 0.230 - = 1.25 Sqm
SB-24 (C22-C34)
Side 1 X 1 X 1.800 X - 0.500 = 0.90 Sqm
1 X 1 X 1.800 X - 0.350 = 0.63 Sqm
Bottom 1 X 1 X 1.800 X 0.230 - = 0.41 Sqm
SB-24 (C34-C46)
Side 1 X 2 X 5.220 X - 0.500 = 5.22 Sqm
Bottom 1 X 1 X 5.220 X 0.230 X - = 1.20 Sqm
SB-25 (C10-C23)
Side 1 X 2 X 5.440 X - 0.350 = 3.81 Sqm
Bottom 1 X 1 X 5.440 X 0.230 - = 1.25 Sqm
SB-25 (C23-C35)
Side 1 X 2 X 1.800 X - 0.350 = 1.26 Sqm
Bottom 1 X 1 X 1.800 X 0.230 - = 0.41 Sqm
SB-25 (C35-C47)
Side 1 X 2 X 5.220 X - 0.350 = 3.65 Sqm
Bottom 1 X 1 X 5.220 X 0.230 X - = 1.20 Sqm
SB-26 (C11-C24)
Side 1 X 2 X 5.440 X - 0.350 = 3.81 Sqm
Bottom 1 X 1 X 5.440 X 0.230 - = 1.25 Sqm
SB-26 (C24-C36)
Side 1 X 2 X 1.800 X - 0.350 = 1.26 Sqm
Bottom 1 X 1 X 1.800 X 0.230 - = 0.41 Sqm
SB-26 (C36-C48)
Side 1 X 2 X 5.220 X - 0.350 = 3.65 Sqm
Bottom 1 X 1 X 5.220 X 0.230 X - = 1.20 Sqm
SB-27 (C12-C25)
Side 1 X 1 X 5.440 X - 0.500 = 2.72 Sqm
1 X 1 X 5.440 X - 0.350 = 1.90 Sqm
Bottom 1 X 1 X 5.440 X 0.230 - = 1.25 Sqm
SB-27 (C25-C37)
Side 1 X 2 X 1.800 X - 0.350 = 1.26 Sqm
Bottom 1 X 1 X 1.800 X 0.230 - = 0.41 Sqm
SB-27 (C37-C49)
Side 1 X 2 X 5.220 X - 0.350 = 3.65 Sqm
Bottom 1 X 1 X 5.220 X 0.230 X - = 1.20 Sqm
SB-29 (C14-C26)
Side 1 X 1 X 5.440 X - 0.500 = 2.72 Sqm
1 X 1 X 5.440 X - 0.350 = 1.90 Sqm
Bottom 1 X 1 X 5.440 X 0.230 - = 1.25 Sqm
SB-29 (C26-C38)
Side 1 X 1 X 1.800 X - 0.500 = 0.90 Sqm
1 X 1 X 1.800 X - 0.350 = 0.63 Sqm
Bottom 1 X 1 X 1.800 X 0.230 - = 0.41 Sqm
SB-29 (C38-C50)
Side 1 X 1 X 5.220 X - 0.500 = 2.61 Sqm
1 X 1 X 5.220 X - 0.350 = 1.83 Sqm
Bottom 1 X 1 X 5.220 X 0.230 X - = 1.20 Sqm
Total Quantity = 255.93 Sqm
C/O TCMB -
Sign by Contractor Checked by JE Checked by AE

Page no- 20
Date of Measurement
Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and Removal of form for
3.2.7 : Stairs, (eexcluding landings) except spiral-staircases
Particular Nos x Nos x L x B x H = Quantity Unit
C7-C8 Staircase
Waist Slab 1 X 1 X 3.35 X - X 1.500 = 5.03 Sqm
Side 1 X 2 X 3.35 X - X 0.300 = 2.01 Sqm
Riser 11 X 1 X 1.50 X - X 0.150 = 2.48 Sqm
C12-C13 Staircase
Waist Slab 1 X 1 X 3.35 X - X 1.200 = 4.02 Sqm
Side 1 X 2 X 3.35 X - X 0.300 = 2.01 Sqm
Riser 11 X 1 X 1.20 X - X 0.150 = 1.98 Sqm
Total Quantity = 17.53 Sqm
C/O TCMB -

Date of Measurement
Providing and laying in position machine batched and machine mixed design mix M-25
grade cement concrete for reinforcd cement concrete work , using coarse aggregate as well
as fine aggregate derived from natural source and cement cocrete as per approved design
mix , including pimping of con crete to site laying but excluding the cost of centering ,
Agreement No. 3.6 : shuttering,finishing and reinforecd , including admixture in recommended proportion as per
IS: 9103 to accelerated, retard setting of concrete , improve workability without impairing
strength and durability as per direction of Engineer-in-Charge.

3.6.2 : All works above plinth level upto floor V level


Particular Nos x Nos x L x B x H = Quantity Unit
2nd floor R.H.S slab R.C.C
S1 1 x 1 x 2.57 x 1.85 x 0.15 = 0.71 Cum
S2 1 x 1 x 2.77 x 1.19 x 0.15 = 0.49 Cum
S3 1 x 1 x 1.62 x 2.51 x 0.15 = 0.61 Cum
S4 1 x 1 x 2.50 x 1.63 x 0.15 = 0.61 Cum
S5 1 x 1 x 1.19 x 2.79 x 0.15 = 0.50 Cum
S6 1 x 1 x 2.80 x 1.21 x 0.15 = 0.51 Cum
S7 1 x 1 x 1.63 x 2.47 x 0.15 = 0.60 Cum
S8 1 x 1 x 5.91 x 1.86 x 0.15 = 1.65 Cum
S9 1 x 1 x 2.77 x 1.09 x 0.15 = 0.45 Cum
S10 1 x 1 x 2.79 x 1.07 x 0.15 = 0.45 Cum
S11 1 x 1 x 2.80 x 1.08 x 0.15 = 0.45 Cum
S12 1 x 1 x 3.07 x 1.15 x 0.15 = 0.53 Cum
S13 1 x 1 x 2.57 x 1.78 x 0.15 = 0.69 Cum
S14 1 x 1 x 4.61 x 3.19 x 0.15 = 2.21 Cum
S15 1 x 1 x 4.61 x 3.19 x 0.15 = 2.21 Cum
S16 1 x 1 x 4.65 x 3.19 x 0.15 = 2.23 Cum
S17 1 x 1 x 2.52 x 1.40 x 0.15 = 0.53 Cum
S18 1 x 1 x 5.91 x 1.80 x 0.15 = 1.59 Cum
S19 1 x 1 x 4.61 x 1.80 x 0.15 = 1.24 Cum
S20 1 x 1 x 4.64 x 1.80 x 0.15 = 1.25 Cum
S21 1 x 1 x 4.63 x 1.80 x 0.15 = 1.25 Cum
S22 1 x 1 x 4.65 x 1.80 x 0.15 = 1.25 Cum
S23 1 x 1 x 4.59 x 3.20 x 0.15 = 2.20 Cum
B/F = 24.21 Cum
Sign by Contractor Checked by JE Checked by AE

Page no- 21
Particular Nos x Nos x L x B x H = Quantity Unit
C/O = 24.21 Cum
S24 1 x 1 x 4.64 x 3.20 x 0.15 = 2.22 Cum
S25 1 x 1 x 4.65 x 3.20 x 0.15 = 2.23 Cum
S26 1 x 1 x 4.65 x 3.20 x 0.15 = 2.23 Cum
S27 1 x 1 x 2.31 x 1.62 x 0.15 = 0.56 Cum
S28 1 x 1 x 2.73 x 1.12 x 0.15 = 0.46 Cum
S29 1 x 1 x 2.78 x 1.12 x 0.15 = 0.47 Cum
S30 1 x 1 x 2.31 x 1.63 x 0.15 = 0.56 Cum
S31 1 x 1 x 2.31 x 1.62 x 0.15 = 0.56 Cum
S32 1 x 1 x 2.80 x 1.09 x 0.15 = 0.46 Cum
S33 1 x 1 x 2.80 x 1.09 x 0.15 = 0.46 Cum
S34 1 x 1 x 2.31 x 1.62 x 0.15 = 0.56 Cum
S35 1 x 1 x 2.75 x 0.98 x 0.15 = 0.40 Cum
S36 1 x 1 x 2.78 x 0.97 x 0.15 = 0.40 Cum
S37 1 x 1 x 2.80 x 0.96 x 0.15 = 0.40 Cum
S38 1 x 1 x 2.80 x 0.96 x 0.15 = 0.40 Cum
S39 1 x 1 x 5.91 x 5.89 x 0.15 = 5.22 Cum
Slab Projection Bottom of Beam
C46-C47-C48 1 x 1 x 7.45 x 1.20 x 0.10 = 0.89 Cum
C48-C49-C50 1 x 1 x 6.79 x 1.20 x 0.10 = 0.81 Cum
C9-C10 1 x 1 x 4.55 x 0.98 x 0.10 = 0.45 Cum
C10-C11-C12 1 x 1 x 7.48 x 0.98 x 0.10 = 0.73 Cum
Beam R.C.C of 1st Floor slab R.H.S
SB-02 (C8-C9) 1 X 1 X 2.390 X 0.230 X 0.500 = 0.27 Cum
SB-02 (C9-C10) 1 X 1 X 4.590 X 0.230 X 0.500 = 0.53 Cum
SB-02 (C10-C11) 1 X 1 X 4.560 X 0.230 X 0.500 = 0.52 Cum
SB-02 (C11-C12) 1 X 1 X 4.500 X 0.230 X 0.500 = 0.52 Cum
SB-03 (C13-C14) 1 X 1 X 1.690 X 0.230 X 0.500 = 0.19 Cum
SB-04 (C8-C9) 1 X 1 X 2.600 X 0.230 X 0.500 = 0.30 Cum
SB-05 (C8-C9) 1 X 1 X 2.600 X 0.230 X 0.500 = 0.30 Cum
SB-07 (C7-C8) 1 X 1 X 3.070 X 0.230 X 0.500 = 0.35 Cum
SB-08 (C12-C13) 1 X 1 X 2.530 X 0.230 X 0.500 = 0.29 Cum
SB-10 (C21-C22) 1 X 1 X 5.700 X 0.230 X 0.500 = 0.66 Cum
SB-10 (C22-C23) 1 X 1 X 4.580 X 0.230 X 0.500 = 0.53 Cum
SB-10 (C23-C24) 1 X 1 X 4.550 X 0.230 X 0.500 = 0.52 Cum
SB-10 (C24-C25) 1 X 1 X 4.500 X 0.230 X 0.500 = 0.52 Cum
SB-10 (C25-C26) 1 X 1 X 4.550 X 0.230 X 0.500 = 0.52 Cum
SB-12 (C33-C34) 1 X 1 X 5.700 X 0.230 X 0.500 = 0.66 Cum
SB-12 (C34-C35) 1 X 1 X 4.580 X 0.230 X 0.500 = 0.53 Cum
SB-12 (C35-C36) 1 X 1 X 4.550 X 0.230 X 0.500 = 0.52 Cum
SB-12 (C36-C37) 1 X 1 X 4.500 X 0.230 X 0.500 = 0.52 Cum
SB-12 (C37-C38) 1 X 1 X 4.550 X 0.230 X 0.500 = 0.52 Cum
SB-14 (C45-C46) 1 X 1 X 5.700 X 0.230 X 0.500 = 0.66 Cum
SB-14 (C46-C47) 1 X 1 X 4.580 X 0.230 X 0.500 = 0.53 Cum
SB-14 (C47-C48) 1 X 1 X 4.550 X 0.230 X 0.500 = 0.52 Cum
SB-14 (C48-C49) 1 X 1 X 4.500 X 0.230 X 0.500 = 0.52 Cum
SB-14 (C49-C50) 1 X 1 X 4.550 X 0.230 X 0.500 = 0.52 Cum
SB-21 (C7-C21) 1 X 1 X 5.440 X 0.230 X 0.500 = 0.63 Cum
SB-21 (C21-C33) 1 X 1 X 1.800 X 0.230 X 0.500 = 0.21 Cum
SB-21 (C33-C45) 1 X 1 X 5.220 X 0.230 X 0.500 = 0.60 Cum
SB-22 (SB12-SB14) 1 X 1 X 5.890 X 0.230 X 0.500 = 0.68 Cum
SB-23(FB 10-C8) 1 X 1 X 6.250 X 0.230 X 0.500 = 0.72 Cum
SB-24 (C9-C22) 1 X 1 X 5.440 X 0.230 X 0.500 = 0.63 Cum
SB-24 (C22-C34) 1 X 1 X 1.800 X 0.230 X 0.500 = 0.21 Cum
B/F = 59.88 Cum

Sign by Contractor Checked by JE Checked by AE

Page no- 22
Particular Nos x Nos x L x B x H = Quantity Unit
C/O = 59.88 Cum
SB-24 (C34-C46) 1 X 1 X 5.220 X 0.230 X 0.500 = 0.60 Cum
SB-25 (C10-C23) 1 X 1 X 5.440 X 0.230 X 0.500 = 0.63 Cum
SB-25 (C23-C35) 1 X 1 X 1.800 X 0.230 X 0.500 = 0.21 Cum
SB-25 (C35-C47) 1 X 1 X 5.220 X 0.230 X 0.500 = 0.60 Cum
SB-26 (C11-C24) 1 X 1 X 5.440 X 0.230 X 0.500 = 0.63 Cum
SB-26 (C24-C36) 1 X 1 X 1.800 X 0.230 X 0.500 = 0.21 Cum
SB-26 (C36-C48) 1 X 1 X 5.220 X 0.230 X 0.500 = 0.60 Cum
SB-27 (C12-C25) 1 X 1 X 5.440 X 0.230 X 0.500 = 0.63 Cum
SB-27 (C25-C37) 1 X 1 X 1.800 X 0.230 X 0.500 = 0.21 Cum
SB-27 (C37-C49) 1 X 1 X 5.220 X 0.230 X 0.500 = 0.60 Cum
SB-29 (C14-C26) 1 X 1 X 5.440 X 0.230 X 0.500 = 0.63 Cum
SB-29 (C26-C38) 1 X 1 X 1.800 X 0.230 X 0.500 = 0.21 Cum
SB-29 (C38-C50) 1 X 1 X 5.220 X 0.230 X 0.500 = 0.60 Cum
SB-30 (C9-SB31) (SB31-C11) (C11-SB31) (SB31-C47)(C47-SB31)(SB31-C49)(C49-SB31)
7 X 1 X 2.800 X 0.230 X 0.500 = 2.25 Cum
SB-31(FB02- FB33) 3 X 1 X 2.500 X 0.230 X 0.500 = 0.86 Cum
SB-31(FB35- FB14) 4 X 1 X 2.500 X 0.230 X 0.500 = 1.15 Cum
SB-33 (C9-C10) 1 X 1 X 4.620 X 0.230 X 0.500 = 0.53 Cum
SB-33 (C10-C11) 1 X 1 X 4.620 X 0.230 X 0.500 = 0.53 Cum
SB-33 (C11-C12) 1 X 1 X 4.680 X 0.230 X 0.500 = 0.54 Cum
SB-35 (C46-C47) 1 X 1 X 4.620 X 0.230 X 0.500 = 0.53 Cum
SB-35 (C47-C48) 1 X 1 X 4.620 X 0.230 X 0.500 = 0.53 Cum
SB-35 (C48-C49) 1 X 1 X 4.680 X 0.230 X 0.500 = 0.54 Cum
SB-35 (C49-C50) 1 X 1 X 4.670 X 0.230 X 0.500 = 0.54 Cum
StairCase RCC 4th Flight
C7-C8
Waist Slab 1 X 1 X 3.35 X 1.500 X 0.150 = 0.75 cum
Tread & Riser 10 X 0.5 X 1.50 X 0.300 X 0.150 = 0.34 Cum
C12-C13
Waist Slab 1 X 1 X 3.35 X 1.200 X 0.150 = 0.60 cum
Tread & Riser 10 X 0.5 X 1.20 X 0.300 X 0.150 = 0.27 Cum
Total Quantity = 76.20 Cum
C/O TCMB -
Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and Removal of form for
3.2.6 : Column, Pillars, piers, Abustments, posts and struts
Particular Nos x Nos x L x B x H = Quantity Unit
ASOS Mess L/H Side Column R.C.C From 3rd floor upto roof slab 2.40 MT ht
C4 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C5 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C6 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C18 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C19 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C20 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C30 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C31 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C32 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C42 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C43 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C44 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
Total Quantity = 48.96 Sqm
C/O TCMB -

Sign by Contractor Checked by JE Checked by AE

Page no- 23
Date of Measurement
Providing and laying in position machine batched and machine mixed design mix M-25
grade cement concrete for reinforcd cement concrete work , using coarse aggregate as well
as fine aggregate derived from natural source and cement cocrete as per approved design
mix , including pimping of con crete to site laying but excluding the cost of centering ,
Agreement No. 3.6 : shuttering,finishing and reinforecd , including admixture in recommended proportion as per
IS: 9103 to accelerated, retard setting of concrete , improve workability without impairing
strength and durability as per direction of Engineer-in-Charge.

3.6.2 : All works above plinth level upto floor V level


Particular Nos x Nos x L x B x H = Quantity Unit

ASOS Mess L/H Side Column R.C.C From 3rd floor upto roof slab 2.4mt ht
C4 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C5 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C6 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C18 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C19 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C20 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C30 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C31 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C32 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C42 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C43 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C44 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
Total Quantity = 5.04 Cum

C/O TCMB -

Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and Removal of form for
3.2.6 : Column, Pillars, piers, Abustments, posts and struts
Particular Nos x Nos x L x B x H = Quantity Unit
ASOS Mess L/H Side Column R.C.C From 2.4 mt height upto Roof slab
C4 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C5 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C6 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C18 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C19 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C20 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C30 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C31 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C32 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C42 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C43 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
C44 1 x 2 x( 0.35 + 0.50 )x 0.75 = 1.28 sqm
Porch front round column from 2.4 mt upto 3.90mt
C51 1 x 2 x 3.14 x 0.15 x 1.50 = 9.87 sqm
C52 1 x 2 x 3.14 x 0.15 x 1.50 = 9.87 sqm

Total Quantity = 35.10 Sqm


C/O TCMB -
Sign by Contractor Checked by JE Checked by AE

Page no- 24

Date of Measurement
Providing and laying in position machine batched and machine mixed design mix M-25
grade cement concrete for reinforcd cement concrete work , using coarse aggregate as well
as fine aggregate derived from natural source and cement cocrete as per approved design
mix , including pimping of con crete to site laying but excluding the cost of centering ,
Agreement No. 3.6 : shuttering,finishing and reinforecd , including admixture in recommended proportion as per
IS: 9103 to accelerated, retard setting of concrete , improve workability without impairing
strength and durability as per direction of Engineer-in-Charge.

3.6.2 : All works above plinth level upto floor V level


Particular Nos x Nos x L x B x H = Quantity Unit

ASOS Mess L/H Side Column R.C.C From 2.4 mt height upto Roof slab
C4 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C5 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C6 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C18 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C19 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C20 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C30 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C31 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C32 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C42 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C43 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
C44 1 x 1 x 0.35 x 0.50 x 0.90 = 0.16 Cum
Porch front round column 2.4 mt to 3.90mt
C51 1 x 3.14 x 0.15 x 0.15 x 1.50 = 0.11 Cum
C52 1 x 3.14 x 0.15 x 0.15 x 1.50 = 0.11 Cum
Total Quantity = 2.14 Cum

C/O TCMB -
Sign by Contractor Checked by JE Checked by AE

Page no- 25
Date of Measurement:
Item No:- 3.4 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position
and binding all complete above plinth level.
Item No:- 3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more.
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
Reinforcement of L/H Side Roof slab Beam Re-inforcement
Long Direction
RB-01 (C4-C5-C6) (230 X 500)
Top Main Bar 16 mm 1 x 2 x 11.00 = --- --- --- 22.00 --- ---
Bottom Main Bar 16 mm 1 x 2 x 11.00 = --- --- --- 22.00 --- ---
Top Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Bottom Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Stirrup
(C4-C5) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
(C5-C6) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
RB-06 (C18-C19-C20 ) (230 X 500)
Top Main Bar 16 mm 1 x 2 x 11.00 = --- --- --- 22.00 --- ---
Bottom Main Bar 16 mm 1 x 2 x 11.00 = --- --- --- 22.00 --- ---
Top Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Bottom Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Stirrup
(C18-C19) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
(C19-C20) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
RB-08 (C30-C31-C32 ) (230 X 500)
Top Main Bar 16 mm 1 x 2 x 11.00 = --- --- --- 22.00 --- ---
Bottom Main Bar 16 mm 1 x 2 x 11.00 = --- --- --- 22.00 --- ---
Top Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Bottom Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Stirrup
(C30-C31) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
(C31-C32) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
RB-10 (C42-C43-C44 ) (230 X 500)
Top Main Bar 16 mm 1 x 2 x 11.00 = --- --- --- 22.00 --- ---
Bottom Main Bar 16 mm 1 x 2 x 11.00 = --- --- --- 22.00 --- ---
Top Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Bottom Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Stirrup
(C42-C43) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
(C43-C44) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 17 x 1.38 = 23.46 --- --- --- --- ---
RB-32 (RB-12 TO RB-14 (230 X 500)
Top Main Bar 12 mm 1 x 3 x 10.80 = --- --- 32.40 --- --- ---
Bottom Main Bar 12 mm 1 x 3 x 10.80 = --- --- 32.40 --- --- ---
Top Lap 12 mm 1 x 3 x 0.60 = --- --- 1.80 --- --- ---
Bottom Lap 12 mm 1 x 3 x 0.60 = --- --- 1.80 --- --- ---
Stirrup
(C4-C5) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 18 x 1.38 = 24.84 --- --- --- --- ---
(C5-C6) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 18 x 1.38 = 24.84 --- --- --- --- ---
B/F = 237.36 284.00 68.40 188.80 0.00 0.00

Sign by Contractor Checked by JE Checked by AE

Page no- 26
Steel (TMT Bars)
Particulars Dia No. Length
Page13-10
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 237.36 284.00 68.40 188.80 0.00 0.00
RB-34 (RB-12 TO RB-14) (230 X 500)
Top Main Bar 12 mm 1 x 3 x 10.80 = --- --- 32.40 --- --- ---
Bottom Main Bar 12 mm 1 x 3 x 10.80 = --- --- 32.40 --- --- ---
Top Lap 12 mm 1 x 3 x 0.60 = --- --- 1.80 --- --- ---
Bottom Lap 12 mm 1 x 3 x 0.60 = --- --- 1.80 --- --- ---
Stirrup
(C42-C43) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 18 x 1.38 = 24.84 --- --- --- --- ---
(C43-C44) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 18 x 1.38 = 24.84 --- --- --- --- ---
RB-30 (C4-RB31) (230 X 500)
Top Main Bar 12 mm 1 x 3 x 4.00 = --- --- 12.00 --- --- ---
Bottom Main Bar 12 mm 1 x 3 x 4.00 = --- --- 12.00 --- --- ---
Stirrup
10 mm 1 x 17 x 1.42 = --- 24.14 --- --- --- ---
8 mm 1 x 8 x 1.38 = 11.04 --- --- --- --- ---
RB-30 (C6-RB31) (230 X 500)
Top Main Bar 12 mm 1 x 3 x 3.90 = --- --- 11.70 --- --- ---
Bottom Main Bar 12 mm 1 x 3 x 3.90 = --- --- 11.70 --- --- ---
Stirrup
10 mm 1 x 16 x 1.42 = --- 22.72 --- --- --- ---
8 mm 1 x 8 x 1.38 = 11.04 --- --- --- --- ---
RB-30 (RB31-C43-RB31) (230 X 500)
Top Main Bar 12 mm 1 x 3 x 7.00 = --- --- 21.00 --- --- ---
Bottom Main Bar 12 mm 1 x 3 x 7.00 = --- --- 21.00 --- --- ---
Lap 12 mm 1 x 3 x 0.60 = --- --- 1.80 --- --- ---
Stirrup
10 mm 1 x 32 x 1.42 = --- 45.44 --- --- --- ---
8 mm 1 x 18 x 1.38 = 24.84 --- --- --- --- ---
RB-31 (230 X 500)=4 NOS
Top Main Bar 12 mm 4 x 3 x 3.55 = --- --- 42.60 --- --- ---
Bottom Main Bar 12 mm 4 x 3 x 3.55 = --- --- 42.60 --- --- ---
Stirrup
10 mm 4 x 16 x 1.42 = --- 90.88 --- --- --- ---
8 mm 4 x 6 x 1.38 = 33.12 --- --- --- --- ---
RB-12 (C42-C30-C18-C4 ) (230 X 500)
Top Main Bar 16 mm 1 x 2 x 15.30 = --- --- --- 30.60 --- ---
Bottom Main Bar 16 mm 1 x 2 x 15.30 = --- --- --- 30.60 --- ---
Top Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Bottom Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Stirrup
(C42-C30) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 21 x 1.38 = 28.98 --- --- --- --- ---
(C30-C18) 10 mm 1 x 18 x 1.42 = --- 25.56 --- --- --- ---
(C18-C4) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 23 x 1.38 = 31.74 --- --- --- --- ---
RB-13 (C43-C31-C19-C5 ) (230 X 500)
Top Main Bar 16 mm 1 x 2 x 15.30 = --- --- --- 30.60 --- ---
Bottom Main Bar 16 mm 1 x 2 x 15.30 = --- --- --- 30.60 --- ---
Top Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Bottom Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Extra top at C43 12 mm 1 x 1 x 2.70 = --- --- 2.70 --- --- ---
Extra top at C31& C19 20 mm 1 x 2 x 2.50 = --- --- --- --- 5.00 ---
Extra top at C5 12 mm 1 x 1 x 2.70 = --- --- 2.70 --- --- ---
B/F = 427.80 606.34 318.60 317.60 5.00 0.00

Sign by Contractor Checked by JE Checked by AE

Page no- 27
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
Page14-10
C/O = 427.80 606.34 318.60 317.60 5.00 0.00
Stirrup
(C43-C31) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 21 x 1.38 = 28.98 --- --- --- --- ---
(C31-C19) 10 mm 1 x 18 x 1.42 = --- 25.56 --- --- --- ---
(C19-C5) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 23 x 1.38 = 31.74 --- --- --- --- ---
RB-14 (C44-C32-C20-C6) (230 X 500)
Top Main Bar 16 mm 1 x 2 x 15.30 = --- --- --- 30.60 --- ---
Bottom Main Bar 16 mm 1 x 2 x 15.30 = --- --- --- 30.60 --- ---
Top Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Bottom Lap 16 mm 1 x 2 x 0.80 = --- --- --- 1.60 --- ---
Extra top at C32& C20 12 mm 1 x 2 x 2.50 = --- --- 5.00 --- --- ---
Stirrup
(C44-C32) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 21 x 1.38 = 28.98 --- --- --- --- ---
(C32-C20) 10 mm 1 x 18 x 1.42 = --- 25.56 --- --- --- ---
(C20-C6) 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 23 x 1.38 = 31.74 --- --- --- --- ---

Total (In M) = 549.24 771.06 323.60 382.00 5.00 0.00


0.395 0.616 0.888 1.579 2.467 3.850
Total Weight (In KG) = 216.95 474.97 287.36 603.18 12.34 0.00

C/O TCMB / P - 1594.80 Kg

Sign by Contractor Checked by JE Checked by AE

Page no- 28
Date of Measurement:
Item No:- 3.4 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position
and binding all complete above plinth level.
Item No:- 3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more.
Steel (TMT Bars)
Particulars Dia No. Length
Page15-10
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
Measurement Of L/H Side Roof Slab Reinforcement
Long Direction
(C42-C44)to(C4-C6)
Bottom bar 10 mm 1 x 40 x 15.60 = --- 624.00 --- --- --- ---
Crank bar 10 mm 1 x 15 x 15.80 = --- 237.00 --- --- --- ---
Top bar 10 mm 1 x 27 x 15.60 = --- 421.20 --- --- --- ---
Extra top 10 mm 1 x 13 x 4.30 = --- 55.90 --- --- --- ---
At RB-6& RB-08 10 mm 1 x 13 x 4.00 = --- 52.00 --- --- --- ---
At RB-01& RB-32 10 mm 1 x 13 x 4.30 = --- 55.90 --- --- --- ---
Short direction
(C4-C42)to(C6-C44)
Bottom bar 10 mm 1 x 35 x 11.30 = --- 395.50 --- --- --- ---
10 mm 1 x 41 x 10.70 = --- 438.70 --- --- --- ---
Crank bar 10 mm 1 x 8 x 11.50 = --- 92.00 --- --- --- ---
Top bar 10 mm 1 x 24 x 11.30 = --- 271.20 --- --- --- ---
10 mm 1 x 36 x 10.70 = --- 385.20 --- --- --- ---
Extra top at RB-14 10 mm 1 x 5 x 2.00 = --- 10.00 --- --- --- ---
10 mm 1 x 5 x 1.40 = --- 7.00 --- --- --- ---
Extra top at RB-13 10 mm 1 x 5 x 2.52 = --- 12.60 --- --- --- ---
10 mm 1 x 5 x 2.52 = --- 12.60 --- --- --- ---
Extra top at RB-12 10 mm 1 x 5 x 1.90 = --- 9.50 --- --- --- ---
10 mm 1 x 5 x 1.90 = --- 9.50 --- --- --- ---
Front chajja
Top and bottom 10 mm 2 x 5 x 11.30 = --- 113.00 --- --- --- ---
L/H Side chajja
Top and bottom 10 mm 2 x 5 x 14.60 = --- 146.00 --- --- --- ---
Back Side chajja
Top and bottom 10 mm 2 x 5 x 10.50 = --- 105.00 --- --- --- ---
R/H Side chajja
Top and bottom 10 mm 2 x 5 x 6.60 = --- 66.00 --- --- --- ---
Lapping 10 mm 1 x 255 x 0.50 = --- 127.50 --- --- --- ---
Chair 10 mm 1 x 170 x 1.39 = --- 236.30 --- --- --- ---
False column vertical 12 mm 13 x 4 x 1.65 = --- --- 85.80 --- --- ---
False column ring 8 mm 13 x 2 x 0.52 = 13.52 --- --- --- --- ---
Total (In m) = 13.52 3883.60 85.80 0.00 0.00 0.00
0.395 0.616 0.888 1.579 2.467 3.850
Total Weight (In Kg) 5.34 2392.30 76.19 0.00 0.00 0.00
C/O TCMB / P - 2473.83 kg
Item No:- 3.4 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position
and binding all complete above plinth level.
Item No:- 3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more.
Measurement for Stirrup For Column and Beam Junction at Roof Slab of L/H side
C4 10 mm 1 x 4 x 1.78 = --- 7.12 --- --- --- ---
C5 10 mm 1 x 4 x 1.78 = --- 7.12 --- --- --- ---
C6 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C18 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C19 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C20 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C30 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C31 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C32 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C42 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C43 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
C44 10 mm 1 x 4 x 1.58 = --- 6.32 --- --- --- ---
Total (In m) = 0.00 77.44 0.00 0.00 0.00 0.00
0.395 0.616 0.888 1.579 2.467 3.850
Total Weight (In Kg) 0.00 47.70 0.00 0.00 0.00 0.00
C/O TCMB / P - 47.70 Kg

Sign by Contractor Checked by JE Checked by AE


Page no- 29

Item No:- 3.4 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position
and binding all complete above plinth level.
Item No:- 3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more.
Front porch area beam and projected slab reinforcement
L/H side beam

Page16-10
Top and bottom 16 mm 2 x 3 x 4.90 = --- --- --- 29.40 --- ---
Extra top 12 mm 1 x 1 x 1.20 = --- --- 1.20 --- --- ---
Stirups 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 15 x 1.38 = 20.70 --- --- --- --- ---
R/H side beam
Top and bottom 16 mm 2 x 3 x 4.90 = --- --- --- 29.40 --- ---
Extra top 20 mm 1 x 1 x 1.20 = --- --- --- --- 1.20 ---
Stirups 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 15 x 1.38 = 20.70 --- --- --- --- ---
Front beam
Top and bottom 16 mm 2 x 3 x 7.10 = --- --- --- 42.60 --- ---
Stirups 10 mm 1 x 20 x 1.42 = --- 28.40 --- --- --- ---
8 mm 1 x 22 x 1.38 = 30.36 --- --- --- --- ---
L/H side projected slab
Top and bottom main 10 mm 2 x 25 x 0.80 = --- 40.00 --- --- --- ---
Binder 10 mm 2 x 6 x 4.40 = --- 52.80 --- --- --- ---
R/H side projected slab
Top and bottom main 10 mm 2 x 30 x 0.80 = --- 48.00 --- --- --- ---
Binder 10 mm 2 x 6 x 5.00 = --- 60.00 --- --- --- ---
Front side projected slab
Top and bottom main 10 mm 2 x 52 x 0.80 = --- 83.20 --- --- --- ---
Binder 10 mm 2 x 6 x 7.50 = --- 90.00 --- --- --- ---
Slope vrtical reinforcement upto casting
L/H side 10 mm 1 x 25 x 0.35 = --- 8.75 --- --- --- ---
R/H side 10 mm 1 x 30 x 0.35 = --- 10.50 --- --- --- ---
Front 10 mm 1 x 52 x 0.35 = --- 18.20 --- --- --- ---
Lapping 10 mm 1 x 25 x 0.50 = --- 12.50 --- --- --- ---
16 mm 1 x 14 x 0.80 = --- --- --- 11.20 --- ---

Total (In m) = 71.76 509.15 1.20 112.60 1.20 0.00


0.395 0.616 0.888 1.579 2.467 3.850
Total Weight (In Kg) 28.35 313.64 1.07 177.80 2.96 0.00

C/O TCMB / P - 523.82 Kg

Sign by Contractor Checked by JE Checked by AE


Page no- 30

Steel reinforcement for R.C.C work including straightening , cutting , bending placing in
3.4
position and binding all complete above plinth level
3.4.1 Thermo-Mechanically Treated bars of Grade Fe-500D or more
Reinforcement of Column R/H Side From 2nd Floor upto 3rd Floor
C-7 (350X600)
Main Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Page17-10
Lap 20 mm 1 x 8 x 1.00 = --- --- --- --- 8.00 ---
Stiruups (master ring) 10 mm 1 x 24 x 1.74 = --- 41.76 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-8 (350X600)
Main Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 8 x 1.00 = --- --- --- --- 8.00 ---
Stiruups (master ring) 10 mm 1 x 24 x 1.74 = --- 41.76 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-9 (350X500)
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-10 (350X500)
Main Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
Existing Bar 25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 2.60 = --- --- --- --- --- 2.60
25 mm 1 x 1 x 2.60 = --- --- --- --- --- 2.60
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-11 (350X500)
Main Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
Existing Bar 25 mm 1 x 1 x 1.27 = --- --- --- --- --- 1.27
25 mm 1 x 1 x 1.75 = --- --- --- --- --- 1.75
25 mm 1 x 1 x 1.80 = --- --- --- --- --- 1.80
25 mm 1 x 1 x 1.45 = --- --- --- --- --- 1.45
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-12 (350X600)
Main Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 8 x 1.00 = --- --- --- --- 8.00 ---
Stiruups (master ring) 10 mm 1 x 24 x 1.74 = --- 41.76 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-13 (350X600)
Main Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 8 x 1.00 = --- --- --- --- 8.00 ---
Stiruups (master ring) 10 mm 1 x 24 x 1.74 = --- 41.76 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
B/F = 0.00 471.12 0.00 0.00 215.60 32.17

Sign by Contractor Checked by JE Checked by AE

Page no- 31

Steel (TMT Bars)


Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 0.00 471.12 0.00 0.00 215.60 32.17
C-21 (350X500)
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Page18-10
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-22 (350X500)
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-23 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Existing Bar 25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.52 = --- --- --- --- --- 1.52
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-24 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Existing Bar 25 mm 1 x 1 x 1.40 = --- --- --- --- --- 1.40
25 mm 1 x 1 x 1.40 = --- --- --- --- --- 1.40
25 mm 1 x 1 x 1.40 = --- --- --- --- --- 1.40
25 mm 1 x 1 x 1.40 = --- --- --- --- --- 1.40
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-25 (350X500)
Main Bar 25 mm 1 x 8 x 3.30 = --- --- --- --- --- 26.40
Lap 25 mm 1 x 8 x 1.25 = --- --- --- --- --- 10.00
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-26 (350X500)
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-33 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
B/F = 0.00 858.48 0.00 0.00 306.80 188.64

Sign by Contractor Checked by JE Checked by AE

Page no- 32
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 0.00 858.48 0.00 0.00 306.80 188.64
Existing Bar 25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.74 = --- --- --- --- --- 1.74
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
Page19-10
Links
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-34 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Existing Bar 25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-35 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Existing Bar 25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 2.10 = --- --- --- --- --- 2.10
25 mm 1 x 1 x 1.78 = --- --- --- --- --- 1.78
25 mm 1 x 1 x 2.35 = --- --- --- --- --- 2.35
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-36 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Existing Bar 25 mm 1 x 1 x 2.61 = --- --- --- --- --- 2.61
25 mm 1 x 1 x 1.67 = --- --- --- --- --- 1.67
25 mm 1 x 1 x 1.50 = --- --- --- --- --- 1.50
25 mm 1 x 1 x 2.10 = --- --- --- --- --- 2.10
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-37 (350X500)
Main Bar 25 mm 1 x 8 x 3.30 = --- --- --- --- --- 26.40
Lap 25 mm 1 x 8 x 1.25 = --- --- --- --- --- 10.00
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-38 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-45 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
B/F = 0.00 1245.84 0.00 0.00 363.60 336.89

Sign by Contractor Checked by JE Checked by AE

Page no- 33
Steel (TMT Bars)
Particulars Dia No. Length
8 mm 10 mm 12 mm 16mm 20mm 25mm
C/O = 0.00 1245.84 0.00 0.00 363.60 336.89
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Existing Bar 25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 1.90 = --- --- --- --- --- 1.90
25 mm 1 x 1 x 2.50 = --- --- --- --- --- 2.50
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Page20-10
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-46 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Existing Bar 25 mm 1 x 1 x 2.10 = --- --- --- --- --- 2.10
25 mm 1 x 1 x 2.10 = --- --- --- --- --- 2.10
25 mm 1 x 1 x 2.10 = --- --- --- --- --- 2.10
25 mm 1 x 1 x 2.10 = --- --- --- --- --- 2.10
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-47 (350X500)
Main Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 8 x 1.00 = --- --- --- --- 8.00 ---
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-48 (350X500)
Main Bar 20 mm 1 x 8 x 3.30 = --- --- --- --- 26.40 ---
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
Existing Bar 25 mm 1 x 1 x 1.45 = --- --- --- --- --- 1.45
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
25 mm 1 x 1 x 2.50 = --- --- --- --- --- 2.50
25 mm 1 x 1 x 1.75 = --- --- --- --- --- 1.75
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-49 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 20 mm 1 x 4 x 1.00 = --- --- --- --- 4.00 ---
25 mm 1 x 4 x 1.25 = --- --- --- --- --- 5.00
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
C-50 (350X500)
Main Bar 25 mm 1 x 4 x 3.30 = --- --- --- --- --- 13.20
Main Bar 20 mm 1 x 4 x 3.30 = --- --- --- --- 13.20 ---
Lap 20 mm 1 x 1 x 1.00 = --- --- --- --- 1.00 ---
25 mm 1 x 1 x 1.25 = --- --- --- --- --- 1.25
Stiruups (master ring) 10 mm 1 x 24 x 1.54 = --- 36.96 --- --- --- ---
Links 10 mm 1 x 24 x 0.45 = --- 10.80 --- --- --- ---
10 mm 1 x 24 x 0.70 = --- 16.80 --- --- --- ---
TOTAL = 0.00 1633.20 0.00 0.00 486.20 414.99
Provisional Weight considered for Measurements 0.395 0.616 0.888 1.579 2.467 3.850
Weight in Kg 0.00 1006.05 0.00 0.00 1199.46 1597.71
Total (in Kg) 3803.22
C/O TCMB / P -

Sign by Contractor Checked by JE Checked by AE

Page no- 34

Page21-10
Date of Measurement
Providing and laying in position machine batched and machine mixed design mix M-25
grade cement concrete for reinforced cement concrete work, using coarse aggregate as well
as fine aggregate derived from natural sources and cement content as per approved
design mix, including pumping of concrete to site of laying but excluding the cost of
Agreement No. 3.6 :
centering, shuttering, finishing and reinforcement, including admixtures in
recommended proportions as per IS: 9103 to accelerate, retard setting of concrete,
improve workability without impairing strength and durability as per direction of Engineer-in-
charge
3.6.2 : All works above plinth level upto floor V level
Particulars Nos x Nos x L x B x H = Quantity Unit
Asos mess building L/H Side Roof slab beam R.C.C
Linear Direction
R.B-01 (C4-C5) 1 X 1 X 4.56 X 0.23 X 0.50 = 0.52 Cum
R.B-01 (C5-C6) 1 X 1 X 4.46 X 0.23 X 0.50 = 0.51 Cum
RB-32 (C4-C18) to (C5-C19)
1 X 1 X 4.67 X 0.23 X 0.50 = 0.54 cum
RB-32 (C5-C19) to (C6-C20)
1 X 1 X 4.59 X 0.23 X 0.50 = 0.53 cum
RB-06 (C18-C19) 1 X 1 X 4.56 X 0.23 X 0.50 = 0.52 Cum
RB-06 (C19-C20) 1 X 1 X 4.46 X 0.23 X 0.50 = 0.51 Cum
RB-08 (C30-C31) 1 X 1 X 4.56 X 0.23 X 0.50 = 0.52 Cum
RB-08 (C31-C32) 1 X 1 X 4.46 X 0.23 X 0.50 = 0.51 Cum
RB-34 (C42-C30) to (C43-C31)
1 X 1 X 4.67 X 0.23 X 0.50 = 0.54 cum
RB-34 (C43-C31) to (C44-C32)
1 X 1 X 4.59 X 0.23 X 0.50 = 0.53 cum
RB-10 (C42-C43) 1 X 1 X 4.56 X 0.23 X 0.50 = 0.52 Cum
RB-10 (C43-C44) 1 X 1 X 4.46 X 0.23 X 0.50 = 0.51 Cum
RB-30 (Sub Beam)(C4- X X X X =
1 1 2.72 0.23 0.50 0.31 Cum
C5)
RB-30 (Sub Beam)(C5- X X X X =
1 1 2.89 0.23 0.50 0.33 Cum
C6)
RB-30 (Sub Beam)(C42- X X X X =
1 1 2.77 0.23 0.50 0.32 Cum
C43)
RB-30 (Sub Beam)(C43- X X X X =
1 1 2.81 0.23 0.50 0.32 Cum
C44)
Lateral Direction
RB-12 (C4-C18) 1 X 1 X 5.40 X 0.23 X 0.50 = 0.62 Cum
RB-12 (C18-C30) 1 X 1 X 1.77 X 0.23 X 0.50 = 0.20 Cum
RB-12 (C30-C42) 1 X 1 X 5.17 X 0.23 X 0.50 = 0.59 Cum
RB-13 (C5-C19) 1 X 1 X 5.40 X 0.23 X 0.50 = 0.62 Cum
RB-13 (C19-C31) 1 X 1 X 1.77 X 0.23 X 0.50 = 0.20 Cum
RB-13 (C31-C43) 1 X 1 X 5.17 X 0.23 X 0.50 = 0.59 Cum
RB-14 (C6-C20) 1 X 1 X 5.40 X 0.23 X 0.50 = 0.62 Cum
RB-14 (C20-C32) 1 X 1 X 1.77 X 0.23 X 0.50 = 0.20 Cum
RB-14 (C32-C44) 1 X 1 X 5.17 X 0.23 X 0.50 = 0.59 Cum
RB-31 (Sub Beam)
4 X 1 X 2.40 X 0.23 X 0.50 = 1.10 Cum
B/F = 12.87 Cum

Sign by Contractor Checked by JE Checked by AE

Page no- 35
Particular Nos x Nos x L x B x H = Quantity Unit
C/O = 12.87 Cum
ASO'S MESS Building L/H Side roof slab
(RB12-RB31)(RB01- X X X X =
1 1 2.72 1.20 0.15 0.49 Cum
RB30)(C4-C5)
(RB12-RB31)(RB30- X X X X =
1 1 2.72 0.98 0.15 0.40 Cum
RB32)(C4-C5)
(RB31-RB13)(RB01- X X X X =
1 1 2.40 1.62 0.15 0.58 Cum
RB32)(C4-C5)
(RB12-RB13)(RB32- X X X X =
1 1 4.56 3.34 0.15 2.28 Cum
RB06)(C18-C19)
(RB1-RB32)(RB13- X X X X =
1 1 2.40 1.61 0.15 0.58 Cum
RB31)(C5-C6)
(RB31-RB14)(RB1 X X X X =
1 1 2.89 1.20 0.15 0.52 Cum
-RB30)(C5-C6)
(RB31-RB14)(RB30- X X X X =
1 1 2.89 0.98 0.15 0.42 Cum
RB32)(C5-C6)
(RB13-RB14)(RB32 X X X X =
1 1 4.74 3.34 0.15 2.37 Cum
-RB06)(C19-C20)
(C18-C19) to(C30-C31) 1 X 1 X 4.56 X 1.80 X 0.15 = 1.23 Cum
(C19-C20) to(C31-C32) 1 X 1 X 4.74 X 1.80 X 0.15 = 1.28 Cum
(RB12-RB13)(RB08- X X X X =
1 1 4.56 3.10 0.15 2.12 Cum
RB34)(C30-C31)
(RB34-RB10)(RB12- X X X X =
1 1 2.40 1.62 0.15 0.58 Cum
RB31)(C42-C43)
(RB31-RB13)(RB34- X X X X =
1 1 2.77 1.20 0.15 0.50 Cum
RB30)(C42-C43)
(RB31-RB13)(RB30- X X X X =
1 1 2.77 0.98 0.15 0.41 Cum
RB10)(C42-C43)
(RB13-RB14)(RB08- X X X X =
1 1 4.74 3.10 0.15 2.20 Cum
RB34)(C31-C32)
RB13-RB31)(RB34- X X X X =
1 1 2.81 1.20 0.15 0.51 Cum
RB30)(C43-C44)
(RB13-RB31)(RB30- X X X X =
1 1 2.81 0.98 0.15 0.41 Cum
RB10)(C43-C44)
(RB34-RB10)(RB31- X X X X =
1 1 2.40 1.62 0.15 0.58 Cum
RB14)(C43-C44)
Projected Slab
Front 1 X 1 X 11.30 X 0.60 X 0.10 = 0.68 Cum
L/H side 1 X 1 X 14.00 X 0.60 X 0.10 = 0.84 Cum
Back side 1 X 1 X 9.90 X 0.60 X 0.10 = 0.59 Cum
R/H side 1 X 1 X 6.00 X 0.60 X 0.10 = 0.36 Cum
Total Quantity (Cum) = 32.80 Cum
C/O TCMB / P -

Sign by Contractor Checked by JE Checked by AE

Page no- 36

Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and removal of form for
3.2.5 : Lintels, beams, plinth beams, girders, bressumers and cantilevers.
Particular x Nos x L x B x H = Quantity Unit
ASO'S MESS Building L/H Side Shuttering work for R.C.C roof slab beam
Linear Direction
RB-1 (C4-C5)
Outer Side 1 X 1 X 4.56 X 0.40 X - = 1.82 Sqm
Inner Side 1 X 1 X 4.56 X 0.35 X - = 1.60 Sqm
Bottom 1 X 1 X 4.56 X 0.23 X - = 1.05 Sqm
RB-1 (C5-C6)
Outer Side 1 X 1 X 4.46 X 0.40 X - = 1.78 Sqm
Inner Side 1 X 1 X 4.46 X 0.35 X - = 1.56 Sqm
Bottom 1 X 1 X 4.46 X 0.23 X - = 1.03 Sqm
RB-32 (RB12-RB13)
Side 1 X 2 X 4.67 X 0.35 X - = 3.27 Sqm
Bottom 1 X 1 X 4.67 X 0.23 X - = 1.07 Sqm
RB-32 (RB13-RB14)
Side 1 X 2 X 4.59 X 0.35 X - = 3.21 Sqm
Bottom 1 X 1 X 4.59 X 0.23 X - = 1.05 Sqm
RB-06 (C18-C19)
Side 1 X 2 X 4.56 X 0.35 X - = 3.19 Sqm
Bottom 1 X 1 X 4.56 X 0.23 X - = 1.05 Sqm
RB-06 (C19-C20)
Side 1 X 2 X 4.46 X 0.35 X - = 3.12 Sqm
Bottom 1 X 1 X 4.46 X 0.23 X - = 1.03 Sqm
RB-08 (C30-C31)
Side 1 X 2 X 4.56 X 0.35 X - = 3.19 Sqm
Bottom 1 X 1 X 4.56 X 0.23 X - = 1.05 Sqm
RB-08 (C31-C32)
Side 1 X 2 X 4.46 X 0.35 X - = 3.12 Sqm
Bottom 1 X 1 X 4.46 X 0.23 X - = 1.03 Sqm
RB-34 (RB12-RB13)
Side 1 X 2 X 4.67 X 0.35 X - = 3.27 Sqm
Bottom 1 X 1 X 4.67 X 0.23 X - = 1.07 Sqm
RB-34 (RB13-RB14)
Side 1 X 2 X 4.59 X 0.35 X - = 3.21 Sqm
Bottom 1 X 1 X 4.59 X 0.23 X - = 1.05 Sqm
RB-10 (C42-C43)
Outer Side 1 X 1 X 4.56 X 0.40 X - = 1.82 Sqm
Inner Side 1 X 1 X 4.56 X 0.35 X - = 1.60 Sqm
Bottom 1 X 1 X 4.56 X 0.23 X - = 1.05 Sqm
RB-10 (C43-C44)
Outer Side 1 X 1 X 4.460 X 0.400 X - = 1.78 Sqm
Inner Side 1 X 1 X 4.46 X 0.35 X - = 1.56 Sqm
Bottom 1 X 1 X 4.46 X 0.23 X - = 1.03 Sqm
RB-30 (Sub Beam)(C4-C5)
Side 1 X 2 X 2.72 X 0.35 X - = 1.90 Sqm
Bottom 1 X 1 X 2.72 X 0.23 X - = 0.63 Sqm
RB-30 (Sub Beam)(C5-C6)
Side 1 X 2 X 2.89 X 0.35 X - = 2.02 Sqm
Bottom 1 X 1 X 2.89 X 0.23 X - = 0.66 Sqm
RB-30 (Sub Beam)(C42-C43)
Side 1 X 2 X 2.77 X 0.35 X - = 1.94 Sqm
Bottom 1 X 1 X 2.77 X 0.23 X - = 0.64 Sqm
B/F = 59.45 Sqm

Sign by Contractor Checked by JE Checked by AE

Page no- 37
Particular x Nos x L x B x H = Quantity Unit
C/O = 59.45 Sqm
RB-30 (Sub Beam)(C43-C44)
Side 1 X 2 X 2.81 X 0.35 X - = 1.97 Sqm
Bottom 1 X 1 X 2.81 X 0.23 X - = 0.65 Sqm
Lateral Direction
RB-12 (C4-C18)
Out side 1 X 1 X 5.40 X 0.40 X - = 2.16 Sqm
inside 1 X 1 X 5.40 X 0.35 X - = 1.89 Sqm
Bottom 1 X 1 X 5.40 X 0.23 X - = 1.24 Sqm
RB-12 (C18-C30)
Side 1 X 1 X 1.77 X 0.40 X - = 0.71 Sqm
1 X 1 X 1.77 X 0.35 X - = 0.62 Sqm
Bottom 1 X 1 X 1.77 X 0.23 X - = 0.41 Sqm
RB-12 (C30-C42)
1 X 1 X 5.17 X 0.40 X - = 2.07 Sqm
Side
1 X 1 X 5.17 X 0.35 X - = 1.81 Sqm
Bottom 1 X 1 X 5.17 X 0.23 X - = 1.19 Sqm
RB-13 (C5-C19)
1 X 1 X 5.40 X 0.35 X - = 1.89 Sqm
Side
1 X 1 X 5.40 X 0.35 X - = 1.89 Sqm
Bottom 1 X 1 X 5.40 X 0.23 X - = 1.24 Sqm
RB-13 (C19-C31)
Side 1 X 2 X 1.77 X 0.35 X - = 1.24 Sqm
Bottom 1 X 1 X 1.77 X 0.23 X - = 0.41 Sqm
RB-13 (C31-C43)
1 X 1 X 5.17 X 0.35 X - = 1.81 Sqm
Side
1 X 1 X 5.17 X 0.35 X - = 1.81 Sqm
Bottom 1 X 1 X 5.17 X 0.23 X - = 1.19 Sqm
RB-14 (C6-C20)
Inner Side 1 X 1 X 5.40 X 0.35 X - = 1.89 Sqm
Outer Side 1 X 1 X 5.40 X 0.50 X - = 2.70 Sqm
Bottom 1 X 1 X 5.40 X 0.23 X - = 1.24 Sqm
RB-14 (C20-C32)
Inner Side 1 X 1 X 1.77 X 0.35 X - = 0.62 Sqm
Outer Side 1 X 1 X 1.77 X 0.50 X - = 0.89 Sqm
Bottom 1 X 1 X 1.77 X 0.23 X - = 0.41 Sqm
RB-14 (C32-C44)
Inner Side 1 X 1 X 5.17 X 0.35 X - = 1.81 Sqm
Outer Side 1 X 1 X 5.17 X 0.40 X - = 2.07 Sqm
Bottom 1 X 1 X 5.17 X 0.23 X - = 1.19 Sqm
RB-31 (Sub Beam)
4 X 1 X 1.19 X 0.35 X - = 1.67 Sqm
Side 4 X 1 X 0.98 X 0.35 X - = 1.37 Sqm
4 X 1 X 2.40 X 0.35 X - = 3.36 Sqm
Bottom 4 X 1 X 2.40 X 0.23 X - = 2.21 Sqm
Total Quantity (Sq.m) = 107.08 Sqm
C/O TCMB / P -

Sign by Contractor Checked by JE Checked by AE

Page no- 38

Date of Measurement
Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and removal of form for
3.2.3 : suspended floor s, roof ,landings balconies and access platform
Particular x Nos x L x B x H = Quantity Unit
ASO'S MESS Building L/H Side Shuttering Work For R.C.C Roof slab
(RB12-RB31)(RB01- X X X X =
1 1 2.72 1.20 - 3.26 Sqm
RB30)(C4-C5)
(RB12-RB31)(RB30- X X X X =
1 1 2.72 0.98 - 2.67 Sqm
RB32)(C4-C5)
(RB31-RB13)(RB01- X X X X =
1 1 2.40 1.62 - 3.89 Sqm
RB32)(C4-C5)
(RB12-RB13)(RB32- X X X X =
1 1 4.56 3.34 - 15.23 Sqm
RB06)(C18-C19)
(RB1-RB32)(RB13- X X X X =
1 1 2.40 1.61 - 3.86 Sqm
RB31)(C5-C6)
(RB31-RB14)(RB1 X X X X =
1 1 2.89 1.20 - 3.47 Sqm
-RB30)(C5-C6)
(RB31-RB14)(RB30- X X X X =
1 1 2.89 0.98 - 2.83 Sqm
RB32)(C5-C6)
(RB13-RB14)(RB32 X X X X =
1 1 4.74 3.34 - 15.83 Sqm
-RB06)(C19-C20)
(C18-C19) to(C30-C31) 1 X 1 X 4.56 X 1.80 X - = 8.21 Sqm
(C19-C20) to(C31-C32) 1 X 1 X 4.74 X 1.80 X - = 8.53 Sqm
(RB12-RB13)(RB08- X X X X =
1 1 4.56 3.10 - 14.14 Sqm
RB34)(C30-C31)
(RB34-RB10)(RB12- X X X X =
1 1 2.40 1.62 - 3.89 Sqm
RB31)(C42-C43)
(RB31-RB13)(RB34- X X X X =
1 1 2.77 1.20 - 3.32 Sqm
RB30)(C42-C43)
(RB31-RB13)(RB30- X X X X =
1 1 2.77 0.98 - 2.71 Sqm
RB10)(C42-C43)
(RB13-RB14)(RB08- X X X X =
1 1 4.74 3.10 - 14.69 Sqm
RB34)(C31-C32)
RB13-RB31)(RB34- X X X X =
1 1 2.81 1.20 - 3.37 Sqm
RB30)(C43-C44)
(RB13-RB31)(RB30- X X X X =
1 1 2.81 0.98 - 2.75 Sqm
RB10)(C43-C44)
(RB34-RB10)(RB31- X X X X =
1 1 2.40 1.62 - 3.89 Sqm
RB14)(C43-C44)
Projected Slab
Front 1 X 1 X 11.30 X 0.60 X - = 6.78 Sqm
L/H side 1 X 1 X 14.00 X 0.60 X - = 8.40 Sqm
Back side 1 X 1 X 9.90 X 0.60 X - = 5.94 Sqm
R/H side 1 X 1 X 6.00 X 0.60 X - = 3.60 Sqm
Total = 141.26 Sqm
C/O TCMB -
Agreement No. 3.2.8 : Edges of slabs and breaks in floors and wallsfor
3.2.8.1 : Under 20 cm wide
Particular Nos x L x B x H = Quantity Unit
Slab edge shuttering
Projected Slab side shuttering of L/H side Roof slab
Front 1 X 11.30 X - - = 11.30 mtr
L/H side 1 X 14.60 X - - = 14.60 mtr
Back side 1 X 10.50 X - - = 10.50 mtr
R/H side 1 X 6.60 X - - = 6.60 mtr
Total Quantity = 43.00 mtr

C/O TCMB -

Sign by Contractor Checked by JE Checked by AE

Page no- 39
Date of Measurement
Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and Removal of form for
3.2.6 : Column, Pillars, piers, Abustments, posts and struts
Particular Nos x Nos x L x B x H = Quantity Unit
ASOS Mess R/H Side Column Shuttering From 3rd floor slab upto 2.40mt
C7 1 x 2 x( 0.35 + 0.60 )x 2.40 = 4.56 sqm
C8 1 x 2 x( 0.35 + 0.60 )x 2.40 = 4.56 sqm
C9 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C10 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C11 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C12 1 x 2 x( 0.35 + 0.60 )x 2.40 = 4.56 sqm
C13 1 x 2 x( 0.35 + 0.60 )x 2.40 = 4.56 sqm
C21 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C22 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C23 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C24 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C25 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C26 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C33 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C34 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C35 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C36 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C37 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C38 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C45 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C46 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C47 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C48 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C49 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm
C50 1 x 2 x( 0.35 + 0.50 )x 2.40 = 4.08 sqm

Total Quantity = 103.92 Sqm


C/O TCMB -

Sign by Contractor Checked by JE Checked by AE

Page no- 40
Date of Measurement
Providing and laying in position machine batched and machine mixed design mix M-25
grade cement concrete for reinforcd cement concrete work , using coarse aggregate as well
as fine aggregate derived from natural source and cement cocrete as per approved design
Agreement No. 3.6 : mix , including pimping of con crete to site laying but excluding the cost of centering ,
shuttering,finishing and reinforecd , including admixture in recommended proportion as per
IS: 9103 to accelerated, retard setting of concrete , improve workability without impairing
strength and durability as per direction of Engineer-in-Charge.

3.6.2 : All works above plinth level upto floor V level


Particular Nos x Nos x L x B x H = Quantity Unit
ASOS Mess R/H Side Column R.C.C From 3rd floor slab upto 2.40mt
C7 1 x 1 x 0.35 x 0.60 x 2.40 = 0.50 Cum
C8 1 x 1 x 0.35 x 0.60 x 2.40 = 0.50 Cum
C9 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C10 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C11 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C12 1 x 1 x 0.35 x 0.60 x 2.40 = 0.50 Cum
C13 1 x 1 x 0.35 x 0.60 x 2.40 = 0.50 Cum
C21 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C22 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C23 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C24 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C25 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C26 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C33 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C34 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C35 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C36 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C37 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C38 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C45 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C46 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C47 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C48 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C49 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
C50 1 x 1 x 0.35 x 0.50 x 2.40 = 0.42 Cum
Total Quantity = 10.82 Cum
C/O TCMB -
Providing and laying in position machine batched and machine mixed design mix M-25
grade cement concrete for reinforcd cement concrete work , using coarse aggregate as well
as fine aggregate derived from natural source and cement cocrete as per approved design
Agreement No. 3.6 : mix , including pimping of con crete to site laying but excluding the cost of centering ,
shuttering,finishing and reinforecd , including admixture in recommended proportion as per
IS: 9103 to accelerated, retard setting of concrete , improve workability without impairing
strength and durability as per direction of Engineer-in-Charge.

3.6.2 : All works above plinth level upto floor V level


Particular Nos x Nos x L x B x H = Quantity Unit
ASOS Mess front porch beam and projected slab R.C.C
L/H side beam 1 x 1 x 4.31 x 0.23 x 0.50 = 0.50 Cum
R/H side beam 1 x 1 x 4.31 x 0.23 x 0.50 = 0.50 Cum
Front beam 1 x 1 x 5.90 x 0.23 x 0.50 = 0.68 Cum
L/H side projected slab 1 x 1 x 4.40 x 0.60 x 0.10 = 0.26 Cum
Front 1 x 1 x 6.90 x 0.60 x 0.10 = 0.41 Cum
R/H side projected slab 1 x 1 x 4.40 x 0.60 x 0.10 = 0.26 Cum
Total Quantity = 2.61 Cum

C/O TCMB -

Sign by Contractor Checked by JE Checked by AE

Page no- 41
Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and removal of form for
3.2.5 : Lintels, beams, plinth beams, girders, bressumers and cantilevers.
Particular x Nos x L x B x H = Quantity Unit
ASOS Mess front porch beam Shuttering
L/H side beam
Outer Side 1 X 1 X 4.31 X - X 0.40 = 1.72 Sqm
Inner Side 1 X 1 X 4.31 X - X 0.50 = 2.16 Sqm
Bottom 1 X 1 X 4.56 X - X 0.23 = 1.05 Sqm
R/H side beam
Outer Side 1 X 1 X 4.31 X - X 0.40 = 1.72 Sqm
Inner Side 1 X 1 X 4.31 X - X 0.50 = 2.16 Sqm
Bottom 1 X 1 X 4.56 X - X 0.23 = 1.05 Sqm
Front
Outer Side 1 X 1 X 5.90 X - X 0.40 = 2.36 Sqm
Inner Side 1 X 1 X 5.90 X - X 0.50 = 2.95 Sqm
Bottom 1 X 1 X 5.90 X - X 0.23 = 1.36 Sqm
Total Quantity = 16.53 Sqm

C/O TCMB -
Agreement No. 3.2 : Centering and shuttering including strutting, propping etc. and removal of form for
3.2.3 : suspended floor s, roof ,landings balconies and access platform
Particular x Nos x L x B x H = Quantity Unit
ASOS Mess front porch projected slab shuttering
L/H side 1 X 1 X 4.40 X 0.60 X - = 2.64 Sqm
R/H side 1 X 1 X 6.90 X 0.60 X - = 4.14 Sqm
Front side 1 X 1 X 4.40 X 0.60 X - = 2.64 Sqm
Total Quantity = 9.42 Sqm

C/O TCMB -

Agreement No. 3.2.8 : Edges of slabs and breaks in floors and walls for
3.2.8.1 : Under 20 cm wide
Particular Nos x L x B x H = Quantity Unit
Slab edge shuttering
ASOS Mess front porch projected slab side shuttering
L/H side 1 X 4.40 X - - = 4.40 mtr
Front side 1 X 7.50 X - - = 7.50 mtr
R/H side 1 X 5.00 X - - = 5.00 mtr
Total Quantity = 16.90 mtr

C/O TCMB -

Sign by Contractor Checked by JE Checked by AE

Page no- 42
ABSTRACT OF COST 6th R.A. Bill
Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn,
1 Name of work : ITBP at Karchia Sonapur (Assam) including water supply, sanitary
installation & internal electrical installation.
2 Agreement No- : 04/CE/EE/PD/2020-21
3 Agency - : M/s Khatri Enterprises
4 Date of Start : 10.08.2020
5 Date of Complittion : 09.08.2021
6 Time Allowed : 12 (Twelve) months
7 Date of completion (Actual) : Work in Progress
8 Date of Abstract : 6/26/2023
9 Sl.No Of Bill : 6th R.A bill
Rate
Item
Description B/F Page No. Quantity Unit : Amount
No. Agmnt in this bill

Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over


areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting
1.2
out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by
Engineer-in-charge.
1.2.1 All kinds of soil
Agrt. Qnty - 1080.00 Cum
Qty. B/F CMB No COM/ITBP/PD-
II/860 vide Page No. 1109.13

Total 1109.13 cum :


As per agreement qty. 1080.00 cum 175.55 175.55 cum : 189594.00
Qty upto Deviation Limit 29.13 cum 175.55 175.55 cum : 5113.77
Earth Work in excavation by mechanical means ( Hydraulic exavator) / manual means in
foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including
1.3
getting out the excavated soil and disposal of surplus excavated soil as directed within a
lead of 50m
1.3.1 All Kinds of Soil
Agrt. Qnty - 192.00 Cum
Qty. B/F CMB No COM/ITBP/PD-
II/860 vide Page No. 159.63
cum
Total 159.63 cum 227.00 227.00 cum : 36236.01

Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers
1.5.1 not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up
to 50m and lift upto 1.5m.

Agrt. Qnty - 1015.00Cum


Qty. B/F CMB No COM/ITBP/PD-
1137.75
II/860 vide Page No. cum
Total 1137.75 cum 160.05 160.05 cum : 182096.89
Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or
1.6
stacked materials.

1.6.1 All kinds of soil

Agrt. Qnty - 269.00 Cum


Qty. B/F CMB No COM/ITBP/PD-
:
II/860 vide Page No. 315.68 cum
Total 315.68 cum :
As per agreement qty. 269.00 cum 65.65 65.65 cum : 17659.85
Qty upto Deviation Limit 46.68 cum 65.65 65.65 cum : 3064.54
B/F = 433765.06
Page no- 43

c/O = 433765.06
Supplying and filling in plinth with sand under floors, including watering, ramming,
1.7
consolidation and dressing complete.
Agrt. Qnty -103.00 cum
Qty. B/F CMB No COM/ITBP/PD-
II/860 vide Page No. 71.62 cum
Total 71.62 cum 1265.05 1265.05 cum : 90602.88
Providing and laying in position cement concrete of specified grade excluding the cost of
2.1
centering and shuttering - All work upto plinth level:

1:5:10 (1 cement : 5 coarse sand (Zone-III) derived from natural sources : 10 graded stone
2.1.2
aggregate 40 mm nominal size derived from natural sources )
Agrt. Qnty - 142.97 Cum
Qty. B/F CMB No COM/ITBP/PD-
86.86
II/860 vide Page No. cum
Total 86.86 cum 5524.40 5524.40 cum : 479849.38
3.2 Centering and shuttering including strutting, propping etc. and removal of form for
3.2.1 Foundations, footings, bases of columns, etc. for mass concrete
Agrt. Qnty - 413.00 Sqm
Qty. B/F CMB No COM/ITBP/PD-
386.26
II/860 vide Page No. sqm
Total 386.26 sqm 234.05 234.05 Sqm : 90404.15
3.2.2 Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
Agrt. Qnty - 367.24 Sqm
Qty. B/F CMB No COM/ITBP/PD-
145.72 sqm
II/860 vide Page No.
Total 145.72 sqm 500.05 500.05 Sqm : 72867.29
3.2.3 suspended floor s, roof ,landings balconies and access platform
Agrt. Qnty - 2273.75 Sqm
Qty. B/F CMB No COM/ITBP/PD-
1178.66 sqm
II/860 vide Page No.
Qty B/F TCMB 307.55 sqm
Qty B/F TCMB 141.26 sqm
Qty B/F TCMB 9.42 sqm
Total 1636.89 sqm 546.55 546.55 Sqm : 894642.23
3.2.5 Lintels, beams, plinth beams, girders, bressumers and cantilevers.
Agrt. Qnty - 2964.90 Sqm
Qty. B/F CMB No COM/ITBP/PD-
1435.19 sqm
II/860 vide Page No.
Qty B/F TCMB 255.93 sqm
Qty B/F TCMB 107.08 sqm
Qty B/F TCMB 16.53 sqm
Total 1814.73 sqm 432.70 432.70 Sqm : 785233.67
3.2.6 Columns, Pillars, Piers, Abutments, Posts and Struts
Agrt. Qnty - 998.00 Sqm
Qty. B/F CMB No COM/ITBP/PD-
760.35 sqm
II/860 vide Page No.
Qty B/F TCMB 33.88 sqm
Qty B/F TCMB 48.96 sqm
Qty B/F TCMB 35.10 sqm
Qty B/F TCMB 103.92 sqm
Total 982.21 sqm 579.15 579.15 Sqm : 568846.92
3.2.7 Stairs,(excluding landings) except spiral-staircases
Agrt. Qnty - 159.00 Sqm
Qty. B/F CMB No COM/ITBP/PD-
84.76 sqm
II/860 vide Page No.
Qty B/F TCMB 17.53 sqm
Total 102.29 sqm 579.15 579.15 Sqm : 59241.25
B/F = 3475452.83
Page no- 44

C/O = 3475452.83

3.2.8 Edges of slabs and breaks in floors and walls for


3.2.8.1Under 20 cm wide
Agrt. Qnty - 212.00 mtr
Qty. B/F CMB No COM/ITBP/PD-
II/860 vide Page No. 202.02
mtr.
Qty B/F TCMB 34.99 mtr.
Qty B/F TCMB 43.00 mtr.
Qty B/F TCMB 16.90 mtr.
Total 296.91 mtr. 159.65 159.65 mtr : 47401.68
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in
3.3
position and binding all complete upto plinth level.
3.3.1 Thermo-Mechanically Treated bars of grade Fe-500D or more..
Agrt. Qnty - 37500.00 kg
Qty. B/F CMB No COM/ITBP/PD-
II/860 vide Page No. 23685.45

Total 23685.45 kg 75.55 75.55 kg : 1789435.75


Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in
3.4
position and binding all complete above plinth level.
3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more..
Agrt. Qnty - 67000.00 kg
Qty. B/F CMB No COM/ITBP/PD-
56758.03 Kg
II/860 vide Page No.
Qty B/F TCMB 4608.46 Kg
Qty B/F TCMB 5615.88 Kg
Qty B/F TCMB 102.21 Kg
Qty B/F TCMB 1531.53 Kg
Qty B/F TCMB 1594.80 Kg
Qty B/F TCMB 2473.83 Kg
Qty B/F TCMB 47.70 Kg
Qty B/F TCMB 523.82 Kg
Qty B/F TCMB 3803.22 Kg
Total 77059.48 kg
As per agreement qty. 67000.00 kg 75.55 75.55 kg : 5061850.00
Qty upto Deviation Limit 10059.48 kg 75.55 75.55 kg : 759993.71

Providing and laying in position machine batched and machine mixed design mix M-25
grade cement concrete for reinforced cement concrete work, using coarse aggregate as well
as fine aggregate derived from natural sources and cement content as per approved
design mix, including pumping of concrete to site of laying but excluding the cost of
3.6
centering, shuttering, finishing and reinforcement, including admixtures in
recommended proportions as per IS: 9103 to accelerate, retard setting of concrete,
improve workability without impairing strength and durability as per direction of Engineer-in-
charge
3.6.1 All works upto plinth level.
Agrt. Qnty - 265.00 cum
Qty. B/F CMB No COM/ITBP/PD- Cu
263.19
II/860 vide Page No. m
Total 263.19 cum 8084.30 8084.30 cum : 2127706.92
B/F = 13261840.89
Page no- 45

C/O = 13261840.89
3.6.2 All works above plinth level upto floor V level
Agrt. Qnty - 560.00 cum
Qty. B/F CMB No COM/ITBP/PD-
366.35 Cum
II/860 vide Page No.
Qty B/F TCMB 4.28 Cum
Qty B/F TCMB 76.20 Cum
Qty B/F TCMB 5.04 Cum
Qty B/F TCMB 2.14 Cum
Qty B/F TCMB 32.80 Cum
Qty B/F TCMB 10.82 Cum
Qty B/F TCMB 2.61 Cum
Total 500.24 cum
Total (A) 32.80 cum 9098.00 6823.50 cum 223810.80
Total (B) 467.44 cum 9098.00 9098.00 cum 4252769.12
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and
4.1
plinth in :
4.1.2 Cement mortar 1:6 (1 cement : 6 coarse sand)
Agrt. Qnty - 88.00cum
Qty. B/F CMB No COM/ITBP/PD-
II/860 vide Page No. 48.03
Total 48.03 cum 7879.85 7879.85 cum : 378469.20
10.1 12 mm Cement Plaster of Mix :
10.1.1 1:4 (1 Cement : 4 coarse sand)
Agrt. Qnty - 3220.00 sqm
Qty. B/F CMB No COM/ITBP/PD-
II/860 vide Page No. 262.00 sqm

Total 262.00 sqm 231.05231.05 sqm : 60535.10


Total : 18177425.11
Contractor enhancement. @3.65% (below) : -663476.02
Gross value upto work done 17513949.09
Demolishing brick work manually/ by mechanical means including stacking of serviceable material and
E/S-1 disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. :
In Cement Mortar :
Qty. B/F CMB No COM/ITBP/PD-
10.18 cum
II/860 vide Page No.
Total 10.18 cum 1698.45 1273.84 cum : 12967.67
E/S-2 Add for using extra cement in the items of design mix over and above the specified cement content therein
Qty B/F TCMB Qtl
Total 0.00 Qtl 0.00 0.00 Qtl : 0.00

Extra for additional height in centering, shuttering where ever required with adequate bracing, propping etc.,
including cost of de-shuttering and decentering at all levels, over a height of 3.5 m, for every additional
E/S-3 height of 1 metre or part thereof (Suspended floors, roofs, landing, beams and balconies (Plan area to be
measured)
Qty B/F TCMB 178.52 sqm
Total 178.52 sqm 262.95 239.85 sqm : 42818.02

Gross value upto work done 17569734.78


Less already paid in 5TH RA Bill 14228070.43
Gross value in this bill : 3341664.35
RECOVERIES:
1 Security Deposit @ 2.5% on "Gross value " : 83542.00
Already recovered in pervious bill :
Now to be recovered : 83542.00
2 Income Tax @2% on 3,341,664.35 : 66833.00
3 WWC @1% on 3,341,664.35 : 33417.00
4 CGST @ 1% on 3,341,664.35 : 33417.00
5 SGST @ 1% on 3,341,664.35 : 33417.00
TOTAL RECOVERY: : (-) -250626.00
Net value in this bill : 3091038.35
Say = Rs. Rs.3,091,038.00
Page no- 46

Certify that:-
1. The work has been done as per CPWD specification and agreement
2. No Govt. T&P has been issued to the contractor
3. No Labour complaint has been received so far.
4. Water has been arranged by the contractor at his own source.
5. Contractor has engaged technical staff.
6. F.N.Labour report has been submitted by the contractor

Assistant Engineer
SPSD-II, Project Division
CPWD, Assam
6th R.A. Bill

Gross value upto work done 17569734.78


Less already paid in 5th RA Bill 14228070.43
Gross value in this bill : 3341664.35

RECOVERIES:
1 Security Deposit @ 2.5% on "Gross value " : 83542.00
Already recovered in pervious bill :
Now to be recovered : 83542.00

2 Income Tax @2% on 3,341,664.35 : 66833.00

3 WWC @1% on 3,341,664.35 : 33417.00

4 CGST @ 1% on 3,341,664.35 : 33417.00

5 SGST @ 1% on 3,341,664.35 : 33417.00

6 Mildstone S.L no 1 to 4 = 4% already withheld at 4th R.A Bill

TOTAL RECOVERY: : (-) -250626.00

Net value in this bill : 3091038.35


Say = Rs. Rs.3,091,038.00
Executive Engineer
Project Division
Page no- 47 CPWD, guwahati-15
Abstract of steel

Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP at Karchia Sonapur
1 Name of Work:-
(Assam) including water supply, sanitary installation & internal electrical installation.

2 Agreement No.:- 04/CE/EE/PD/2020-21

3 Agency:- M/s Khatri Enterprises

4 Sl.No Of Bill 6th R.A Bill

5 Date of Entry
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and
3.4
binding all complete above plinth level.
3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more.
REINFORCEMENT (TMT BAR)
Item Page Total in
Reference MB No.
No. No. 8mm 10 mm 12 mm 16 mm 20mm 25 mm ( Kg )

B/F TCMB 460.61 1093.40 360.47 2671.97 22.01 0.00 4608.46

B/F TCMB 0.00 5325.05 290.83 0.00 0.00 0.00 5615.88

B/F TCMB 0.00 102.21 0.00 0.00 0.00 0.00 102.21

B/F TCMB 0.00 468.75 0.00 103.58 678.92 280.28 1531.53

B/F TCMB 216.95 474.97 287.36 603.18 12.34 0.00 1594.80

B/F TCMB 5.34 2392.30 76.19 0.00 0.00 0.00 2473.83

B/F TCMB 0.00 47.70 0.00 0.00 0.00 0.00 47.70

B/F TCMB 28.35 313.64 1.07 177.80 2.96 0.00 523.82

B/F TCMB 0.00 1006.05 0.00 0.00 1199.46 1597.71 3803.22

Total 711.25 11224.07 1015.92 3556.53 1915.69 1877.99 20301.45


Total In(Kg) Kg Kg Kg Kg Kg Kg kg

Junior Engineer Assistant Engineer


Sonapur Project Sub Division-II Sonapur Project Sub Division-II
CPWD, Assam CPWD, Assam
INNER SHEET
6th R.A Bill
1 Name of work Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP at Karchia Sonapur (Assam) including water
supply, sanitary installation & internal electrical installation.

2 Agreement No. 04/CE/EE/PD/2020-21


3 Name of Agency M/s Khatri Enterprises
4 Stp. date of start 10.08.2020
5 Stp. date of completion 09.08.2021
6 Actual date of completion Work in Progress
Rate Since
Item No. Description of Items Qty. Unit Upto date In previous bill
Agmnt In this bill Previous
1.2 Earth work in excavation by mechanical means (Hydraulic excavator)/manual
means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm
on plan) including getting out and disposal of excavated earth lead upto 50 m
and lift upto 1.5 m, as directed by Engineer-in-charge.

1.2.1 All kinds of soil


Total 1109.13 Cum
As Per Agrrement Qty. 1080.00 cum 175.55 175.55 189,594.00 189,594.00 0.00
Qty Upto Deviation Limit 29.13 cum 175.55 175.55 5,113.77 5,113.77 0.00
1.3 Earth Work in excavation by mechanical means ( Hydraulic exavator) / manual
means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm
on plan), including getting out the excavated soil and disposal of surplus
excavated soil as directed within a lead of 50m
1.3.1 All Kinds of Soil
Total 159.63 cum 227.00 227.00 36,236.01 36,236.01 0.00
1.5.1 Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundation etc. in layers not exceeding 20cm in depth, consolidating each
deposited layer by ramming and watering, lead up to 50m and lift upto 1.5m.

Total 1137.75 Cum 160.05 160.05 182,096.89 182,096.89 0.00


1.6 Extra for every additional lift of 1.5 m or part thereof in excavation / banking
excavated or stacked materials.
1.6.1 All kinds of soil
Total 315.68 Cum
As Per Agrrement Qty. 269.00 Cum 65.65 65.65 17,659.85 17,659.85 0.00
Qty Upto Deviation Limit 46.68 Cum 65.65 65.65 3,064.54 3,064.54 0.00
1.7 Supplying and filling in plinth with sand under floors, including watering,
ramming, consolidation and dressing complete.
Total 71.62 Cum 1265.05 1265.05 90,602.88 90,602.88 0.00
Rate Since
Item No. Description of Items Qty. Unit Upto date In previous bill
Agmnt In this bill Previous
2.1 Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work upto plinth level:

2.1.2 1:5:10 (1 cement : 5 coarse sand (Zone-III) derived from natural sources : 10
graded stone aggregate 40 mm nominal size derived from natural sources )

Total 86.86 Cum 5524.40 5524.40 479,849.38 479,849.38 0.00


3.2 Centering and shuttering including strutting, propping etc. and removal of form for

3.2.1 Foundations, footings, bases of columns, etc. for mass concrete


Total 386.26 Sqm 234.05 234.05 90,404.15 90,404.15 0.00
3.2.2 Walls (any thickness) including attached pilasters, butteresses, plinth and string
courses etc.

Total 145.72 Sqm 500.05 500.05 72,867.29 72,867.29 0.00


3.2.3 suspended floor s, roof ,landings balconies and access platform

Total 1636.89 Sqm 546.55 546.55 894,642.23 644,196.62 250445.61


3.2.5 Lintels, beams, plinth beams, girders, bressumers and cantilevers.

Total 1814.73 Sqm 432.70 432.70 785,233.67 621,006.71 164226.96


3.2.6 Columns, Pillars, Piers, Abutments, Posts and Struts
Total 982.21 Sqm 579.15 579.15 568,846.92 440,356.70 128490.22
3.2.7 Stairs,(excluding landings) except spiral-staircases
Total 102.29 Sqm 579.15 579.15 59,241.25 49,088.75 10152.50
3.2.8 Edges of slabs and breaks in floors and wallsfor
3.2.8.1 Under 20 cm wide
Total 296.91 mtr 159.65 159.65 47,401.68 32,252.49 15149.19
3.3 Steel reinforcement for R.C.C. work including straightening, cutting, bending,
placing in position and binding all complete upto plinth level.

3.3.1 Thermo-Mechanically Treated bars of grade Fe-500D or more..

Total 23685.45 Kg 75.55 75.55 1,789,435.75 1,789,435.75 0.00


Rate Since
Item No. Description of Items Qty. Unit Upto date In previous bill
Agmnt In this bill Previous
3.4 Steel reinforcement for R.C.C. work including straightening, cutting, bending,
placing in position and binding all complete above plinth level.

3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more..


Total 77059.48 Kg 75.55 75.55 5,821,843.71 4,284,906.51 1536937.20

3.6 Providing and laying in position machine batched and machine mixed design
mix M-25 grade cement concrete for reinforced cement concrete work, using
coarse aggregate as well as fine aggregate derived from natural sources
and cement content as per approved design mix, including pumping of concrete
to site of laying but excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended proportions as per IS: 9103
to accelerate, retard setting of concrete, improve workability without impairing
strength and durability as per direction of Engineer-in-charge

3.6.1 All works upto plinth level.


Total 263.19 Cum 8084.30 8084.30 2,127,706.92 2,127,706.92 0.00
3.6.2 All works above plinth level upto floor V level

Total 500.24 cum


Total (A) 32.80 cum 9098.00 6823.50 223,810.80 524,658.92 -300848.12
Total (B) 467.44 cum 9098.00 9098.00 4,252,769.12 2,633,507.08 1619262.04
4.1 Brick work with common burnt clay F.P.S. (non modular) bricks of class
designation 7.5 in foundation and plinth in :
4.1.2 Cement mortar 1:6 (1 cement : 6 coarse sand)
Total 48.03 cum 7879.85 7879.85 378,469.20 378,469.20 0.00
10.1 12 mm Cement Plaster of Mix :
10.1.1 1:4 (1 Cement : 4 coarse sand)
Total 262.00 sqm 231.05 231.05 60,535.10 60,535.10 0.00
Total 18,177,425.11 14,753,609.51 3423815.60
Contractor enhancement. @3.65% (below) -663,476.02 -538,506.75 -124,969.27
Total 17,513,949.09 14,215,102.76 3,298,846.33
Rate Since
Item No. Description of Items Qty. Unit Upto date In previous bill
Agmnt In this bill Previous
E/S-1 Demolishing brick work manually/ by mechanical means including stacking of
serviceable material and disposal of unserviceable material within 50 metres lead
as per direction of Engineer-in-charge.
In Cement Mortar
Total 10.18 cum 1698.45 1273.84 12,967.67 12,967.67 0.00

E/S-2 Add for using extra cement in the items of design mix over and above the
specified cement content therein

Total 189.12 Qtl 0.00 0.00 - - 0.00


E/S-3 Extra for additional height in centering, shuttering where ever required with
adequate bracing, propping etc., including cost of de-shuttering and decentering
at all levels, over a height of 3.5 m, for every additional height of 1 metre or part
thereof (Plan area to be measured).Suspended floors, roofs, landing, beams and
balconies (Plan area to be measured)

Total 178.52 sqm 239.85 239.85 42,818.02 - 42818.02

Total 17,569,734.78 14,228,070.43 3,341,664.35

Assistant Engineer
SPSD-II, Project Division
CPWD, Assam
Based On DSR 2021 Item No 5.35
EIS-II Add for using extra cement in the items of design mix over and
Code above the specified cement content
Description Unit therein
Quantity Rate Amount
Details of cost for 1 Quintal.
MATERIAL:
0367 Portland Cement tonne 0.100 7343.80 734.38
2209 Carriage of Cement tonne 0.100 0.00 0.00
TOTAL 734.38
Add for water charge @ 1 % 7.34
Total 741.72
Add for 12% GST applicable on work contract
by reversible method (multiplying fqactor 104.21
0.1405)
Total 845.94
Add for contractor’s profit and over-heads @ 15% 126.89
Total 972.83
Cost of 1 Quintal 972.83
Say 972.85

Month of Execution - Sep,2023


Analysis Based on DAR'2021, Item Code No.5.11.1
EIS/3 Extra for additional height in centering, shuttering where ever required with
adequate bracing, propping etc. including cost of de-shuttering and decentering at
all levels, over a height of 3.5 m, for every additional height of 1 metre or part
thereof (Plan area to be measured).
(a) Suspended floors, roofs, landing, beams and balconies (Plan area to be measured).
Code Description Unit Quantity Rate Amount
Details of cost for a room of size 6mx
4.8m = 28.8 sqm.
MATERIAL:
7345 Prop 4 m each 0.446 1170.00 522.17
Qty taken for cost using once = 21 x0.85/
40 = 0.4463
Deduct the rate of 3m prop
7343 Adjustable telescopic prop 3 m (2.02 each -0.446 1200.00 -535.56
Qty taken for cost using once = 21x0.85/
40 = 0.4463
Difference of rate between 4m prop and
3m prop
7330 M.S. tube 40 mm dia metre 1.097 280.00 307.02
Bracing MS tube 40mm
7x4.8m = 33.60m
3x6.0m= 18.00m
Total = 51.60m
Qty taken for cost using once = 51.6x0.85/
40= 1.0965
7346 Double coupler each 0.446 55.00 24.55
(40x40)
Qty taken for cost using once = 21 x0.85/
40 =0.4463
9999 Carriage L.S. 65.000 0.00 0.00
LABOUR:
0116 Fitter (grade 1) day 3.000 695.00 2085.00
0114 Beldar day 6.000 494.00 2964.00
9999 Sundries L.S. 130.000 2.25 292.50
TOTAL 5659.68
Add for water charge @ 1 % 56.60
Total 5716.28

Add for 12% GST applicable on work contract by reversible 803.14


method (multiplying fqactor 0.1405)
Total 6519.41
Add for contractor’s profit and over-heads @ 15% 977.91
Total 7497.33
Add 1% Labour Cess 74.97
Cost of 28.8 sqm 7572.30
Cost of 1 sqm 262.93
Say 262.95
PROFORMA FOR SUBMISSION OF BILL

6th R.A Bill


1 Name of work : : Construction of 45 Nos. SO
Accomodation ) for 33rd bn, ITBP at
(Assam) including water supply, sani
internal electrical installation.

2 Agreement No. : 04/CE/EE/PD/2020-21

3 Estimate amount : 5,90,40,588.00

4 Tendered Amount : 5,68,85,607.00

5 Name of Agency: : M/s Khatri Enterprises

6 Time Allowed as per agreement: : 12 (Twelve) months


7 Work in Progress/ Date of Completion : Work in progress
8 Is there any delay in completion whether : Yes
application of extension of Time Received.

9 Amount of Test Check by the AE : Yes

10 Is theoritcal calculation statement submitted : NA


for the item of store issued?

11 Is any balance materials? if so whose : Nil


custody these are?

12 Is Cement Register maintain in proper : Yes


form ?

13 Is materials issued upto date shown in the : Nil


recovery statement?

14 Is approved design & drawings being : Yes


followed?

15 Is dia-wise statement of steel submitted? : Yes

16 How much Extra/Sub Item Executed? : Nil

17 Wheather proper permission obtained to : Nil


execute the exta Subs. Item?

18 Position of abnormally high low rate item : No any


statement
19 Is foundation and other imprtant item : Nil
recorded as per CPWD 23AE

20 Is all item Executed as per CPWD : Yes


Specification?

21 Where from water supplied for the work? : Tube well

22 Is any Departmental T & P issued? : No

23 Completion report if recorded in case of final :


bill

24 Is labour report submitted timely? (Report to : Yes


be enclosed)

25 Is Engineer (Diploma/ Degree) holder : Yes


engaged by the Contractor?

26 Position of Dismentled materilas : Nil

27 Any other point to be brough to the notice of : Nil


the Divisional officer
PROFORMA FOR SUBMISSION OF BILL

6th R.A Bill


Construction of 45 Nos. SO's suites (ASI
Accomodation ) for 33rd bn, ITBP at Karchia Sonapur
(Assam) including water supply, sanitary installation &
internal electrical installation.

04/CE/EE/PD/2020-21

5,90,40,588.00

5,68,85,607.00

M/s Khatri Enterprises

12 (Twelve) months
Work in progress

No any
Assistant Engineer
SPSD-II, Project Division
CPWD, (Assam)
5th R/A Bill C.P.W.A.-26 (Revised)
RUNNING ACCOUNT BILL
(Referred to in Paragraph 10-2-10 and 10-2-12)
(Final Payment must invariably the made on forms Printed on Yellow paper which should not be used for intermediate payment)

(For Contractor : This form provides for (1) advance payment (2) Payment for Measured Works. The form of Account Secured Advance which
has been printed separately should be attached, where necessary).

Division : PD Sub Division: - SPSD-II

Cash Book voucher No. :


M/s Khatri Enterprises
Name of Contractor :
Name of work : Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn,
ITBP at Karchia Sonapur (Assam) including water supply, sanitary
installation & internal electrical installation.
Serial No. of this Bill : 6th R.A bill
No. & Date of the previous bill of this work :
Reference to Agreement No. : 04/CE/EE/PD/2020-21
Date of written Order to commence work:- :
Date of actual completion of work:- : Work in progress

I. ACCOUNT OF WORK EXECUTED


Payment on the basis of actual
Item of works (grouped under "sub-head" and measurements
Unit Rate Remarks
"sub-works" of estimate) Since previous
Up-to-date bill
1 2 3 4 5 6 7
Rs. P. Rs. P. Rs. P.

[Details as per Inner sheet enclosed]


Certified that

1. The work has been done as per CPWD specification as per direction of Engineer in charge

2. No Govt. T&P has been issued to the contractor

3. No Labour complaint has been received so far.

4. Water and electricity has been arranged by the contractor at his own source.

5. Clause 36 has been complied


6. F.N.Labour report has been submitted by the contractor

7) Necessary Mandatory tests have been conducted.

Total value of work done to date(a) Rs. 17569734.78


Deduct value of work shown on previous Bill. 14228070.43
Net value of work since previous bill(F) Rs. 3341664.35

N.B.-- When there are two or more entries in column 6 relating to each Sub-head of estimate they should in case of work the accounts
of which are kept by sub-heads be totalled and the recorded in column 7 for posting the work abstract.
II. Certificate & Signature

1. The measurement on which are based the entires in column 1 to 6 of account I were verified by JE, SPSD-II on ____________ and
are recorded at Computer Measurement Book No.

2. Certified that in addition to and quite a part from the quantities of work actually executed as shown in column 4 of the account I some
work has actually been done in connection with several items and the value of such work after deducting there from proportionate
amount of required advance if any ultimately recoverable on account of the materials used therein) is in no case less than the advance
payment as per item 2 of the memorandum if payments made or proposed to be made for the convenience of the contractor in
anticipation of and subject to the result of detailed measurements which will be made as such as possible.

Dated Signature of Officer (………………………………….


preparing the Bill Assistant Engineer
SPSD-II, Project Division
CPWD, Sonapur Assam

Dated Signature of Dated Signature of Officer (………………………………….


Contractor authorising payment (Rank …………………………..)

* This certificate must be signed by Sub Divisional Officer or Divisional Officer.


* This signature is necessary only when the officer who prepares the bill is not the officer who authorizes the
payment. In case a case the two signature are essential.
III Memorandum of Payments
` P.
1 Total value of work actually measured, as per Acct. 1, col. 5 entry (A) 17569734.78
2 Total up-to-date, advance payment for work not yet measured, as per details give
below : Rs. P.
a) Total as per Previous bill (-) 14228070.43

b) Since previous bill………………………….as per page………..………..of ) (Advance payment) 0.00


M. B. No……………………………………… (D) 3341664.35
3
Total 'up-to-date secured advance on security of materials as per annexure form (26-A) Col. 8 Entry (C) 0.00
….. …… …. ….. …..
4 Total Items (1-2+3) ….. …… …. ….. ….. 3341664.35
5 Deduct amounts withhold-----
Figure for work abstract (a) From Previous bill as per last Running Account bill ….
Rs. P. (b) From this bill Rs. P.
6 Balance i.e. "up-to-date" payments item 4--5) ----(K*)
7. Total amount of payments already made as per entry (K) of last Running
Account
Less Bill Voucher
Mobilisation No…. dated ………..….. forwarded with accounts for CMB
advance
Less Secured Advance advance 0.00
8. Payments now to be made as detailed below :
Rs. P. Rs. P. 3341664.35
a) By recovery of amount creditable
to this work (a)
…..………C.O.T.….……………… 0.00
Total 5 (b) + 8 (a) (G)
b) By recovery amount creditable to
other work or heads of account--- (b)

i) Security Deposit 2.5% 83,542.00


ii) EMD already deposite
Now to be recovered 83,542.00
iii) Income tax Recovery @2% 66,833.00 250626.00
iv) LW Cess deduct @ 1% on 33,417.00
v) CGST @ 1% 33,417.00
vi) SGST @ 1% 33,417.00
3091038.35

Net Payable Amount 3091038.00


Pay Rs. 3091038/-

Dated initials of Disbursing Officer


Executive Engineer
Project Division
CPWD, Guwahati-15
Received Rs.
as per above memorandum on acount of this work.
Received Rs.
Dated ……………………… STAMP

* Witness ………………… Signature of Contractor

Checked Account Clerk Divisional Accountant

Paid by me vide cheque **No. Dated………


Dated initials of person actually making the payment

*This figure should be tested to see that it agree with the total of item 7 & 8.
If the net amount be paid is less than Rs.10 and it cannot be included in cheque the payment should be made in cash this entry being
alteered suitable and the alteration attested by dated initials.

@ Here specify the net amount payable vide item 8 (C)


== The Payee's acknowledgement should be for the amount paid as per item 8 (i.e.a+b+c)
* Payment should be attested by some known person when payee's acknowledgement is given by a mark seal or thumb
impression.

Remarks
This space is reserved for any remarks which the Disbursing Officer of the Divisional Officer may wish to recorded in respect of
the execution of the work check of measurements or the state of contractor's amount.

FOR USE IN DIVISIONAL OFFICE

Checked

Accounts Clerk Divisional Accountant

FOR USE IN ACCOUNTANT GENERAL'S OFFICE

Computer Classification Reviewed

Checked with schedule


of rates / checked with
rates as per agreement

Auditor Superintendent Gazetted Officer


RECOVERY STATEMENT

DIVISION: Project Division, CPWD, Guwahati Sub-division: SPSDII,Sonapur _____________________


Sl No. of Bill 6th R/A Bill
Name of work: Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP at Karchia Sonapur (Assam) including water supply,
sanitary installation & internal electrical installation.

Work Order no: 04/CE/EE/PD/2020-21 Agency: M/s Khatri Enterprises

3341664.35
GROSS TOTAL VALUE OF WORK DONE

1. Security Deposit 2.5% on Gross/Tendered Amount Rs.________ 0.00 i.e. Rs. 83542.00

2. Income Tax 2% on Rs.________0.00 i.e. Rs. 66833.00

3. WWC 1% Rs.________66833.00 i.e. Rs. 33417.00

4. Education Cess 3% on I.T. and S.C. Rs.________0.00 i.e. Rs. 0.00

5. Labour welfare cess 1% on Gross value Rs.________ 0.00 i.e. Rs. 0.00

6. GST 2%
(a) CGST 1% Rs.________ 0.00 i.e. Rs. 33417.00
(b) SGST 1% Rs.________ 0.00 i.e. Rs. 33417.00

7 Forest Royalty (As per Statement) Rs.________ 0.00 i.e. Rs. 0.00
Total recovery Rs. 250626.00

Assistant Engineer
SPSD II,PD
Assam,Guwahati
6th R.A Bill

PART RATE STATEMENT


1 Name of Work: Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn,
ITBP at Karchia Sonapur (Assam) including water supply, sanitary
installation & internal electrical installation.

2 Agency: M/s Khatri Enterprises


6 Date of Start (Stp.): 10.08.2020
7 Date of Completion(Stp.): 09.08.2021
8 Time Allowed: 365 Days
Rate
Sl. No. Description Qty Provisional Per Remarks
Full
Rate

Providing and laying in position machine


batched and machine mixed design mix M-25
grade cement concrete for reinforced cement
concrete work, using coarse aggregate as well
as fine aggregate derived from natural
sources and cement content as per approved
design mix, including pumping of concrete to
3.6
site of laying but excluding the cost of
centering, shuttering, finishing and
reinforcement, including admixtures in
recommended proportions as per IS: 9103 to
accelerate, retard setting of concrete, improve
workability without impairing strength and
durability as per direction of Engineer-in-charge

Curing on Progress.
28 Days Test Report
3.6.2 All works upto plinth level. 32.80 9098.00 6823.50 Cum Awaited

Demolishing brick work manually/ by mechanical


means including stacking of serviceable material
E/S-1 and disposal of unserviceable material within 50
metres lead as per direction of Engineer-in-
charge.

Extra Item not to be


In Cement Mortar 10.18 1698.45 1273.84 cum
Sanctioned Yet

Extra for additional height in centering,


shuttering where ever required with adequate
bracing, propping etc., including cost of de-
shuttering and decentering at all levels, over a
E/S-3
height of 3.5 m, for every additional height of 1
metre or part thereof (Suspended floors, roofs,
landing, beams and balconies (Plan area to be
measured)

Extra Item not to be


Total 178.52 262.95 239.85 Sqm
Sanctioned Yet

Assistant Engineer/SPSD-II Executive Engineer


Theoritical Consumption of Cement Statement
1 Name of Work: Construction of 45 Nos. SO's suites (ASI Accomodation )
for 33rd bn, ITBP at Karchia Sonapur (Assam) including
water supply, sanitary installation & internal electrical
installation.

2 Agency: M/s Khatri Enterprises


3 Agreement No.: 04/CE/EE/PD/2020-21
4 Time Allowed: 12 (Twelve) months
5 Sl. No. of bill 6th RA Bill
Sl. N. Description of item Qty Unit Co. off (In Qtl) Cement Reqd.
Providing and laying in position cement concrete of
2.1 specified grade excluding the cost of centering and
shuttering - All work upto plinth level:
1:5:10 (1 cement : 5 coarse sand (Zone-III) derived from
2.1.2 natural sources : 10 graded stone aggregate 40 mm 86.86 Cum 1.30 (Qtl/cum) 112.92 Qntal
nominal size derived from natural sources )

Providing and laying in position machine batched and


machine mixed design mix M-25 grade cement concrete
for reinforced cement concrete work, using coarse
aggregate as well as fine aggregate derived from
natural sources and cement content as per approved
design mix, including pumping of concrete to site of
3.6
laying but excluding the cost of centering, shuttering,
finishing and reinforcement, including admixtures in
recommended proportions as per IS: 9103 to accelerate,
retard setting of concrete, improve workability without
impairing strength and durability as per direction of
Engineer-in-charge:

3.6.1 All works upto plinth level. 263.19 Cum 4.076 (Qtl/cum) 1,072.76 Qntal
3.6.2 All works above plinth level upto floor V level 500.24
In 3rd R/A bill 34.76 Cum 4.076 (Qtl/cum) 141.68 Qntal
In 3rd R/A bill 141.17 Quantity Excuted By R.M.C
In 4th R/A bill 14.09 Cum 4.076 (Qtl/cum) 57.43 Qntal
In 4th R/A bill 77.49 Quantity Excuted By R.M.C
In 5th R/A bill 10.45 Cum 4.076 (Qtl/cum) 42.59 Qntal
In 5th R/A bill 88.39 Quantity Excuted By R.M.C
In this bill 48.37 Cum 4.076 (Qtl/cum) 197.16 Qntal
In this bill 85.52 Quantity Excuted By R.M.C

Brick work with common burnt clay F.P.S. (non modular)


4.1
bricks of class designation 7.5 in foundation and plinth in :

4.1.2 Cement mortar 1:6 (1 cement : 6 coarse sand) 48.03 cum 0.625 (Qtl/cum) 30.02 Qntal
10.1 12 mm Cement Plaster of Mix :
10.1.1 1:4 (1 Cement : 4 coarse sand) 262.00 sqm 0.055 (Qtl/Sqm) 14.33 Qntal

1,668.89
Variation (+2%) 33.38 Qtl
1,702.27 Qtl
3,405.00 Bags
Variation (-2%) 33.38 Qtl
3,371.62 Bags
Qty brought at site = 2895.00 Bags
Actual Consumption = 2865.00 Bags
Balance = 30.00 Bags

Junior Engineer Assistant Engineer


Sonapur Project Sub Division-II Sonapur Project Sub Division-II
CPWD, Assam CPWD, Assam
Dia Wise Steel Consumption Statement
Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP at Karchia Sonapur (Assam) including water
Name of Work : supply, sanitary installation & internal electrical installation.

Agency: M/s Khatri Enterprises

Agreement No. : 04/CE/EE/PD/2020-21

Date of Start as per agreement 10.08.2020

Stipulated Date of completion : 09.08.2021

Serial No of This Bill : 6th R.A Bill

Thermo Mechanically Treated Bars


Description Page No. Total Unit
8 mm 10 mm 12mm 16 mm 20 mm 25 mm
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete
3.3 upto plinth level.

3.3.1 Thermo-Mechanically Treated bars of grade Fe-500D or more..

upto 5TH R.A Bill 1007.31 4096.32 4178.86 11489.85 899.94 2013.17 23685.45

Total (A) = 1007.31 4096.32 4178.86 11489.85 899.94 2013.17 23685.45 Kgs
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete
3.4 above plinth level.

3.4.1 Thermo-Mechanically Treated bars of grade Fe-500D or more..

in 3rd R.A Bill 1874.10 11739.04 1518.52 7459.19 1742.71 1986.37 26319.93

in 4TH R.A Bill 550.60 6335.48 1101.15 3422.03 1438.34 2059.75 14907.35

in 5TH R.A Bill 457.88 8054.41 1138.35 3400.89 865.30 1613.92 15530.75

In this Bill 711.25 11224.07 1015.92 3556.53 1915.69 1877.99 20301.45

Total (B) = 3593.83 37353.00 4773.94 17838.64 5962.04 7538.03 77059.48 Kgs

TOTAL (A+B) 4601.14 41449.32 8952.80 29328.49 6861.98 9551.20 100744.93 Kgs

Add 3% Wastage 138.03 1243.48 268.58 879.85 205.86 286.54 3022.34 Kgs

GRAND TOTAL 4739.17 42692.80 9221.38 30208.34 7067.84 9837.74 103767.27 Kgs

TOTAL (In M.T) 4.74 42.69 9.22 30.21 7.07 9.84 103.77 M.T

Brought at site (In M.T) 5.57 44.65 9.66 33.37 9.47 10.56 113.28 M.T

Balance at Site 0.83 1.96 0.44 3.16 2.40 0.72 9.51 M.T

Junior Engineer Assistant Engineer


SPSD CPWD SPSD, CPWD
C.P.W.A-26A
ACCOUNTS OF SECURED ADVANCES (Referred to in Paragraphs 10.2.12)
Division: Project Division II Sub-Division: SPSD-II Name of Contractor: M/s Khatri Enterprises
Name of work:- Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP at Karchia Sonapur (Assam) including water supply, sanitary installation &
internal electrical installation.

S.No. of the Bill to which the accounts pertains: 5th RA Bill


Reference to Agreement No : 04/CE/EE/PD/2020-21 Cash Book Voucher No. Dated
Account of secured advances allowed on the security of material brought to site
Reasons for non
Deduct qty. Full Rates as Reference of Divn.
Qty. out *Qty outstanding I/c Reduced rate **Up-to-date clearance of advance
utilised in works assessed by Description of Officers written
standing from qty. brought to site Unit at which Amount of when outstanding for
measured since the Divisional materials orders authorising
previous Bill since previous bill advance is paid advance more than three
previous Bill Officer the advance.
Months.
1 2 3 4 5 6 7 8 9 10
16.19 16.19 0.00 36950.00 TMT Bars MT 26960.00 0.00

0.00
Say 0.00
* Total amount outstanding as per this account © Rs. 0.00
Deduct :- amount outstanding as per entry (C) of Annexure to previous bil Rs. 0.00
Net Amount since Previous bill (in words) 0.00
(-) (E) Rs. 0.00

* Entries relating to each description of materials should be posted thus in column 3 first enter the difference between quantities in column 1 and 2 then show below this entry, the
quantities of any brought to site against which a f
** Entries in column 8 show the money values of the total quantities outstanding as per column 3.
*** Certified (1) that the plus quantities of materials shown in the column 3 of the account have actually been brought by the Contractor at site of the work and the Contractor has not
previously received any advance on these quantities.
(2) that these materials are of an imperishable nature and all required by the contractor for use on the work in connection with the items for which rates for finished work have been
agreed upon .
(3) that a formal agreement in form 31 signed and executed by the Contractor in accordance with the pragraphs 10.2.24 (a) of the CPWD Account Code is recorded in the Divisional
Office
(4) The quality of materilas is as per the specifications.

Dated Signature of Officer preparing the bill (Rank) Dated Signature of Officer authorising payment (Rank)
Assistant Engineer(Civil) Executive Engineer
Sonapur Project Sub Division-II Project Division-II
CPWD, Guwahati-15 CPWD, Guwahati-15.
*** These Certificate must be signed by the Sub-Divisional or Divisional Officer.
# This signature is necessary only when officer who prepares the bill is not the Officeer who authorises the payment.
In such case the two signatures are essential.
0 7/1/2023 TO 7/15/2023
1. Name of Agency: M/s Khatri Enterprises
Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP
2. Name of work : at Karchia Sonapur (Assam) including water supply, sanitary installation &
internal electrical installation.

3. Agreement no:- 04/CE/EE/PD/2020-21

4. Stipulated Date of Start:- 10.08.2020

5. Stipulated Date of Completion:- 09.08.2021

(A) Number of Workers employed (B) Wages Paid (E) No.


Of
Total Amount female
Daily Rate (C) workers (F) The (G)
Sl. NO. Category Male Female Total Paid dg. The (D) Amount of
of Wages Working who accident that Remarks
period overtime wages
Hours have occurred drg. (if any)
been
I II III IV V I II allowed
to

1. Unskilled 105 105 ₹ 550.00 57750 8:00 AM


to 12:00
2. Semiskilled 51 51 ₹ 650.00 33150 Noon &
3. Skilled 32 32 ₹ 700.00 22400 1:00 PM
to 5:00
4. Highly Skilled 25 25 ₹ 800.00 20000 PM

TOTAL : ₹ 133,300.00

Signature of Contractor

Date :
FORTNIGHTLY LABOUR REPORT FOR THE PERIOD FROM 7/16/2023 TO 7/31/2023
1. Name of Agency: M/s Khatri Enterprises
Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP
2. Name of work : at Karchia Sonapur (Assam) including water supply, sanitary installation &
internal electrical installation.

3. Agreement no:- 04/CE/EE/PD/2020-21

4. Stipulated Date of Start:- 10.08.2020

5. Stipulated Date of Completion:- 09.08.2021


(E) No.
(A) Number of Workers employed (B) Wages Paid Of
female
Total Amount (C) workers (F) The (G)
Daily Rate (D) Amount of
Sl. NO. Category Male Female Total Paid dg. The Working who accident that Remarks
of Wages overtime wages
period Hours have occurred drg. (if any)
been
I II III IV V I II allowed
to
1. Unskilled 98 98 ₹ 550.00 53900 8:00 AM
to 12:00
2. Semiskilled 65 65 ₹ 650.00 42250 Noon &
3. Skilled 40 40 ₹ 700.00 28000 1:00 PM
to 5:00
4. Highly Skilled 26 26 ₹ 800.00 20800 PM

TOTAL : ₹ 144,950.00

Signature of Contractor

Date :
FORTNIGHTLY LABOUR REPORT FOR THE PERIOD FROM 8/1/2023 TO 8/15/2023
1. Name of Agency: M/s Khatri Enterprises
Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP
2. Name of work : at Karchia Sonapur (Assam) including water supply, sanitary installation &
internal electrical installation.

3. Agreement no:- 04/CE/EE/PD/2020-21

4. Stipulated Date of Start:- 10.08.2020

5. Stipulated Date of Completion:- 09.08.2021

(A) Number of Workers employed (B) Wages Paid (E) No.


Of
female
Total Amount
Daily Rate (C) workers (F) The (G)
Sl. NO. Category Male Female Total Paid dg. The (D) Amount of
of Wages Working who accident that Remarks
period overtime wages
Hours have occurred drg. (if any)
been
I II III IV V I II allowed
to

1. Unskilled 112 112 ₹ 550.00 61600 8:00 AM


to 12:00
2. Semiskilled 84 84 ₹ 650.00 54600 Noon &
3. Skilled 71 71 ₹ 700.00 49700 1:00 PM
to 5:00
4. Highly Skilled 36 36 ₹ 800.00 28800 PM

TOTAL : ₹ 194,700.00

Signature of Contractor

Date :
FORTNIGHTLY LABOUR REPORT FOR THE PERIOD FROM 8/16/2023 TO 8/25/2023
1. Name of Agency: M/s Khatri Enterprises
Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP
2. Name of work : at Karchia Sonapur (Assam) including water supply, sanitary installation &
internal electrical installation.

3. Agreement no:- 04/CE/EE/PD/2020-21

4. Stipulated Date of Start:- 10.08.2020

5. Stipulated Date of Completion:- 09.08.2021


(E) No.
(A) Number of Workers employed (B) Wages Paid Of
female
Total Amount (C) workers (F) The (G)
Daily Rate (D) Amount of
Sl. NO. Category Male Female Total Paid dg. The Working who accident that Remarks
of Wages overtime wages
period Hours have occurred drg. (if any)
been
allowed
I II III IV V I II to
1. Unskilled 84 84 ₹ 550.00 46200 8:00 AM
to 12:00
2. Semiskilled 60 60 ₹ 650.00 39000 Noon &
3. Skilled 45 45 ₹ 700.00 31500 1:00 PM
to 5:00
4. Highly Skilled 24 24 ₹ 800.00 19200 PM

TOTAL : ₹ 135,900.00

Signature of Contractor

Date :
TEST CHECK STATEMENT
1 Name of Work :- Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP at
Karchia Sonapur (Assam) including water supply, sanitary installation & internal
electrical installation.

2 Agreement No. :- 04/CE/EE/PD/2020-21


3 Agency :- M/s Khatri Enterprises
4 Division :- PD
5 Sub-Division :- SPSD-II
6 Serial No. of Bill :- 6th R.A Bill

Ref. of Amount of
SL
No.
Description of Items MB & Quantity Amount of AE Test Check EE Test
page Check

Upto 5th R.A Bill Rs. 6,746,977.00


In This Bill Rs. 2,145,755.00
Upto Date Total Rs. 8,892,732.00

Amount in this bill ` 3,341,664.35


Gross amount of Work ` 17,569,734.78

50.61

Assistant Engineer
SPSD-II, Project Division
CPWD, Assam
r 33rd bn, ITBP at
stallation & internal

Remarks

Engineer
ect Division
Assam
MANDATORY TEST
6th R.A Bill
1 Name of Work: Construction of 45 Nos. SO's suites (ASI Accomodation ) for 33rd bn, ITBP at Karchia
Sonapur (Assam) including water supply, sanitary installation & internal electrical
installation.

2 Agency: M/s Khatri Enterprises


3 Agreement No.: 04/CE/EE/PD/2020-21
4 Estimated Cost: Rs.59,040,588.00
5 Tender Amount: 5,68,85,607.00
6 Date of Start (Stp.): 10.08.2020
Date of
7 09.08.2021
Completion(Stp.):
8 Time Allowed: 365 Days

Remarks/
Frequency as per No. of tests No of tests
Sl. No. Description of item Qty Upto date Qty Reasons for
specification required. actually done
shortfall, if any.

5 nos Report
Awaited ( Work
suspended
1 Water Test 22 Months 3 Months 8 Nos 8 Nos 8 Nos 14/7/21-7/3/22
17/3/22-5/10/22
12/10/22-
14/3/23)
2 Steel Test
8mm dia 5.57 tonne 25 tonnes 1 No. 1 No. 4 No. Satisfactory
10mm dia 44.65 tonne 35 tonnes 2 No. 2 No. 5 No. Satisfactory
12 mm dia 9.66 tonne 35 tonnes 2 No. 2 No. 4 No. Satisfactory
16mm dia 33.37 tonne 35 tonnes 2 No. 2 No. 5 No. Satisfactory
20mm dia 9.47 tonne 35 tonnes 2 No. 2 No. 4 No. Satisfactory
25mm dia 10.56 tonne 45 tonnes 1 Nos. 1 Nos. 3 No. Satisfactory
1Nos test Report
3 Cement Test 2895.00 Bags 1000 Bags 3 Nos. 3 Nos. 6 Nos. Awaited
1Nos lab test
4 Cube Test of RCC M-25 763.43 Cum 50 Cum 14 Nos. 14 Nos. 31 Nos. Report Awaited
1Nos test Report
5 Slump Test M-25 763.43 Cum 50 Cum 14 Nos. 14 Nos. 54 Nos. Awaited
8 Brick test 24000.00 Nos. 50000 Nos. 1 Nos. 1 Nos. 1 Nos. Satisfactory
6 Coarse Sand
i) Bulking Test 358.11 Cum 20 Cum 18 Nos. 14 Nos. 17 Nos. Satisfactory
ii) Silt Content Test. 358.11 Cum 20 Cum 18 Nos. 14 Nos. 17 Nos. Satisfactory
iii) Particle Size Distribution. 358.11 Cum 40 Cum 9 Nos. 7 Nos. 8 Nos. Satisfactory

7 Stone Aggregate
(i) 40 mm stone aggregate 56.46 Cum
(a) Particle Size Distribution 56.46 Cum 40 cum 2 Nos. 2 Nos. 3 Nos. Satisfactory
(b) Deleterious Material 56.46 Cum 40 cum 2 Nos. 2 Nos, 3 Nos. Satisfactory
(ii) 20 mm stone aggregate 379.69 Cum
(a) Particle Size Distribution 379.69 Cum 40 cum 10 Nos. 10 Nos. 12 Nos. Satisfactory
(b) Deleterious Material 379.69 Cum 40 cum 10 Nos. 10 Nos, 12 Nos. Satisfactory
(iii) 10 mm stone aggregate 176.67 Cum
(a) Particle Size Distribution 176.67 Cum 40 cum 5 Nos. 5 Nos. 7 Nos. Satisfactory
(b) Deleterious Material 176.67 Cum 40 cum 5 Nos. 5 Nos, 7 Nos. Satisfactory

Junior Engineer Assistant Engineer


SPSD-II, Project Division SPSD-II, Project Division
CPWD, (Assam) CPWD, (Assam)
FOREST
5th R.A B
1 Name of Work: #REF!

2 Agency: M/s Khatri Enterprises


3 Agreement No.: 04/CE/EE/PD/2020-21
4 Estimated Cost: 5,90,40,588.00
5 Tender Amount: 56,885,607.00
10.08.2020
6 Date of Start (Stp.):

09.08.2021
7 Date of Completion(Stp.):

8 Time Allowed: 365 Days


Coarse Sand Fine Sand
Quantity Coeff of Coeff of
Item No. Sub-Head and Item of works Unit exeacuted in consumption Quantity
consumption
this bill consumed
(Cum Per (Cum Per
(Cum)
Unit) Unit)

2.1 Providing and laying position


cement concrete of specified grade
excluding the cost of centering and
shuttering - All work up to plinth
level:
2.1.2 1:5:10 ( 1 cement : 5 course sand :
10 graded stone aggregate 40 mm cum 86.86 0.47 40.82
nominal size)

3.6 Providing and laying in position


machine batched and machine
mixed design mix M-25 …. @ 330
kg/cum. Excess or less cement
used as peer design mix is payable
or recoverable separately.
3.6.1 All work up to plinth level cum 263.19 0.425 111.86
3.6.2 All work above plinth level upto floor cum 500.24 0.425 212.60

4.1 Brick wark with common burnt clay


F.P.S. (non modular ) bricks of
class designation 7.5 in foundation
and plinth in.

4.1.2 cement mortar 1:6 (1 cement : 6


coarse sand ) cum 48.03 0.25 12.01

10.1 12 mm Cement Plaster of Mix :


10.1.1 1:4 (1 cement : 4 coarse sand ) sqm 262.00 0.144 37.73
Total = 415.02

Contractor Junior Engineer


FOREST PRODUCT
5th R.A Bill

Fine Sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate Bricks


Coeff of Coeff of Coeff of Coeff of Quantity consumed
Quantity Quantity Quantity Quantity
consumption consumption consumption consumption (Nos.)
consumed consumed consumed consumed
(Cum Per (Cum Per (Cum Per (Cum Per
(Cum) (Cum) (Cum) (Cum)
Unit) Unit) Unit) Unit)

0.65 56.46 0.24 20.85

0.57 150.02 0.28 73.69


0.57 285.14 0.28 140.07

450.00 21614.00
56.46 456.01 213.76 21614.00

nior Engineer Assistant Engineer