PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

PEJABAT TANAH DAN JAJAHAN


PASIR PUTEH

LAPORAN KEMAJUAN KERJA


MEMBINA JALAN KE TAPAK
WETLAND TOK BALI

JAJAHAN : PASIR PUTEH


PARLIMEN : PASIR PUTEH
DUN : SEMERAK
DAERAH PENGGAWA : SEMERAK
NAMA KAWASAN : WETLAND TOK BALI

1
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

ISI KANDUNGAN
1. MAKLUMAT PROJEK...........................................................................................................................1
2. PETA LOKASI........................................................................................................................................2
a) GAMBAR SATELIT TAPAK PROJEK...................................................................................................2
b) LAKARAN JALAN UTAMA................................................................................................................3
c) LUKISAN SKEMATIK JALAN UTAMA................................................................................................4
d) PETA JAJAHAN PASIR PUTEH..........................................................................................................5
e) KEMAJUAN PEMBUKAAN JALAN....................................................................................................6
3. SKOP KERJA.........................................................................................................................................7
a) Membersih / Mencuci Tapak..........................................................................................................7
b) Kerja-kerja Pengukuran Jalan.........................................................................................................9
c) Penandaan Aras dan Point Jalan Baharu......................................................................................10
d) Pengambilan Tanah di Jeram Pasu...............................................................................................11
e) Kerja-kerja Timbunan Tanah.........................................................................................................12
f) Membina Jalan Baru Sepanjang 15km (keseluruhan), Kelebaran 20 Kaki (6.096m) Berasaskan 2
Lorong 2 Hala........................................................................................................................................13
4. CARTA ORGANISASI PEJABAT TANAH DAN JAJAHAN PASIR PUTEH................................................14
a) CARTA ORGANISASI PENTADBIRAN PROJEK................................................................................14
b) CARTA ORGANISASI KUMPULAN MYSTEP....................................................................................15
5. LAPORAN KEMAJUAN.......................................................................................................................18
a) MENCUCI TAPAK...........................................................................................................................19
i. Laluan Pasir Puteh – Tok Bali...............................................................................................19
ii. Gong Kulim..............................................................................................................................21
iii. Beris Lalang.............................................................................................................................22
b) KERJA-KERJA MENGUKUR DAN PENANDAAN..............................................................................23
i. Laluan Pasir Puteh – Tok Bali...............................................................................................23
ii. Gong Kulim..............................................................................................................................25
iii. Beris Lalang.............................................................................................................................26
c) PENIMBUNAN TANAH...................................................................................................................28
i. Jumlah Perjalanan dan Kuantiti Tanah................................................................................31
d) PENGAMBILAN TANAH DI JERAM PASU.......................................................................................32
6. ANGGARAN PERATUSAN KEMAJUAN KERJA....................................................................................33
a) Pembersihan Tapak....................................................................................................................33

i
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

a. Penimbunan Tanah....................................................................................................................33

ii
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

1. MAKLUMAT PROJEK

JAJAHAN : PASIR PUTEH

DAERAH : SEMERAK

MUKIM : SEMERAK DAN GONG KULIM

KAWASAN : JALAN WETLAND TOK BALI

JENIS KERJA : PEMBUKAAN JALAN BAHARU

PAJANG : 15 Kilometer (KM)

LEBAR : 20 kaki (6.096m)

TEMPOH PROJEK :

TARIKH MULA : 26 Mac 2023

JANGKAAN SELESAI :

KOS PROJEK :

1
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

2. PETA LOKASI
a) GAMBAR SATELIT TAPAK PROJEK

2
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

Gambaran dari Satelit Tapak Projek

b) LAKARAN JALAN UTAMA

3
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

Cadangan Laluan Utama Pembinaan Jalan Raya

c) LUKISAN SKEMATIK JALAN UTAMA

4
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

Lukisan Skematik Jalan Utama

d) PETA JAJAHAN PASIR PUTEH

KAWASAN TAPAK PROJEK

Peta Jajahan Pasir Puteh

5
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

e) KEMAJUAN PEMBUKAAN JALAN

Petunjuk:-

Cadangan Jalan Utama

Jalan Tanah Sediada

Kawasan yang telah dibersihkan

Kemajuan Pembukaan Jalan

6
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

3. SKOP KERJA

a) Membersih / Mencuci Tapak

7
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

b) Kerja-kerja Pengukuran Jalan

8
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

c) Penandaan Aras dan Point Jalan Baharu

9
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

d) Pengambilan Tanah di Jeram Pasu

10
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

e) Kerja-kerja Timbunan Tanah

11
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

f) Membina Jalan Baru Sepanjang 15km (keseluruhan), Kelebaran 20 Kaki


(6.096m) Berasaskan 2 Lorong 2 Hala.

12
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

4. CARTA ORGANISASI PEJABAT TANAH DAN JAJAHAN


PASIR PUTEH

a) CARTA ORGANISASI PENTADBIRAN PROJEK

TIMBALAN KETUA JAJAHAN


MOHD KAMARULZAMAN BIN AB WAHAB

KPKJ PEMBANGUNAN
MOHD ARPI BIN ARIFIN

PENOLONG JURUTERA (KUP)


NORMALA BINTI AB GHANII

PENOLONG JURUTERA
MOHD HAPIZA BIN MOHD SALLEH

PENOLONG JURUTERA
MOHD AFIQ B. AZMAN

13
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

b) CARTA ORGANISASI KUMPULAN MYSTEP


KUMPULAN 1 (MYSTEP)

SHAHID BIN SABRY


Penolong Jurutera

MOHAMAD HAFIZ NAZRUL


BIN NAWI
Pembantu Kemahiran

MOHAMMAD SHAHEEDUL
MOHD ROSLI BIN MAT ISA
MUSLIM BIN OTHMAN
Pembantu Awam
Pembantu Awam

MOHAMAD SYAFI BIN


AHFAMIN BIN AHMAD
HAMZAH
Pembantu Awam
Pembantu Awam
14
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

KUMPULAN 2 (MYSTEP)

MUHAMMAD AMIRUL AIMAN


BIN MOHD AMRI
Penolong Jurutera

WAN MOHAMAD ALIFF HAIQAL


BIN WAN ROSLEE
Pembantu Kemahiran

RAJA AMIRUL ASHRAF BIN MOHAMMAD DANISH ADAM BIN


RAJA SELAFUDIN MOHAMMAD ZULKARNAIN
Pembantu Awam Pembantu Awam

MOHAMMAD SHAFIQ BIN MOHAMAD SYAZWAN BIN


MAHADI MOHAMAD YUSOFF
Pembantu Awam Pembantu Awam

15
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

KUMPULAN 3 (MYSTEP)

MOHAMAD HAFIZUDDIN BIN


MOHD ROSDI
Penolong Jurutera

MOHAMAD ROHAIZAD BIN


MOHD KHALIL
Pembantu Awam

MOHAMAD KHAIRUL ISRAFF


BIN MOHD ARZORIE
Pembantu Awam

MOHD SYAHRIL BIN MUSTAFA


Pembantu Awam

MUHAMMAD NOR FIRDAUS BIN


MUHAMMAD
Pembantu Awam

16
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

5. LAPORAN KEMAJUAN

TARIKH MULA : 30 Mac 2023

Persekitaran awal permulaan projek

JALAN TANAH SEDIADA : 300 meter


KOORDINAT MULA : 5.866664, 102.440039

17
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

a) MENCUCI TAPAK

i. Laluan Pasir Puteh – Tok Bali

TARIKH MULA : 30 Mac 2023

KOORDINAT MULA : 5.866664, 102.440039

KOORDINAT AKHIR : 5.885275, 102.431467

JARAK : 2.29KM

ii. Gong Kulim

TARIKH MULA : 9 Mei 2023

KOORDINAT MULA : 5.881064, 102.421169

KOORDINAT AKHIR : 5.885275, 102.431467

JARAK :1.31KM

18
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

iii. Beris Lalang

TARIKH MULA : 9 Mei 2023

KOORDINAT MULA : 5.895754, 102.454629

KOORDINAT AKHIR : 5.891975, 102.446944 (Terkini)

JARAK :

19
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

b) KERJA-KERJA MENGUKUR DAN PENANDAAN

i. Laluan Pasir Puteh – Tok Bali

TARIKH MULA : 2 April 2023

KOORDINAT MULA : 5.866664, 102.440039

KOORDINAT AKHIR : 5.885275, 102.431467

JARAK : 2.29KM

Kerja-kerja Penandaan Jalan

20
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

Gambar selepas mencuci jalan

21
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

ii. Gong Kulim

TARIKH MULA : 9 Mei 2023

KOORDINAT MULA : 5.881064, 102.421169

KOORDINAT AKHIR : 5.885275, 102.431467

JARAK : 1.3KM

22
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

iii. Beris Lalang

TARIKH MULA : 9 Mei 2023

KOORDINAT MULA : 5.895754, 102.454629

KOORDINAT AKHIR : 5.885275, 102.431467

JARAK : 2.83KM

23
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

24
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

c) PENIMBUNAN TANAH

TARIKH MULA : 17 Mei 2023

TARIKH LAPORAN : 18 Mei 2023

KOORDINAT MULA : 5.866664, 102.440039

JENIS BAHAN : TANAH BUKIT

JENIS JENTERA : LORI 10 TAYAR, EXCAVATOR

Proses Penimbunan T

25
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

26
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

27
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

i. Jumlah Perjalanan dan Kuantiti Tanah

BIL TARIKH HARI JENIS PENGANGKUTAN BILANGAN JUMLAH PERJALANAN (TRIP) MUATAN TANAH/LORI (m3) JUMLAH MUATAN TANAH (m3)

1 17/5/2023 RABU LORI TAYAR 10 13 56 12.6 705.6

2 18/5/2023 KHAMIS LORI TAYAR 10 5 31 12.6 390.6

3 20/5/2023 SABTU LORI TAYAR 10 19 137 12.6 1726.2

4 22/5/2023 ISNIN LORI TAYAR 10 17 96 12.6 1209.6

5 23/5/2023 SELASA LORI TAYAR 10 8 34 12.6 428.4

28
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

d) PENGAMBILAN TANAH DI JERAM PASU

TARIKH LAPORAN : 18 Mei 2023

KOORDINAT MULA : 5.798665, 102.338753

KAWASAN : Jeram Pasu

HAK MILIK : Kerajaan

Penggalian Bukit

Tanah Diangkut dengan Lori 6 Tan

29
PROJEK MEMBINA JALAN KE TAPAK WETLAND TOK BALI

6. ANGGARAN PERATUSAN KEMAJUAN KERJA

a) Pembersihan Tapak

Jarak : 4.9km

Jarak Keseluruhan : 15km

Peratusan Kerja : 32.66%

Peratusan Kemajuan Kerja

33%

67%

Jarak Keseluruhan Jarak siap dibersihkan

a. Penimbunan Tanah

Jarak : 0.538km (Kemaskini pada 22 Mei 2023)

Jarak Keseluruhan : 15km

Peratusan Kerja Siap : 3.58%

Peratusan Kemajuan Kerja


4%

96%

Jarak Keseluruhan Jarak Ditambun