ID Task Mode Task Name Duration Start Finish September 1 November 1 January 1 March 1 May 1 July 1 September 1

8/20 9/17 10/15 11/12 12/10 1/7 2/4 3/3 3/31 4/28 5/26 6/23 7/21 8/18 9/15
1 Kick off Meeting 1 day Sat 10/14/23 Sat 10/14/23
2 Block 2 221 days Fri 11/3/23 Fri 9/6/24
3 Substructure
4 Basement floor
5 Excavation 7 days Fri 11/3/23 Mon 11/13/23
6 PCC 8 days Tue 11/7/23 Thu 11/16/23
7 Raft steel barbending 16 days Wed 11/8/23 Wed 11/29/23
8 Column &footing 16 days Fri 11/10/23 Fri 12/1/23
9 Barbending
Raft Shuttering 19 days Fri 11/10/23 Wed 12/6/23
10 Raft concreting 17 days Tue 11/14/23 Wed 12/6/23
11 Footing shuttering 17 days Wed 11/15/23 Thu 12/7/23
12 Footing Concreting 17 days Thu 11/16/23 Fri 12/8/23
13 Retaining wall Barbending 20 days Fri 11/17/23 Thu 12/14/23
14 Retaining wall shuttering 21 days Mon 11/20/23 Mon 12/18/23
15 Retaining wall concreting 23 days Wed 11/22/23 Fri 12/22/23
16 Column barbending 20 days Mon 11/20/23 Fri 12/15/23
17 Column Shuttering 22 days Tue 11/21/23 Wed 12/20/23
18 Column concreting 22 days Wed 11/22/23 Thu 12/21/23
19 Basement floor Slab 27 days Thu 11/23/23 Fri 12/29/23
20 Shuttering
Basement floor slab barbending
31 days Fri 11/24/23 Fri 1/5/24
21 Basement floor slab concreting
27 days Wed 12/6/23 Thu 1/11/24
22 Ground floor
23 Column barbending 19 days Tue 12/12/23 Fri 1/5/24
24 Column Shuttering 18 days Thu 12/14/23 Mon 1/8/24
25 Column Concreting 21 days Wed 12/13/23 Wed 1/10/24
26 Slab Shuttering 26 days Wed 12/20/23 Wed 1/24/24
27 Slab Barbending 31 days Fri 12/22/23 Fri 2/2/24
28 Slab Concreting 31 days Fri 12/29/23 Fri 2/9/24
29 First floor
30 Column barbending 19 days Tue 1/2/24 Fri 1/26/24
31 Column Shuttering 18 days Thu 1/4/24 Mon 1/29/24
32 Column Concreting 21 days Wed 1/3/24 Wed 1/31/24
33 Slab Shuttering 26 days Wed 1/10/24 Wed 2/14/24
34 Slab Barbending 31 days Fri 1/12/24 Fri 2/23/24
35 Slab Concreting 31 days Fri 1/19/24 Fri 3/1/24
36 Second floor
37 Column barbending 19 days Tue 1/23/24 Fri 2/16/24
38 Column Shuttering 18 days Thu 1/25/24 Mon 2/19/24
39 Column Concreting 26 days Wed 1/24/24 Wed 2/28/24
40 Slab Shuttering 26 days Wed 1/31/24 Wed 3/6/24
41 Slab Barbending 31 days Fri 2/2/24 Fri 3/15/24
42 Slab Concreting 31 days Tue 2/13/24 Tue 3/26/24
Task Project Summary Manual Task Start-only Deadline

Project: casa jbc schedule Split Inactive Task Duration-only Finish-only Progress

Date: Tue 10/31/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Mode Task Name Duration Start Finish September 1 November 1 January 1 March 1 May 1 July 1 September 1
8/20 9/17 10/15 11/12 12/10 1/7 2/4 3/3 3/31 4/28 5/26 6/23 7/21 8/18 9/15
43 Third floor
44 Column barbending 19 days Thu 2/15/24 Tue 3/12/24
45 Column Shuttering 18 days Thu 2/15/24 Mon 3/11/24
46 Column Concreting 26 days Fri 2/16/24 Fri 3/22/24
47 Slab Shuttering 26 days Wed 2/21/24 Wed 3/27/24
48 Slab Barbending 31 days Tue 2/27/24 Tue 4/9/24
49 Slab Concreting 31 days Wed 3/6/24 Wed 4/17/24
50 Fourth floor
51 Column barbending 19 days Wed 3/6/24 Mon 4/1/24
52 Column Shuttering 18 days Fri 3/8/24 Tue 4/2/24
53 Column Concreting 26 days Tue 3/12/24 Tue 4/16/24
54 Slab Shuttering 26 days Fri 3/15/24 Fri 4/19/24
55 Slab Barbending 31 days Thu 3/21/24 Thu 5/2/24
56 Slab Concreting 31 days Thu 3/28/24 Thu 5/9/24
57 Fifth floor
58 Column barbending 19 days Fri 3/29/24 Wed 4/24/24
59 Column Shuttering 18 days Tue 4/2/24 Thu 4/25/24
60 Column Concreting 26 days Wed 4/3/24 Wed 5/8/24
61 Slab Shuttering 26 days Wed 4/10/24 Wed 5/15/24
62 Slab Barbending 31 days Mon 4/15/24 Mon 5/27/24
63 Slab Concreting 31 days Wed 4/17/24 Wed 5/29/24
64 Headroom 35 days Fri 4/19/24 Thu 6/6/24
65 Masonary work
66 Ground floor 47 days Wed 1/10/24 Thu 3/14/24
67 First floor 44 days Fri 2/2/24 Wed 4/3/24
68 Second floor 45 days Mon 2/26/24 Fri 4/26/24
69 Third floor 51 days Tue 3/19/24 Tue 5/28/24
70 Fourth floor 51 days Tue 4/9/24 Tue 6/18/24
71 Fifth floor 49 days Wed 5/1/24 Mon 7/8/24
72 Headroom and parapet 47 days Mon 5/13/24 Tue 7/16/24
73 wall
Internal plastering work
74 Basement floor 44 days Fri 1/26/24 Wed 3/27/24
75 Ground floor 44 days Fri 1/26/24 Wed 3/27/24
76 First floor 45 days Mon 2/19/24 Fri 4/19/24
77 Second floor 39 days Tue 3/19/24 Fri 5/10/24
78 Third floor 36 days Fri 5/3/24 Fri 6/21/24
79 Fourth floor 36 days Fri 5/17/24 Fri 7/5/24
80 Fifth floor 38 days Wed 6/5/24 Fri 7/26/24
81 External Plastering
82 West side - core D 9 days Tue 5/21/24 Fri 5/31/24
83 North side - core D 16 days Mon 5/27/24 Mon 6/17/24
84 South side - Core D 23 days Wed 6/5/24 Fri 7/5/24
Task Project Summary Manual Task Start-only Deadline

Project: casa jbc schedule Split Inactive Task Duration-only Finish-only Progress

Date: Tue 10/31/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Mode Task Name Duration Start Finish September 1 November 1 January 1 March 1 May 1 July 1 September 1
8/20 9/17 10/15 11/12 12/10 1/7 2/4 3/3 3/31 4/28 5/26 6/23 7/21 8/18 9/15
85 East side -core D 18 days Fri 6/14/24 Tue 7/9/24
86 West side 25 days Thu 6/27/24 Wed 7/31/24
87 North side 21 days Tue 7/9/24 Tue 8/6/24
88 South side 20 days Thu 7/18/24 Wed 8/14/24
89 East side 25 days Thu 7/25/24 Wed 8/28/24
90 Hand over 13 days Wed 8/21/24 Fri 9/6/24

Task Project Summary Manual Task Start-only Deadline

Project: casa jbc schedule Split Inactive Task Duration-only Finish-only Progress

Date: Tue 10/31/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone