PRE-ENERGIZATION CHECK LIST

Project & Tender No.:

Client/Owner : NEOM

Owner's Engineer :

Contractor:
Status
Sl.No. Description of Check Remarks
Yes No

1 Whether all the Installations completed as per approved drawings.

Whether all the Site Tests Completed & SAT (Site Acceptance Test) Reports
2
available?
Are there any changes w.r.to IFC drawings? If so, Red mark-up drawings
3
available?
4 Whether Fire Alarm System is in operation & approved.
Whether approved Fire Alarm Layout showing the zone indications with
5
Operation manual available at site?

6 Whether earthing is done for all the equipments as per approved drawing?

Whether Single Line Diagram is available & provided at transformer, switchgear


7
room/in DBs?
Whether Danger and/or High Voltage sign boards are placed on all the
8
panels?
9 Whether approved relay settings available at site?

10 Whether all the Cables are properly supported in trenches and pull pits?

Whether all the cables are protected from touching edges of chequer
11
plate/ trench cover slabs?
Whether all the unused cable entry holes/sleeves (inside trenches/pull
12 pits, earthing/lighning protection sleeves etc.) closed properly with fire
rated foam/approved mortar?
13 Whether all the earthing pits are labelled?
Whether the Fire extinguishers are placed as per approved Fire Alarm &
14
Fire Fighting Layout drawing?
15 Whether all the equipment name plates are provided?
16 Whether all the Room name plates are provided?
Whether Emergency Exit/escape routes are identified/marked and
17
emergency escape plan is placed in each room?
Whether the Cable trenches inside and outside are properly covered &
18
sealed?
Whether operating/tools are avialable & fixed on the board in 13.8 KV
19
switchgear room?

20 Whether LOTO Station is ready with necessary Tags & LOTO Box?

Whether approved method statements of installation & procedures testing


21
are avilable with Risk Assessment?

Page 1 of 2 Pre -Energization Check List


Status
Sl.No. Description of Check Remarks
Yes No
Whether Pre-energization HSE Inspection of DPC is completed & all the
22
high risk punch list points are closed?
Whether Punch list (Electrical, Civil , Mechanical ) is made & is mutually
23
agreed ?

24 Testoing and precommissioning reports available?

DESIGNATION SIGNATURE
CONTRACTOR SITE ENGINEER
CONTRACTOR QC INSPECTOR

Page 2 of 2 Pre -Energization Check List