This risk assessment document summarizes the hazards, risks, and control measures for working at heights at an industrial construction site. It identifies possible risks such as falls, slips, trips, and injuries from falling objects. Existing control measures include using ladders, scaffolding, harnesses, and cleaning work areas. Additional controls recommended are using life lines, ensuring skilled workers construct scaffolding, and avoiding overloading scaffolding. The residual risk level for most activities is low after controls are implemented.
This risk assessment document summarizes the hazards, risks, and control measures for working at heights at an industrial construction site. It identifies possible risks such as falls, slips, trips, and injuries from falling objects. Existing control measures include using ladders, scaffolding, harnesses, and cleaning work areas. Additional controls recommended are using life lines, ensuring skilled workers construct scaffolding, and avoiding overloading scaffolding. The residual risk level for most activities is low after controls are implemented.
This risk assessment document summarizes the hazards, risks, and control measures for working at heights at an industrial construction site. It identifies possible risks such as falls, slips, trips, and injuries from falling objects. Existing control measures include using ladders, scaffolding, harnesses, and cleaning work areas. Additional controls recommended are using life lines, ensuring skilled workers construct scaffolding, and avoiding overloading scaffolding. The residual risk level for most activities is low after controls are implemented.
Cluster : Name of the Job Site :Indofil Industries Ltd, Larox Building Extensition Date : 18.02.2022 Working at height Sl. Hazard / Probabili Severit Risk / Additional Possible Out Residu N Activity Environment Existing Control Measure ty Rating y Impact Control Action By come al Risk o Aspect Rating Level Measures JSA RA Improper Falls/ slips/ trips Provision of access either by Ladder / access Scaffold tower with platform / ramp / stair tower / stair case / steps. Site 3 2 M L Maintaining the steps / ramp free of loose Engineer gravel, sand etc. Provide proper platform as per standard. Non use of Fall of person, Use of full body harness is must. Hook at 1. Working P.P.E. Head injury, cut Use of safety helmet, safety shoes is must. rigged support at Site or trip injury 3 2 M / use of life L height Engineer line wherever possible Slippery Slips & Trips / Loading crew are instructed to clean the Surface / Hit Injury approach every day. Site 4 3 M L Projecting Engineer Materials Collapse of Injury to Scaffold to be prepared as per standard. scaffold workmen Scaffold to be prepared by experienced Ensure skilled / trained workers are used for the Site 4 4 H L activity. Engineer Avoid excessive load / materials on the scaffolding person only. ___________________ PM / Section Head HSEO