PROJECT: SUPPLY & INSTALLATION OF FDAS


LOCATION: BGRY EMMANUEL 1 Attention To: Mr. Lloyd Lara Date: October 19,2023

MATERIALS
ITEM NO. DESCRIPTION QTY UNIT
Unit Cost Total Cost TOTAL

I.PRELIMINARIES

1 Mobilization/Demobilization 1 lot 35,000.00

2 Design Plan and BFP Permit Fees 1 lot 20,000./00


II. DEVICES
3 Smoke Detector Pc 2,150.00 34,400.00 34,400.00
16 s
4 FACP 4 zones (conventional FDAS Panel) 1 se 18,000.00 18,000.00 18,000.00
t
5 Manual Push Station 7 pc 1,500.00 10,500.00 10,500.00

6 Fire Alarm Bell 3 pc 2,500.00 7,500.00 7,500.00

7 Siren w/strobe light 3 Pc 1,000.00 3,000.00 3,000.00

7
1 lot 15,200.00 15,200.00 15,200.00
III. ROUGHING INS
9 TF wire#16 (Philflex) 2 rol 3,200 6,400.00 6,400.00
l
IV. PVC FITTINGS AND 1 lot 50,000.00 50,000.00 50,000.00
CONSUMABLES
V. LABOR AND INSTALLATION 1 lot 45,000.00

TOTAL
AMOUNT ₱ 245,000

Scope of Works:

1 Design plan with sign and Permits for BFP Requirements (including fees)

2 Supply and Install FDAS devices.

3 Termination from devices to FACP

4 Roughing Ins, Cable pulling.

5 Test and Commissioning

Note:

1 6 mons Workmanship Warranty;devices

2 Estimated Project Duration: 10-25 days

Mode of Payment:

50%- Down Payment

30%- Progress Billing (50% of Total Accomplishment)

20%-Completion (Upon Test and Commissioning )

Prepared by:

Maritess Verzosa

PROJECT IN CHARGE