POKHARA METROPOLITAN CITY OFFICE

Office of Muncipal Excutive


Newroad Pokhara
Gandaki Provinnce , Kaski
MEASUREMENT BOOK

Name Of Project:कालिमाटी भित्रिबाटो सडक निर्माण।


Location: Pokhara-27
S.N Description No. Length Breadth Height Quantity Unit Rate Amount Remarks
A Side Wall construction
E/W excavation in Soft Soil having silt and clay
1
including 10m lead & 1.5m lift with all complete.
2.00 8.00 0.25 0.20 0.80
0.80 cum 82.57 66.056
Boulder Soling and levelling works in foundation
2
including 30m lead with all complete.
2.00 8.00 0.25 0.10 0.40
0.40 cum 3825.00 1530.00
Plum cement Works including labor and material
required for mixing Placing in position vibrating
compacting finishing curing and all other
3 incidentals required to produce concrete of
specified strength per specification.Rates include
all the work of making fixing and removing all the
centres and forms required for the work
2.00 8.00 0.25 0.45 1.80
1.80 cum 8742.11 15735.80
A Road PCC Works
E/W excavation in Soft Soil having silt and clay
1
including 10m lead & 1.5m lift with all complete.
1.00 9.00 4.90 0.20 8.82
8.82 cum 82.57 728.2674
Boulder Soling and levelling works in foundation
2
including 30m lead with all complete.
1.00 9.00 4.90 0.10 4.41
4.41 cum 3825.00 16868.25
3 PCC Works in 1:2:4 including material collection &
30m lead with all complete.
1.00 9.00 4.90 0.1 4.41
4.41 cum 9453.83 41691.39
Sub- Total 76619.76
contengencies @ 3% 68575.69
Grand total 145195.45

Prepared By: Sundar Poudel Checked By Aproved By


Er Ramji Tripathi
Pokhara Metropolitan City
Office of municipal executive
Newroad, Kaski

Cost Estimate
for

(FY 080/81)

Name Of Project:कालिमाटी भित्रिबाटो सडक निर्माण।


POKHARA METROPOLITAN CITY OFFICE
Office of Municipal Executive
Newroad, Kaski
BILL OF QUANTITY
Project Name : CHITEPANI KRISHI CAMPUS RAIKAR MACHHAPUCHHRE
GAUPALIKA
Contract No: SADAK

Amount
S.N. Description Unit Quantity Rate Remarks
(NRs.)
A General
Insurance of works, equipment, Contractor's workmen
1 and employees and Third party Insurance against damage to other LS Err:509
persons and property.
2 Supply and place standard size sign board for contract information. Nos Err:509
B Civil Work
Roadway excavation in all types of soil material including disposal of
3 excavated material at approved environmentally safe tipping sites. In m3 Err:509
Hard Soil
C Stone solling work
Stone Soling Works in foundation including Material, labour,
4 transportation, as per specification etc all complete as directed by m3 Err:509
Engineer. [ C10 (6-5) ]
D Plane Concrete work for Structures

Supply and place concrete class M 15 (1:2:4) including Material, labour,


5 transportation, Curing etc as per specification all complete as directed by m3 Err:509
Engineer. [D1(7-2) gha]
E Stone Masonary work

Supply and place un-coursed random rubble masonry work in 1:4


6 cement sand mortar including Material, labour, transportation, Curing etc m3 Err:509
as per specificationall complete as directed by Engineer. [ C6(6ka) 1-2 ]

F Plum Concrete work for Structures


Plum Cement Concrete work. It includes (Concrete M15 grade + 40%
7 Boulder in foundation)
m3 Err:509

G Formwork and Surface Finish for Structures


Supply and place formwork for concrete works & Plum Concrete Works.
8 including Material, labour, transportation, as per specification etc all m2 Err:509
complete as directed by Engineer. [DOR 18.2 a i]
H Rainforcement Work

9 Reinforcement bar for RCC works including cutting, binding, kg Err:509


bending & placing as per drawing with 30m lead
I Plywood For Expansion Joint

10 Supply and Laying of 4mm playwood for the expansion Joint per 4 meter Sq.m Err:509

J Hume Pipe for cross drainage


supply & Laying of NP3 Hume pipe fixing, Jointing including Material,
11 labour, transportation, Curing etc as per specification all complete as RM Err:509
directed by Engineer a)900 mm Ø
supply & Laying of NP3 Hume pipe fixing, Jointing including Material,
12 labour, transportation, Curing etc as per specification all complete as RM Err:509
directed by Engineer b)600 mm Ø
K Black Top pavement Construction Work

Roadway Excavation in All types of Soil including removal of Stumps and


13 other deterious matters , with all lifts and lead (Mechanical means)
m3
Err:509
Providing and laying granular sub-base on prepared surface, mixing at
14 OMC, and compacting to achieve the desired density, complete (Manual m3
Means) Err:509
Providing and laying Crusher Run Material on a prepared surface,
15 spreading and mixing , watering and compacting to form a layer of Base m3
course (For 53mm Maximum size) Err:509
Providing and Applying prime coat with Hot Bitumen (including Cutter)
16 on Prepared surface of granular base including cleaning of road surface Ltr
and spraying at specified rate by manual means. Err:509
Providing and Applying tack coat with Hot Bitumen at specified rate on
17 the prepared surface including cleaning by Manual Means.
Ltr Err:509
Providing and laying open-graded premix carpet of 20 mm thickness
18 composed of 13.2 mm to 5.6 mm aggregates as wearing course on a m3
previously prepared base Err:509
Sub-Total A -
VAT @13% -
Total B -
Contingencies 1.0% -
Total -
POKHARA METROPOLITAN CITY OFFICE
Office of Municipal Executive
Newroad, Kaski
ABSTRACT OF COST
Project Name : CHITEPANI KRISHI CAMPUS RAIKAR MACHHAPUCHHRE GAUPALIKA SADAK
Contract No:

Amount
S.N. Description Unit Quantity Rate Remarks
(NRs.)
A General
Insurance of works, equipment, Contractor's workmen
1 and employees and Third party Insurance against damage to other LS Err:509 Err:509 Err:509
persons and property.
Carry out additional tests for material and works as required and
2 instructed by the Engineer.
PS 1.00 Err:509 Err:509
3 Supply and place standard size sign board for contract information. Nos Err:509 Err:509 Err:509
B Civil Work
Roadway excavation in all types of soil material including disposal of
4 excavated material at approved environmentally safe tipping sites. In m3 Err:509 Err:509 Err:509
Hard Soil
C Stone solling work
Stone Soling Works in foundation including Material, labour,
5 transportation, as per specification etc all complete as directed by m3 Err:509 Err:509 Err:509
Engineer. [ C10 (6-5) ]
D Plane Concrete work for Structures

Supply and place concrete class M 15 (1:2:4) including Material, labour,


6 transportation, Curing etc as per specification all complete as directed by m3 Err:509 Err:509 Err:509
Engineer. [D1(7-2) gha]
Supply and place concrete class M 20 (1:1.5:3) including Material,
labour, transportation, Curing etc as per specification all complete as m3 Err:509 Err:509 Err:509
directed by Engineer. [D2(7-4)kha]
E Stone Masonary work

Supply and place un-coursed random rubble masonry work in 1:4


7 cement sand mortar including Material, labour, transportation, Curing etc m3 Err:509 Err:509 Err:509
as per specificationall complete as directed by Engineer. [ C6(6ka) 1-2 ]
F Plum Concrete work for Structures
Plum Cement Concrete work. It includes (Concrete M15 grade + 40%
8 Boulder in foundation)
m3 Err:509 Err:509 Err:509
-
G Formwork and Surface Finish for Structures
Supply and place formwork for concrete works & Plum Concrete Works.
9 including Material, labour, transportation, as per specification etc all m2 Err:509 Err:509 Err:509
complete as directed by Engineer. [DOR 18.2 a i]
H Rainforcement Work

10 Reinforcement bar for RCC works including cutting, binding, kg Err:509 Err:509 Err:509
bending & placing as per drawing with 30m lead
I Plywood For Expansion Joint

11 Supply and Laying of 4mm playwood for the expansion Joint per 4 meter Sq.m Err:509 Err:509 Err:509

J Hume Pipe for cross drainage


supply & Laying of NP3 Hume pipe fixing, Jointing including Material,
12 labour, transportation, Curing etc as per specification all complete as RM Err:509 Err:509 Err:509
directed by Engineer a)900 mm Ø
supply & Laying of NP3 Hume pipe fixing, Jointing including Material,
13 labour, transportation, Curing etc as per specification all complete as RM Err:509 Err:509 Err:509
directed by Engineer b)600 mm Ø
K Black Top pavement Construction Work
-
Roadway Excavation in All types of Soil including removal of Stumps and
14 other deterious matters , with all lifts and lead (Mechanical means)
m3 Err:509 Err:509
Err:509
Providing and laying granular sub-base on prepared surface, mixing at
15 OMC, and compacting to achieve the desired density, complete (Manual m3 Err:509 Err:509
Means) Err:509
Providing and laying Crusher Run Material on a prepared surface,
16 spreading and mixing , watering and compacting to form a layer of Base m3 Err:509 Err:509
course (For 53mm Maximum size) Err:509
Providing and Applying prime coat with Hot Bitumen (including Cutter)
17 on Prepared surface of granular base including cleaning of road surface Ltr Err:509 Err:509
and spraying at specified rate by manual means. Err:509
Providing and Applying tack coat with Hot Bitumen at specified rate on
18 the prepared surface including cleaning by Manual Means.
Ltr Err:509 Err:509 Err:509
Providing and laying open-graded premix carpet of 40 mm thickness
19 composed of 13.2 mm to 5.6 mm aggregates as wearing course on a m3 Err:509 Err:509
previously prepared base Err:509
Sub-Total A Err:509
VAT @13% Err:509
Total B Err:509
Contingencies 1.0% Err:509
Total Err:509
Pokhara Metropolitan city
Office of Municipal Executive
Newroad, Kaski

Detail Estimate & Abstract of Cost

Name Of Project:कालिमाटी भित्रिबाटो सडक निर्माण।


Location: Pokhara-27
S.N. Particulars No. Length Width Height Quantity unit Rate Amount Remarks
A General works
Carry out additional tests for material and works as required and instructed
1 by the Engineer. 1 1 ls 12000 12000
2 Supply and place standard size sign board for contract information. 1 1 ls 500 500
B Road works
E/W excavation in Soft Soil having silt and clay including 10m lead & 1.5m
1
lift with all complete.
for road 1.00 140.00 0.45 1.00 63.00
grade cutting 1.00 20.00 5.00 0.20 20.00
83.00 cum 79.38 6588.54
Earthwork in excavation in foundation in all types of soils including lead
2
and lift. All complete work
1.00 170.00 0.45 0.3 22.95
22.95 cum 119.07 2732.6565

Boulder Soling and levelling works in foundation including 30m lead with all
3
complete.

a for road 1.00 220.00 5.00 0.10 110.00


b for side drain 1.00 140.00 0.95 0.10 13.30
c for dpc wall
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.30 0.10 0.30
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.30 0.10 0.30
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.25 0.10 0.25
1.00 10.00 0.30 0.10 0.30
1.00 10.00 0.30 0.10 0.30
1.00 10.00 0.30 0.10 0.30
170.00
127.80 cum 4410.36 563644.01
4 PCC Works in 1:2:4 including material collection & 30m lead with all
complete.
for road 1 220 5.00 0.1 110.00
110.00 cum 10051.17 1105628.70
5 P.C.C Works in 1:3:6 including material collection and 30 m lead with all
complete
for side drain 1 120 0.45 0.075 4.05
4.05 cum 8801.23 35644.98
Providing and laying plum concrete (Boulder mixed concrete) as per drawing
6 and specifications. 60% M15 conctere and 40% boulders/stones using
mechanical Aids. ( Rate including formworks)
for side drain 2.00 120 0.25 0.5 30.00
for dpc wall
1.00 10.00 0.25 0.61 1.53
1.00 10.00 0.30 0.61 1.83
1.00 10.00 0.25 0.61 1.53
1.00 10.00 0.25 0.61 1.53
1.00 10.00 0.30 0.30 0.90
1.00 10.00 0.25 0.76 1.90
1.00 10.00 0.25 0.76 1.90
1.00 10.00 0.25 0.76 1.90
1.00 10.00 0.25 0.61 1.53
1.00 10.00 0.25 0.75 1.88
1.00 10.00 0.25 0.76 1.90
1.00 10.00 0.25 0.76 1.90
1.00 10.00 0.25 0.76 1.90
1.00 10.00 0.25 0.76 1.90
1.00 10.00 0.30 0.91 2.73
1.00 10.00 0.30 0.46 1.38
1.00 10.00 0.30 0.31 0.93
59.07 cum 9420.41 556463.62
7 Supply and laying of Ply wood for expansion joint along cross section of
minimum 4mm thick
22.00 5.00 0.10 11.00
11.00 cum 241.24278 2653.67

Total 2285856.18
Contingencies @3% 68575.69
Grand total 2354431.87

Prepared By Checked by: Recommended By Approved by


10
POKHARA METROPOLITAN CITY
Office of Muncipal Excutive
Newroad Pokhara
Gandaki Provinnce , Kaski

User Bill

Name Of Project:कालिमाटी भित्रिबाटो सडक निर्माण। Bill No. Final Bill


Agency Name : User s Committee Previous voucher No:
Date of |Contract Aggrement:2080/02/16 Current voucher No.:
Date of Work Oder:2080/02/17 Date of Payment:
Date of Work to Be Completed:2080/03/15 Page No. of Payment Book:
Date of Time Extension: M.B. Number: LooseMB
Date Of Work Completed:2080/03/06 M.B. Page No. from To
Date Of Measurement:2080/03/10

Total Amount up to This Bill Preious Bill Amt. In This Bill


Description Unit Contract Quantity
Item No. Qty. Rate Amount Qty Amount Qty Amount

General works - -
E/W excavation in Soft Soil having silt and clay including 10m Cum 83.00 0.80 79.38 63.50 0.80 63.50
lead & 1.5m lift with all complete.
Boulder Soling and levelling works in foundation including 30m Cum 127.80 0.40 4,410.36 1,764.14 0.40 1,764.14
lead with all complete.
Err:509 Cum Err:509 1.80 Err:509 Err:509 1.80 Err:509
Err:509 0.00 - - - - -
Err:509 Cum Err:509 8.82 Err:509 Err:509 8.82 Err:509
Err:509 cum Err:509 4.41 Err:509 Err:509 4.41 Err:509
PCC Works in 1:2:4 including material collection & 30m lead cum 110.00 4.41 10,051.17 44,325.66 4.41 44,325.66
with all complete.
Sub Total Err:509 Sub Total Err:509

Total Amount from this Bill Err:509

Prepared By Checked By Approved By


Sundar Poudel Er Ramji Tripathi
INDEX OF MEASUREMENTS ENTERED

Pages Measured By Checked By Remarks


Done By
From To Name signature & date Name Signature & date

Name Of Project:कालिमाटी
1 1 User's Committee Sundar poudel Er.Ramji Tripathi
भित्रिबाटो सडक निर्माण।
Name Of Project:कालिमाटी भित्रिबाटो सडक निर्माण।

POKHARA METROPOLITAN CITY OFFICE

MEASUREMENT BOOK
Issued To:
Site Incharge: Sundar poudel

Name Of Project:कालिमाटी भित्रिबाटो सडक निर्माण।


Location Of Project:- P.M.C-27

Issuing Officer :

Date of first entry:


Date of last entry:2080/03/10

Certified that this books contains 2 Page of pre - numbered measurement sheets.

Engineer Chief Administrative Officer


Pokhara Lekhanath Metropolitan city
Office of municipal executive
Newroad, Kaski

Contract Bill
Name of Project :-
Location: Bill No:
Contract No: Previous Voucher No:
Agency Name: current of Payment:
Date of Agreement: Date of Payment:
Date of work order: Page no of Payment book:
Date of work to be Complete: M.B.Number:
Date of time extention: M.B.page No. from to
Date of work complete:
Date of measurement:

contract Amount upto this bill Previous Bill Current Bill


S.N Discription of Work Unit Qty. Quantity Rate Remarks
Amount Quantity Amount Quantity Amount

Total

Prepared ByName: Checked By Name: Approved ByName:


14

kf]v/f dxfgu/kflnsf
gu/ sfo{kflnsfsf] sfof{no
Go'/f]8, kf]v/f
sfo{ ;DkGg k|ltj]bg
योजनाको नाम : कोलेफाँट भित्रि बन कु ना अधुरो बाटो ढलान प्रतिवेदनको मिति: १०/०३/२०८०
कामको नाम : Road PCC Works & Plum concrete काम सुरु भएको मिति : 17/2/2080
लागत अनुमानको कु ल रकम : Err:509 काम सम्पन्न गर्नु पर्ने मिति: 15/03/2080
खर्च भएको कु ल रकम : Err:509 सम्पन्न भएको मिति: 6/3/2080
सुरु लागत अनुमान भन्दा घटी बढीको प्रतिशित : Err:509
l;=g+=ljj/0f O{li6d]6 cg';f/ v'b nfu]sf] vr{ km/s kg{ cfPsf] s}lkmot
kl/df0f b/ /sd kl/df0f b/ /sd kl/df0f k|ltzt /sd
A General works
E/W excavation in Soft Soil having silt
1 and clay including 10m lead & 1.5m lift 83.00 79.38 6588.54 0.80 79.38 63.50 -82.200 -99.0 -6525.04
with all complete.
Boulder Soling and levelling works in
2 foundation including 30m lead with all 127.80 4410.36 563644.01 0.40 4410.36 1764.14 -127.400 -99.7 -561879.87
complete.
3 Err:509 Err:509 Err:509 Err:509 1.80 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509
1 Err:509 Err:509 Err:509 Err:509 8.82 Err:509 Err:509 Err:509 Err:509 Err:509
2 Err:509 Err:509 Err:509 Err:509 4.41 Err:509 Err:509 Err:509 Err:509 Err:509

PCC Works in 1:2:4 including material


3 110.00 10051.17 1105628.70 4.41 10051.17 44325.66 -105.590 -96.0 ###
collection & 30m lead with all complete.

Total Err:509 Err:509 Err:509


Contengencies 68,575.69 68,575.69 -
Grand Total Err:509 Err:509 Err:509

Prepared BySundar Poudel Checked By Approved By


Er Ramji Tripathi
POKHARA METROPOLITAN CITY OFFICE
Office of Municipal Executive
NEW ROAD, POKHARA
Gandaki Province, Nepal

Road Measurement sheet


Name Of Project:कालिमाटी भित्रिबाटो सडक निर्माण।
Location: Pokhara-27

Av
S.N. Ch Length Breadth Quantity Unit Remarks
Breadth
1 0+000 0 5.00 -
2 0+010 10 5.00 5.00 50.00
3 0+020 10 5.00 5.00 50.00
4 0+030 10 4.95 4.98 49.80
5 0+040 10 5.00 4.98 49.80
6 0+050 10 5.00 5.00 50.00
7 0+060 10 5.50 5.25 52.50
8 0+070 10 5.10 5.30 53.00
9 0+080 10 6.00 5.55 55.50
10 0+090 10 6.20 6.10 61.00
11 0+100 10 6.10 6.15 61.50
12 0+110 10 6.20 6.15 61.50
13 0+120 10 6.10 6.15 61.50
14 0+130 10 6.00 6.05 60.50
15 0+0140 10 6.00 6.00 60.00
Total 140 776.60
5.5471429

Av
S.N. Ch Length Breadth Breadth Quantity Unit Remarks
1 0+000 0 5.80 -
2 0+010 10 5.60 5.70 57.00
3 0+020 10 5.40 5.50 55.00
4 0+030 10 5.40 5.40 54.00
5 0+040 10 5.20 5.30 53.00
6 0+045 5 5.20 5.20 26.00
Total 45 245.00
5.4444444
Pokhara Lekhanath Metropolitan city
Office of municipal executive
Newroad, Kaski

Detail Measurement

Name of Project :-
Location:

S.N. Description of works No. Length Breadth Height Quantity Unit Rate Amount Remarks

Total -

Measured byName: Checked by Name: Approved byName:


General AnalysisPage 17

POKHARA METROPOLITAN CITY OFFICE


OFFICE OF MUNICIPAL EXECUTIVE
NEW ROAD-8, POKHARA
SUMMARY OF RATE ANALYSIS "GENERAL WORKS"( F/Y 2075/076 )

Rate
S.N. Norms no. Description unit Remarks
Dept.
1
Site cleareance (Grass Cutting, Weep out
A3 their root, removal of debris, Levelling and
lead of debris) SqM 19.07
2 Earthwork excavation in ………..including
10m lead & 1.5m lif
A B1-1 Soft Soil having silt and clay CuM 580.41
B B1-2 Boulder Mixed Soil CuM 663.32
C B1-2 Medium Rock CuM 2487.45
D Deep Foundation, Drain, Pipe line trench in B.M.S.
2(14) WS
including 10m lead & 1.5m lift CuM 1318.35
3 Boulder Soling & levelling works in
C10 (6-5)
foundation including 30m lead. CuM 3691.5
4
Plain cement concrete works in foundation including
material collection & 30m lead
A D1(7-2) ga In ( 1:3:6 ) CuM 11544.33
B D1(7-2) gha B. In ( 1:2:4 ) CuM 13305.57
5
Plain cement concrete works in superstructure, Slab &
Beams including material collection with 30m lead.
A D2(7-4)ka M15 (1:2:4) CuM 15490.57
B D2(7-4)kha M20 (1:1.5:3) CuM 16994.41

6 Stone masonry works including material collection,


preparation of motar with 5m lift & 10m lead
A C6(6ka) 1-2 Random Rubble in 1:4 c/s mortar CuM 12100.16
B C6(6ka) 1-3 Random Rubble in 1:6 c/s mortar CuM 11134.14
C C6(6ka) 2-1 Dry Stone masonry work CuM 5037.00
D C6(6ka) 2-2 Stone masonry work in mud motar CuM 5525.94

7
Brick masonry works including materials collection,
preparation of mortar with 30m transportation.
A C2(5-1)kha2 /
Chimney Bhatta Bricks in c/s mortar 1:4
5(2)ka CuM 16368.97
B C2(5-1)kha3 /
Chimney Bhatta Bricks in c/s mortar 1:6
5(2)ka CuM 15839.38
C C1(5-1)ka2 /
Machine Made(Chinese) Bricks in c/s mortar 1:4
5(2)ka CuM 16401.36
D C1(5-1)ka3 /
Machine Made(Chinaese) Bricks in c/s mortar 1:6
5(2)ka CuM 15896.88

Prepared By Checked By Recommended By Approved By


General AnalysisPage 18

POKHARA METROPOLITAN CITY OFFICE


OFFICE OF MUNICIPAL EXECUTIVE
NEW ROAD-8, POKHARA
SUMMARY OF RATE ANALYSIS "GENERAL WORKS"( F/Y 2075/076 )

Rate
S.N. Norms no. Description unit Remarks
Dept.
8 12.5mm th. Cement plaster works in…………
A I1(12-1)ga Wall & floor in 1:3 C/S motar SqM 417.78
B I1(12-1)ga Wall & floor in 1:4 C/S motar SqM 405.82
C I1(12-1)gha Wall & floor in 1:6 C/S motar SqM 379.01
D I7(12-1)kha Ceiling in 1:4 C/S motar SqM 472.52
9 1/8" thick Flush pointing works in…..
A I8(14-1)ka Brick wall in 1:1 C/S motar SqM 282.88
B I8(14-1)kha Brick wall in 1:2 C/S mortar SqM 264.53
C I9(14-2)ka Boulder stone wall in 1:1 C/S motar SqM 354.71
D I9(14-2)kha Boulder stone wall in 1:2 C/S motar SqM 319.54
10 14/6, 123 3mm thick cement punning works (1:1) SqM 265.08
11 Form Works including selection of materials, centering &
shuttering as per drawing with 30m lead.
A E1(8-3)Ka Form works on Column by using local wood SqM 1238.07
B Form works on beam having beam height upto 0.3m by
E3(8-4)Ka 1297.48
using local wood SqM
C Form works on beam having beam height 0.3m to 0.8 m
E4(8-4)Kha 983.53
by using local wood SqM
D Form works by using iron props and 18mm thick Water
E6(8-4)Ka 875.58
proof Ply wood SqM
E Form works by using iron props and 10mm thick Water
DOR 18.2 a i 681.42
proof Ply wood SqM
Reinforcement bar for RCC works including
12 D9(7-5) cutting, binding, bending & placing as per Kg 122.33
drawing with 30m lead
13
C.G.I sheet roofing works including material collection.
A F1(9-1) 24 gauge SqM 1099.21
B F1(9-1) 24 gauge Colour SqM 1265.15
C F1(9-1) 26 gauge SqM 910.11
D F1(9-1) 26 gauge Colour SqM 1049.04
E F1(9-1) 28 gauge SqM 771.19
F 9/1, 69 Ridge Plain sheet Roofing Works works including material
28 gauge Colour SqM 898.54
14 collection.
A F4(9-2) 24 Gauge Plain Sheet RM 1151.28
B F4(9-2) 26 Gauge Plain Sheet RM 1038.08
C F4(9-2) 28 Gauge Plain Sheet RM 849.43

Prepared By Checked By Recommended By Approved By


General AnalysisPage 19

POKHARA METROPOLITAN CITY OFFICE


OFFICE OF MUNICIPAL EXECUTIVE
NEW ROAD-8, POKHARA
SUMMARY OF RATE ANALYSIS "GENERAL WORKS"( F/Y 2075/076 )

Rate
S.N. Norms no. Description unit Remarks
Dept.
15 C.G.I Gutter Works including material collection.
A 150 mm -450mm wide Colour G.I. Plain sheet Rain
F7
Gutter works including iron bracket, Notbolt, Washer . RM 1264.03
B 150 mm -450mm wide plain G.I. Plain sheet Rain Gutter
F7
works including iron bracket, Notbolt, Washer . RM 1051.79
1.2 mm thick heavy Corrugated Fiber sheet
16 F14 Roofing works including material collection all SqM 3879.90
complete works .
17 1.2mm thick heavy Ridge Fiber plain sheet
F15 Roofing works including material collection all
complete works . RM 2616.63
18 Slate Roofing works including material
F9(9-5)
collection with all complete works. SqM 2104.50
19 UPVC Roofing works including material collection with all
complete
A F22 2mm thick UPVC Roofing Works SqM 2068.67
B F23 3mm thick UPVC Roofing Works SqM 2811.11
20 3mm thick UPVC Ridge covering works including
F15
material collection all complete works . RM 1720.40
21 Wood Works
A G1(10-1) Salwood frame with wood size 100*75mm CuM 278151.89
B G1(10-1) Local wood frame with wood size 100*75mm CuM 95016.58
C G2(10-2) 38mm th.sal wood in panneled door & window shutter. SqM 14653.91
D G2(10-2) 38mm th.local wood in panneled door & window shutter. SqM 8038.55
E 4mm th. glazed window shutter with 38*75mm sal wood
G3(10-4)
frame. SqM 10365.39
F 4mm th. glazed window shutter with 38*75mm local
G3(10-4)
wood frame. SqM 6707.16
G Flush door with 38mm th. Sal wood frame & 4mm
G4(10-7)
commercial plywood shutter. SqM 8590.82
H Flush door with 38mm th.local wood frame & 4mm
G4(10-7)
commercial plywood on both side SqM 6024.92
I Door shutter with 38mm th.local wood frame & fixing of 26
G4(10-9)
gauge plain sheet in both side. SqM 6452.74
J G4(10-10)
Mosquito proof door & window shutter with 38mm th.sal wood
frame & 24 gauge G.I wire. SqM 5853.61
K Mosquito proof door & window shutter with 38mm
G4(10-10)
th.Shisham wood frame & 24 gauge G.I wire. SqM 4884.43

Prepared By Checked By Recommended By Approved By


General AnalysisPage 20

POKHARA METROPOLITAN CITY OFFICE


OFFICE OF MUNICIPAL EXECUTIVE
NEW ROAD-8, POKHARA
SUMMARY OF RATE ANALYSIS "GENERAL WORKS"( F/Y 2075/076 )

Rate
S.N. Norms no. Description unit Remarks
Dept.
L F21 Making & fixing of salwood truss CuM 265277.83
M F21 Making & fixing of local wood truss CuM 90466.85
N F20(10-19) Making & fixing of 25mm sal wood eaves board. SqM 6043.12
O F20(10-19) Making & fixing of 25mm local wood eaves board. SqM 1464.74
P 4mm Commercial plywood ceilling with 50*75mm salwood size
N7(10-16)ka
& 600*900mm frame size. SqM 3768.48
Q Commercial plywood ceilling with 50*75mm local wood size &
N7(10-16)ka
600*900mm frame size. SqM 1661.70
22 Flooring Works
A H1(11-1)kha
38mm thick 1:2:4 Cement Concrete floor Carting including
finishing by rubbing Cement. SqM 669.42
B H1(11-1)ga
50mm thick 1:2:4 Cement Concrete floor Carting including
finishing by rubbing Cement. SqM 818.34
C H1(11-1)gha
75mm thick 1:2:4 Cement Concrete floor Carting including
finishing by rubbing Cement. SqM 1101.47
D 25 mm th.mosaic flooring with 12.5mm th cement plaster (1:2)
H4(11-4) base course & 6 mm th marble chips with white cement (1:1)
surface course including rubbing & polishing SqM 4026.80
E H6(11-7) Procelain glazed flooring tile in (1:4) Cement Sand mortar SqM 2895.83
F 15 mm th. marble with cement sand (1:2) surface course
H34 including rubbing & polishing SqM 4930.38
G H26(11-6)
16mm Granaite with 20mm thick cement sand (1:2) surface
course including rubbing & polishing SqM 7380.43
H H19(11-9) 37.5 mm th Flagstone paving in 1:4 cement sand mortar SqM 2091.28
I H19(11-20) Brick ballast filling works. CuM 4818.50
23 Painting works
A J4(13-4)kha 2 coat waterproof cement paint works. SqM 137.35
B J1(13-1)kha 2 coat white washing in new surface in wall SqM 32.84
C J1(13-1)kha 2 coat white washing in new surface in ceiling SqM 39.37
D J2(13-2) White washing in old surface SqM 17.90
E
J3(13-3)ka and ga
Two coat distemper painting over one coat primer . SqM 118.22
F J5(13-5)ka and
kha One coat Emulsion paint over one coat primer . SqM 213.34
G
J5(13-5)ka and ga
Two coat Emulsion paint over one coat primer . SqM 323.74
H J18(13-5)kha One Coat Weather Coat(apex) Excluding primer . SqM 156.40
I J18(13-5)kha Two Coat Weather Coat(apex) Excluding primer . SqM 290.95
J
J5(13-5)ka and ga
2 coat Weather coat (apex) over one coat primer. SqM 378.94

Prepared By Checked By Recommended By Approved By


General AnalysisPage 21

POKHARA METROPOLITAN CITY OFFICE


OFFICE OF MUNICIPAL EXECUTIVE
NEW ROAD-8, POKHARA
SUMMARY OF RATE ANALYSIS "GENERAL WORKS"( F/Y 2075/076 )

Rate
S.N. Norms no. Description unit Remarks
Dept.
K
J5(13-5)ka and ga
2 coat readymade Enamelpaint over one coat primer. SqM 314.54
L 2 coat readymade Aluminium paint over one coat
J6(13-6)
primer. SqM 314.02
M J11(12-4)ga One Coat Red oxide paint SqM 98.79
N J11(12-4)gha Two Coat Red oxide paint SqM 174.40
24 Irons works
A Making & fixing 3*20 mm iron gril including one coat Red
M1(24-1)ka
oxide paint after rubbing with sand paper. SqM 2821.27
B
M2(24-1)kha Making & fixing 4.5*20 mm iron gril including one coat
Red oxide paint after rubbing with sand paper. SqM 3758.20
C Making & fixing of rolling shutter including one coat red
M6(24-2) oxide paint after rubbing with sand paper with all
complete . SqM 2214.95
D M9(24-6) Barbed wire fencing work RM 76.38
25 DoR SNo-24.2, Supply and Laying
Box size 1.5x1x1m usingof Gabion
heavy box including
zinc coated Hexagonal Stone filling
A Ref. to ss mesh type 100x120mm , mesh wire 3mm, selvage wire
2402(A),Sno 24.3
DoR SNo-24.2, 3.9mm
Box sizelacing wireusing
2x1x1m 2.4mmheavy zinc coated Hexagonal Per box 8098.30
B and SNo24.4
Ref. to ss mesh type 100x120mm , mesh wire 3mm, selvage wire
2402(A),Sno 24.3
DoR SNo-24.2, 3.9mm
Box sizelacing wireusing
3x1x1m 2.4mmheavy zinc coated Hexagonal Per box 10433.95
C and SNo24.4
Ref. to ss mesh type 100x120mm , mesh wire 3mm, selvage wire
2402(A),Sno 24.3 3.9mm lacing wire 2.4mm Per box 14361.20
26 and SNo24.4 Hollow Concrete block works
A 5/1(b)3, 31 4" thick in 1:4 C /S motar CuM 8665.25
B 5/1(b)3, 31 6" thick in 1:4 C /S motar CuM 7976.98

27 Back filling work with ordinary soil by making 15, 15cm


layer and compact by labour including 10m lead
A B2,2(25)kha Back filling work with ordinary soil with sprinkling water CuM 1378.18
Back filling work with ordinary soil without sprinkling
B B2,2(25)kha
water CuM 1045.93
28 Dismantalling Works
A L1(19-1) Dismantalling of mud mortar masonary with deposition
up to 10 mtr. Lead works CuM 853.30

B L1(19-2) Dismantalling of Cement mortar masonary with


deposition up to 10 mtr. Lead works CuM 1706.60
C Dismantalling of R.C.C. or R.B.C. with deposition up
L1(19-3)
to10 mtr. Works CuM 8855.00
D Dismantalling P.C.C. with deposition up to 10 mtr. Lead
L4(19-4)
works CuM 3220.00

Prepared By Checked By Recommended By Approved By


General AnalysisPage 22

POKHARA METROPOLITAN CITY OFFICE


OFFICE OF MUNICIPAL EXECUTIVE
NEW ROAD-8, POKHARA
SUMMARY OF RATE ANALYSIS "GENERAL WORKS"( F/Y 2075/076 )

Rate
S.N. Norms no. Description unit Remarks
Dept.
E Dismantalling Cement Plaster with deposition up to 10
L5
mtr. Lead works CuM 86.94
F Cutting and Remove Reinforcement using on RCC or
L20
RBC with deposition up to 10 mtr. Lead works SqM 920.00
G Dismantalling of Gabion box with deposition up to 10
L21
mtr. Lead works SqM 920.00
H Dismantalling of CGI Roofing with deposition up to 10
L22
mtr. Lead works SqM 63.25

29 Miscellaneous Works
A
Plum Cement Concrete work. It includes all labour and
material required for mixing, placing in position, vibrating,
compaction, finishing, curing and all other incidentals
41 (a) spec.cl.No11 required to produce concrete of specified strength as per
the specification. Rate includes athe work of making,
fixing and removing of all centres and forms required for
the work. (Concrete M15 grade + 40% Boulder in
foundation) CuM 9825.03
B Putting works on wall and ceiling over Plastered surface
H24
including all complete works. SqM 293.39
C Supplying and fitting of Gypsum board Suspended False
H24
Ceiling with all complete works SqM 1299.27

Prepared By Checked By Recommended By Approved By


POKHARA METROPOLITAN CITY OFFICE
OFFICE OF MUNICIPAL EXECUTIVE
NEW ROAD, POKHARA

SUMMARY OF RATE ANALYSIS ROAD WORKS( F/Y 2075/076 )

S.N. Norms Description unit Dept. Rate Remarks

DoR-SN 2.3, SS- Sq.m. 8.05


1 Site Clearance Work (Manual)
201

2 A Earthwork in excavation in cutting

Roadway Excavation in All types of Soil including Cum. 1,283.98


DoR-SN9.1, SS-
A removal of stumps and other deleterious matter, with
905, I, A
all lifts and lead (Manual Means)

Roadway Excavation in All types of Soil including Cum. 32.90


DoR-SN9.1, SS-
B removal of stumps and other deleterious matter, with
905, I, B
all lifts and lead (Mechanical Means)
Cum. 1,478.52
DoR-SN9.1, SS- Roadway Excavation in Ordinary rock (BMS)
C
905, II, A inclusing all lift and lead (Manual Means)
Cum. 98.71
DoR-SN9.1, SS- Roadway Excavation in Ordinary rock (BMS)
D
905, II, B including all lifts and lead (Mechanical Means)
Sq.m. 4.70
Preparation and Surface Treatement of Formation by
DoR-SN9.7, SS- removing mud and slury, watering to the extent
3
909,910 needed to maintain desired moisture content,
compacting all complete.

Construction of Embankment with Material obtained


4
from Road way Cutting
Cum. 510.72
Providing, laying, spreading and compacting
DoR-SN9.9, SS-
A embankment with Roadway cutting material and
909,910 A
compact to the required density (Manual Means)
Cum. 161.88
Providing, laying, spreading and compacting
DoR-SN9.9, SS-
B embankment with Roadway cutting material and
909,910 B
compact to the required density (Mechanical Means)

5 Scarifying Existing Road

Scarifying Existing Road surface to a depth of 50mm Sq.m. 27.10


DoR-SN10.1, SS-
A and disposal of scarified Material with in all lifts and
1003A
lead (Manual Means)
Sq.m. 6.34
Scarifying Existing bitumenus road surface to a
DoR-SN10.2, SS-
B depth of 50mm and disposal of scarified Material with
1003B
in all lifts and lead (Mechanical Means)
Cum. 1913.75
Providing and laying granular sub-base on prepared
DoR-SN12.1, SS-
6 surface, mixing at OMC, and compacting to achieve
1201B
the desired density, complete (Manual Means)

Prepared By Checked By Recommended By Approved By


POKHARA METROPOLITAN CITY OFFICE
OFFICE OF MUNICIPAL EXECUTIVE
NEW ROAD, POKHARA

SUMMARY OF RATE ANALYSIS ROAD WORKS( F/Y 2075/076 )

S.N. Norms Description unit Dept. Rate Remarks

Providing and laying Crusher Run Material on a


7 prepared surface, spreading and mixing , watering
and compacting to form a layer of Base course
Cum. 2801.40
Providing and laying Crusher Run Material on a
DoR-SN12.7, SS- prepared surface, spreading and mixing , watering
A
1204A and compacting to form a layer of Base course (For
53mm Maximum size)

Providing and laying Crusher Run Material on a Cum. 2751.10


DoR-SN12.7, SS- prepared surface, spreading and mixing , watering
B
1204A and compacting to form a layer of Base course (For
45mm Maximum size)

Providing and Applying prime coat with Hot Bitumen Ltr. 193.93
DoR-SN13.1, SS- (including Cutter) on Prepared surface of granular
8
1302B base including cleaning of road surface and spraying
at specified rate by manual means.
Providing and Applying tack coat with Hot Bitumen at Ltr. 143.52
DoR-SN13.2, SS-
9 specified rate on the prepared surface including
1302B
cleaning by Manual Means.
Providing and laying open-graded premix carpet of Sq.m. 238.28 11024.30
DoR-SN13.3, SS- 20 mm thickness composed of 13.2 mm to 5.6 mm Per cuM
10
1307 aggregates as wearing course on a previously
prepared base
Filling Pot-holes and Patch Repairs with open
11
Graded Premix surfacing , 20mm
Sq.m. 273.44
Providing required material and repair the potholes
including removal of failed material, trimming and
DoR-SN29.11, SS-
A finishing the surface applying tack coat on the side
2903A
sand base of excavation, backfilling with hot
bituminous Material and compaction

DoR-SN13.11, SS- Providing and Laying of Seal coat sealing the voids Sq.m. 71.24
12
1310 in a Bitumenous surface.
Solid block Edging Works including soil filling & RM 370.30
13 15(25)c 143
compaction.
RM 354.20
Brick Edging Works including soil filling &
14 15(25)b 143 compaction by bricks laying with edge
standing(250mm ht.)

Prepared By Checked By Recommended By Approved By


POKHARA METROPOLITAN CITY OFFICE
OFFICE OF MUNICIPAL EXECUTIVE
NEW ROAD-8, POKHARA
Rate Analysis General Works (075/076)
Site cleareance (Grass Cutting, Weep out their root, removal of debris, Levelling and
1 Item : lead of debris)
Norms No. A3
Unit 10Sq.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md
Unskilled Md 0.23 700.00 161.00
Sub-Total 161.00
Tools & Plants @ 3% 4.83
Sub Total 165.83
Contractor Overhead@15% 24.87
Total (Dept. Rate) 190.70 19.07

2 Item : Earthwork excavation in ………..including 10m lead & 1.5m lift


A Soft Soil having silt and clay
Norms No. B1-1
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md
Unskilled Md 0.70 700.00 490.00
Sub-Total 490.00
Tools & Plants @ 3% 14.70
Sub Total 504.70
Contractor Overhead@15% 75.71
Total (Dept. Rate) 580.41

B Boulder Mixed Soil


Norms No. B1-2
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md
Unskilled Md 0.80 700.00 560.00
Sub-Total 560.00
Tools & Plants @ 3% 16.80
Sub Total 576.80
Contractor Overhead@15% 86.52
Total (Dept. Rate) 663.32

C Medium Rock
Norms No. B1-2
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md
Unskilled Md 3.00 700.00 2100.00
Sub-Total 2100.00
Tools & Plants @ 3% 63.00
Sub Total 2163.00
Contractor Overhead@15% 324.45
Total (Dept. Rate) 2487.45
3 Item : Boulder Soling & levelling works in foundation including 30m lead.
Norms No. C10 (6-5)
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md
Unskilled Md 1.50 700.00 1050.00
Material Boulder Stone Cu.M 1.20 1800.00 2160.00
Sub Total 3210.00
Contractor Overhead@15% 481.50
Total (Dept. Rate) 3691.50

4 Item : Plain cement concrete works in foundation including material collection & 30m lead
A In (1:3:6)
Norms No. D1(7-2) ga
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 1.0 1000.00 1000.00
Unskilled Md 4.0 700.00 2800.00
Material Cement(N.S. marks) M.T 0.22 16500.00 3630.00
Agg. 40 mm Cu.M 0.65 1850.00 1202.50
Agg. 20 mm Cu.M 0.24 1850.00 444.00
Course Sand Cu.M 0.47 2000.00 940.00
Water Litre 120 0.18 21.60
Sub Total 10038.10
Contractor Overhead@15% 1505.72
Total (Dept. Rate) 11543.82

B In ( 1:2:4 )
Norms No. D1(7-2) gha
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 1.0 1000.00 1000.00
Unskilled Md 4.0 700.00 2800.00
Material Cement(OPC) M.T 0.32 16500.00 5280.00
Agg. 40 mm Cu.M 0.52 1850.00 962.00
Agg. 20 mm Cu.M 0.22 1850.00 407.00
Agg. 10 mm Cu.M 0.11 1850.00 203.50
Sand(crusher screen) Cu.M 0.445 2000.00 890.00
Water Litre 150 0.18 27.00
Sub Total 11569.50
Contractor Overhead@15% 1735.43
Total (Dept. Rate) 13304.93

Plain cement concrete works in superstructure, Slab & Beams including material
5 Item :
collection with 30m lead.
A M15 (1:2:4)
Norms No. D2(7-4)ka
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 0.8 1000.00 800.00
Unskilled Md 7.0 700.00 4900.00
Material Cement (OPC) M.T 0.32 16500.00 5280.00
Agg. 40 mm(Crusher) Cu.M 0.52 1850.00 962.00
Agg. 20 mm(Crusher) Cu.M 0.22 1850.00 407.00
Agg. 10 mm(Crusher) Cu.M 0.11 1850.00 203.50
Sand(Crusher Screen) Cu.M 0.445 2000.00 890.00
Water Litre 150 0.18 27.00
Sub Total 13469.50
Contractor Overhead@15% 2020.43
Total (Dept. Rate) 15489.93

B M20 (1:1.5:3)
Norms No. D2(7-4)kha
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 0.8 1000.00 800.00
Unskilled Md 7.0 700.00 4900.00
Material Cement (OPC) M.T 0.4 16500.00 6600.00
Agg. 20 mm(Crusher) Cu.M 0.57 1850.00 1054.50
Agg. 10 mm(Crusher) Cu.M 0.29 1850.00 536.50
Sand(Crusher screen) Cu.M 0.425 2000.00 850.00
Water Litre 200 0.18 36.00
Sub Total 14777.00
Contractor Overhead@15% 2216.55
Total (Dept. Rate) 16993.55

Stone masonry works including material collection, preparation of motar with 5m lift
6 Item :
& 10m lead
A Random Rubble in 1:4 c/s mortar
Norms No. C6(6ka) 1-2
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 1.5 1000.00 1500.00
Unskilled Md 5.0 700.00 3500.00
Material Cement(N.S. marks) M.T 0.159 16500.00 2623.50
Block stone Cu.M 1.00 1800.00 1800.00
Bond stone Cu.M 0.10 1800.00 180.00
Sand(Crusher Screen) Cu.M 0.45 2000.00 900.00
Water Litre 100 0.18 18.00
Sub Total 10521.50
Contractor Overhead@15% 1578.23
Total (Dept. Rate) 12099.73
Form Works including selection of materials, centering & shuttering as per drawing
11 Item :
with 30m lead.

D Form works by using iron props and 10mm thick Water proof Ply wood
Norms No. DOR 18.2 a i
Unit 10 Sq.M.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 2.200 1,000.00 2200.00
Unskilled Md 2.200 700.00 1540.00
Material Ply Wood 10mm Sqm 11.000 53.80 591.80 8 times Used
Strut Lallies etc Sq.m 0.400 3,383.88 1353.55 12times Used
Nails Kg 2.500 96.00 240.00
Sub-Total 5925.35 Per sq.m
Contractor Overhead@15% 888.80
Total (Dept. Rate) 6814.15 681.42

Assembling mechanical woven Gabion boxes, placing in polition including


stretching, forming compartments, tying the side and diapharagms with binding wire
in each mesh, tying with bracing wires and tie wires and tying down the lid complete
25 Item : including stone filling
Box size 1.5x1x1m using heavy zinc coated Hexagonal mesh type 100x120mm ,
A mesh wire 3mm, selvage wire 3.9mm lacing wire 2.4mm
Norms No. DoR SNo-24.2, Ref. to ss 2402(A),Sno 24.3 and SNo24.4
Unit Per box
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 0.41 1000.00 410.00
Unskilled Md 1.76 700.00 1232.00
Gabion wire machine
made10x12/3.0/3.9/2.4/z
Material
n Sqm 9 270.00 2430.00
Filling Stone CuM 1.65 1800 2970.00
Sub-Total 7042.00
Contractor Overhead@15% 1056.30
Total (Dept. Rate) 8098.30
Box size 2x1x1m using heavy zinc coated Hexagonal mesh type 100x120mm , mesh
B wire 3mm, selvage wire 3.9mm lacing wire 2.4mm
Norms No. DoR SNo-24.2, Ref. to ss 2402(A),Sno 24.3 and SNo24.4
Unit Per box
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 0.54 1000.00 540.00
Unskilled Md 2.29 700.00 1603.00
Gabion wire machine
made10x12/3.0/3.9/2.4/z
Material n Sqm 11 270.00 2970.00
Filling Stone CuM 2.2 1800 3960.00
Sub-Total 9073.00
Contractor Overhead@15% 1360.95
Total (Dept. Rate) 10433.95
Box size 3x1x1m using heavy zinc coated Hexagonal mesh type 100x120mm , mesh
C wire 3mm, selvage wire 3.9mm lacing wire 2.4mm
Norms No. DoR SNo-24.2, Ref. to ss 2402(A),Sno 24.3 and SNo24.4
Unit Per box
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 0.6 1000.00 600.00
Unskilled Md 2.6 700.00 1820.00
Gabion wire machine
Material made10x12/3.0/3.9/2.4
/zn Sqm 16 270.00 4128.00
Filling Stone CuM 3.3 1800 5940.00
Sub-Total 12488.00
Contractor Overhead@15% 1873.20
Total (Dept. Rate) 14361.20

29 Item Miscellaneous Works

Plum Cement Concrete work. It includes all labour and material required for mixing, placing in
position, vibrating, compaction, finishing, curing and all other incidentals required to produce
concrete of specified strength as per the specification. Rate includes athe work of making, fixing
and removing of all centres and forms required for the work. (Concrete M15 grade + 40%
A Boulder in foundation)
Norms No. 41 (a) spec.cl.No11 (60% Concrete & 40% Boulder stone)
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 0.3 1000.00 300.00
Unskilled Md 4.0 700.00 2800.00
Material Cement(N.S. marks) M.T 0.192 16500.00 3168.00
Boulder stone 225 mm Cu.M 0.44 1800.00 792.00
Aggregate all Type Cu.M 0.51 1850.00 943.50
Sand (Crusher screen) Cu.M 0.27 2000.00 540.00
Sub-Total 8543.50
Contractor Overhead@15% 1281.53
Total (Dept. Rate) 9825.03

D 24" Dia R.C.C hume pipe NP3


Norms No.
Unit 32 m
Particular Description Unit Quantity Rate Amount Remarks
Skilled Labour MD 9 1000 9000
Unskilled Labour MD 35 700 24500
a. 24" dia hume pipe np3RM 32 5785.12 185123.84
b.cement MT 0.218 16500 3597
c.Sand CUM 0.3 1800 540
d.jute KG 7 00
Sub-Total 222760.84
Contractor Overhead@15% 33414.126 Per Meter
Total (Dept. Rate) 256174.97 8005.47

D 36" Dia R.C.C hume pipe NP3


Norms No.
Unit 32 m
Particular Description Unit Quantity Rate Amount Remarks
Skilled Labour MD 9 1000 9000
Unskilled Labour MD 35 700 24500
a. 24" dia hume pipe np3RM 32 10661.16 341157.12
b.cement MT 0.218 16500 3597
c.Sand CUM 0.3 1800 540
d.jute KG 7 00
Sub-Total 378794.12
Contractor Overhead@15% 56819.118 Per Meter
Total (Dept. Rate) 435613.24 13612.91
Assamble Stone Filling
Sk 0.013 0.2 0.3
Usk 0.063 0.8 1.2

Assamble Stone Filling


Sk 0.14 0.2 0.4
Usk 0.69 0.8 1.6
Assamble Stone Filling
Sk 0.20 0.2 0.4
Usk 1.00 0.8 1.6
POKHARA METROPOLITAN CITY OFFICE
OFFICE OF MUNICIPAL EXECUTIVE
NEWROAD-8, POKHARA
Rate Analysis Road works ( 2075/076 )

1 Item : Site Clearance Work (Manual)

B Roadway Excavation in All types of Soil including removal of stumps and other
deleterious matter, with all lifts and lead (Mechanical Means)
Norms No: DoR-SN9.1, SS-905, I, B
Unit : 360 Cum
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 1.0 1,000.00 1,000.00
Unskill Md 3.0 700.0 2,100.00
Equipment Excavator Hr 6.0 1,200.00 7,200.00
Sub Total 10,300.00
Overhead @15% 1,545.00 Per CuM Rate
Total 11,845.00 32.90

6 Item : Providing and laying granular sub-base on prepared surface, mixing at OMC,
and compacting to achieve the desired density, complete (Manual Means)
Norms No: DoR-SN12.1, SS-1201B
Unit : 200 CuM
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 2.00 1,000.00 2,000.00
Unskill Md 60.00 700.00 42,000.00
Material Sub-Base Material CuM 256.00 1,100.00 281,600.00 S1or S2
Cost of Water KL 23.00 183.75 4,226.25
Equipment Vibratory Roller Hr 6.00 500.00 3,000.00
Sub Total 332,826.25
Overhead @15% 49,923.94 Per CuM Rate
Total 382,750.19 1,913.75

7 Item : Providing and laying Crusher Run Material on a prepared surface, spreading and
mixing , watering and compacting to form a layer of Base course
Providing and laying Crusher Run Material on a prepared surface, spreading and mixing
A
, watering and compacting to form a layer of Base course (For 53mm Maximum size)
Norms No: DoR-SN12.7, SS-1204A
Unit : 360 CuM
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 3.00 1,000.00 3,000.00
Unskill Md 14.00 700.00 9,800.00
Material Crusher run Material Base Material
63 to 45 mm CuM 157.46 1,850.00 291,301.00
22.5 to 5.6 mm CuM 151.06 1,750.00 264,355.00
Below 5.6mm CuM 166.68 1,750.00 291,690.00
Cost of Water KL 36.00 183.75 6,615.00
Equipment Vibratory Roller Hr 6.00 500.00 3,000.00
Motor Grader Hr 6.00 1,200.00 7,200.00
Sub Total 876,961.00
Overhead @15% 131,544.15 Per CuM Rate
Total 1,008,505.15 2,801.40

Providing and Applying prime coat with Hot Bitumen (including Cutter) on
8 Item : Prepared surface of granular base including cleaning of road surface and
spraying at specified rate by manual means.
Norms No: DoR-SN13.1, SS-1302B
Unit : 1000 Lit
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 3.00 1,000.00 3,000.00
Unskill Md 100.00 700.00 70,000.00
Bitumen (cutback) with
Material MC 70 Tonne 1.10 70,000.00 77,000.00
Cost of Water KL 10.00 183.75 1,837.50
Equipment Tractor Hr 6.00 300.00 1,800.00
Bitumen Sprayer Hr 6.00 1,300.00 7,800.00
Boiler Hr 8.00 750.00 6,000.00
Generator Hr 8.00 150.00 1,200.00
Sub Total 168,637.50

Overhead @15% 25,295.63 Per Lit Rate


Total 193,933.13 193.93
Providing and Applying tack coat with Hot Bitumen at specified rate on the
9 Item : prepared surface including cleaning by Manual Means.
Norms No: DoR-SN13.2, SS-1302B
Unit : 1000 Lit
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 3.00 1,000.00 3,000.00
Unskill Md 40.00 700.00 28,000.00
Material Bitumen (cutback) with
MC 70 Tonne 1.10 70,000.00 77,000.00
Equipment Tractor Hr 6.00 300.00 1,800.00
Bitumen Sprayer Hr 6.00 1,300.00 7,800.00
Boiler Hr 8.00 750.00 6,000.00
Generator Hr 8.00 150.00 1,200.00
Sub Total 124,800.00
Overhead @15% 18,720.00 Per Lit Rate
Total 143,520.00 143.52

Providing and laying open-graded premix carpet of 20 mm thickness composed


10 Item : of 13.2 mm to 5.6 mm aggregates as wearing course on a previously prepared
base
Norms No: DoR-SN13.3, SS-1307
Unit :500 SqM (10CuM)
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 21.00 1,000.00 21,000.00
Unskill Md 8.00 700.00 5,600.00
Material Bitumen Tonne 0.73 70,000.00 51,100.00
Crushed stone Chipping
13.2-5.6mm CuM 13.50 1,400.00 18,900.00
Equipment Mixer Hr 4.00 750.00 3,000.00
Bitumen boiler oil fired Hr 4.00 750.00 3,000.00

Smooth wheeled Roller Hr 2.00 500.00 1,000.00

Sub Total 103,600.00

Overhead @15% 15,540.00 Per SqM Rate


Total 119,140.00 238.28
Total 119,140.00 11,914.00
Per CuM Rate
,
Pokhara Metropolitan City
Office of municipal executive
Newroad, Kaski

Cost Estimate
for

(FY 075/76)

Name of Project :-
Chitepani Raikar, Krishi Campus machhapuchhere
Gaunpalika Sadak ,PMC-19

Work Items: Drain ,Masanary and Blacktop