Detail Measurement and Abstract of Cost
Name of project :- Sera Bridge Maintenance F/Y :- 080/081
Site :- PMC-25 Date:- 2080-05-12
S.N Description No. Length Breadth Height Quantity Unit Rate Amount Remarks

Earthwork in excavation in all tpes


1.00
of soil by mechanical means.
45.20 1.00 3.00 0.20 27.12
27.12 cum 79.38 2152.79
Earthwork in excavation in all types
2.00 of soil for foundation by mechanical
means
gabion foundation 97.00 2.00 1.50 0.75 218.25 cum 119.07 25987.03

Supply and placing and erection with


3.00 binding, lacing and bracing of Machine
made and mechanically selvedged
double twisted hexagonal mesh
products(Meccaferri product) wire Mesh
Net. All complete work
2*1*1 97.00 1067.00 sqm 325.44 347244.48

Providing and filling stone.boulder in


4.00 gabion boxes/ matress etc. Including
dressing, Bedding, bonding all complete
as per Drawing and Technical
Specifications.
2*1*1 97.00 194.00 cum 3795.73 736371.62
Total 1,111,755.92
contengecies @ 3% 33,352.68
Grand total 1,145,108.60

Prepared By:
Checked By:
Ast. Sub-Er.Pratikshya Aryal Recommended By: Approved By:
Er.Prabhat Baral
POKHARA METROPOLITAN CITY OFFICE
NEW ROAD, POKHARA
Detail Estimate and Abstract of Cost
Name of project :- उन्नतसिल आमासमुह भवन मर्मत तथा व्यवस्थापन। F/Y :- 080/081
Site :- PMC-27 Date:- 2080-07-19
S.N Description No. Length Breadth Height Quantity Unit Rate Amount Remarks

Supply and application of One coat


1.00 Emulsion paint over one coat
primer .
long wall 4.00 11.40 3.10 141.36
short wall 4.00 3.53 2.80 39.54
deductions
Main door -2.00 1.07 2.08 -4.45
Window -12.00 1.37 1.37 -22.52
153.93 Sqm 224.87 34614.24
supply and installation of UPVC door
2.00
and window
Main door 1.00 1.07 2.08 2.23
Window 6.00 1.37 1.37 11.26
13.49 Sqm 7950.15 107247.52
Supply and erection of iron works for
3.00 railing with prime coat painting all
complete as per instruction of site
incharge.
specific weight
3.10 1.5 inch square pipe of 1.8 mm thick 1.00 31.26 2.02 63.15
3.20 1 inch suare pipe of 1.8 mm thick 3.00 31.26 1.25 117.23
vertical pole of 1.5 inch square pipe onf 1.8
3.30 mm thick 21 0.90 2.02 38.18
gate
angle of 1.5 inch 2 0.90 1.67 3.01
angle of 1.5 inch 2 0.90 1.67 3.01
patti 5 0.90 0.47 2.12
5 0.90 0.47 2.12
228.820 Kg 180.64 41334.04
Supply and erection of iron grill
4.00 including one coat red oxide paint
after rubbing with sand paper.
4.10 Window 6.00 1.37 1.37 11.26
11.26 Sqm 3044.87 34285.24
38mm thick 1:2:4 Cement Concrete
floor Carting
5.00
including finishing by rubbing
Cement.
5.10 flooring 1.00 12.40 3.53 43.77
43.77 Sqm 660.73 28920.15
Supplying and fitting of Gypsum
board
6.00 Suspended False Ceiling with
coloring all complete works as per
instruction of site incharge.
6.10 1.00 11.40 3.53 40.24
40.24 Sqm 1363.02 54847.92
Electrical Items( Bulb, Holder, wire,
switch, powershocket etc. with
fitting as per instruction of site
7.00
incharge)
Payment will be inaccordance to
detailed measurement in the field.
7.10 1.00 1.00 LS 5000.00 5000.00
Total 306,249.11

Prepared By: Sub-Er.


Checked By:
Naresh Sah Approved By:
Er.Prabhat Baral
POKHARA METROPOLITAN CITY OFFICE
NEW ROAD, POKHARA
Detail Estimate and Abstract of Cost
Name of project :- उन्नतसिल आमासमुह भवन मर्मत तथा व्यवस्थापन। F/Y :- 080/081
Site :- PMC-27 Date:- 2080-07-19
S.N Description No. Length Breadth Height Quantity Unit Rate Amount Remarks
contengecies @ 3% 9,187.47
Grand total 315,436.58
From PMC 300,000.00
From Users 15,436.58

Prepared By: Sub-Er.


Checked By:
Naresh Sah Approved By:
Er.Prabhat Baral
पोखरा महानगरपालिका
नगरपालिकाको कायार्लय
न्यूरोड, कास्की
गण्डकी प्रदेश, नेपाल
कार्य सम्पन्न प्रतिवेदन

कार्य स्थान – ,PMC - 25 Estimate भन्दा बढी वा घटी– less


Name of project :- उन्नतसिल आमासमुह भवन मर्मत तथा व्यवस्थापन। ईस्टमेट रकम #REF! घटी वा बढीको प्रतिशत – #REF!
लागेको खर्च रकम #REF! कार्य सम्पन्न गर्ने माघ्यमः
सि.न. विवरण ईस्टमेट अनुसार खुद लागेको खर्च फरक पर्न आएको कै फियत
परिमाण दर रकम परिमाण दर रकम परिमाण प्रतिशत रकम

Supply and application of One coat Emulsion paint


1 over one coat primer . 153.93 224.87 34614.2391 27.12 224.87 6098.4744 -126.81 -82.38% -28515.7647

2 supply and installation of UPVC door and window 13.49 7950.15 107247.5235 218.25 7950.15 1735120.2375 204.76 1517.87% 1627872.714

Supply and erection of iron works for railing with


prime coat painting all complete as per instruction
3 of site incharge. 228.82 180.64 41334.0448 1067.00 180.64 192742.88 838.18 366.31% 151408.8352

4 #REF! #REF! #REF! #REF! 194.00 #REF! #REF! #REF! #REF! #REF!
Sub Total #REF! #REF! #REF!
contingency @ 3% #REF! #REF!
Grand Total #REF! #REF! #REF! less

तयार पर्नेको सही चेक गर्नेको सही स्वीकृ त गर्नेको सही


Project :- Jalbinaayek Chautara Marmat

POKHARA METROPOLITAN CITY


Office of Municipal Executive
MEASUREMENT BOOK
Gandaki Province , kaski

Issued To:
Site Incharge:

Site Name: Jalbinaayek Chautara Marmat


PMC 03

Issuing Officer :

Date of first entry:


Date of last entry: 2077-12-01

Certified that this books contains 2 Page of pre - numbered measurement sheets.

Engineer Executive officer


INDEX OF MEASUREMENTS ENTERED

Pages Measured By Checked By Remarks


Name of work Done By
From To Name signature & date Name Signature & date

Jalbinaayek Chautara Bikram


1 2 User's Commettee
Marmats Timilsina
POKHARA METROPOLITAN CITY OFFICE
NEW ROAD, POKHARA
Measurment Book
Name of project :-Jalbinaayek Chautara Marmat F/Y :- 077/078
Site :- PMC-03 Date:- 25/11/2077
Kharcha Shirshak 31157
S.N Description No. Length Breadth Height Quantity Unit Rate Amount Remarks
A Construction Works
Dismentalling of cement mortar
1 masonary with deposition upto 10 mtr.
Lead works
1.00 5.80 3.40 0.100 1.97
5.80 1.97 Cum 1558.20 3069.65
2 Excavation of ordinary soft soil
1.00 4.70 5.70 0.150 4.02
0.50 5.70 3.30 0.150 1.41
1.00 11.80 0.30 0.150 0.53
4.70 5.96 Cum 605.64 3609.61
3 Boulder Soling and Levelling works
1.00 5.80 5.70 0.15 4.96
0.50 5.70 3.30 0.15 1.41
1.00 11.80 0.30 0.15 0.53
-3.14 0.55 0.55 0.15 -0.14
-3.14 0.60 0.60 0.15 -0.17
-3.14 0.85 0.85 0.15 -0.34
6.59 Sqm 3502.50 23081.47
4 Pcc works 1:2:4 works
1.00 5.80 5.70 0.075 2.48
0.50 5.70 3.30 0.075 0.71
1.00 11.80 0.40 0.075 0.35
-3.14 0.55 0.55 0.075 -0.07
-3.14 0.60 0.60 0.075 -0.08
-3.14 0.85 0.85 0.075 -0.17
3.39 Sqm 12129.36 41118.53
Stone Paving and Clidding Works 1:4
5
mortar
1.00 5.80 6.00 34.80
0.50 5.70 3.30 9.41

Prepared By: Checked By: Recommended By:


Approved By:
POKHARA METROPOLITAN CITY OFFICE
NEW ROAD, POKHARA
Measurment Book
Name of project :-Jalbinaayek Chautara Marmat F/Y :- 077/078
Site :- PMC-03 Date:- 25/11/2077
Kharcha Shirshak 31157
S.N Description No. Length Breadth Height Quantity Unit Rate Amount Remarks
1.00 12.50 0.40 5.00
1.00 3.45 0.80 2.76
1.00 3.45 0.85 2.93
1.00 1.15 0.85 0.98
1.00 4.10 0.90 3.69
1.00 1.10 0.85 0.94
1.00 1.10 0.65 0.72
-3.14 0.55 0.55 -0.95
-3.14 0.60 0.60 -1.13
-3.14 0.85 0.85 -2.27
56.88 Sqm 1851.99 105341.19

Iron Works 1" Square Pipe 11/2"


6 Square Pipe & 20*3 patti of Raling and 1.00 97.25 102.25 Kg 152.25 15567.56
Chair
Total 191,788.01
contengecies @ 3% 5,968.22
Grand total 197,756.23