Buildings 12 00298 - Compressed

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

buildings

Article
Using a Unique Retaining Method for Building Foundation
Excavation: A Case Study on Sustainable Construction Methods
and Circular Economy
Tai-Yi Liu 1, * , Shiau-Jing Ho 2 , Hui-Ping Tserng 2 and Hong-Kee Tzou 1

1 New Asia Construction and Development Corporation, 15F, No. 760, Sec. 4, Pade Rd., Taipei 10567, Taiwan;
tzou@newasia.com.tw
2 Department of Civil Engineering, National Taiwan University, No. 1, Sec. 4, Roosevelt Rd., Da-An District,
Taipei 10617, Taiwan; jessieho821@gmail.com (S.-J.H.); hptserng@ntu.edu.tw (H.-P.T.)
* Correspondence: tylaytpe@ms9.hinet.net; Tel.: +886-88-691-000-9129

Abstract: The selection of a retaining method during the excavation of building foundations is always
of paramount concern to engineers. In general, the application and use of steel H-shapes are typically
practiced by designers to form the entire retaining system; however, sustainability issues, including
carbon emission reduction, environment protection, material consumption, and resource circulation,
are being increasingly considered when developing a new project. The Linkou Public Housing Project
(LPHP), located in New Taipei City, Taiwan, is introduced in this paper to present a sustainable
soil-retaining method that also exhibits the principles of a circular economy. The triangular shape of
the foundation zone of the LPHP led to difficulty in setting the horizontal strut H-beam system. In
this project, the “Anchor Pile with Steel Cable System (APSCS)” was adopted to retain the 11.5 m
 depth excavation for the LPHP foundation construction. The prime contents of the soil in the Linkou

district comprises a laterite–gravel layer mixed with brown silty and sandy clay, with a groundwater
Citation: Liu, T.-Y.; Ho, S.-J.; Tserng,
H.-P.; Tzou, H.-K. Using a Unique
level (G.L.) of −25 m. By adopting the sustainable APSCS method, the excavation of the LPHP
Retaining Method for Building foundation was safely completed. Approximately NT $350 million in direct and indirect costs of
Foundation Excavation: A Case construction was saved, and the duration of the work was reduced by up to 90 days. Furthermore,
Study on Sustainable Construction the carbon emissions were reduced by 677.6 tons due to the diminished use of the steel H-shaped
Methods and Circular Economy. materials. The authors concluded that the use of the APSCS method in the LPHP was successful
Buildings 2022, 12, 298. https:// and it was a valuable reference for other similar projects. Moreover, the authors presented another
doi.org/10.3390/buildings12030298 retaining-system failure case, which was located near the LPHP site, to compare the success of
Academic Editors: Ming-Gin Lee and the LPHP.
Yeng-Fong Shih
Keywords: case study; circular economy; LPHP; foundation excavation; APSCS; laterite gravel;
Received: 15 January 2022
retaining-system failure
Accepted: 1 March 2022
Published: 3 March 2022

Publisher’s Note: MDPI stays neutral


with regard to jurisdictional claims in 1. Introduction
published maps and institutional affil-
A couple of retaining methods can be selected for a building’s foundation or for
iations.
other excavation works on concrete structures [1–7]. The most popular methods are
diaphragm walls, steel sheet piles, pre-stressed anchors, PC piles, and steel H-shapes/rails
combining the wooden boards. Except for pre-stressed anchors, all of these methods
Copyright: © 2022 by the authors.
need to be performed using horizontal steel H-shapes as the strut members in order to
Licensee MDPI, Basel, Switzerland. form a functional retaining system. Figure 1 shows some representative photos for the
This article is an open access article above-mentioned soil-retaining methods.
distributed under the terms and To present a clearer picture for this paper, the authors illustrated the research frame-
conditions of the Creative Commons work to show the logical development of this study, as shown in the Figure 2.
Attribution (CC BY) license (https:// The authors were aware that each type of retaining method usually required a large
creativecommons.org/licenses/by/ amount of money and would take a long time to construct. A couple of major concerns,
4.0/). such as risk management, impact to the environment, construction duration, construction

Buildings 2022, 12, 298. https://doi.org/10.3390/buildings12030298 https://www.mdpi.com/journal/buildings


Buildings 2022, 12, 298 2 of 16

Buildings 2022, 12, x FOR PEER REVIEW 2 of 18


costs, use of materials, and energy consumption, always influence the selection of the
construction method. Thus, approaches to improve safety concerns and risk reduction,
environmental impact, optimization of construction procedures, and minimization
Buildings 2022, 12, x FOR PEER REVIEW 2 ofof
18
material consumption, are seriously discussed among engineers.

Figure 1. Representative photos for foundation excavation retaining systems.

To present a clearer picture for this paper, the authors illustrated the research
framework to show thephotos
Figure 1. Representative logicalfor
development of this study,
foundation excavation as shown
retaining in the Figure 2.
systems.
Figure 1. Representative photos for foundation excavation retaining systems.

To present a clearer picture for this paper, the authors illustrated the research
framework to show the logical development of this study, as shown in the Figure 2.

Figure
Figure 2. The research
2. The research framework
framework and
and logical
logical development
development of
of this
this study.
study.

For
The these
authorsdifferent types that
were aware of retaining
each type methods, the most
of retaining methodsignificant
usually concerns
required are the
a large
occurrences
amount of some unexpected accidents during construction work. Accidents are usually
Figure 2.of
Themoney
researchand would take
framework and alogical
long development
time to construct. A couple of major concerns,
of this study.
caused
such asby anmanagement,
risk insufficient preliminary
impact to design of the retaining
the environment, system. Liu
construction (2020) proposed
duration, construc-
some sustainability indicators, such as risk mitigation and reliability, ecology, environmen-
tion costs, use of materials, and energy consumption, always influence
The authors were aware that each type of retaining method usually required a largethe selection of
tal protection, carbon emission reduction, energy savings, and waste reduction, which are
the construction
amount of money method. Thus,take
and would approaches
a long timeto improve safety
to construct. concerns
A couple of and
majorrisk reduc-
concerns,
gradually being taken into consideration for greener civil infrastructure development [8].
tion,
suchenvironmental impact,impact
as risk management, optimization
to the of constructionconstruction
environment, procedures,duration,
and minimization
construc-
Some other researchers have also performed studies that took into account the sustainabil-
of material
tion costs, consumption,
use of materials,are and
seriously
energy discussed amongalways
consumption, engineers.
influence the selection of
the construction method. Thus, approaches to improve safety concernsconcerns
For these different types of retaining methods, the most significant and riskare the
reduc-
occurrences of some unexpected accidents during construction work. Accidents
tion, environmental impact, optimization of construction procedures, and minimization are usu-
of material consumption, are seriously discussed among engineers.
For these different types of retaining methods, the most significant concerns are the
Buildings 2022, 12, 298 3 of 16

ity issues related to infrastructure projects [8–16]. This study presents a unique retaining
method named the “Anchor Pile with Steel Cable System (APSCS)”, which achieved signif-
icant sustainable goals. During the foundation excavation of the LPHP, the steel anchors
were installed at a 5 to 6 m distance from the excavated surface to serve as the anchor piles
for the steel H-shaped retaining columns. To verify that the soil condition was applicable
for the APSCS method, the shear-wave velocity test (SWVT) was performed before the
LPHP began. The SWVT results showed that the construction site had a high-shear base.
The authors present two other cases in the following section to serve as the com-
parison studies for the LPHP: the A7 Public Housing Building—Part C (A7PHB-C) and
the A7 Public Housing Building—Part D (A7PHB-D). The A7PHB-C and -D are located
close to the LPHP and were constructed a little bit earlier than the LPHP. The geological
investigation results of the LPHP and the A7PHB-C and -D revealed the similarity of the
ground condition.

2. Case Studies on the Similar Projects


2.1. Case 1: A7 Public Housing Building—Part C (A7PHB-C)
Located in the Linkou district near the LPHP project, the A7 Public Housing Building—
Part C (A7PHB-C) is part of another public housing project. The A7PHB included four
individual projects (A–D); six buildings each of 18 to 20 stories were built in this project.
The contractor of the A7PHB-C project was the same as that for the project that served
as the main study of this paper (LPHP), which was New Asia Corp. (NAC), and both of
these two projects were contracted on a design–build (DB) basis. The retaining system
designed in the A7PHB project used a traditional method, which comprised a vertical
retaining column and a horizontal strut H-beam to retain the lateral force of soils during the
basement excavation. Three layers of horizontal strut H-beam were used in the A7PHB-C
project. The excavation work has a depth of 11.2 m and the total duration of the basement
construction was 222 days. Table 1 shows some construction information for A7PHB-C.

Table 1. Summary of the excavation-related work for A7PHB-C.

Excavation Items Sum/unit Remarks


Planned area of excavation 11,739 m2 Close to rectangular shape
Divided into four layers
Depth of excavation 11.2 m
of excavation
Total soil volume of excavation 134,960 m3
Struts with single and double
Steel strut layers Three layers
H-shaped struts
Total struts weight 2163 tons
This included the lean
Duration of excavation work Two months and six days concrete placement and
strut erection
This included the construction
Basement construction duration Five months and six days for the first-floor slab and the
strut demolition

The A7PHB-C basement was completed in 2014. During the construction stage of
the basement, no accidents or disasters occurred. The retaining method for basement
excavation used the traditional horizontal strut system. This method was different from
the APSCS method applied in the LPHP. As the H-shapes were not used, the cost of the
horizontal steel strut system in the LPHP was reduced by up to NT $350 million. We
were aware that the horizontal strut steel members always seriously interfered with the
construction work, such as the material hang-in, rebar installation, and concrete placement.
This led to a longer construction duration. Thus, as the result of this traditional retaining
method, the total construction duration of the basement, including the excavation and
structure construction, lasted 7 months and 12 days. This was at least 90 days longer than
horizontal steel strut system in the LPHP was reduced by up to NT $350 million. We
were aware that the horizontal strut steel members always seriously interfered with the
construction work, such as the material hang-in, rebar installation, and concrete place-
Buildings 2022, 12, 298 4 of 16
ment. This led to a longer construction duration. Thus, as the result of this traditional re-
taining method, the total construction duration of the basement, including the excava-
tion and structure construction, lasted 7 months and 12 days. This was at least 90 days
the basement
longer construction
than the basement duration of the
construction LPHP. Figure
duration 3 showsFigure
of the LPHP. some 3different stagesdif-
shows some of
the basement
ferent construction.
stages of the basement construction.

Figure 3.
Figure 3. Different
Differentstages
stagesofofthe
theLPHP
LPHPbasement construction:
basement (a) the
construction: soil soil
(a) the excavation, (b) the
excavation, (b)hori-
the
zontal steel strut members and steel pin piles, (c) the bottom foundation, and (d) the B3 floor in-
horizontal steel strut members and steel pin piles, (c) the bottom foundation, and (d) the B3 floor
spected by the corresponding author.
inspected by the corresponding author.

From the
From thesustainability
sustainability viewpoint,
viewpoint, longer
longer construction
construction increases
increases indirect
indirect costs
costs and
and
raises risk during excavation. Furthermore, the massive quantity of materials
raises risk during excavation. Furthermore, the massive quantity of materials used for the used for
the retaining system may also increase carbon emissions during basement construction.
retaining system may also increase carbon emissions during basement construction. In this
In thisthe
paper, paper, the A7PHB-C
A7PHB-C case as
case is used is used as a comparison
a comparison project
project for for the LPHP.
the LPHP.

2.2. Case
2.2. Case 2:
2: A7
A7 Public
Public Housing
Housing Building—Part
Building—Part D D (A7PHB-D)
(A7PHB-D)
For comparison
For comparison with with the
the LPHP
LPHP andand A7PHB-C,
A7PHB-C, the the authors
authors present
present thethe A7PHB-D
A7PHB-D
project,which
project, whichwas wasthe
thesame
samedevelopment
developmentproject
projectreferred
referredto toin
inCase
Case1.1.The
Thecontractor
contractorofof
thisproject
this projectwas
wasdifferent
differenttotothat
thatofof A7PHB-C
A7PHB-C andand LPHP.
LPHP. Basic
Basic information
information in this
in this pro-
project,
ject, as
such such
the as the subsurface
subsurface condition,condition, excavation
excavation depth,
depth, and and groundwater
groundwater level, was level,
similarwas
to
that of A7PHB-C
similar to that ofand the LPHP;
A7PHB-C andhowever,
the LPHP;the however,
retaining method selected
the retaining by theselected
method contractor
by
was different in
the contractor wasthis project in
different from
this the other
project twothe
from projects.
other two The retaining
projects. Thesystem was
retaining a
sys-
combination of vertical H-beam
tem was a combination columns
of vertical H-beamandcolumns
soil blocks
andthat
soilwere protected
blocks that wereby shotcrete.
protected
Figure 4 shows
by shotcrete. the vertical
Figure 4 showssection and the
the vertical soil and
section profile
the of the
soil retaining
profile of thesystem for sys-
retaining the
A7PHB-D
tem for theproject.
A7PHB-D project.
The major components of this retaining method were the vertical H-beam columns.
They were retained by the soil block, which had a height of 9.5 m. There was no horizontal
steel strut designed for this retaining system. The total length of vertical steel columns was
uncertain. However, site observation showed that the penetration length of the vertical
steel columns into the soil was insufficient for the retaining system. Table 2 shows the
basement construction information for the A7PHB-D project.
Buildings
Buildings 2022,
2022, 12,12,
298x FOR PEER REVIEW 5 of
5 of 1618

Figure4.4.The
Figure Theretaining
retainingsystem’s
system’svertical
verticalsection
sectionand
andsoil
soilprofile
profile for
for the
the A7PHB-D
A7PHB-D project.
project.

Themajor
Table 2.The basement construction
components of information for method
this retaining the A7PHB-D
wereproject.
the vertical H-beam columns.
They were retained by the soil block, which had a height of 9.5 m. There was no horizon-
Excavation Items Sum/Unit Remarks
tal steel strut designed for this retaining system. The total length of vertical steel col-
Depth of excavation 12.3 m Divided into four layers of excavation
umns
Steel was
strut uncertain. However, site observation
layers No Strut showed that the penetration length of
the vertical steel columns into the soil was insufficient This for the retaining
included the leansystem.
concrete Table 2
shows the basement construction information for the placementproject.
A7PHB-D and reconstruction of the
Duration of excavation work Seven months and six days
failed retaining steel H-shaped
column
Table 2. The basement construction information for the A7PHB-D
This project.
included the construction for the
Basement construction duration Six months
first-floor slab
Excavation Items Sum/Unit Remarks
Depth of excavation 12.3 m Divided into four layers of excavation
In this A7PHB-D case, the excavation depth was slightly larger than that of the LPHP.
Steel strut layers No Strut
Initially, in order to save on costs, the contractor of A7PHB-D did not implement any
horizontal steel struts or a pre-stressed anchor This included
system during thethe basement
lean concrete place-
excavation
Seven months and
Duration
case. A freeofsoil
excavation
block was work
applied tosix bedays
the passivement and
earth reconstruction
pressure, as shown of the failed 4.
in Figure
retaining steel H-shaped
Unfortunately, the failure of the retaining system occurred when excavation work reached column
Basement
the bottom construction
of the basement.dura-Figure 5 shows the This included
severe failure the construction
of the for theH-
steel retaining
Six months
tion
columns in the excavation of A7PHB-D project. first-floor slab
The subsurface contained two layers of soil. The first layer (G.L. 0 to G.L. −6) com-
prisedIn this A7PHB-D silty
a reddish-brown case,clay,
the which
excavation depth was
was medium slightly
to firm, and larger than layer
the second that of the
(G.L.
−LPHP.
6 to G.L. −30) had
Initially, in order
a veryto save laterite
dense on costs, the contractor
gravel combined of withA7PHB-D
the brown didsilty
notandimplement
sandy
clay.
anyFigure 6 shows
horizontal steelthe distribution
struts of the lateral
or a pre-stressed anchorearth pressure
system from
during the
the soils (PA1excava-
basement , PA2 ,
PA3 ) and
tion theAretaining
case. free soilforce
blockexhibited by thetosoil
was applied be block (Ws). Inearth
the passive this case, the vertical
pressure, as shown steelin
columns
Figure 4. didUnfortunately,
not produce many effects of
the failure in this system. system occurred when excavation
the retaining
Buildings 2022, 12, x FOR PEER REVIEW 6 of 18

Buildings 2022, 12, 298 6 of 16


work reached the bottom of the basement. Figure 5 shows the severe failure of the steel
retaining H-columns in the excavation of A7PHB-D project.

Figure 5. Failure of steel retaining H-columns in the A7PHB-D project.

The subsurface contained two layers of soil. The first layer (G.L. 0 to G.L. −6) com-
prised a reddish-brown silty clay, which was medium to firm, and the second layer (G.L.
−6 to G.L. −30) had a very dense laterite gravel combined with the brown silty and sandy
clay. Figure 6 shows the distribution of the lateral earth pressure from the soils (PA1, PA2,
PA3) and the retaining force exhibited by the soil block (Ws). In this case, the vertical steel
columns did notofproduce
Figure 5. Failure manyH-columns
steel retaining effects in this system.
in the A7PHB-D project.
Figure 5. Failure of steel retaining H-columns in the A7PHB-D project.

The subsurface contained two layers of soil. The first layer (G.L. 0 to G.L. −6) com-
prised a reddish-brown silty clay, which was medium to firm, and the second layer (G.L.
−6 to G.L. −30) had a very dense laterite gravel combined with the brown silty and sandy
clay. Figure 6 shows the distribution of the lateral earth pressure from the soils (PA1, PA2,
PA3) and the retaining force exhibited by the soil block (Ws). In this case, the vertical steel
columns did not produce many effects in this system.

Thedistribution
Figure6.6.The
Figure distributionof
ofthe
thesoil
soilblock’s
block’slateral
lateralforce
forcefrom
fromthe
thesoil
soil and
and the
the retaining
retaining system.
system.

The equations [17] used to calculate the forces and the computed results are listed
The equations [17] used to calculate the forces and the computed results are listed
in Table 3.
in Table 3.
According to the calculated results listed in Table 3, the safety factor obtained for this
retaining system was only 0.948 and it was the primary reason for the retaining-system
failure. We were aware that the safety factor for the temporary retaining system should
have been larger than 1.2 in order to maintain the stability of the soil during the excavation.
Figure 6. The distribution of the soil block’s lateral force from the soil and the retaining system.
In this case, insufficient positive earth pressure was applied to the vertical steel H-columns,
which could not serve as safe retaining forces for the active earth pressure during the
The equations [17] used to calculate the forces and the computed results are listed
excavation. The absence of horizontal steel struts or an anchor system finally caused
in Table 3. of the steel retaining H-columns at the end of the excavation. This accident
the collapse
resulted in the construction team spending at least five months and ten days reinstalling
the retaining system. Fortunately, when the accident occurred, nobody was injured. The
knowledge that we gained from this case was that, even in such dense laterit–gravel
soil conditions, the failure of retaining system would definitely occur when an improper
retaining method was selected for the excavation work.
Buildings 2022, 12, 298 7 of 16

Table 3. The equations used to calculate the forces and the computed results for the A7PHB-D project.

Value of the Value of the Second


Parameters or Items Equations
First Layer Layer
Coefficient of at-rest earth pressure, K0 K0 = 1 − sinØ 0.500 0.426
Coefficient of active earth pressure, KA KA = tan2 (45o − Ø/2) 0.333 0.271
Coefficient of passive earth pressure, KP KP = tan2 (45o + Ø/2) 1.012 1.010
Retaining height, Hc/Hg (m) 6.000 7.000
Dry soil density, rd (t/m3 ) 1.850 2.000
Earth pressure per unit of width due to soil pressure,
3.700 3.700
Pa1 (t) Pa = KA × H × rd
Earth pressure per unit of width due to soil pressure,
3.794
Pa2 (t)
Resultant active earth pressure, PA1 (t) PA1 = Pa1 × Hc × (1/2) 11.100
Resultant active earth pressure, PA2 (t) PA2 = Pa2 × Hg 25.900
Resultant active earth pressure, PA3 (t) PA3 = Pa3 × Hg × (1/2) 13.279
Weight of the soil block (t) V × rd 70.000
Gravity center of soil block in relation to the retaining
3.000
boundary O, L (m)
Height of pressure PA1 , H1 (m) Hc × (1/3) + Hg 9.000
Height of pressure PA2 , H2 (m) Hg × (1/2) 3.500
Height of pressure PA3 , H3 (m) Hg × (1/3) 2.333
Turning moment produced by PA1 , M1 (t–m) PA1 × H1 99.900
Turning moment produced by PA2 , M2 (t–m) PA2 × H2 90.650
Turning moment produced by PA3 , M3 (t–m) PA3 × H3 30.983
Total turning moment, MA (t–m) MA = M1 + M2 + M3 221.533
Turning moment produced by Ws, Ms (t–m) Ms = Ws × L 210.000
Safety factor Ms/MA 0.948

3. Comparison of A7PHB-C and A7PHB-D


For the best realization of the feature differences between the A7PHB-C, A7PHB-D,
and LPHP projects, the authors summarized the essential information of these three projects,
as shown in Table 4. Please note that a detailed description of the LPHP is provided in the
following sections.

Table 4. The comparison of essential information between the A7PHB-C, A7PHB-D, and LPHP projects.

Items A7PHB-C A7PHB-D LPHP Remarks


Laterite–gravel soil (LGS) Laterite–gravel soil (LGS) Laterite–gravel soil (LGS) The soil contents is the
Soil condition layer mixed with brown layer mixed with brown layer mixed with brown same for these three
silty and sandy clay silty and sandy clay silty and sandy clay projects
There was no
Under excavation Under excavation Under excavation
Groundwater level groundwater in the
bottom level bottom level bottom level
Linkou district
Planned area of excavation 11,739 m2 14,295 m2 16,060 m2
Depth of excavation 11.2 m 12.3 m 10.6 m
Steel strut layers Three layers of struts No Strut No Strut
The duration of A7PHB-D
includes the
Duration of excavation Seven months and six One month and seven
Two months and six days reconstruction of the failed
work days days
retaining steel H-shaped
column
Basement construction
Five months and six days Six months Four months and two days
duration
Retaining-system safety
1.792 0.948 1.543
factor
Materials used in the
2163 t 876 t 342 t
retaining system
High carbon emissions High carbon emissions
Environmental protection cause by the high caused by the collapse Low carbon emissions
material consumption accident
The effectiveness of the
Low effectiveness Low effectiveness High effectiveness
construction method
Note: a detailed description for the LPHP is provided in the following sections.
Buildings 2022, 12, 298 8 of 16

4. Description of the Linkou Public Housing Project (LPHP)


The LPHP project was located in the Linkou district, New Taipei City, Taiwan. It
was close to the other two cases, A7PHB-C and D, described above. The LPHP included
nine buildings; each building contained 19–21 stories. The contract between the client
and contractor was a design–build project, and its purpose was to serve as an athletes’
village for the 2017 Taipei Summer Universiade. The project boundary’s outline shape
was somewhat close to triangular, as shown in Figure 7. Table 4 lists some information for
the LPHP basement excavation. The construction results listed in Table 5 were based
Buildings 2022, 12, x FOR PEER REVIEW 9 of on
18
applying the proposed unique retaining method, APSCS, in this paper.

Figure 7. Plan view of the LPHP.


Figure 7. Plan view of the LPHP.
Table
Table 5.
5. Summary
Summaryof
of the
the excavation-related
excavation-related work
work for
for the
the LPHP.
LPHP.
Excavation Items
Excavation Items Sum with
Sum Unit
with Unit Remarks Remarks
Planned
Planned area
area ofofexcavation
excavation 16,06016,060
m m2 Close to a triangular
2 shape shape
Close to a triangular
Depth of excavation
Depth of excavation
10.6 m10.6 m Divided into four into
Divided layersfourof excavation
layers of
excavation
Total soil volume of
Total soil volume of 185,500 m3 m3
185,500
excavation
excavation
Steel strut layers Nonestrut
None strut member
Steel strut
Anchor layers
piles for bearing forces 97 pcs. Steel rails of 50 kg grade, L = 13 m
member This included the lean concrete
Duration of excavation work One month and seven days
Anchor piles for bearing forc- placement
97 pcs. Steel rails of 50included
This kg grade, L = 13 m for
the construction
esBasement construction Four months and two days the
duration
One month and This included the lean
first-floor slab concrete place-
Duration of excavation work
seven days ment
Basement construction
The soil Fourdistrict
profile in the Linkou months is and This included
a laterite–gravel the
soil construction
(LGS) for the
layer mixed with
duration two days first-floor slab
brown silty and sandy clay, which appears as a red/brown color, as shown in Figure 8.

The soil profile in the Linkou district is a laterite–gravel soil (LGS) layer mixed with
brown silty and sandy clay, which appears as a red/brown color, as shown in Figure 8.
The soil combination is mainly LGS, and the groundwater level in this area is 25 m be-
low ground level (i.e., G.L. −25 m) and did not cause any interference with the excava-
Buildings 2022, 12, 298 9 of 16

The soil combination is mainly LGS, and the groundwater level in this area is 25 m below
ground level (i.e., G.L. −25 m) and did not cause any interference with the excavation work.
A total of 16 boreholes were made for standard penetration tests (SPTs) and soil samples
were gathered for laboratory testing and analysis before the excavation work began [18].
Buildings 2022, 12, x FOR PEER REVIEW Figure 9 shows the example of the standard penetration test (SPT) results, and Table 6 10 of 18
shows the simplified soil parameters of the LPHP site, which were based on the 16 holes of
Buildings 2022, 12, x FOR PEER REVIEW 10 of 18
the SPT results.

Figure 8. The appearances of the laterite–gravel soil (LGS) layer mixed with brown silty and sandy
Figure
Figure8.8.The
Theappearances
appearances ofofthe
thelaterite–gravel
laterite–gravel
soilsoil (LGS)
(LGS) layer
layer mixed
mixed with with
brownbrown silty
silty and and sandy
sandy
clay in the Linkou district.
clay in the Linkou district.
clay in the Linkou district.

Figure 9. Example of site SPT results for the LPHP.

Table 6. Simplified soil parameters of the LPHP site.

Depth Figure
Figure9.9.Example
Unit of
Example of siteSPT
site
Cc/Cs SPTresults
results
Kv forfor
thethe LPHP. Su
LPHP.
Kh c Ø C’ Ø’
Layer Contents N Value
(G.L.) Weight (T/m ) 3 (T/m )3 (T/m )3 (T/m ) (T/m )
3 3 (o) (T/m )3 (o)
Table 6. Simplified soil parameters of the LPHP site.
6~12
Clay/ 0~5 1.84 0.2/0.02 1600 1600 4.2 2.5 15.0 0.0 29.0
Depth (say 8) Unit Cc/Cs Kv Kh Su c Ø C’ Ø’
1 Lateritic–
Layer Contents N Value
12~24 Weight (T/m3)
gravel soil(G.L.)
5~9.8 1.87 0.2/0.02 (T/m3) 2230
3600 (T/m3) 10.8
(T/m3) 5.5(T/m315.0
) (o) 0.0 (T/m 3)
32.0 (o)
Buildings 2022, 12, 298 10 of 16

Table 6. Simplified soil parameters of the LPHP site.

Depth N Unit Cc/Cs Kv Kh Su c Ø C’ Ø’


Layer Contents
(G.L.) Value Weight (T/m3 ) (T/m3 ) (T/m3 ) (T/m3 ) (T/m3 ) (o) (T/m3 ) (o)

Clay/ 6~12
0~5 1.84 0.2/0.02 1600 1600 4.2 2.5 15.0 0.0 29.0
1 Lateritic–gravel (say 8)
soil 12~24
5~9.8 1.87 0.2/0.02 3600 2230 10.8 5.5 15.0 0.0 32.0
(say 18)
Lateritic–gravel
2 9.8~ >50 2.20 NP 8000 3380 NP 1.0 35.0 0.0 42.0
soil

As was already realized, the excavation of the basement construction was typically
protected by a vertical retaining system with horizontal steel struts and pin piles, which are
shown in Figures 1 and 2. In the LPHP case, due to the triangular shape of the construction
site, the horizontal steel strut system was not suitable to be the retaining system. For
safety, for the basement excavation of the LPHP the “Anchor Pile with Steel Cable System
(APSCS)” method [19,20] was applied; a detailed description of the APSCS is provided in
the next section.

5. Special Retaining Method for Excavation Work, APSCS


5.1. Detailed Description of the Anchor Pile with Steel Cable System (APSCS)
As mentioned in the previous sections, the site’s shape led to a challenge in designing
and building a horizontal steel strut system. As presented in Section 2.2, a poor retaining-
system design could cause failure or disaster during basement excavation. Thus, a special
retaining method, APSCS, was designed and established to prevent any unforeseen dis-
asters. Not only was the risk/danger of excavation significantly reduced, higher levels
of sustainability were achieved, carbon emissions were reduced, and a circular economy
Buildings 2022, 12, x FOR PEER REVIEW
was reached in the LPHP case. Table 7 shows the major components of the APSCS, 12 andof 18

Figure 10 shows its cross section.

Figure
Figure 10.10. Cross
Cross section
section of of APSCS
APSCS method.
method.

The laterite–gravel soil (LGS) layer might have been softened by contact with water,
which would have caused a serious and drastic increase in the active earth pressure and
reduced the stability of the retaining system. The risk of collapse of the retaining mem-
bers would have been increased under this condition. Avoiding the occurrence of this
Buildings 2022, 12, 298 11 of 16

Table 7. Major components of the APSCS method adopted in the LPHP.

Remarks (G.L. in Reference


Items Description Quantity
to Ground Level)
H350 × 350 × 12 × 19, L = 16
Vertical steel column @0.8~1 m G.L. 0~−16 m
m
Horizontal wales H350 × 350 × 12 × 19 1 G.L. −0.8 m ±
For forces transferring from
Steel cable D32 mmΦ, L = 5~7 m @5~6 m
the anchor pile to the wall
Anchor piles 50 kg grade steel rail, L = 14 m @5~6 m G.L. 0.5~−13.5 m
f’c = 140 kg/cm2 , Thk = 20 cm, On the ground level, around
Protective concrete layer Figure 10. Cross section With D = 6 mm wire mesh
W = 5~6 m of APSCS method. the site

The laterite–gravel soil (LGS) layer might have been softened by contact with water,
whichThe laterite–gravel
would have caused soila (LGS)
seriouslayer
and might
drastichave beenin
increase softened by earth
the active contact with water,
pressure and
which would have caused a serious and drastic increase in the active earth
reduced the stability of the retaining system. The risk of collapse of the retaining mem- pressure and
reduced
bers the have
would stability of the
been retaining
increased system.
under this The risk of collapse
condition. Avoiding of the
the retaining
occurrence members
of this
would have been increased under this condition. Avoiding the occurrence
situation, by setting a 20 mm-thick wire-meshed concrete layer to protect against rain of this situation,
by setting
water andawater
20 mm-thick wire-meshed
from cleaning concrete
and other layer to protect
operations, against
is necessary rainan
with water
LGSand water
layer, as
from cleaning and
shown in Figure 11. other operations, is necessary with an LGS layer, as shown in Figure 11.

Figure 11. The


Figure 11. The layout
layout of
ofthe
theAPSCS
APSCSmembers
memberswith
with the
the wire-mashed
wire-mashed concrete
concrete protection
protection layer
layer at
at the
the ground level.
ground level.

5.2. Analysis by Static Calculation


According to Terzaghi’s formula [17], a horizontal soil pressure diagram with a balance
condition can be reached, as shown in Figure 12.
With the simplified soil parameters obtained from SPT results in Section 3, the balanced
condition of the APSCS cross section is shown in Figure 13 [17].
By adopting the geological equations, the parameters γd , ψ, K0 , KA , and KP , were
then determined, which are listed as shown in Table 8. Table 9 shows the calculated results
for the H350 retaining steel columns, including σ, τ, and ∆.
In Table 9, the equation was adopted to calculate the maximum moment in the H350
column, which was based on the free-body diagram, as shown in Figure 14.
The allowable stress of ASTM A36 materials (σa) is 1500 kg/cm2 , and τa is 1000
kg/cm2 . The σmax , τmax , and ∆max , as shown in Table 9, confirmed the safety of the
retaining-system APSCS method used in the LPHP.
5.2.
5.2.Analysis
Analysisby by
Static Calculation
Static Calculation
Buildings 2022, 12, 298 According
According to Terzaghi’s formula
to Terzaghi’s [17], a[17],
formula horizontal soil pressure
a horizontal diagram with
soil pressure 12 ofa16bal- wit
diagram
ance condition can be reached, as shown in Figure 12.
ance condition can be reached, as shown in Figure 12.

Figure 12. Balanced horizontal soil pressure diagram based on Terzaghi’s formula.

With the simplified soil parameters obtained from SPT results in Section 3, the bal-
anced
Figurecondition of horizontal
12. Balanced the APSCS soilcross section
pressure is shown
diagram inTerzaghi’s
based on Figure 13formula.
[17].
Figure 12. Balanced horizontal soil pressure diagram based on Terzaghi’s formula.

With the simplified soil parameters obtained from SPT results in Section 3, t
anced condition of the APSCS cross section is shown in Figure 13 [17].

Figure
Figure13.
13.The
Thebalanced
balanced condition of the
condition of theAPSCS
APSCScross
crosssection.
section.

Figure 13. The balanced condition of the APSCS cross section.


Buildings 2022, 12, 298 13 of 16

Table 8. The geological equations were adopted to calculate the forces and the computed results for
the LPHP project.

Parameters or Items Equations Calculated Value


Dry soil density, rd (t/m3 ) 2.0
The angle of internal friction (◦ ) 35.0
Surcharge 0.0
Retaining height, H (m) 9.6
Coefficient of at-rest earth pressure,
K0 = 1 − sinØ 0.4264
K0
Coefficient of active earth pressure,
KA = tan2 (45◦ − Ø/2) 0.271
KA
Coefficient of passive earth pressure,
KA = tan2 (45◦ + Ø/2) 3.69
KP
Earth pressure per unit of width due
Pa1 = KA × H × rd 5.203
to soil pressure, Pa1 (t)
Earth pressure per unit of width due
Pa2 = K0 × H × rd 0.0
to soil pressure, Pa2 (t)
Pa1 + Pa2 5.203
Resultant active earth pressure, PA (t) PA = Pa1 × H × (1/2) + Pa2 × H 24.974

Table 9. Calculated results for the H350 retaining steel columns applied in the APSCS LPHP including
σ, τ, and ∆.

Parameters or Items Equations Calculated Value Remark


Maximum lateral force,
Pmax = PA × 1000 24,974
Pmax (kg)
H350 column length, L (cm) L = H × 100 960
Height of H350, Hh (cm) Hh = 350/10 35
Cross sectional area of H350,
173.87
Area (cm2 )
Second axial moment of
Ix = Bh × Hh 3 /12 40,295
H350 shape, Ix (cm4 )
Maximum moment in H350 Pmax × a × b2
× (2 × L + a)/ Please refer to
2,367,905
column, Mmax (kg-cm) (2 × L3 ) Figure 13
Maximum moment stress,
σmax = Mmax × (Hh /2)/Ix 1028
σmax (kg/cm2 )
Maximum shear stress, τmax
τmax = Pmax /Area 144
Buildings 2022, 12, x FOR PEER REVIEW(kg/cm2 ) 15 of 18
Maximum horizontal
∆max = Pmax × L3 /(48 × E × Ix) 5.44 E = 2.1 × 106
deflection, ∆max (cm)

Figure14.
Figure Thefree-body
14.The free-body diagram
diagram for
for the
the calculation
calculationofofthe
themaximum
maximummoment
momentin in
thethe
H350 column.
H350 col-
umn.

The allowable stress of ASTM A36 materials (σa) is 1500 kg/cm2, and τa is 1000
kg/cm2. The σmax, τmax, and Δmax, as shown in Table 9, confirmed the safety of the retain-
ing-system APSCS method used in the LPHP.
Figure 14. The free-body diagram for the calculation of the maximum moment in the H350 col-
umn.

The allowable stress of ASTM A36 materials (σa) is 1500 kg/cm2, and τa is 1000
Buildings 2022, 12, 298 14 of 16
kg/cm2. The σmax, τmax, and Δmax, as shown in Table 9, confirmed the safety of the retain-
ing-system APSCS method used in the LPHP.

5.3.
5.3. Equipped
Equipped Monitoring
Monitoring Results
Results during
during and
and after
after thethe Excavation
Excavation
AA totalofofsix
total sixinclinometers
inclinometerswere
wereinstalled
installedtoto monitor
monitor the
the horizontal
horizontal displacements
displacements of
ofthe
theH350
H350retaining
retainingcolumns
columnsduring thethe
during excavation
excavationstage. Figure
stage. 15 shows
Figure the diachronic
15 shows the dia-
graphics of the horizontal displacements measured by the No.3 inclinometer.
chronic graphics of the horizontal displacements measured by the No.3 inclinometer.

Figure 15. Diachronic graphics of the horizontal displacements monitored by the No.3 inclinometer.

It was clear from Figure 14 that the maximum horizontal displacement at the top of the
H350 steel columns was 13.71 cm. This value was obviously larger than the ∆max , which
was 5.44 cm, as listed in Table 9. This was caused by the horizontal displacement of the
top of the anchor pile. The engineers judged that no safety issue needed to be addressed
during that stage. The value of this horizontal displacement on the anchor pile top was
measured to be 8.27 cm.

5.4. Carbon Emission Reduction for Sustainability and the Circular Economy Issue
Compared to Case 1, A7PHB-C, as described in Section 2.1, the APSCS method
achieved effective carbon reduction and exhibited the principles of a circular economy
because fewer materials were used. Table 10 lists the carbon emission reduction results
achieved by adopting the APSCS.
Furthermore, when compared to Case 1, the APSCS method reduced the construc-
tion costs by up to NT $350 million and shortened the construction duration by at least
90 days. The APSCS also successfully achieved the principle of the circular economy. Most
importantly, without any horizontal struts in the basement construction zone, the APSCS
method provided a safer site environment for the installer/worker to perform construction
work. Compared to Case 2, the A7 public housing building project, Part D (A7PHB-D),
mentioned in Section 2.2, the proposed APSCS method successfully prevented the occur-
rence of any accidents or disasters during the excavation of the basement. Figure 16 shows
the construction site after excavation work (under the corresponding author’s supervision)
Buildings 2022, 12, 298 15 of 16

and the layout of the APSCS members with the wire-meshed concrete protection layer at
the ground level, respectively.

Table 10. Carbon emission reduction results achieved by adopting the APSCS.

Carbon Emission Carbon


No Items Unit Summary Remark
Factor Reduction (kg)
Material
1 Strut Kg 2,550,000 2.42 617,100
ratio = 10%
2 Transportation t-km 99,500 0.24 23,800
3 Diesel fuel (fixed location) L 3100 3.42 10,602
4 Diesel fuel (moved location) L 4320 3.45 14,904
5 Gas fuel L 3500 3.10 10,850
Buildings
6 2022,Power
12, x FOR PEER REVIEW set 350 0.69 242 17 of 18
Total 677,578

Figure 16.
Figure 16. The
Theconstruction
constructionsite
site after
after excavation
excavation using
using the APSCS
the APSCS method
method (under
(under author’s
author’s super-
supervision).
vision).
6. Conclusions
6. Conclusions
In this LPHP project, the application of the APSCS not only had the risk of disaster
been Inprevented,
this LPHP butproject,
also thethe
carbon emissions
application hadAPSCS
of the been reduced
not onlybyhad
up to
the677,578
risk oftons, and
disaster
the
beenprinciple of abut
prevented, circular
also economy
the carbonhad been achieved
emissions had been duereduced
to the decrease
by up toin677,578
the amount
tons,
of
andconstruction
the principlematerials used. economy
of a circular Under a similar
had been soilachieved
condition,
duegroundwater
to the decreaselevel,
inand
the
excavation depth, the construction duration of the LPHP was less than those
amount of construction materials used. Under a similar soil condition, groundwater lev- of A7PHB-C
and A7PHB-D,
el, and excavationwhich were
depth, the119 days and 179
construction days, respectively.
duration of the LPHP Furthermore,
was less than thethosesteel
of
H-shaped materials used for the retaining system of the LPHP were significantly
A7PHB-C and A7PHB-D, which were 119 days and 179 days, respectively. Furthermore, reduced
by
the up to H-shaped
steel 1800, compared to the
materials usedtraditional retaining
for the retaining method
system adopted
of the in thesignificant-
LPHP were A7PHB-C
project.
ly reducedThebyunique
up toretaining system, to
1800, compared thethe
APSCS method,
traditional executed
retaining the excavation
method adopted in of the
the
LPHP foundation with stability and safety. The direct/indirect cost
A7PHB-C project. The unique retaining system, the APSCS method, executed the exca-of construction was
reduced
vation ofby theupLPHP
to NTfoundation
$350 million, and
with the duration
stability was reduced
and safety. by up to 90cost
The direct/indirect days.of Any
con-
possible
struction was reduced by up to NT $350 million, and the duration was reduced byspecial
accidents or disasters were also prevented. The authors concluded that the up to
APSCS method is a successful, reliable, and functional method to serve as the retaining
90 days. Any possible accidents or disasters were also prevented. The authors concluded
system for basement excavations.
that the special APSCS method is a successful, reliable, and functional method to serve
as the retaining system for basement excavations.
Author Contributions: Conceptualization, T.-Y.L. and S.-J.H.; software, H.-P.T.; validation, H.-K.T.;
formal analysis, T.-Y.L. and S.-J.H.; investigation, T.-Y.L., S.-J.H., and H.-P.T.; resources, T.-Y.L.; data
Author Contributions: Conceptualization, T.-Y.L. and S.-J.H.; software, H.-P.T.; validation, H.-
curation, T.-Y.L. and S.-J.H.; writing—original draft preparation, T.-Y.L. and S.-J.H.; writing—review
K.T.; formal analysis, T.-Y.L. and S.-J.H.; investigation, T.-Y.L., S.-J.H., and H.-P.T.; resources, T.-
and editing, H.-P.T. and H.-K.T.; supervision, H.-P.T. and H.-K.T.; project administration, T.-Y.L. and
Y.L.; data curation, T.-Y.L. and S.-J.H.; writing—original draft preparation, T.-Y.L. and S.-J.H.;
H.-K.T.; All authors have read and agreed to the published version of the manuscript.
writing—review and editing, H.-P.T. and H.-K.T.; supervision, H.-P.T. and H.-K.T.; project admin-
istration, T.-Y.L.
Funding: and H.-K.T.;
This research All
received noauthors
externalhave read and agreed to the published version of the
funding.
manuscript.
Institutional Review Board Statement: Not applicable.
Funding: This research received no external funding.
Institutional Review Board Statement: Not applicable.
Informed Consent Statement: Not applicable.
Buildings 2022, 12, 298 16 of 16

Informed Consent Statement: Not applicable.


Data Availability Statement: Not applicable.
Acknowledgments: The authors would like to express special appreciation to all leaders of the New
Asia Construction and Development Corporation. Furthermore, their efforts on disaster prevention,
carbon emission reduction, and circular economies have successfully achieved many outstanding
results during the past few years. These results were of the utmost important for the completion of
this paper.
Conflicts of Interest: The authors declare no conflict of interest.

References
1. Lim, A.; Ou, C.-Y.; Hsieh, P.-G. Investigation of the integrated retaining system to limit deformations induced by deep excavation.
Acta Geotech. 2018, 13, 973–995. [CrossRef]
2. Lim, A.; Ou, C.-Y.; Hsieh, P.-G. A novel strut-free retaining wall system for deep excavation in soft clay: Numerical study. Acta
Geotech. 2020, 15, 1557–1576. [CrossRef]
3. Xu, C.; Chen, Q.; Wang, Y.; Hu, W.; Fang, T. Dynamic Deformation Control of Retaining Structures of a Deep Excavation. J.
Perform. Constr. Facil. 2016, 30, 04015071. [CrossRef]
4. Ye, S.; Zhao, Z.; Wang, D. Deformation analysis and safety assessment of existing metro tunnels affected by excavation of a
foundation pit. Undergr. Space 2020, 6, 421–431. [CrossRef]
5. Liu, J.; Song, J.; Zhang, Z.; Hu, N. Influence of the Ground Displacement and Deformation of Soil around a Tunnel Caused by
Shield Backfilled Grouting during Construction. J. Perform. Constr. Facil. 2016, 31, 04016117. [CrossRef]
6. Commend, S.; Geiser, F.; Crisinel, J. Numerical simulation of earthworks and retaining system for a large excavation. Adv. Eng.
Softw. 2004, 35, 669–678. [CrossRef]
7. Alipour, A.; Eslami, A. Design adaptations in a large and deep urban excavation: Case study. J. Rock Mech. Geotech. Eng. 2019, 11,
389–399. [CrossRef]
8. Liu, T.Y. Establishment of Sustainability Key Indicators for Civil Engineering and Their Applications in Green Infrastructure Projects.
Ph.D. Dissertation, Department of Civil Engineering, College of Engineering, National Taiwan University, Taipei, Taiwan, 2020.
[CrossRef]
9. Liu, T.-Y.; Chen, P.-H.; Chou, N.N.S. Comparison of Assessment Systems for Green Building and Green Civil Infrastructure.
Sustainability 2019, 11, 2117. [CrossRef]
10. Shen, L.; Wu, Y.; Zhang, X. Key Assessment Indicators for the Sustainability of Infrastructure Projects. J. Constr. Eng. Manag. 2011,
137, 441–451. [CrossRef]
11. Lin, S.J.; Liu, T.Y.; Chou, N.N.; Chen, P.H.; Liao, C.L. Soil Improvement and In-spection Techniques for the Base Course of Rigid
Pavement for an Airport Runway. ASCE J. Perform. Constr. Facil. 2020, 35, 06021001. [CrossRef]
12. Shau, H.-J.; Liu, T.-Y.; Chen, P.-H.; Chou, N.N.S. Sustainability Practices for the Suhua Highway Improvement Project in Taiwan.
Int. J. Civ. Eng. 2019, 17, 1631–1641. [CrossRef]
13. Yates, J.K. Design and Construction for Sustainable Industrial Construction. J. Constr. Eng. Manag. 2014, 140, B4014005. [CrossRef]
14. Chisholm, D.; Reddy, K.; Beiler, M.R.O. Sustainable Project Rating Systems, Including Envision. In Engineering for Sustainable
Communities: Principles and Practices; ASCE: Reston, VA, USA, 2017; Chapter 20. [CrossRef]
15. PAS 2050; Specification for the Assessment of the Life Cycle Greenhouse Gas Emissions of Goods and Services. British Standards
Institution (BSI): London, UK, 2011.
16. ISO/TS 14067; Specifies Principles, Requirements and Guidelines for the Quantification and Communication of the Carbon
Footprint of a Product. British Standards Institution (BSI): London, UK, 2013.
17. Bowles, J.E. Foundation Analysis and Design; McGraw-Hill, Inc.: New York, NY, USA, 1988.
18. New Asia Construction and Development Corp. Site SPT Test Report for Taipei 2017 Summer Universiade Athlete’s Village and
Linkou Public Housing Project. 2013; unpublished article. (In Chinese)
19. New Asia Construction and Development Corp. Basement Excavation Plan for Taipei 2017 Summer Universiade Athlete’s Village
and Linkou Public Housing Project. 2013; unpublished article. (In Chinese)
20. New Asia Construction and Development Corp. Analysis and Calculation of Basement Excavation Retaining Method for Taipei
2017 Summer Universiade Athlete’s Village and Linkou Public Housing Project. 2003; unpublished article. (In Chinese)

You might also like