Professional Documents
Culture Documents
Disputes and Claims
Disputes and Claims
eventuate the Contractor avoiding pricing where the lenders require “greater certainty” about a
risks which are not easy ( ) to project's costs to the Employer than is allowed for under the
evaluate accurately. allocation of risks provided for by FIDIC's traditional forms of contracts.
Consensual variation,
variation compared with a limited restrictions on its right to
limited,
unilaterally ordered variation, requires vary to achieve its objectives.
mutual agreement and consideration.
work.
work
breach of contract by the employer This may apply in circumstances where the
employer or the contractor is responsible
for the risk that has led to the standstill on
the project.
The length of pipe in the bill of quantities , work done beyond low-water mark is
corresponded with the length of pipe shown in not covered by any price in the schedule of
. .
paying the higher rate, the Engineer failing to instruct the Contractor to
ordered the omission of topsoil import fill where he still intended to have
obtained off site and employed another
the full quantities of topsoil placed.
Contractor for that purpose.
Where extra work is outside he would have attics involving 10 extra bedrooms
added to the houses, and he totally changed the plan
the contract of the back of the building, with the object of
converting the premises into an inn.
Half the contract price of £375 was to be paid for in
“store‐goods” from B’s store. The Architect valued the
extra work at £513.
W sued for the balance due and B claimed to rely Meyer v Gilmer - 1899
on the contract for a delay penalty and also for the A contract in New Zealand provided by Cl. 12 that
“store-goods”
g method of p
payment.
y no variations should be paid for unless a
Held. This was not extra work done under the written order was given by the Architect.
wholly
h ll deviating
d i ti f
from th
the alteration of an old building,
b ilding there were
ere many
man and
former contract, which could not be in any sense extensive alterations no resemblances
regarded as work done upon the terms thereof. between the plans and the works as finished.
Employer, although he had not obtained the contract and were not such as were
instructions in writing. contemplated by the contract as extras.
Once it was shown to be impossible to follow Havant BC v South Coast Shipping (1996)
the method statement, doing the work The job was a beach replenishment scheme.