Professional Documents
Culture Documents
03 Uap Docs 301 1
03 Uap Docs 301 1
SECTION 1: DEFINITIONS
• CONTRACT DOCUMENTS – consists of the
following:
1. Agreement
2. General conditions
3. Special provisions
4. Specifications
5. Drawings
OWNER
person ordering the project for execution
ARCHITECT
commissioned by the owner
ENGINEER
person so named in the contract document
PROJECT REPRESENTATIVE
full time construction inspector hired by owner
assisting in the supervision of the work.
CONTRACTOR
person or firm whose proposal has been
accepted & contract awarded
SUB-CONTRACTOR
having direct contact with contractor, acts in
behalf of the contractor in executing any part of
the contract
SURETY
person, firm, or corporation providing guarantee
for contractor’s bonds
PROPOSAL
offer of a bidder
PROPOSAL BOND
cashier’s check or surety bond with the proposal
submitted by the bidder to guarantee that the
bidder will enter into the contract.
PERFORMANCE BOND
(15%) approved form of security furnished by
the contractor as a guarantee to execute work in
accordance with terms of the contract.
PAYMENT BOND
(15%) approved form of security furnished by
the contractor as guarantee to pay all
obligations arising from the contract
GUARANTEE BOND
(15%) approved form of security furnished by
the contractor to guarantee to the quality of
materials and workmanship performed.
AGREEMENT
(15%) approved form of security furnished by
the contractor to guarantee to the quality of
materials and workmanship performed.
ADVERTISEMENT/ INVITATION
TO BID
notice or invitation issued to bidders giving
information of the magnitude and extent of the
project, nature, etc.
BID BULLETIN
additional information on contract documents
INSTRUCTION TO BIDDERS
list of instructions on preparation & conditions
for award of contract
DRAWINGS
graphical representation of work
GENERAL CONDITIONS
printed documents stipulating procedural and
administrative aspects of the contract
SPECIAL PROVISIONS
instructions that supplement or modify
drawings, specs, & general conditions of the
contract.
SPECIFICATIONS
written or printed description of work describing
qualities of materials and mode of construction
SUPPLEMENTARY SPECS
addt’l info issued as an addition or amendment
to provisions of specs.
SCHEDULE OF MATERIALS AND
FINISHES
outline specs enumerating type and trade
names of materials used
BREAKDOWN OF WORK AND
CORRESPONDING VALUES
list of work and corresponding value in materials
& labor including profit and overhead
allowance.
WRITTEN NOTICE
info, advice or notification pertinent to the
project
ACT OF GOD/ FORCE MAJEURE
catastrophes, phenomena of nature,
misfortunes and accidents which human
prudence cannot foresee or prevent.
TIME LIMITS
duration of time allowed by the contract for
project completion
LOCAL LAWS
laws, ordinances, and government regulations
applicable to the project
WORK
includes labor and materials, equipment,
transportation, faculties necessary for
completion of the project
FURNISH
purchase and/or fabricate and deliver to the
jobsite”
INSTALL
build in, mount in positions, connect or apply
PROVIDE
“furnish and install”
SECTION 2:
• EXECUTION, CORRELATION AND INTENT OF
DOCUMENTS
• Documents signed in quintuplicate by owner
and contactor duly witnessed
Intent of contract documents
- prescribe the complete work
- Intention is to include labor, materials, equipment
and transportation necessary for completion and
Execution
- Specs shall take control in discrepancies in
drawings and specs
- Any discrepancies, errors and omissions shall be
reported to the architect or engineer. Any work
done involving errors are the contractor’s risk
Intent of contract documents
- Architect or engineer shall furnish additional detail
drawings and instructions consistent to contract
documents.
- Contractor and architect and engineer shall jointly
prepare a schedule in accordance to progress of work.
- Contractor shall keep a copy of all drawings, specs,
breakdown of work, and schedule of constructions
work, instructions at the site.
- Drawings, specs, and models are property of the
architect and are to be returned at completion of work
and before final payment to the contractor is made
ARTICLE 3: DRAWINGS AND SPECS
• Owner shall furnish contractor 3 sets of
drawings and specs for free
• Drawings and models must cooperate with
specs to form as part of the contract
documents. Figures are to be followed in
preference to measurement and scale.
ARTICLE 3: DRAWINGS AND SPECS
The contractor shall explain and verify any doubt as to
the meaning of the drawings and specs.
1. If there is a conflict in both drawings and specs, the
contractor, with the architect’s permission, shall
submit to the owner proposals as to which method or
material is required. If the les expensive work is done,
the contractor shall credit the owner the amount
equivalent to the difference of the expensive and less
expensive work.
2. The contractor must first refer to the architect before
proceeding with the work
ARTICLE 3: DRAWINGS AND SPECS
Discrepancies in figures, drawings must be
referred to the architect before any adjustment
be made by the contractor. The decision of the
architect will govern and must be followed by
the contractor
ARTICLE 4: DETAIL DRAWINGS AND
INSTRUCTIONS
Supplementary drawings and instructions shall
be promptly supplied by the architect and must
conform to contract documents. Contractor shall
do no work without proper drawings and
instructions.
Contractor and architect shall prepare a
schedule a when detail drawings will be
required.
ARTICLE 5: SHOP DRAWINGS
• Contractor shall prepare at his own expense and
submit 2 copies of all shop drawings to the
architect, who will make the necessary
corrections, and file the corrected copies.
• Contractor shall check drawings before
submitting to sub-contractors.
• Shop drawings shall represent:
1. Working and erection dimension
2. Arrangements and sectional views
3. Necessary details
4. Kinds of materials and finishes
ARTICLE 5: SHOP DRAWINGS
• Shop Drawings shall be dated and contain:
1. Name of project
2. Descriptive names of equipment, materials and
classified item numbers
3. Location at which materials or equipment are to be
installed.
• All permits and licenses necessary shall be secured and fees paid by
the contractor but may be reimbursed from the owner. Contractor
is responsible if construction starts without necessary permits.
• Contractor will secure the occupancy permit.
• Owner is responsible for establishment of boundaries made by a
licensed surveyor. He may delegate the responsibility to the
contractor but the owner must pay for surveyor’s fees.
1. Contractor shall verify all grades, lines and levels as
indicated on drawings.
2. Contractor shall provide batter boards and maintain them.
He shall establish grade marks at
each floor line.
3. Contractor shall layout exact location of partitions
ARTICLE 7: PERMITS, TAXES AND SURVEYS
If failure to complete work at the said contract time, the contractor will
pay the owner the liquidated damages in the amount stipulated in the
contract agreement.
ARTICLE 22: PAYMENTS
• The contractor shall, within 15 days from receipt of notice to proceed,
submit a complete breakdown of work and corresponding value for
approval and will be used as basis for all requests for payment.
• The contractor shall submit a request for payment for work done, not
more than once each month. Each request shall be computed from the
work completed on all items listed in the breakdown of work, less 10%
retention. When 50% of the contract has been accomplished, no retention
shall be made.
• The contractor, at his own expense, shall furnish the architect progress
photographs which shall be taken monthly.
1. Photograph size shall be 6” by 8”. Four exposures shall be taken (2 copies
for each exposure = 8), a total of 8 prints to be delivered to the architect,
and all negatives bearing the date of exposure and name of work.
2. No partial payment may be considered for approval without the pictures
accompanying request for payment.
ARTICLE 22: PAYMENTS
• 15 days upon receipt of the request for payment, the architect shall
either issue a certificate of payment or withhold the request and
inform the contractor in writing the reasons for withholding it. The
certificate of payment shall include the value of work accomplished
during the period of time covered by the certificate.
• The architect may recommend withholding of payment on any of
the following:
1. Defective work not remedied.
2. Reasonable evidence indicating probable filing of claims.
3. Failure of contractor to make payments to sub-contractors
or for material and labor.
4. Reasonable doubt that the contract can be completed for
the balance then unpaid.
5. Damage to another contractor.
ARTICLE 22: PAYMENTS
• The architect shall estimate the value of work using the
breakdown of work and corresponding values as a basis.
• Estimates of the architect are considered final and
conclusive evidence of the amount of work performed and
shall be basis for the full measure of the compensation of
the contractor, but bear in mind that the estimates are
approximate only.
• Within 15 days from the date of approval of a request for
payment and issuance of certificate of payment, the owner
shall pay the amount as certified, or such other amount he
deems is due the contractor informing both the contractor
and architect in writing his reasons for paying the amended
amount.
ARTICLE 22: PAYMENTS
• The contractor shall pay promptly his workmen, materials
and equipment used, taxes and remit all amount withheld
from salaries and wages of his employees. If required by
the owner, the contractor shall swear before an officer duly
authorized to administer oath that all persons who have
done work and all materials furnished have been paid for.
• No payments shall be made in excess of 65% of the
contract price unless a notarized statement is submitted by
the contractor to the effect that all bills for labor, other
than current wages, and bills for materials have been paid.
• The contractor shall promptly remove from the premises all
work condemned by the architect as failing to conform to
the contract. He shall replace and re-execute his own work
in accordance to the contract documents at his own
expense.
ARTICLE 22: PAYMENTS
• The contractor shall submit the following before final payment is
made:
1. Certificate of final building occupancy
2. Certificate of final inspection of utilities
3. Original and 3 sets of prints of “as-built-drawings” of
electrical, sanitary, gas, telephone and mechanical works.
4. 3 copies of directory of panel boards and list of circuits.
5. 3 copies of instructions and manual for operating fixtures
and equipment.
6. 3 copies of keying schedule.
7. Guarantee bond equivalent to 30% of the contract price
covering a period of 1 year after the final acceptance of the
work.
ARTICLE 22: PAYMENTS
• The architect shall proceed to verify the work, make final estimates,
certify the completion of work and accept the same.
1. The owner shall then pay the contractor the remainder of the fee
provided that the final payment of the contract shall not be made
until the contractor has submitted a sworn statement showing
that all taxes due from him, all materials and labor have been duly
paid.
2. The making and acceptance of the final payment shall constitute a
waiver of all claims by the contractor.
The final certificate of payment nor any provisions may relieve the
contractor of responsibility for faulty materials. He shall remedy
defects and pay for the damage, which will appear within a year’s
period from date of acceptance of work by the owner.
Claim for damages shall be made in writing to the party liable within a
reasonable time and not later than the final payment and shall be
adjusted by agreement or arbitration.
ARTICLE 33: LIENS, DISPUTE AND
ARBITRATION
Disputes:
1. The architect shall make decisions on all claims of owner
and contractor on all matters relating to the progress and
execution of work or interpretation of contract
documents.