Professional Documents
Culture Documents
Design and Constrcution of TSF
Design and Constrcution of TSF
Design and Constrcution of TSF
FOR
Submitted
2
The site sterilization can be done by the client who will produce a report of the
sterilization including a site map.
Our understanding of the scope of work is the design and construction of the TSF. This
will cover carrying out ground investigations to assist in the design of the TSF and
production of the operating manual (OMS) to allow client to operate the TSF in a safe
manner.
Lowest operating costs with emphasis on pumping costs, piping costs for
the life of the TSF
Lowest cost for closure and final decommissioning of the TSF
1.1.2 Baseline Survey
a. EIA survey and mapping - preliminary EIA and mitigation report
b. Carrying out Ground Investigations whose results will be necessary for the
design.
i. The design of the TSF complete with Starter wall, Under-drainage system,
Decant-system, Delivery system, Return water system, HDPE liner, Storm
water diversion, Roads, fences, and gates.
2.0 Deliverables
a. Feasibility Study Report- based on site visits and desk top studies
b. Ground Investigation Report - Detailing and interpreting the Ground Investigation,
lab data etc.
c. Geotechnical Design Report with drawings and Appendices. Appendices to
include Specifications, Bill of quantities, Construction quality monitoring
documentation, and relevant drawings
d. Operating Manual for the TSF
e. A draft design report shall be submitted initially and then the final design report
incorporating comments and any changes that may be deemed necessary.
Properties of the tailings such angle of friction, dry density, gradation etc.
Rainfall and evaporation data,
Groundwater details. We would prefer to carry out the analysis of the
groundwater properties as part of our EIA baseline survey and scoping.
Production plans
4.0 Survey
5.0 Duration
We anticipate that it will take approximately 7 weeks from the date of commissioning to
produce the required reports and drawings. The construction will depend on the data
obtained from the design but is estimated to take not more than 6 weeks. Please note
that the OMS will be produced during the construction of the TSF to incorporate any
changes that may be required during construction.
6.0 Quotation
The quotation below is for undertaking the work whose Scope is outlined in Clause 3
and estimated duration in Clause 6.0 above.
Excavate stockpile
1.6 Storm Water drain trench
1.7 External soln drain
7.0 OTHERS
TOTAL
Add: Preliminaries & General
SUBTOTAL
Add: 15% VAT
GROSS TOTAL
b) Maximum Rate of rise- this is at 1.5metres per year depending on the type of
material expected to be received to also ensure good consolidation and
compaction.
c) Maximum Slurry Disposal Rate- will be estimated at 336, 000 tons per year
determined by 28 000 tons per month of ore from a retreatment dump.
d) Side Wall Angle-which will be 32 degrees to ensure maximum stability.
e) Density- for consolidation of tailings on the tailings dam, slurry density is
normally 1.45 tones per cubic meter
f) Basin Area- an estimated 2.316 hectares will be required for the tailings facility.
g) Return water Pond- this pond will be required for constant recycling of process
water to the process plant for re-use. This is water being pumped from the basin
through the penstock and under drains.
h) Emergency pond – The one which can hold excess water in case of a storm
i) Access Road-a light vehicle access road will need to be constructed for access
to the solution pond pump station for periodic maintenance.
j) Fencing-a diamond wire fence is required by law to prevent the ingestion by
livestock and entrance by unauthorized personnel. This will be gated and sign
posted to depict the hazards of entering the area.
k) Clay material with a thickness of about 20cm
l) 500 micron geomembrane will be used
m) The ground is sloping at about 10 to 15 degrees
n) Material that will come out of the ground when levelling can be used to build
starter wall if its characteristics allow
o) Upstream insitu material will be used for starter walls.
p) Tailings from the plant are pumped to the tailings dam at 40-50% solids.
q) Piezometers for monitoring water levels
r) Rainfall pattern for the location
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
mm