This document provides 3 methods to calculate the quantity of excavation required for building foundations:
1. Total Length Method: Calculates the total length of excavation by adding the lengths of all walls and subtracting overlaps.
2. Separate Wall Method: Calculates the length of each wall separately based on their center-to-center lengths and widths.
3. Center Line Method: Calculates the total length of the center line of all walls and subtracts overlaps to get the excavation length.
This document provides 3 methods to calculate the quantity of excavation required for building foundations:
1. Total Length Method: Calculates the total length of excavation by adding the lengths of all walls and subtracting overlaps.
2. Separate Wall Method: Calculates the length of each wall separately based on their center-to-center lengths and widths.
3. Center Line Method: Calculates the total length of the center line of all walls and subtracts overlaps to get the excavation length.
This document provides 3 methods to calculate the quantity of excavation required for building foundations:
1. Total Length Method: Calculates the total length of excavation by adding the lengths of all walls and subtracting overlaps.
2. Separate Wall Method: Calculates the length of each wall separately based on their center-to-center lengths and widths.
3. Center Line Method: Calculates the total length of the center line of all walls and subtracts overlaps to get the excavation length.
ALL METHODS OF CALCULATE THE QUANTITY OF EXACAVATION IN FOUNDATION OF BUILDING.
Total Length Method
Length Breadth Height
Sr. No. Descriptoins Nos. Qty. Unit Remarks (Feet) (Feet) (Feet) Cubic Feet 1 Excavation in foundation of building, including dagbelling, dressing, Total Wall Length refilling in layers around structure with excavated earth, watering and (2x30)+(2x24.75)+(2x12 ramming in ordinary soil )+28.75=167.75 1 157.50 2.50 2.75 1082.81 Cft Length of Excav. =167.75-6/2 (2.5- .75)=157.50 Total 1082.81 Cft
Separate Wall Method
Length Breadth Height
Sr. No. Descriptoins Nos. Qty. Unit Remarks (Feet) (Feet) (Feet) Cubic Feet 1 Excavation in foundation of building, including dagbelling, dressing, Total Length of refilling in layers around structure with excavated earth, watering and excavation of Horizontal ramming in ordinary soil 3 27.00 2.50 2.75 556.875 Cft wall = c/c length - Horizontal walls Breadth of wall from Foundation Bed Vertical walls Total Length of excavation of vertical 2 28.00 2.50 2.75 385 Cft wall = c/c length +Breadth of wall from foundation Bed Vertical walls Total Length of excavation of vertical 2 10.25 2.50 2.75 140.94 Cft wall = c/c length - Breadth of wall from Foundation Bed Total 1082.81 Cft
Center Line Method
Length Breadth Height
Sr. No. Descriptoins Nos. Qty. Unit Remarks (Feet) (Feet) (Feet) Cubic Feet 1 Excavation in foundation of building, including dagbelling, dressing, Total of center line refilling in layers around structure with excavated earth, watering and =(3x29.5)+(2x25.5)+(2x1 ramming in ordinary soil 1 157.50 2.50 2.75 1082.81 Cft 2.75)=165 Length of Excav. =165- 6/2 x2.5=157.50