ALL METHODS OF CALCULATE THE QUANTITY OF EXACAVATION IN FOUNDATION OF BUILDING.

Total Length Method

Length Breadth Height


Sr. No. Descriptoins Nos. Qty. Unit Remarks
(Feet) (Feet) (Feet)
Cubic Feet
1 Excavation in foundation of building, including dagbelling, dressing, Total Wall Length
refilling in layers around structure with excavated earth, watering and (2x30)+(2x24.75)+(2x12
ramming in ordinary soil )+28.75=167.75
1 157.50 2.50 2.75 1082.81 Cft
Length of Excav.
=167.75-6/2 (2.5-
.75)=157.50
Total 1082.81 Cft

Separate Wall Method

Length Breadth Height


Sr. No. Descriptoins Nos. Qty. Unit Remarks
(Feet) (Feet) (Feet)
Cubic Feet
1 Excavation in foundation of building, including dagbelling, dressing,
Total Length of
refilling in layers around structure with excavated earth, watering and
excavation of Horizontal
ramming in ordinary soil
3 27.00 2.50 2.75 556.875 Cft wall = c/c length -
Horizontal walls
Breadth of wall from
Foundation Bed
Vertical walls Total Length of
excavation of vertical
2 28.00 2.50 2.75 385 Cft wall = c/c length
+Breadth of wall from
foundation Bed
Vertical walls Total Length of
excavation of vertical
2 10.25 2.50 2.75 140.94 Cft wall = c/c length -
Breadth of wall from
Foundation Bed
Total 1082.81 Cft

Center Line Method

Length Breadth Height


Sr. No. Descriptoins Nos. Qty. Unit Remarks
(Feet) (Feet) (Feet)
Cubic Feet
1 Excavation in foundation of building, including dagbelling, dressing,
Total of center line
refilling in layers around structure with excavated earth, watering and
=(3x29.5)+(2x25.5)+(2x1
ramming in ordinary soil
1 157.50 2.50 2.75 1082.81 Cft 2.75)=165
Length of Excav. =165-
6/2 x2.5=157.50

Total 1082.81 Cft