Professional Documents
Culture Documents
MSF Safety Flash 14.02
MSF Safety Flash 14.02
The communications lines were clear and had been in use on this vessel for some time – UHF
between vessel deck and bridge; VHF between vessel bridge and facility (including crane driver as
required); hand signals from the vessel deck to crane operator as per COSWP. The senior officer
on the bridge (in this case the Master) being in control of the operation as far as the vessel and the
procedures to be followed was concerned.
The IP had been on the vessel for approximately 2 weeks prior to the incident, he had been on a
sister vessel as AB for the previous 5 years; an induction was completed on the Vessel as per
documented company procedures.
Direct Causes Hose snagged under capstan but not hard fast
IP standing in an unsafe position
Crane heaving up / vessel movement downwards resulting
in hose self-release from underneath capstan when under
tension
It was apparent that no RA or TBT process was followed. It was also noted that during the day
when a number of hose operations had been undertaken there was no reference to the
management system processes except the dry bulk checklist being completed. Training in the
Company’s procedures is completed at induction and through on-board training regimes.
From this incident, it is construed that for jobs that were seen as routine, then no risk
assessment or job planning was considered
The information available on this Safety Flash and our associated web site is provided in good faith and only
for the purposes of enhancing safety and best practice. For the avoidance of doubt no legal liability shall be
attached to any guidance and/or recommendation and/or statement herein contained.
-1-