Professional Documents
Culture Documents
Lifting and Hoisting
Lifting and Hoisting
Title page
TITLE:
NOTES:
This document is part of the Health, Safety and Environment Integrated Management System (HSE IMS) of Eni in
Nigeria.
This document replaces and substitutes: Doc. HSE-DIV-C5-OPER-012 Rev02 “Rigging and Lifting Procedure” and HSE-
DIV-C5-OPER-021 Rev00 “Personnel Lifting Procedure”.
This official document is available at the HSE link of the myeni Nigeria intranet.
After downloading the document from the shared area, the document shall be considered as non-controlled copy.
Review
Revision Description Date
INDEX
1. OBJECTIVES 6
2. SCOPE OF APPLICATION 6
3. REFERENCES 7
3.1 Internal references 7
3.2 External references 7
4. DEFINITIONS, ABBREVIATIONS AND ACRONYMS 8
5. ACTIVITIES AND OPERATING METHODS 12
5.1 Roles and responsibilities 13
5.1.1 Lifting Functional Organization Scheme 13
5.1.2 Specific roles and responsibilities 14
5.1.3 Personnel Competence and Qualification 19
6. CHANGES MADE 81
1. OBJECTIVES
The objective of this procedure is to provide guidance for the management of lifting and hoisting operations, with the
intent of avoiding and reducing Hazards associated with the execution of such operations, in Eni in Nigeria onshore and
offshore facilities to promote Safety of Personnel, Environment and Asset Integrity.
This procedure also assists those persons responsible for planning, implementing, managing, and controlling, safely and
efficiently all Lifting and Hoisting (L&H) operations.
2. SCOPE OF APPLICATION
This document covers L&H operations including the hiring and procurement of Lifting Appliances and Accessories for
the Eni Nigeria companies NAOC and NAE hereafter referred to as Eni in Nigeria.
This document does not apply, despite in principle can be adapted, to:
Drilling crown block, traveling block and top drive operations;
Elevators carrying personnel or freight;
Ship/rig anchor handling;
Earthmoving equipment and operations;
Tree cutting and associated movement of lumber;
Helicopter lifting operations;
Fall protection;
Manual lifting operations;
Manual handling;
Marine towing.
This procedure shall be compliant with Nigerian local government and statutory regulations. In case of conflicts of the
present document with legal requirements, the most stringent shall apply. In case of contradictions between the
provisions of this document and local legislation, applicable laws shall prevail.
Note: the term Lifting is used throughout this document to describe all types of lifting and hoisting.
3. REFERENCES
TERM/ACRONYM DESCRIPTION
Banksman Banksmen are operatives trained to direct vehicle movement on or around site.
A lift where at any point in time during the lifting operation the crane operator cannot
Blind lift
directly see the load.
Structural capacity is the rated capacity based on strength of materials as well as efficiency
of hoisting devices; winches, cylinders, etc. Static capacity is the rated capacity of the
equipment based on the safety factors and safe design of its components. Dynamic
capacity is the rated capacity of the equipment when introducing dynamic loading into
Capacity the machine or its components due to accelerating or decelerating forces, the effects of
(dynamic and static) vessel movements, etc.
Thus, applies to all loads lifted from or to a stationary vessel to a moving or floating vessel
or from a floating vessel to another floating vessel or structure. Cranes mounted on fixed
structures have a formula for deductions for all water lifts, which shall be available to the
operator and lift engineer.
Cargo Carrying Units. Any mean used for transportation of loads (i.e.: Skips, containers,
CCU
open top, racks, frames, Tote tank, etc.).
Cargo Transport Units. Any mean used for transportation of loads (i.e.: Skips, containers,
CTU
open top, racks, frames, Tote tank, etc.).
An approved, legally compliant method of checking and providing evidence that a piece
Certification
of equipment has been inspected and meets Standards.
A person who has sufficient theoretical knowledge, practical experience and the required
Competent Person qualities for the task in hand. He/she Is able to perform the activities within an occupation
or function to the standard expected in the task.
GU Geographical Unit.
Source, situation, or act with a potential for harm in terms of human injury or ill health, or a
Hazard
combination of these (ISO 14001, ISO 45001).
State of complete physical, mental and social well-being. Not only the absence of illness or
Health
injury.
Part of the overall management system that enables the management of the HSE risks
associated with the business of the organization, fulfilment of compliance obligations, and
HSE Management addresses risk and opportunities. Management System is a set of interrelated or interacting
System (HSE MS) elements of an organization to establish policies and objectives and process to achieve those
objectives. The system elements include the organisation’s structure, roles and
responsibilities, planning and operation, performance evaluation and improvement.
Lifting Equipment Inspector or Engineer who has practical and theoretical knowledge and
Independent experience of the crane and equipment used in lifting operations as necessary to perform
Competent Person the job required on behalf of the Eni in Nigeria. He/She is competent and independent to
allow impartial, objective decisions to be made.
Person or organization that can affect, be affected by, or perceive itself to be affected by a
Interested Party
decision or activity.
Any device used to connect a lifting appliance to a load, and does not form part of the load.
Lifting Accessory These include but are not limited to wire rope (and other types of) slings, shackles, eye bolts,
hoist and swivel rings, turnbuckles, spreader beams, hooks, pad eyes, pallet hook, etc.
Any mechanical device capable of raising or lowering a load. These include offshore pedestal
cranes, mobile cranes, A-frames and derricks (excluding drilling derricks), tower cranes,
Lifting Appliance
overhead/gantry cranes, lifting beam, jacks, mobile/aerial platforms, hoists, winches,
forklifts, beam trolleys, etc.
Any device used to suspend the load, including containers, tanks, skips, baskets, cargo nets,
Lifted Equipment
pipe racks, frames, skids, bulk containers, etc.
Any item used to connect a load to a lifting machine or appliance, but which is not in itself
Lifting Gear
capable of providing any movement to lift or lower the load.
The details of how a lifting operation should be executed, including details of lifted
Lifting Plan equipment and lifting Accessories to be used, rigging/slinging methods to be employed and
control measures in place to manage identified risks.
Loose gear The following items are considered loose gear: shackles, hooks, swivels, lifting eyes,
connecting plates, master links, rings, tackles and blocks, etc., through which loads may be
connected to the Lifting appliance but which are not an integral part of it and which may be
easily disassemble.
Lifting Technical Authority. Lifting Technical Authority. Someone who is formally appointed
and technically competent on the overall lifting process and related aspects such as in depth
LTA knowledge of the equipment, required Personnel competence, major process development,
operations. The Technical Authority shall be referred to as the Competence Centre for the
definition of guidelines and instructions for the operation/control of the lifting activities.
The action of lifting or lowering a person directly attached to the line from a hoist or winch.
Man-riding
Normally associated with drill rig operations.
Winch/hoist that is dedicated to Man-riding (i.e. is not used for other purposes), and has
dual braking capability. The hoisting motion releases the brake but is applied as soon as the
Man-riding winch/hoist
lever is returned to neutral or released. This action is automatic, and does not require the
hoist operator’s input.
MS Method Statement.
Non-routine Lifts Non-routine lifts are defined as all operations not falling into the routine lifts.
Offshore Installation
The OIM is the overall responsible for the rig and its Personnel.
Manager (OIM)
Person in Charge. The person designated as the person in charge of the lifting operation.
PIC He/she shall ensure that the required controls are in place and the lift is carried out following
the Plan.
A visual check and, where necessary, functional check of lifting equipment by a competent
Pre-use inspection
person before use.
Defines the modus operandi of the company’s business that shall be followed. Procedures
describe the tasks and responsibilities of the organizational roles involved, management and
Procedure (pro) control methods, and communication flows. They govern local operations, also for the
purpose of compliance with local regulations. The content is defined in accordance with the
Policies and MSGs, as implemented by the company.
Competent Person, qualified by a third party. Able to perform inspection tasks as foreseen
Qualified Inspector in the Inspection schedule and provide technical conformity judgment on the material
equipment inspected against the relevant standard.
A person with adequate skills and competence to attach loads to/from equipment, cranes
Rigger or structures using lifting Accessories. In this document, it is considered synonym of slinger,
handler and roustabout.
Effect of uncertainty, deviation from the expected (positive or negative). Risk is often
Risk expressed in terms of a combination of the consequences of an event (including changes in
circumstances) and the associated “likelihood” of occurrence.
Lifts involving loads of known weight, shape and centre of gravity. These lifts are carried out
on a regular basis, they require no detailed engineering planning and have been previously
Routine lift
subject to a generic risk assessment and lift plan as appropriate. They are performed in
normal environmental conditions using standard rigging arrangements.
Self-acting / An automatic braking system that applies the hoist brake at any time the control lever is
returned to neutral. The self-acting braking system will apply a spring applied braking system
fail safe to prevent uncontrolled movement of the hoist rope or drum.
Refers to any office, premise, onshore location (drilling site, production site, construction
Site site, logistic yard, warehouse and workshop), offshore platform and any other offshore
support to production or drilling activities.
Pre-job meeting required to be carried out prior to start for all work. The pre-job meeting
must be done at the work site. It is the final check in the Hazard assessment process and the
Toolbox Talk (TbT) start of the implementation of the work. The Toolbox Talk shall cover the work plan, the
Hazards, the controls, roles & responsibilities, and any recovery measures to be taken if the
controls are not completely effective.
Working Load Limit The maximum load, determined by the manufacturer, which an item of lifting equipment is
(WLL) designed to raise, lower or suspend under design conditions.
Planning shall be an integral part in every lifting operation and the prime consideration to be made in the interest of
safety of Personnel, the Environment and Asset Integrity, to reduce risks and ultimately improve workplaces and
worksites Safety.
Therefore, Eni in Nigeria provides that each lifting operation shall be:
competently planned by preparing a Lift Plan;
risk assessed;
appropriately supervised;
performed by adequately trained and experienced Personnel;
performed by using certified equipment;
carried out in a safe manner.
lifting categorization;
preparation of lifting documents package;
development and analysis of factors affecting the lifting operations, aimed to ensure that an increasing level of
attention, competency and authorization apply as the complexity level of the operation increases.
Shall:
ensure the fulfilment of the Lifting Management System requirements with the
support of the Lifting Technical Authority and HSE Department in order to duly
fulfil its responsibilities;
have responsibility to set up a proper management system for the lifting process;
have responsibility to ensure adequate number of resources to operate the lifting
process safely;
GU Management Eni in Nigeria
have responsibility to implement a proper lifting culture and guarantee a safe
working environment;
have responsibility to monitor and review the effectiveness of the lifting
management system and actuate internal auditing for a self-verification
assessment;
identify and assign the necessary roles and responsibilities in accordance with the
Lifting Management System.
HSE Department assists the Site Manager and the Person in Charge (PIC) and
participates in Risk Assessments of lifting operations and assists in the implementation
HSE Department Eni in Nigeria of the measures listed in the Lift Plan for prevention of incidents and their mitigation.
HSE Department shall monitor that safety aspects related to the lifting are duly taken
into due consideration and implemented along the lifting process.
Lifting Technical Authority (LTA) shall assist and support all Parties involved in the
definition of any aspect related to the Lifting Process. Lifting Technical Authority shall
be referred to as the Competence Center for the definition of guidelines and
instructions for the operation and control of the Lifting Activities and shall be activated
inside the logistics department of the GU, where present.
Lifting Technical Authority shall perform his duty in strict connection with the Lifting
Team and coordination with all the other departments involved in the lifting process
(i.e. HSE, QA/QC, Maintenance, Procurement, etc.), providing:
Eni in Nigeria advisory services required for the correct lifting management system
Lifting Technical and implementation;
Authority Contractors / technical advisory and guidelines for the engineering and planning of the
Subcontractors operations, when required;
technical advisory for the control of the lifting operations lessons learnt;
technical advisory for lifting process review;
technical support in the selection process of contractors/subcontractors for lifting
operations;
technical advisory for lifting process deviations determination;
technical auditing of the Lifting Management System implementation in field
carrying out regular site visits.
The Site Responsible Person has the overall responsibility for the site and for applying
the HSE integrated management system including the execution of safe lifting and
hoisting operations.
He/She can be identified as the responsible for the single onshore/offshore working
(development, operation, production) site (e.g. Base Manager, Plant Manager, OIM,
Drilling Site Manager, Yard Superintendent, etc.).
In particular, He/She shall:
appoint a qualified person, identified as the Person In Charge (P.I.C.), who has the
required competence to oversee all lifting operations, either for a specific lift or
generally for any type of lifting operations;
authorize or designate a qualified lifting equipment operator/contractor as
Site Responsible required;
Eni in Nigeria
Person
ensure that personnel in lifting and hoisting operations have received adequate
training, and are competent in their respective jobs and are in possession of the
proper certificates;
ensure that all lifting operations, and in particular complex, heavy and critical
lifting operations, are properly studied, assessed, designed and calculated and that
prevention, control and mitigation measures are implemented;
authorize (issuing) the Permit to Work for the areas under his responsibility;
provide suitable and certified equipment and machinery;
ensure contractors, subcontractors and vendors fully comply with the Company’s
requirements.
Lifting Operational Advisor (LOA) shall be available to support the overall process of
the Lifting Management System. He shall be responsible for:
supporting the lifting team and HSE Department in the preparation of the Risk
Assessment;
supporting the Site unit for any request/doubt related to the lifting;
participating in the preparation of the Lifting Management System;
controlling that Lifting Management System has been built up to meet the
requirements of this manual;
Lifting Operational setting and participating in monitoring and assessment activities dedicated to the
Eni in Nigeria lifting at Company sites;
Advisor (LOA)
providing technical support in the selection process of contractors/subcontractors
for lifting operations;
providing technical advisory for lifting process deviations determination.
The minimum requirements for the Lifting Advisor are the following:
Bachelor’s degree in engineering;
minimum 10 years of experience in operating and/or maintaining various type of
lifting equipment.
Lifting Operational Engineer (LOE) shall be activated in the preparation stage of all
lifting operations which require an engineering study.
He shall be responsible for:
studying in detail the load to be lifted and determine its’ weight and Centre of
Gravity, or supporting the Department requesting the lift in doing so;
designing and calculating suitable lifting points and lifting lugs/eyes;
Eni in Nigeria determining the weight of the load (including impact loads during lifting);
Lifting Operational and proposing suitable crane(s) and Lifting equipment for the lifting operation;
Engineer (LOE) Contractors / supporting the definition of the potential Hazards and its associated Risks involved
Subcontractors the lifting operation;
Supporting the Inspection and Maintenance team for the assessment of the
structural integrity of lifting equipment.
The minimum requirements for the Lifting Engineer are the following:
Bachelor’s degree in engineering;
Minimum 5 years of experience in the design of lifting equipment and operations.
Lifting Appliance Operator shall be trained and authorized to operate the specific
equipment being used, and shall operate the equipment within the technical
parameters and safe procedures of that equipment.
Moreover, Lifting Appliance Operator shall:
perform pre-operation inspection on lifting appliance and all its associated parts
including safety devices, ensuring they are in good working condition. Fill in the
dedicated check list;
Eni in Nigeria
Lifting Appliance verify weight of load does not exceed the safe working load of appliance and lifting
Operator and equipment in all geometrical conditions;
Contractors / inspect ground condition where lifting appliance is to be seated before setting up;
Subcontractors
ensure lifting appliance location is safe and adequate level of visibility during lifting
operations at site;
communicate with the Banksman before operation to establish common
understanding signs and instructions that will be used, the potential hazards and
risks that may exist during lifting and their prevention, control and mitigation
measures;
have the responsibility not to carry lift or suspend loads above people;
be compliant with procedures and HSE documents and indicated safety measures;
drive, in case of forklift operation, at a speed appropriate for the existing
conditions (space, load, lighting, surface conditions, etc.) and at or below posted
limits, and he shall also ensure other personnel are not in the swing radius prior to
performing turning maneuvers.
They carry out their jobs of slinging and guiding loads under the direction of the
Person-In-Charge. A slinger shall be a person responsible for attaching and detaching
the load to and from the crane hook, and for the use of the correct lifting gear and
equipment in accordance with the Lift Plan.
The slinger shall be responsible for giving the start signal to the banksman for the
planned movement of the crane and load. If there is more than one slinger, only one
of them shall have this responsibility at any one time, depending on their positions
relative to the crane.
Finally, the slinger/rigger shall inspect the rigging, participate in JSA/Risk assessment
for the lift and may contribute to selecting suitable rigging.
Eni in Nigeria
The minimum requirements shall ensure that Slinger/Rigger is:
and
Slinger / Rigger competent (LOLER awareness course or equivalent, Planning and Risk Assessment
Contractors / or equivalent, OPITO approved rigger assessment standard Stage 3, positively
Subcontractors assessed or equivalent);
fit, with particular regard to eyesight, hearing, reflexes and agility;
physically able to handle lifting gear and equipment;
able to assess masses, balance loads and judge distances, heights and clearances;
trained in the techniques of slinging;
capable of selecting lifting gear and equipment in suitable condition for the load
to be lifted;
trained in the techniques of signalling and understand the signal code;
recommended at least a minimum experience of 5 years in lifting operations.
relay instructions to the crane operator via hand signals or radio during operations;
maintain an overview of the hoisting operations area, including potential areas
where the boom may come in contact with a fixed equipment or structure;
be the sole signaller at any given time;
have a direct line of sight of the load at any time and adheres to a clear process;
If a handover to another signaller/banksman is required, he shall inform the Person
in Charge as well as the appliance operator clearly about the handover.
A designated individual who shall be responsible for managing all Lifting Accessories
and Loose Lifting Gears in a given site. He shall be responsible to manage the Rigging
Loft where the Accessories are stored. In particular, they shall perform recording,
tracking and verification activity in order to determine the correct flow, disposal,
certification availability and proper condition of all the Accessories.
The minimum requirements shall ensure that lifting Rigging Loft Controller is:
Rigging Loft competent;
Eni in Nigeria
Controller
fully conversant with the equipment under its responsibilities and related hazards;
properly instructed and trained;
familiar with the procedures and precautions recommended in the Accessories
manuals;
provided with training and qualification as required by the Maintenance
Department Standards.
The Lifting Equipment Audit Team shall be comprised of PIC and HSE personnel with
capabilities and proper training to perform internal auditing sessions for the review
and assessment of the performance of the lifting process.
The minimum requirements for the Audit Team shall be the following:
Eni in Nigeria and competent;
Lifting Equipment
Contractors / fit, with particular regard to eyesight, hearing, reflexes and agility and
Audit Team
Subcontractors communication skills;
able to hold auditing sessions to reflect conformity to standards of the process
subject to assessment;
trained in the auditing techniques and with relevant qualification;
recommended at least a minimum experience of 5 years.
Assigned personnel involved in the lifting process shall have adequate training to develop and maintain the required
competency for the assigned role. Refresher training must be provided at prescribed intervals.
Formal training and competence (and any formal Certification) shall be provided by an independent organization in
accordance with internationally recognized standards and practices, and comply with Local regulatory and statutory
requirements.
All training and competency assessments shall be documented and retained in the employee’s training file. Training
shall be provided both by external recognized organizations and by internal in-situ competent person. Training shall be
given both through theoretical and practical exercises.
Program Training could be built up taking also into consideration, among various international standards such as OPITO,
OMHEC, etc., also the following:
ISO 15513:2000 requirements;
ISO 9926-1:1992 provisions.
GU Management shall define training requirements and ensure that competency assessments are conducted
periodically.
Suggested minimum Training application is reported in the table as shown below.
Rigger/Slinger/Load Handler
The competencies which a slinger shall possess before being authorized as a slinger are:
The competency requirement in-line with ISO 15531:2000 shall be based on:
Banksman
The competency which a Banksman shall possess before being authorized as a signaller is the application of signalling
methods. The competency requirement in-line with ISO 15531:2000 shall be based on:
For the offshore operation, in addition to what has been described above the following point shall be take into account.
The PRFLO may be a member of the permanent crew and it may be deemed necessary to appoint sufficient
personnel to this role to ensure at least one PRFLO offshore at all times. If it is not possible to have a PRFLO as
part of the permanent crew, a PRFLO will be contracted and appointed for each specific lift;
The PRFLOs responsibilities shall include facilitating the completion of the following and approving the key
documents. The PRFLO may delegate responsibilities to other equally competent and certified personnel but the
PRFLO will ultimately review and approve the work.
Annex A2 below provides a flowchart aiding the identification of Routine and Non-Routine Lifts and a Lifting Category
Identification Checklist.
Personnel involved in the lifting operation, their competency, roles and responsibilities;
Method of planning and procedures to be adopted for the lifting operation.
The following paragraphs outline the factors in greater detail and identify areas that must be considered before any
lifting operation is carried out. It is important to note that the following areas are by no means exhaustive. The adequate
degree of planning shall always reflect the criticality of the operation.
Where more details are needed, all necessary documentation shall be prepared with the concerned party in accordance
with the lifting categorization process.
In order to conduct a proper selection of the lifting equipment, it is necessary to perform an assessment to identify the
Hazards and assess the Risks associated with the equipment for the foreseeable range of lifting operations. For example,
the applications, loads and configurations of the equipment that will be used. Based on this assessment, the appropriate
Lifting equipment for the lifting operation may then be selected.
This equipment assessment shall consider, but not necessarily be limited to the following:
Lifting Capacity;
Having decided upon the type of lifting appliance – e.g. the type of crane – and knowing the overall requirements
involved, a particular crane that will safely meet all the requirements of a planned lift shall be selected. The aspects to
be considered in making this selection include the following:
Weight, CoG, dimensions and characteristics of load(s);
Operational radius, heights of lift and working areas;
Site, ground and environmental conditions or restrictions;
Space available for crane access, erection, travelling, operation and dismantling;
Any special operational requirements or limitations.
It is worth noting that, for lifting operations involving multiple loads of different shapes and sizes, the capacity of the
lifting appliance shall be selected based on the weight of the heaviest load to prevent overloading.
Other important aspects to be considered in making the selection of a lifting appliance are:
The Integrity of the Lifting equipment to ensure its structural safe. Based on past incidents, attention needs to be
focused on the following critical load bearing parts;
The presence of safety mechanism and devices such as:
• Brakes, connected to the hoisting mechanism, which allow the Lifting appliance to lift or suspend a load.
Any failure in the brakes will result in an unintended free-fall of the suspended load;
• Limit switches or sensors to stop or prevent the Lifting equipment from entering into an unsafe mode of
operation. For example, automatic device should be installed to stop boom drum motion when the
maximum permissible boom angle is reached. It is therefore critical to ensure that such safety devices are
functioning properly. They shall never be by-passed during a normal operation.
5.2.2.3 Load
Information on load to be handled must be provided to give a clear, but brief, description that will clearly identify the
lift(s) to be undertaken. A separate risk assessment needs to take into account the typology and dimensions of the load
in order to consider the possible impact on the surrounding environment and lifting appliance itself.
The main parameters to be taken in consideration to obtain a complete description of the load are:
• Weight;
• Method of Rigging.
Weight
This is the most important parameter that must be determined to prevent overloading of the Lifting equipment. When
the load is part of an assembled item, the weight of each component can be determined from the engineering drawings.
Alternatively, calculations shall be made based on material density and volume of the load being lifted.
Particular attention shall be paid when the load is made of materials with different densities. It is safer to be extra
careful and estimate a heavier weight than assuming a lighter one.
When slings are connected to the bottom of the load with lift points below the CoG, even if the CoG of the lifted item
is beneath the load-line, the load results to be unstable.
Depending on the shape and size of the load, the CoG may not be obvious. For liquids and granulates, a changing CoG
could cause instability (dynamic and static): as a rule of thumb, tanks containing liquids shall either be completely empty
at the time of lifting, or filled at least at 85% of their volume.
The manufacturers normally provide the CoG locations of equipment (e.g. transformer, heat exchangers, vessel, etc.) If
in doubt, it is advisable to consult an engineer who is able to deduce the CoG by the information shown in the
manufacturer’s drawings. However, it could happen that there is not enough information. When this occurs,
conservative assumptions will need to be made to proceed with the study at hand. In this case the engineer is
responsible for contacting the appropriate people and validating the assumptions.
Method of rigging
There are different methods of rigging that are well established in the industry. The objective of the rigging method is
to ensure that the load is stable throughout the lifting operation. For loose items such as bricks and bags of concrete, it
is critical that they are secured using an appropriate receptacle such as safety nets or metal cage to avoid any accidental
dislodgement in mid-air.
5.2.2.4 Environment
Once the Lifting equipment is selected and the load is determined, the planning must then focus on the environment in
which the Lifting equipment is operating in and how the Lifting equipment is set up. Besides environmental weather
conditions, every worksite will have to consider the specific localized Hazards which have to be eliminated or mitigated
to ensure a safe lifting operation.
Offshore
Working in an offshore environment might bring in additional risks. Selection of the most adequate lifting equipment
and method to be used/implemented shall reflect the working scenario and the impact it may have on the operation
execution and the environment. Especially on the use of synthetic slings in an offshore environment, the following shall
be taken into account:
Using synthetic slings for loading and back-loading of cargo or any other dynamic hoisting situation is never allowed;
In case the load to be hoisted can be subject to snatch or shocks, synthetic slings shall never be used;
It is recommended that wire rope slings have preference over synthetic slings in an offshore environment.
(Nevertheless, these can be used if properly maintained and inspected).
In case of complex/critical lifting operations, such as e.g. subsea operations, decommissioning operations or very heavy
operations, slings manufactured from a fiber are allowed under the following conditions:
Ground
The stability of the Lifting equipment is highly dependent on the ground condition of the location where the Lifting
equipment will be set up. Special care must be taken to ensure that the ground is level and has sufficient bearing capacity.
Cranes that are equipped with outriggers shall be evenly and fully extended. In addition, when using mobile or crawler
cranes, it is recommended that steel plates with adequate strength and size are used to provide a firm ground support,
distribute ground pressure and ensure this is within the maximum allowable value in order to prevent any crane toppling
incidents.
Stable subsoil
The subsoil must be sufficiently stable to withstand the expected axle loads and hence the ground bearing pressure
being transferred by the outriggers.
When there is no specific information available about the subsoil structure, the maximum allowable surface pressure
shall not exceed 10 ton/m2.
Mobile cranes shall be equipped with outrigger plates making sure that ground bearing pressure will never exceed
10 ton/m2. These outrigger plates shall be used at all times to prevent the equipment toppling over!
Within one (1) meter of concrete foundations: the maximum allowable surface pressure shall never exceed 5 ton/m2.
Ground bearing pressure can be decreased through the application of appropriate cribbing plates. These plates shall be
placed under the outrigger in a central position and positioned horizontally.
For general guidance on most type of soil and allowed GBP, refer to the following values.
Note:
Ground bearing capacity depends on the bearing surface and its interaction underlying layers; hence the above
listed values shall be used as general reference only. The support of a competent personnel shall be sought in case
of doubts regarding ground conditions.
Ground bearing pressure can be decreased through the application of mattress plates. These plates shall be placed
under the outrigger in a central position and positioned horizontally. These outrigger plates should be always used
in order to ensure that pressure on ground will never exceed the maximum admissible ground capacity.
Subservices
Particular attention in the positioning of the appliance should be posed to subservices (e.g. water distribution system,
sewerage network, etc.). The danger to or from these underground services should not overlooked.
Precautions should be taken to ensure that the crane standing is clear of any underground services. Where this is not
possible, the services shall be adequately protected to prevent damages.
Level subsoil
The access road and the subsoil must be sufficiently levelled to adequately support lifting equipment. The manholes
and manhole covers in the access road may pose a risk with regard to insufficient strength and unevenness.
Obstacles
Any fixed or temporary installations such as buildings, overhead power lines, bridges or underground utilities / pipelines
that are within the proximity of the operation zone are considered as obstacles during a lifting operation due to Risk of
the Lifting equipment or load coming into contact with the installations which can result in an accidental dislodgement
of the load. Such obstacles can also refer to blind spots or entrapment points during maneuvering of the load or Lifting
equipment, especially in congested areas.
Lighting condition
Adequate lighting particularly during a night operation is very crucial. Depending on the lift, the operator, rigger or
signalman will need to see the suspended load clearly in order to guide it to its safe destination.
It is a legal requirement to have suitable and sufficient lighting on every workplace.
If crane operators and banksman have to look towards strong lights, place and angle the lights so that they do not dazzle
the operator either directly or by his mirrors.
Necessary lighting shall be provided to ensure a well-lit working area for the members of the lifting team and for all the
people in the vicinity of the job. Special attention must be paid to the visibility of the banksman and the load.
Demarcation
The zone of operation shall be clearly demarcated to inform and prevent persons who are not involved in the lifting
operation from entering into the zone unintentionally. In areas where tower, dockside and overhead travelling cranes
are continuously in operation and span a wide area, it is important to designate the affected zone of operation. In
addition to that, other measures shall also be taken to prevent any person from walking under the suspended load.
Such measures include deployment of more signalmen to guide the load or installing audible alarm to warn workers
about the on-going lifting operation.
Prior to commencement of the lifting operations, it must be ensured that the signals do not influence one another.
Whenever radio signals are used for communication, a frequency must be selected so no disturbances are originated.
A risk assessment shall be performed for all expected chemicals and temperature levels which will be in direct or indirect
contact with the lifting and hoisting equipment.
Chains
Chains of grade 8 and 10 may not come into contact with chemical substances such as acids and bases.
Hoisting chains of quality grade 4 can be implemented when chemical substances are present. Consult the directions
for use from the manufacturer for this purpose!
The capacity of grade 8 chain shall be reduced by temperature as follow:
Temperature between +200°C and 300°C => 10% reduction;
Temperature between +300°C and 400°C => 25% reduction.
Synthetic slings
The materials from which synthetic slings are manufactured all have a different resistance to chemicals. Seek the advice
of the manufacturer or supplier of the sling if there is any probability of it being exposed to chemicals. It should also be
noted that the effects of chemicals increase with rising temperatures.
The resistance of synthetic slings to chemical reactions and temperatures is summarized in the following table:
Weather conditions
Weather conditions such as heavy rain, haze or glaze represent an important variable in lifting operations, especially in
offshore applications, and will impact the visibility of the lifting team. Other weather conditions that can impact the
stability and safety of the lifting operations include strong wind, thunderstorms or lightning.
It is advisable to stop all lifting operations when there is adverse weather conditions.
When assessing weather conditions related to the impact on lifting operations, the following topics should be
considered.
Wind
Cranes shall only be operated below the maximum allowable wind speeds, as stated in crane manufacturer operation
manual.
Suitable devices shall be put on the field for measuring wind speed and operator shall monitor environmental effects
that will affect the operation’s safety. All personnel involved shall be aware about environmental limits for the lift and,
in case of any changes in job scope or conditions, a further evaluation shall be made to ensure the job may still be
carried out safely (e.g. crane secured in an out-of-service condition) and stopped, if necessary. Therefore, risks shall be
reassessed and Toolbox Talk re-done before the job is restarted.
The higher the elevation from ground, the stronger the wind speed, therefore during the planning of any lifting
operation, the expected wind speed must be taken into consideration for comparison with the allowable one according
to the crane manufacturer’s operation manual.
However, in the event there is no statement made in the manufacturer’s operation manual, lifting operations shall be
carefully assessed to guarantee safe operation.
Special care must be taken during high wind conditions with regard to:
The geometry and shape of the load (e.g. load with large dynamic surface and minimal weight);
Based on object geometry, lifting of irregularly shaped loads will require additional verification and possibly the
consultation of manufacturer prior to the lift, if necessary. Load weight to surface area ratio shall also be taken into
account. As a rule of thumb, when the load weight to surface area ratio is found to be significantly less than 1.0 ton/m2,
particular attention should be paid to the wind conditions in the area:
!"#$ &'()*+
≪ 1.0 &'(/*1 => Pay attention to wind conditions!
!"#$ ,-./#0' #.'#
The lifting operation shall be stopped, whenever the wind speed is such that it could cause the load to oscillate
significantly.
Offshore operations
Prior to commencement of discharging cargo from and back loading of cargo to supply vessels, the crane operator
should confirm that the prevailing wind and sea-state conditions are within the Installation Adverse Weather Policy
limits. Under no circumstances shall lifting operations exceed the limits applicable for the vessel, crane or installation.
The Beaufort scale is an empirical measure that relates wind speed to observed conditions at sea or on land, as follows:
Sea-State
Offshore cranes can be used up to a certain sea-state. The crane operator must ensure that the Rated Capacity Indicator
(RCI) is set to the appropriate sea-state and that any alteration in sea-state during cargo handling operations is taken
into account and the RCI adjusted accordingly.
Temperature
Extreme cold weather can have a negative effect on safety of lifting operations. Always be aware of the chill factor
during high winds. Based on the temperature range the crane capacity shall be de-rated according to the following table:
From -30⁰C to -40⁰C 40% (for all lifting operations) Refer to the equipment manual.
Free space
When erecting cranes and working with machines, entrapment dangers to people should be avoided. An entrapment
danger can arise when equipment is erected in the vicinity of fixed objects.
5.2.2.5 Personnel
It is important that every single member of the lifting team (operator, rigger, signalman and PIC) shall be adequately
trained and competent to carry out his duties correctly. They shall be fully conversant with the actual lifting procedures,
if applicable and the generic lifting operation documentation.
Here are factors that shall be considered.
Key Players and Roles involved in the lifting process are detailed in Section 5.1.
In line with company’s FTW procedure, a FTW certificate from approved facilities/ clinics shall be sent to company’s
Medical Department for proper checks and documentation.
Communications
Providing communication devices such as handheld radio or application of standard crane hand signals will ensure there
is a common understanding between members of the lifting crew. Employers must take into consideration the local
workforce which comprises workers from various countries with different languages when forming the lifting crew.
5.2.2.6 Method
Most general type of lifting operations rely on established procedures after determining factors such as selection of
lifting equipment, environment and personnel as discussed earlier. These types of lifts are categorized as routine lifting
operations. Whether the lift is routine or not, there are other important factors in the life-cycle of a lifting operation
that needs to be considered.
If the weight of the load is unknown, the general rule of thumb is not to lift the load as it could lead to overloading and
toppling of the Lifting appliance but to carry out a load test at very limited height (e.g. 50cm from ground). In order to
proceed with the lift, an estimate of the weight – provided reasonable safety factors are used – can be applied, too.
Securing the load using appropriate lifting gears such as slings, nets or receptacles
If the load is not properly rigged or loose, there is a Risk that the load will be dislodged and dropped while being
transferred from one location to another.
If the CoG is not directly beneath the load-line, the load will swing when it is lifted off the ground. In addition, it is
dangerous and will destabilize the crane if the load is being pulled or dragged.
Stability of the suspended load and personnel safety during movement / slewing of the crane.
While moving or slewing the crane, the load shall be prevented from jerking or swinging at all times.
When the load is lifted by crane, it shall be arranged and planned, as far as practicably possible, for lifting without the
load to be touched with any part of the body, especially when it is swinging or rotating.
When lifting with offshore cranes on floating installations, the load shall be landed to release potential energy and to
gain control on rotational and swaying / swinging movements, before the load can be touched after “clear signal” from
crane operator.
Extensive operations
Frequently situations arise during which an extensive amount of lifting operations are to be executed over a period of
one day up to several weeks with one or more cranes on location.
If during the day or somewhere in the overall period of the lifting activities the crane needs to be set-up on another
location, this new location shall be shown on the plot plan as well. Crane operator shall be instructed that setting up of
the crane and hoisting operations are only allowed from the pre-determined positions. Variation from the pre-
determined set-up positions of the cranes shall result in the job being stopped, reassessed and having adequate
measures in place to ensure continued safe operations.
SIMOPS
SIMOPS (Simultaneous Operations) are described as the potential clash or overlapping of activities which take place
concurrently and, hence, could lead to an undesired event or hazardous set of circumstances (e.g. safety, environment,
damage to assets, schedule, commercial, financial etc.).
In particular, these are defined as the act of performing two or more operations concurrently among various discipline
(well operations, production, construction, etc.) within the same area.
SIMOPS often involve multiple companies (owners, contractors, subcontractors, and vendors), large multi-disciplined
workforces and a wide range of daily, 24 hours, routine and non-routine construction and commissioning activities.
The goal of Permit to Work is to ensure a coherent and efficient management of all works conducted on the different
work sites, in a way to protect human, environment and material resources.
Lifting operations shall be controlled in accordance with Eni in Nigeria PtW Procedure (pro hse 002 eni ng “Permit to
Work”). The Lift Plan package (Lift Plan, Risk Assessment, applicable checklists) shall be attached to the Permit-to-Work.
In the preparation of the Permit to Work the significant steps are the risk assessment, the PTW coordination meeting
and the Toolbox talk.
The risk assessment shall be prepared by HSE function, in collaboration with Lifting Team and Lifting Technical Authority,
when required, making reference to the Eni Upstream “opi sg hse 001 – Risk management and reporting” or the relevant
BU version of the OPI, where applicable.
The PIC shall take ownership of the Lift Plan and make it available to the lifting team. The underlying principle is that all
foreseeable Risks were assessed and eliminated or mitigated.
• necessary equipment;
• personnel;
• resources;
• controls and actions;
• access to lifting attachment points.
The purpose of a proper Lift Plan and Permit to Work is to verify that the necessary control measures have been taken.
Those documents, together with the Risk Assessment are complementary and shall not be seen as mere paper exercises.
The Lift Plan shall be attached to the PtW with the associated Risk Assessment based on the Method Statement
connected to the lifting activity. Annex A3 below provides the list of contents of the Lift Plan.
The Lift Plan shall include but not be limited to the following considerations:
The personnel required;
What is to be lifted, its weight, configuration, lift points, center of gravity – including the NET and GROSS weights;
Type and location of lifting/rigging points;
Selection of appropriate Lifting equipment, lifting gear and Appliances and relevant certificates;
Application of the correct lifting methods;
Position of Lifting appliance, personnel and of the load, before and after the lift operation;
The work site operation including proximity of other Lifting appliance and work activities;
Environmental factors detrimental to the lifting operations such as ground conditions, adverse weather, wind, and
poor illumination;
To a larger extent, for Non-Routine lifting operation, Lift Plan content should include:
General information:
• Document information;
• Description of the site and the activity;
• Method Statement.
Details of the LOAD:
• Description of the load;
• Engineering data: Dimension / Weight / CoG.
Details of the LIFTING APPLIANCE:
• Type and Model;
• Load chart and capacity for the intended configuration (Safe Working Load – SWL);
• Crane sitting study.
Details of the RIGGING ARRANGEMENT:
• Type of Accessories/Lifted Equipment;
• Lifting Rigging Arrangement Capacity (WLL).
Unity Check;
Lifting drawings:
• General Lifting Drawing of the Lifting Model / Technique;
• Additional drawings views (elevation, additional side views) and detailing Rigging Arrangement.
Consideration of environmental and working area condition:
• Ground;
• Obstacle;
• Lighting;
• Demarcation;
• Environment.
Personnel involved in the lifting operation;
Means of communication;
Simultaneous Operations (SIMOPS).
Drawings should provide a crane details and load break down including but not limited to the below:
Crane Model;
Boom Length;
Radius;
Capacity at worst case radius;
Maximum radius at expected load;
Load weight;
Tackle weight;
Hook block weight;
Vessel stability;
Communications Protocol for vessels entering the 500m zone (if applicable);
Load and safety factors including but not limited to:
• Weight contingency factors;
• Consequence factors;
• Hook loads;
• Lift point and sling loads;
• Dynamic Amplification Factors (DAF);
• Skew Load factors (SKL), if applicable;
• Sling and grommet safety factors;
• Shackle safety factors.
Bumper and guide details;
Lift point design;
Load stability;
Interface between floating Lifting Appliances and fixed structures;
Critical clearances;
Lift vessel ballast management including pick up and set down.
Changes in the weather and environmental conditions which have an adverse impact to the lifting operation;
Changes to safety-critical personnel.
In any case procedures for recovering and landing the load in the event of the lift being aborted should be clearly
identified.
In addition, it shall cover the work plan, the Hazards, the controls, roles & responsibilities, and any recovery measures
to be taken if the controls are not completely effective.
The Toolbox Talk is a meeting involving a two-way dialogue to ensure that everyone clearly understands the task
involved along with its Hazards and the precautions to be put in place.
Furthermore, TbT provides opportunities for PIC and also the rest of the team to emphasize the importance of particular
issues or procedures as well as the chance to personnel to ask questions or make comments.
During TbT, all personnel involved in the lifting operation shall have their individual responsibilities clearly allocated.
All personnel should have the opportunity to review the findings of the Risk Assessment and the details of the Lift Plan
to ensure that everyone clearly understands and agrees with the methods and control measures to be used.
The TbT record document shall be attached to the PtW. Refer to pro hse 002 eni ng “Permit to Work”.
Refer to Annex A20 “Ten Questions for a Safe Lift” during TbT.
Two-way radio communications shall be used as the primary means of communication during lifting operations. The
availability and use of radios to communicate with the crane operator is a particularly effective way to reduce the risk
of injuries associated with lifting operations.
When using a radio communication:
The radio should be tested prior to use to ensure that the transmission is clear and reliable;
Each crane should use a separate channel, if frequencies are available;
Make sure that the crane operator and other ground personnel communicating with the crane operator have been
trained on how to properly use the radio equipment.
Hand signals, are an acceptable alternative method for lifting operations, except for blind lifts and offshore pedestal
crane operations involving boats. They can be used in addition to the radio equipment and shall be used as back–up in
the event of radio equipment failure.
After completing the lifting operation, everyone involved in the lift shall have the opportunity to discuss and make
improvements to the Lift Plan. Any learning points noted on the plan should be reported to the PIC, reviewed and,
where appropriate, generate Lesson Learned (LL) and improvement actions shall be taken and disseminated amount
worksites.
Assessment (Audit)
A program of planned and systematic assessment shall be enclosed in the Lifting Management System to ensure that
both Company and Contractors comply with the provision set in the lifting system and that the process is in compliance
with this manual.
Assessments shall be performed on:
Lifting operations;
Lifting process.
Lifting operations assessment shall be based on the degree of Risk and the results of previous assessment findings and
shall consider the conformity of all operational aspects in terms of equipment effectiveness, lifting techniques,
personnel, etc.
A reference checklist to perform lifting assessment is reported in Annex A5.
Lifting Operation assessment shall include, but are not limited to the verification of:
Recording actions taken in response to lifting incidents, accidents and lessons learned;
Recording all defects and remedial actions;
Recording of KPIs.
Lifting process assessment shall consider the overall process performance and consistency in order to ensure that
adequate resources, personnel requirements and methodologies are in place, together with the compliance to the
procedures put in place, and the conformance of the required recording for tracking purposes.
The above actions are part of the process and operational control system and contribute to the implementation of a
rigorous assurance and self-verification system to be set at appropriate intervals depending on the Risk Situation.
5.3.2 Recording
Records shall be kept to demonstrate auditable and effective control of lifting operations and equipment.
The implementation of a Track Recording System is mandatory - an electronic traceability database is recommended.
Tracking Recording System shall assist the proper data records management which is an integral part of the overall
lifting process management.
As a minimum the following records shall be contained in the Tracking Recording System:
Equipment Registry
The Lifting Equipment shall be recorded in a registry available on the site and accompanied by a declaration of
conformity, instructions for use and a manual containing information about the operation, maintenance, assembly,
disassembly and transport.
As minimum the following data shall be included for all Lifting equipment:
Manufacturer and description;
Identification number;
SWL;
Date when the equipment was first taken in use;
Particulars of defects and steps taken to remedy them;
Dates and numbers of certificates of tests, inspections, and examinations, and name of person who performed
these;
Due dates for previous and next periodic inspection or periodicity of inspections.
This may be done either in a dedicated register and/or as part of a maintenance management system. The Lifting
Equipment records are periodically updated on the Lifting Information System (LIS).
Lifting Accessories (devices that connect the load to the Lifting appliance, such as slings, shackles and the like);
Lifted equipment (device used to suspend the load, e.g. containers, baskets, etc.).
5.4.1.2 Inspection
All Lifting Equipment shall be inspected prior to each use. An inspection is defined as a visual check, supported as
required and where practicable by a function check, to ensure there are no obvious damage or deterioration to the
Lifting Appliances or Accessories and to ensure that safety conditions are maintained.
Pre-use checks or pre-use inspection of cranes are required to ensure that the appliance is safe to use and that any
deterioration or damages are detected and rectified before the crane becomes unsafe. It should be carried out at the
start of each shift during which the crane is to be used. These are to test the functionality of the crane and visually check
for any obvious defects.
All Lifting Accessories shall be inspected prior to each use to ensure they are in good state and safe to carry out the task
at hand.
Appliance operators shall be sufficiently experienced and competent - as specified above in Section 7 - shall carry out
inspections.
Frequency of inspection
Frequency of inspection shall be performed prior to each use in accordance with Company’s recommendation but there
may be variation depending on conditions of use. As a general guide:
Prior to each use, as far as reasonably practicable;
At weekly intervals, depending on type of activity (e.g. in case of routine lifts with minor handling of rigging);
At other intervals or under conditions identified by the manufacturers or Risk Assessment.
Samples of Pre-Use/ Periodical Inspection Check-List for Mobile Cranes, Cranes and Forklifts are shown Annex A8.
This examination may require some dismantling of the equipment to expose the critical working parts. Thorough
Periodic Inspections shall be performed by company’s approved third-party Certification Authority and a Report of
Thorough Examination issued. Equipment that has been involved in any of the following shall be thoroughly examined:
An incident, lifting incident or environmental;
Overload;
Subject to modification or major repair to components in the load path or other safety critical components;
Changes in condition of use including periods out of service, etc.
The extent of the thorough examination should reflect the likelihood of failure and the actual risk which could arise
from any such failure. It should also take into account when the appliance was built and put in use and the likely
deterioration since manufacture, which could increase risks in use. Records of tests and inspections carried out by the
manufacturer should also be taken into account.
Frequency of Thorough Examinations
All Lifting Appliances and Accessories shall be subject to thorough examination on a regular basis. Frequency of thorough
examination shall not exceed 12 months (6 months for lifting Appliances used in lifting of Personnel). If required by local
legislation and/or by manufacturer, it shall be more frequent. Thorough examination is required in the following
circumstances:
before being put into use for the first time, unless it has a valid regulatory documentation or report of thorough
examination;
where a regulatory requirement was issued more than six months before the lifting Appliances is put into service,
or as the relevant regulator requires;
where the equipment is involved in an accident or dangerous occurrence;
after a significant change in conditions of use, for example after assembly and before being put into service at a
new site or new locations, this includes installation, relocations, modifications and repair;
after long periods out of use;
each time that an exceptional circumstance (such as overload) is liable to jeopardize the safety of the lifting
Appliances.
A program shall be prepared describing competent control for each type of lifting appliance according to the applicable
Lifting Plan.
Thorough examination shall be carried out in accordance with manufacturer’s recommendation with documentation
that defines the permissible operating conditions, design criteria, documentation of testing, maintenance and operation
manuals, and examination/inspection requirements.
Local statutory controlling documents shall address maintenance, inspection and Certification criteria in accordance
with a recognized Standard and/or manufacturers’ recommendation and in compliance with national local regulations.
Pre-used equipment shall also be supplied with operations and maintenance history, including:
major repairs;
modifications or limitations arising from previous use.
Following the thorough examination by the Independent Competent Person (Third Party), a report of examination shall
be prepared and issued, describing the examination being undertaken and findings and certification with validity
defined in accordance with the abovementioned process.
5.4.1.4 Certification
The manufacturer or service provider shall supply all Lifting Appliances with documentation that defines the permissible
operating conditions, design criteria, documentation of testing, maintenance and operation manuals, and
examination/inspection requirements.
All Lifting Appliances shall be marked with the Safe Working Load (SWL) or Working Load Limit (WLL) and identification
number allowing full traceability to current Certification.
No Lifting Equipment shall be used without full traceability to valid Certificate.
The suggested frequency of the certification – as per International Standard – for each main Lifting Appliance type and
relevant special requirements as well is reported in the table as shown in Annex A9.
Upon satisfactory completion of the procedures indicated above the competent person shall complete and issue the
Register of Lifting Appliances and attach the appropriate Certificates.
Offshore cranes for personnel lifting
General Cranes intended for lifting or moving of personnel shall be equipped with the specific features given in the
subsequent paragraphs, in addition to the other requirements
For personnel transfer on offshore units, cranes should meet the applicable requirements for Man-riding operation (e.g.:
API Spec 2C; EN 13852-1).
The crane shall be fully operational, properly maintained, certified and currently in compliance with its required
inspections. Attention is drawn to the fact that many national shelf authorities, as well as maritime authorities, have
their own requirements pertaining to lifting of persons.
Annex A10 below provides the list of types of Lifting Accessories and corresponding description.
facilitate the identification of the equipment and its component including whether it is genuine and compatible
with the equipment.
All Lifting Accessories shall be permanently and clearly identified and marked with at least:
Safe Working Load (SWL) or Working Load Limit (WLL);
unique ID mark (serial number);
CE mark or equivalent;
tare weight for lifting beams and/or spreaders;
diameter and/or length as deemed necessary.
SWL is defined as the maximum load the Lifting Equipment is certified to withstand under normal use. Thus, it is a value
or set of values based on the strength and/or stability of the equipment when lifting. A range of SWLs can be specified
for the same equipment when used in different configuration.
Where a number of Lifting Accessories are assembled to form a single Lifting Equipment which is not dismantled after
use, the assembly shall be marked to indicate its safety characteristics to users.
Where there are other characteristics which may cause a lifting accessory to become unsuitable for use in a particular
application, this information shall be marked or otherwise made available to the user.
For items having different working loads, depending on the hoisting position, the SWL of the item at each hoisting
position is also to be marked.
Particular attention shall be addressed to verifying that test marks on the item of Loose Gear are noted on the relevant
test certificate. Where there is no evidence of this, the item concerned is to be subjected to a further test.
Test marks shall be in a visible position and are not to affect the tension strength of the item.
Where marking is performed on a plate permanently linked to the item, the plate shall be resistant to corrosion and the
marks may be of greater dimensions than the above.
Marking of the SWL on spreaders, lifting beams and similar items shall be such as to be clearly visible for the operators.
All Lifting Accessories and lifting points of Lifted Equipment (e.g. pad-eyes, trunnions, slings, etc.) shall be color coded
to enable to enable staff to identify easily equipment that is within test date and hence with valid certification. At each
thorough examination the independent competent person should be instructed to remove existing color code and
replace it with a new color.
Color coding is standardized and is in-line with the DPR “Guidelines and Procedure for Lifting Equipment and Lifting
Operations” and shall follow the system shown in the following table. The color must be applied close to the SWL and
cover the old color code.
The color corresponds to the period in which the item is put into operation, either as new or after the periodical
test/examination. Annex A11 below provides examples of color coding for Lifting Equipment.
NOTE:
Change of colour-code is permitted starting from 14 days prior to the end of a period. Under exceptional
circumstances, the use of an out-of-date colour-coded accessory is permitted up to 14 days after the end of a
period;
Red is to be used for equipment that is defective or quarantined and therefore that shall not be used for regular
colour coding purposes;
Black should be used for equipment that should not be used but can be recertified before use;
The permissible colour codes shall be indicated on signs placed at suitable locations: on the operating areas and in
the Lifting Accessories Rigging Loft;
The allowed colour codes in force at any particular time shall be clearly and visibly indicated on signs placed at
suitable locations within the working site: on the operating areas and in the Lifting Accessories rigging loft.
A sign shall be prominently displayed to indicate to staff the current colour code. Lifting Accessories without a
colour code must not be used;
With regard to the man-made fibre slings, such as webbing slings and round slings, the rated capacity – Working
Load Limit (WLL) – is coded by a colour defined in the European Standard EN 1492. All rated capacities from 10 ton
are orange; all intermediate sizes must be identified by a unique different colour. Reference for colour coding
based on WLL may be made on the table.
5.4.3.5 Inspection
Identification of Safe Working Load, SWL
The identification of Safe Working Load (SWL), operating mode and configuration for the safe use of equipment, is
required to ensure that Accessories are used only within the range of operating parameters appropriate to their safe
use.
SWL is defined as the maximum load the Lifting Equipment is certified to withstand under normal use. Thus, it is a value
or set of values based on the strength and/or stability of the equipment when lifting. A range of SWLs can be specified
for the same accessory when used in different configuration.
Initial Inspection
The Person in Charge (PIC) with the assistance of the Rigging Loft Controller shall perform an initial inspection of all
lifting Accessories arriving on site. They shall be subject to a detailed initial inspection, verifying the validity of the color-
coding (i.e. if applied color matches with the “color-code” valid on site) and general conditions prior to first use. In
addition, relevant certificate (thorough examination reports) shall be checked and filed for future reference. If this
certificate is not available, a further examination shall be performed and certification issued by Independent Competent
person.
If the Accessories are new, they shall be stored in a dedicated storage area (rigging loft) where the rigging loft controller
will collect the manufacturer certificate. Prior to first use, the Accessories shall be thoroughly examined, certified and
color coded by a third party (independent competent person).
The non-conforming Accessories shall be identified as such and placed in a suitable area, quarantine area, to prevent
further use. It shall also be ensured that non-conforming Accessories are physically altered prior to being scrapped, to
prevent any further use.
Pre- and Post-use inspection
Prior to the release of Accessories from the storage area, each accessory shall be checked by the Rigging Loft Controller
for certification and color-coding validity.
Prior to use, the final user (Slinger and/or Banksman and/or PIC) shall carry out the pre-use inspection.
All Lifting Accessories returned to the rigging loft shall also be checked for defects; any defected Accessories shall be
marked in red and quarantined.
To ensure the integrity of Lifting Accessories, they shall be subject to a thorough examination by an Independent
Competent Person (Third-Party) who has sufficient detailed knowledge of its design, operation and failure modes to
recognize significant defects. At the end of the examination, the certification document shall be issued and the
Accessories shall be colour-coded.
The scope, methods and applicable Standards of that examination, and acceptance/rejection criteria shall be specified
for all equipment and shall be compliant /consistent with the equipment Manufacturer’s recommendations.
Thorough Periodic Inspections shall be performed also in preparation to a third-party Certification Authority periodic
assessment. The results of the inspections shall be recorded and kept at disposal for the authorities’ review.
5.4.3.7 Certification
All Lifting Accessories shall be subject to a thorough examination by an Independent Competent Person (Third-Party)
who has sufficient detailed knowledge on the design, operation and failure modes to recognize significant defects. At
the end of the examination, the certification document shall be issued and the Accessories shall be colour-coded.
Engineered Lifting Accessories (e.g. spreader bars) shall be designed, manufactured, and tested in compliance with the
relevant industry Standards. Any lifting accessory not certified shall be structurally verified by a qualified engineer and
load tested to an acceptable code.
Lifted Equipment includes Cargo transport units (containers), tote tanks, drum racks, gas cylinder racks, standard ISO
tank container, material basket, frame racks, skids, etc.
Cargo transport unit (containers) and their pad eyes must be designed/validated and certified by a Certification
Authority to meet the DNV Standards 2.7-1, 2.7-2 or 2.7-3 or Lloyd’s Register requirements.
Annex A12 below provides a list of and description of Lifted Equipment.
presence of inspection/test plate with the necessary information clearly shown and readable;
validity of the certification for the intended use (when dispatched from onshore, it shall cover the duration of a
round trip);
correct labelling for the transportation of hazardous substances;
conditions of door locks, seals and other mechanism, as applicable;
conditions, certification and colour-coding of the lifting points;
status and suitability of the rigging arrangement and its components (shackle, slings, etc.).
In case of defects or damaged found during pre-use inspection, these shall be notified and the equipment marked as
“unfit for use” or stored, if possible, in a dedicated quarantined area.
All equipment containing dangerous goods shall be checked for presence of correct hazard label. It is just as important
to remove the old hazard placards and labels when the package, container contains hazardous goods.
A brief description of the above listed Lifted Equipment and relevant minimum requirements are subsequently reported.
All those items or objects that are not arranged in skids, boxes or containerized, shall be subject to additional checks
aimed to ensure that they can be safely lifted. They shall be checked for availability of in-built lifting points (by
manufacturer) allowing general lifting and handling operation or alternative means, if applicable or possible, to perform
a safe rigging operation. In such case, the proposed rigging arrangement shall be checked and validated by an
Independent Competent Person.
ISO 4309;
ISO 4310;
ISO 7363;
ISO 9927-1;
ISO 12482-1.
The frequency and extent of such maintenance should be defined in accordance to various factors affecting the crane
working conditions. Maintenance schedule shall integrate preventive and predictive maintenance techniques.
The Site Manager shall be responsible for the Maintenance Program, developed in collaboration with the Maintenance
and HSE Departments for its definitions, in accordance with law requirements and best practices, based on
manufactures recommendations.
Manufacturer's instruction manual recommends the periodical maintenance, specific tasks and intervals of frequency
in order to ensure the appliance is maintained in good state, efficient working conditions and, hence, safe to use.
Moreover, manufacturer's instruction books specify essential maintenance activities such as replacement of filters and
oil, recommended tires pressure, etc.
Maintenance schedules shall consider the age of the equipment as well as frequency and conditions of use. Particular
attention shall be paid for equipment whose life expectancy is approaching the end of the life cycle.
In case of major repair or replacement of damaged parts or components, these shall be performed only by an authorized
party (generally by the manufacturer) prior to thoroughly examine, test and put into service the appliance. In the event
of Lifting Equipment provided by Contractors, the Site Manager shall support the contract holder in collecting
Contractor’s necessary maintenance information for internal review and acceptance. Copy of the proper manufacturer’s
operation and maintenance manuals of all Lifting Appliances shall be available on site.
Before a crane is delivered and accepted to site, it should be inspected by maintenance personnel and results of the
inspection should be recorded. This record may be required by the Independent Competent Person carrying out the
thorough examination of the crane.
IMPORTANT NOTE:
An effective planned maintenance system should recognize the possible need to prohibit use of the crane until essential
maintenance work is carried out.
Finally, a comprehensive maintenance program of all lifting Appliances and, where applicable, Accessories is significantly
important to meet the necessary requirements for equipment re-certification following thorough examination by an
Independent Competent Person.
In case of need to perform Non-Destructive Examination (NDE) methods/techniques, they shall be in compliance and
consistent with Manufacturer’s recommendations. The Inspection Procedures, relevant /applicable to Inspection
methods used (e.g. MPI, UT, LP etc.), shall be approved by a Level III ISO 9712 and Inspectors, in charge of performing
NDE, shall be certified Level II ISO 9712 or Level I under the supervision of a Level II ISO 9712 certified Inspector.
SWL;
Date when the equipment was first taken in use;
• Man riding;
• Work basket;
Before lifting the personnel for transferring or for other work activities, try to identify an alternative method, if possible.
Lifting of personnel shall be avoided unless the risk has been demonstrated as being ALARP.
As general recommendation, personnel transfer or the use of a lifting appliance for man-riding operations such as the
use of personnel baskets and work baskets shall therefore be carried out in exceptional circumstances and strictly under
Permit to Work system upon risk assessment execution where all hazards involved are taken into consideration and
brought to an ALARP level of acceptance.
In order to ensure safety of the operation, particular attention shall be paid at all times to weather conditions. Any
deviations from limitation criteria, hereafter described, shall be subject to review and approval of Site Authority (Site
manager, OIM, Vessel Master, etc.) and to Risk Assessment.
5.5.1 General
5.5.1.1 Responsibility
All Lifting of Personnel operations are subject to review and approval of Site Manager, OIM and Vessel Master, if the
lifting involves offshore personnel transfer, who is the person responsible for review and approval or personnel transfer
or man-riding operations by means of Lifting Appliances.
All Personnel Lifting operation shall be conducted under Permit To Work system and that a responsible person (PIC)
shall be identified for each type of Personnel Lifting operation (e.g. Marine, Drilling, Construction, etc.) and he shall
ensure a safe conduct of the Personnel Lifting operation and that all personnel involved are fully informed of the lift.
The Person In Charge (PIC) for lifting operations shall be the responsible person for the execution of the Personnel Lifting
operation.
The PIC and the Transfer Vessel Master shall come to agreement that they are confident with the entire transfer and
that this operation can be carried out safely.
5.5.1.2 General safety requirements
Lifting or personnel operation are subject to the following general safety requirement:
All personnel lifts shall be categorized as Non-Routine Lifts and be subject to stringent planning and controls, Risk
assessment and written authorization by the Site Manager, OIM or Vessel Master;
Radio communication between involved parties shall be checked and confirmed as satisfactory prior to personnel
lifting;
Area below lifting of personnel must be barricaded, apart from specific conditions (such as crew boat transfers);
Evaluation on possible interference by simultaneous operations and equipment shall always be carried out;
An Emergency Response Plan shall be prepared or available prior to perform any lifts, which shall include, but not
to be limited to the following:
• Contingency plan;
Participating in lifting operations is voluntary. All personnel involved must have agreed to the lift.
5.5.1.3 Training/Competency
Operator of Lifting Appliance shall have at least one year of experience in personnel lifting with the appliance in subject
or an equivalent one.
Only personnel suitable trained for the operation and safe use of personnel Lifting Appliances and Equipment may be
involved in personnel lifting operations.
A person cannot be deemed competent unless he/she has been trained and assessed for the task. This should include
as a minimum the following:
Understanding of personnel lifting;
Job Safe Analysis (JSA) requirements;
Work-at-height instructions;
Work-over-sea instructions;
PTW procedure;
JSA Form;
TBT Form;
Man-riding log.
Once all checks are completed and Site Manager or OIM and PIC confirm, in coordination with the vessel Master, that
activity may commence.
Annex 14 below provides a “Transfer of Offshore Personnel Decision-Making Flowchart”.
Prior to, during and after lifting operation the following instructions shall be considered and followed, as applicable:
In case of personnel transfer with luggage, toolset boxes or others, these shall be secured on the floor at the centre
of the transfer basket. If this is not possible, they shall be transferred separately. No luggage shall be secured to
the outer ring or walkway;
Luggage weight shall not exceed the maximum allowable weight per passenger;
Lift off and landing areas must be ready and clear for obstructions/obstacles;
Crane operator shall confirm line of sight and communication with banksman;
Crane hook in place and suspended well clear of the transfer basket, but not below head height, until all transit
personnel are secured within the transfer basket;
Rigging shall have sufficient length to allow enough slack to accommodate vessel movements with the hook
remaining above head height while the transfer basket is on deck;
Taglines shall be held to control the initial phase of lifting and then left, ensuring they are free and away from
entrapment points (NOTE: the use of tagline shall be subject to risk assessment, which shall consider all options
and agree whether taglines are safely applicable or not – e.g., lifting of baskets from small surfers) ;
The basket shall be lifted sufficiently to be clear of any obstructions and then swung out over the sea ensuring that
the basket does not collide with any part of the vessel or offshore unit;
Raising and lowering of the basket shall, as far as practicable, take place over water and not over the deck of either
the offshore unit or the vessel;
The vessel where personnel is picked up from or dropped off to shall have a rescue boat available on board, ready
to be put in water in case of need;
Personnel lifts shall only be conducted where there is line of sight (full visibility) between the Crane Operator and
Banksman, and between the Banksman and the person being transferred;
During the transfer basket landing the transit personnel shall remain seated and secured until transfer basket is
stable on the deck;
Transit personnel to wait for assistance from installation personnel before transit personnel securing is removed.
5.5.2.2 Appliances/Accessories
Safe Working Load (SWL) of Lifting Appliance and other Equipment is to be observed. All equipment must have SWL
clearly marked on it and instructions for use must be readily available.
The equipment used for personnel transfer shall be specifically designed, approved/certified and clearly marked as
suitable for personnel lifting operations.
The following Lifting Equipment shall be used for personnel lifting for personnel transfer (see figures below):
Crane operator shall check all crane functions and confirm to the PIC the successful conclusion of the pre-use
inspections. Personnel transfer equipment shall be checked to ensure there are no damages and that all locking
mechanisms are correctly working. A trial lift shall be made prior to the actual transfer. A trial lift without personnel
shall be made prior to the actual transfer.
All personnel involved in the transfer shall wear adequate Personal Protective Equipment (PPE) at all times. Life jacket
shall be issued and worn (with survival suits in areas with cold water).
Finally, the personnel involved in the lift must be familiar with the respective operation manuals for the Lifting
Equipment in question. In case of personnel who have not travelled previously by basket or PTC, these shall be
accompanied by a member of the deck crew.
The sides of the platform enclosed from the toe board to the mid-rail with solid construction or expanded metal
having openings no greater than ½ in. (1.27 cm);
Platform access gates, including sliding or folding types, if installed, shall have a positive acting device to restrain
the gate from accidental opening. Swinging type access gates shall open only to the interior of the personnel lift
platform;
Rough edges exposed to contact by employees surfaced (ground smooth) to prevent injury;
High-visibility colour or marking for easy identification.
The basket rigging system (sling wires, shackles, master links) shall have a minimum specific safety factor on minimum
breaking load (MBL) of the accessory, as follows:
One-leg system – design factor of 1:7 on the MBL;
Two- or three-leg system – design factor of 1:5 on the MBL for each leg;
Four-leg system – design factor of 1:5 on the MBL (considering load acting only on three legs);
Where rotation resistant rope is used, the slings shall be capable of supporting without failure at least ten times
the maximum intended load.
Rigging system shall be arranged in such a way to link the slings to a master-link in order to have an even distribution
of the load and safety type shackles (with safety pin) to avoid accidental disengagement. Moreover, the rigging set shall
be exclusively used for personnel lifting purposes with the work basket only.
Furthermore, the following considerations shall be made when selecting the rigging arrangement for the purpose of
personnel lifting:
Only sling wire are permitted, equipped with thimble eyes decrease the bending curvature of the sling eye
overtime;
No use of synthetic fibre slings is allowed;
The use of wire rope clips, wedge sockets shall be prohibited in any rigging set;
Responsibility
The Site Manager is responsible for the operation, and he takes the final decision on whether the operation can proceed.
The Person-In-Charge (PIC) for lifting operations is the Responsible person for the transfer and information to the
personnel.
In addition to the above listed limitation criteria, the lifting appliance manufactures recommendations shall also be
considered depending on the crane configuration (boom lengths, truck width, etc.).
In case of conflict between criteria, the most stringent shall be followed.
Appliances/Accessories
Safe Working Load (SWL) of Lifting appliance/Accessories shall be observed at all times. All equipment shall be marked
with SWL and instructions for use must be readily available.
The equipment used for personnel transfer shall be specifically designed, approved/certified and clearly marked as
suitable for personnel lifting.
All personnel operating on a work basket shall wear a fall arrestor to be connected to the work basket.
If welding operations are required, there should be no earth connection to the basket or Lifting appliance. Moreover,
during welding operations from the work basket, measures shall be taken to ensure that there is no current leakage
through the Lifting appliance in order to prevent damage to crane components. Attention shall be paid to the use of tag
lines which shall pulled into basket when out of reach/out of use.
Under no circumstances shall Man-riding operations take place where there is no visual contact between the man at
height, the banksman and the winch operator. The winch operator and the banksman must not carry out any other
work during man-rider operations.
Stop the operation if there is a stop signal and/or the safety of the operation is compromised.
Responsibility
The Site Manager is responsible for the safe use of man riding winches (man-riders) and in particular for ensuring this
procedure is strictly enforced to safeguard all personnel engaged in lifting operations.
All personnel involved in man riding have an individual responsibility to ensure the equipment and procedures are fit
for purpose prior to engaging in man riding operations.
General weather requirements are prevailing. Deviation from the general weather criteria can be given by the Site
Manager or OIM. In such cases, a special Risk assessment must be made considering extra precautions, man riding
behind wind wall, etc. This Risk assessment must be documented in a JSA, TBT, or on the PTW itself.
Adverse weather procedures must be considered regarding wind speed. If gusts affect the conditions adversely, work
shall not continue.
Appliances/Accessories
Only winches certified, identified, and marked as being “suitable for man-riding” shall be used for this type of operations.
These winches are painted yellow for identification and are designed in accordance with a recognized Standard (e.g.
NORSOK standards R-003N chapter 4 and D-001 chapter 5.5.3.2., DNV-OS-E101 Offshore Standard).
Wire clamps shall not be used in this connection, a simple connecting link from the winch to the harness which can only
be manually activated shall require a “D-type” shackle, bolt nut and a safety split pin mandatorily.
An independent means of fall protection (static line or inertia reel) must be installed unless safety of the operation is
compromised. The decision not to use an independent means of fall protection must be approved by the OIM, evaluated
in the Risk Assessment and noted on the Permit-To-Work (PTW).
Man-riding harness must be inspected prior to and after operation and must be checked by a colleague for perfect fit
after adjustment, it must be clean, undamaged and marked with an ID number.
All safe and good practices must be well-established within the management system, including all necessary
maintenance. The winch, anti-fall securing equipment and the man-riders must be operated in accordance with internal
procedures. These must agree with the manufacturer’s instructions.
Pre-Checks
The PIC, the winch operator, the flagman and the person in the man-rider shall always discuss the operation in advance
in order to determine the best work method.
The winch operator shall conduct a pre-use check of the man-rider and the fastening (correct use of safety equipment)
and shall ensure that tools to be used by the person in the man-rider have been secured.
The pre-use check list prepared by the manufacturer must be followed. If the manufacturer’s checklist does not include
the following points, these must also be dealt with:
Prior to initial use of man-rider winches, the winch, wire and man-rider must be checked for possible faults;
The shackle used must have the current year’s colour, as well as a lock pin between the harness and the swivel;
Use anti-fall securing equipment on tools;
Function test the winch. Test the emergency stop function. Check the emergency heaving and lowering. Check the
brake;
Check the winch components visually with damage, leaks, etc. in mind;
Be very careful that the wire winds correctly onto the drum, so that the wire does not build up. This may cause an
uncontrolled fall for the person hanging in the man-rider.
Maintain, at all time, eye contact with the person in the man-rider, either personally or through the flagman, and
maintain good communication;
Stop the lifting operation if there is a stop signal and/or the safety of the operation is in doubt.
The trained operators involved in use of MEWP shall have individual responsibility to ensure the equipment and
procedures are fit for purpose prior to their use and carrying out pre-use function check and ensure that maintenance
is regularly carried out as prescribed by the manufacturer.
Records of these checks shall be kept. The operator shall also be fully aware of the procedure their employer expects
them to follow should they identify a fault with the MEWP, e.g. isolate the controls, tag the machine and report the
defect to the person in control.
All types of Mobile Elevating Work Platforms (MEWP), also called Cherry Pickers include the following:
Vertical “scissor” lift;
Self-propelled boom;
Vehicle-mounted boom;
Trailer-mounted boom.
The above listed MEWP types are shown in the figures below:
The MEWP must not be used as winch, elevator, or to drag items. To reduce the Risk from MEWP Hazards, the trained
operator shall take the following precautions:
The area around the platform shall be barricaded so that to prevent personnel injuries in the event of accidental
dropping of tools or objects;
If used to install materials the weight and dimensions of materials shall checked and any manual handling and load
distribution issues shall be considered;
Prior to use, the area shall be checked for presence of overhead cables or power lines and other dangerous
machinery;
Personnel riding a lifting equipment shall wear a safety with a short work restraint lanyard securely attached to
the platform;
The MEWP shall be used on firm and level ground. Any temporary covers should be strong enough to withstand
the applied pressure. Localized ground features, e.g. trenches, manholes and unstable grounds, can all lead to
overturning;
Ensure a good level of housekeeping inside the platform to reduce the Risk of the operator tripping or losing
balance while working.
Responsibility
The Site Manager is responsible for the operation, and he takes the final decision on whether the operation can proceed.
The PIC on duty shall be directly responsible for the safe use of MEWP and in particular for ensuring this procedure is
strictly enforced to safeguard all personnel engaged in lifting operations.
The work at height by mobile work equipment requires an assessment to be carried out before starting any work at
height. If the assessment determines that the work can be carried out in a way that avoids having someone working at
height then this must be done.
However, if the assessment confirms that there is no alternative to working at height then the work must be properly
planned and organized in advance by PIC to ensure that the most suitable work equipment is chosen.
The trained operators involved in use of MEWP shall have individual responsibility to ensure the equipment and
procedures are fit for purpose prior to their use.
Visibility: >100;
Thunder/lightning: must be avoided.
Appliances/Accessories
Safe Working Load (SWL) posted on MEWP shall be observed. All equipment must have SWL clearly marked on it and
instructions for safe use must be available on the equipment. The equipment used for personnel transfer shall be
specifically designed, approved/certified and clearly marked as suitable for personnel lifting.
There must be an established management system, which ensures and documents necessary maintenance.
Pre-Checks
The trained operators shall responsible for carrying out a basic daily/pre-use function check and the basic maintenance
required by the manufacturer. Records of these checks shall be kept. The operator shall also be fully aware of the
procedure their employer expects them to follow should they identify a fault with the MEWP, e.g. isolate the controls,
tag the machine and report the defect to the person in control.
Throughout the operation
The MEWP must not be used as winch, elevator, or to drag items to reduce the Risk from MEWP Hazard the trained
operator shall take the following precautions:
The area around the platform shall be barred off so that falling tools or objects do not strike people below;
If used to install materials the weight and dimensions of materials shall checked and any manual handling and load
distribution issues shall be considered;
The MEWP shall not operate close to overhead cables or other dangerous machinery, or allow any part of the arm
to protrude into a traffic route;
If there is still a Risk of people falling from the platform a harness with a short work restraint lanyard shall be
secured to a suitable manufacturer provided anchorage point within the basket to stop the wearer from getting
into a position where they could fall from the carrier (with respect of this, reference has to be made to the
manufacturer manual and the risk assessment specific for the task;
The MEWP shall be used on firm and level ground. Any temporary covers should be strong enough to withstand
the applied pressure. Localized ground features, e.g. trenches, manholes and uncompacted backfill, can all lead to
overturning;
Keeping the platform tidy will reduce the Risk of the operator tripping or losing balance while in the basket.
The crane shall be fully operational, properly maintained, certified and currently in compliance with its required
inspections prior to being used.
Lifting of personnel may be done by all crane types. This section specifies additional requirements to cranes used for
lifting of personnel.
The requirements specified below are aiming at lifting persons with ordinary crane arrangements and are not intended
for Man-riding winches (lifting/lowering of one person) and other specialized equipment.
When using an appliance for personnel lifting, the unity check (or percentage of utilization) shall not exceed 50% of the
certified load radius for the given configuration.
This information shall be indicated in the instructions, load chart and by the safe load indicator whenever the appliance
is used for this purpose.
5.5.4.2 Brakes
Cranes to be used for lifting of personnel shall be equipped with two mechanically and functionally independent brakes,
with separate control units.
In case the primary braking system fails, the second brake shall be provided in emergency and it shall be fitted for both
main and boom hoisting system.
During testing phase, means shall be provided for separate testing of each brake.
Mechanical brakes shall fulfil the requirements for brakes based on SWL for the actual load cases. SWL will be replaced
by rated capacity for personnel handling provided the brake is used in personnel handling mode only.
Hydraulic restriction may be considered as one of the required two brakes, provided the rated capacity does not exceed
50% of the rated capacity for lifting of loads.
the hydraulic motor shall have a closing valve directly at the high-pressure (load) connection (no pipe or hose
connection in between);
the closing valve shall close as a result of pressure loss at the low-pressure connection (inlet connection during
lowering). This function shall be accomplished by direct bore or piping between the closing valve and the low-
pressure connection;
the hydraulic motor shall always be ensured sufficient working fluid, also in the event of power failure, i.e. gravity
feeding.
Where cylinders are used for luffing, folding or telescopic, they shall be provided with a hydraulic shutoff valve.
Alternatively, each motion shall have two independent cylinders where each cylinder is capable of holding the rated
capacity for lifting of persons.
Steel wire ropes for hoisting shall have a minimum safety factor equal to eight (8) and chains shall have a minimum
safety factor of six (6), related to the rated capacity for the lifting of persons.
Except for emergency operations, the operational limitations for lifting of personnel shall be as follows:
Mean wind velocity: 10 m/s;
Significant wave height: 2 m;
Visibility: daylight or equivalent.
Certified tubular transportation devices or skids should be used where possible and particularly when transporting
tubular goods with an outer diameter of less than 140mm;
Only tubular goods of the same diameter should be bundled together into a lift if it is not in a transportation device;
Ensure that the load does not shift, tubular goods greater than 127mm, where practical, should be bundled into
odd numbers of joints in an effort to compact them together so that the middle joints are gripped by the outer
ones and less likely to slide loose;
The tubular goods sling set should be assembled with two equal length legs of the same construction wire rope
and SWL, heavy duty reeving hard eyes or thimbles at the load end, terminated at the top with soft loops which
can be shackled together and placed in load hook. Alternatively, the soft loops may be placed directly in load hook;
Man-made fiber slings such as flat woven webbing slings should not be used to bundle, lift and transport tubular
goods. Webbing slings are difficult to choke properly and, depending on the type of eye, may loosen and become
slack around the tubular goods bundle when the weight of the load comes off the sling;
When slinging a tubular goods bundle each leg of the sling set should be double wrapped around one end of the
bundle one quarter the way in from each end. The top end of the sling leg should be threaded through the reeving
sleeve in the choke mode and secured. A drop forged wire rope clip (bull dog or other clip) should be placed above
the reeving eye to prevent the wire rope from slipping through the eye thereby slacking off when the load is
lowered to its resting position;
Slings should be placed at equal distance (approximately 25% of total length) from the ends of the load. They
should be double wrapped and choked around the tubular either when using steel slings or nylon webbing;
The inside angle of the choke shall not exceed 120°;
The live end of the wire rope at the bundle should be kept from being positioned under the first wrap and under
other bundles;
Excessively long tubulars such as riser joints may require tag lines to assist with control of the load. Tag lines should
be attached at the very ends of the bundle;
Due care and attention should be taken when loading tubulars to avoid damage to slings;
Prepare the landing site to enable the bundles to be landed without crushing the slings;
Ensure that pipes are protected by means of securely fastened thread protectors and end caps. They shall prevent
damage to the weld bevel and the ingress of moisture or dirt into the pipe;
Temporary storage of tubular goods, whether on the installation or supply vessel, should be stacked or segregated
by pipe posts. Height of tubular bundles should not exceed the height of the structural pipe post.
After the crane operator lowers the bundle to its final position and puts slack in the sling set, the rigger can move
in, detach the sling set from the load hook and place the sling set parallel along the long axis of the bundle so that
the wire rope will not be crushed by the next bundle.
Extreme care must be exercised after bundles have been in transit (grips may have slipped etc.);
Prior to making any hoists, the release of rigging should be considered. Precautions are required to prevent
personnel from being trapped between tubulars during release of rigging.
DO NOT
Annex A17 below provides Safety Pocket Cards for the handling of Tubulars.
Lifting by Crane
The hooks, spreader bars or other devices used for hoisting should have rounded edges and/or protective covers. Safety
hooks with an integrated safety latch shall be used to prevent the hook from accidentally slipping off the loop. Hooks
should have a sufficiently large radius to prevent squeezing the loop. When the FIBC is suspended, the loops must be
vertical, or at a maximum angle as allowed by the instructions on the label, without any twists or knots. An example is
shown in Figure 19 below.
Hoisting by Forklift
Be sure that the forklift tines are spaced correctly. All hoisting loops, sleeves or other hoisting devices should be vertical,
so that no lateral forces will be created in the FIBC. Be sure that the hoisting loops are not twisted.
Forklift tines should have rounded edges and/or being provided with protective covers in order to avoid damage to the
hoisting loops. FIBC’s should be raised or lowered smoothly. An example is shown in Figure 20 below.
Horizontal carrying
When travelling with a FIBC hanging from the forklift tines, there is an increased danger of the forklift becoming
unstable. The FIBC should be held close to the mast and as low as possible with the mast tilted slightly backwards.
Make sure that the wheels of the truck will not damage the FIBC body. The load should not restrict the view of the
driver.
FIBC’s must not be dragged. The truck should be brought to a stop before the FIBC is raised or lowered.
Notes:
Safety Factor (SF) - i.e. 5:1, 6:1 or 8:1 as appropriate;
Class of FIBC - i.e. “heavy-duty reusable”, “standard-duty reusable” or “single-trip”.
Offshore operations
Using FIBC’s in an offshore environment is only allowed under the following strict conditions:
Only FIBC’s with a safety factor 5:1 shall be used;
To be sure that weather or sunlight had no negative influence on quality and strength, only new FIBC’s shall be
used from a recent production batch;
FIBC’s to be used for a single trip only (Single trip is from filling point to supply base, from base to supply vessel,
from supply vessel to offshore installation);
FIBC’s shall be used to a maximum of 66,6% of their SWL in order to overcome dynamic forces in the offshore
environment.
Safety Pocket Card for the Handling of FIBC’s is shown in Annex A18 below.
The following table summarizes the main actions to carry out and avoid for handling FIBC’s:
DO DO NOT
Do select the right FIBC for the job in consultation Don't choose FIBCs without consulting the
with the manufacturer or supplier manufacturer or supplier
Do read the instruction label on the FIBC Don't exceed the SWL in any circumstances
Do inspect reusable FIBCs before refilling Don't fill the FIBCs unevenly
Do check that the discharge spout is closed off Don't stop or start suddenly during
before filling transportation
Do adjust the distance between forklift arms to the Don't allow FIBCs to project over the side of a
correct width for the FIBC being handled vehicle or pallet
Do consider the possibility of static electricity Don't use FIBCs in new conditions without
hazards consulting the manufacturer or supplier
Do ensure the FIBCs are adequately secured in Don't repair heavy-duty reusable FIBCs unless
transportation the as-new requirements can be met
Examples of live facilities are pipes or vessels containing hydrocarbons, electric cables, equipment cooling water supplies,
etc.
Lifting operations over live facilities should be avoided at all times. Only in exceptional circumstances will this
restriction be lifted, but strict procedures and more rigorous controls due to the inherent hazards associated with these
operations shall be in place.
Lifting operations over live facilities shall always be categorized as Non-Routine – Complex lifts, therefore the following
control measures shall be in place:
Permit To Work;
Fully dedicated Risk Assessment;
Method Statement describing the operations step – by – step;
Depending on the complexity of the task at hand and the risks identified, one or more of the following further safety
precautions should be considered:
Additional authorization from the manager of the asset;
Shutting down, isolating, depressurizing and purging the live process plant, equipment or other facilities;
Selecting higher rated lifting and hoisting equipment, so there is no need to exceed 75% of the capacity;
The use of static back-up safety rigging, such as slings hooked up parallel with the hoist to sustain the load in the
event of a hoist brake failure;
Performing a trial run using a water weight;
Have an emergency plan in place;
Safety Pocket Card for the Hoisting Over Live Facilities is shown in Annex A19 below.
The factors to be considered when planning multiple crane lifts include the following aspects:
Mass of the load: the total mass of the load and its distribution should either be known or calculated. Where the
information is taken from a design drawing, allowances should be made for manufacturing tolerances. The
accuracy of the design drawing should be confirmed before starting the lift.
Position of the Centre of Gravity (CoG): due to the variable effect of manufacturing tolerances and rolling margins,
the position of the CoG may not be accurately known. Accordingly, the proportion of the load being carried by
each crane may be uncertain and adequate allowances should be made. This will involve reducing each crane’s
capacity further.
Mass of the lifting gear: the mass of the lifting gear and its distribution should be accurately known and included
as part of the calculated load on the cranes.
Safe working capacity of the lifting gear: the distribution of the forces within the lifting gear that will occur during
the lifting operation should be established. The lifting gear should have a rated capacity in excess of that needed
for its proportioned load. Determine whether special lifting gear is required to suit the maximum variation in
distribution and direction of applied loads and forces which may occur during multiple lifting.
Synchronizing crane motions: if possible, minimize the variation in the direction and magnitude of forces acting
on the cranes by synchronizing the cranes’ motions. Where possible, use cranes of equal capacity and similar
operating characteristics. However, in practice, there will always be some variation due to differences in response
to the activation of the motion controller and the setting and efficiency of the braking system.
All multiple crane lifting operations should be thoroughly planned in advance by a competent person. Where possible
cranes of equal capacity and similar characteristics should be used. The cranes to be used should be selected to have a
capacity margin greater than that needed for the proportioned load when handled as a single lift.
The following minimum capacity requirements for each crane will apply:
Generally, for a tandem lifting operation, each crane shall be capable to lift 75% of the total load in the worst foreseen
geometric condition. Under particular circumstances, this margin may be reduced provided that all the necessary
contingencies and justification are provided for review and approval.
There are numerous ways to utilize multiple cranes. Hereafter the most commonly used combinations are explained
with some specific remarks that need to be addressed during Risk Assessment:
Hoisting a single load using two cranes: when two cranes are going to hoist a load, a determination must be made
on the location of the load attachment points and the CoG. This must be calculated to properly distribute the load
according to the capacities of each crane. If a load is non-symmetrical – i.e. the CoG will not be in the middle of
the load, but closer to one end - it is likely that one crane will be positioned to lift over half of the load weight.
Hoisting a single load using more than two cranes: in this situation the load is divided across more than two cranes.
Hoisting a load, which is suspended from three points, is always in a static determined position. Related to the CoG
of the load, there can be two situations:
• The load is not equally divided over the three suspension points.
Whatever the actual situation, it will be necessary to determine the exact position of the CoG by calculation. In case the
load is not equally divided over three points, each crane will have a different load. Hoisting a load that is suspended
from 4 (or more) points is always in a static undetermined position and extremely hazardous. It is impossible to
determine how the load will be divided between the suspension points. In some specific situations a solution might be
to go back to three suspension points by connecting two of the four hoisting points by means of an equalizing hoisting
beam.
Taking a load from a horizontal position to a vertical position or vice versa: when erecting a pressure vessel or a
structural component from a horizontal position to a vertical position a tailing crane is often used. During this type
of operation, the relationship between the load attachment points and the CoG is very important;
It is essential to accurately calculate the position of the CoG and the actual load exerted on both cranes. As the
load changes from horizontal to vertical, the lead crane will absorb more of the load, until the total weight of the
load is fully transferred to the lead crane;
Using two or more chain lever hoists and or chain blocks: when using more than one chain block or chain lever
hoist, each individual hoist unit should be rated to a capacity of at least 100% of the load;
Planning and control measures for this category, including defined procedures and drawings or sketches, need to
be in place. If two or more lever hoists are used to share the load during hoisting operations, careful consideration
of the operation is necessary as there is the potential to overload one of the hoists (beyond the Working Load
Limit) or under load one of the hoists (below 10% of the Working Load Limit).
6. CHANGES MADE
Pro hse 023 eni ng r00 replaces and supersedes HSE-DIV-C5-OPER-012 Rev02 “Rigging and Lifting Procedure” and HSE-
DIV-C5-OPER-021 Rev00 “Personnel Lifting Procedure”, and integrates man hse 001 eni ng “HSE Integrated
Management System Manual”.
The units and positions involved in the activities described in this document are responsible for noting any events
affecting the company’s operation, which may require these regulations to be updated. Such events are reported to the
HSE function, which coordinates the updating of the document.
The units and positions involved in the activities governed by this document shall ensure, each for the areas under its
responsibility, also through the IT systems in use, the traceability of the data and information and shall keep and file all
printed and/or electronic documents produced, so that all process phases may be properly tracked.
9. LIST OF ANNEXES