Combined Footing Design

105 kip 232 kip


D= 21 feet

x1 (ft)= 14.46 x2 (ft)= 6.54 f'c= 3000 psi


fy= 60000 psi
C/L

Trial, T= 18 inch
T

qa= 1.25 ksf

Trial, L= 30 feet

C1= 12 inch
C1 C2 C1'= 12 inch
C2= 96 inch
B C1' C2'
C2'= 12 inch

Trial, B= 9 feet

d1 (in) C1 (in) d2 (in) C2 (in) d3 (in)

0.48 12 198 96 53.52 Dimensions 'ok'

137.18 kip a1= 0.06 inch


0.68 kip a2= 11.94 inch
a3= 99.97 inch
a4= 98.03 inch
a5= 61.93 inch
a6= 34.07 inch
-75.46 kip
-139.9 kip

M1= 0 kip-ft/ft M2= 30.6 kip-ft/ft


As1= 0.39 sq-in/ft As2= 0.51 sq-in/ft

M(mid)= -72.4824 kip-ft/ft


As(mid)= 1.2 sq-in/ft
Required Area, A(req) = 269.6 sft
Provided Area, A = 270 sft Area 'ok'
Upward soil pressure, qup = 1.88 ksf
Effective depth, d= 15 inch
Punching Capacity, v1= 164 psi
One way Shear, v2= 82 psi
Punching Shear for P1, vp1= 91.35 psi ok for punching
Punching Shear for P2, vp2= 74.61 psi ok for punching
Beam Shear for P1 side, vb1= -12.638 psi ok for shear
Beam Shear for P2 side, vb2= 33.527 psi ok for shear
minimum As= 0.39 sq-inch