Professional Documents
Culture Documents
Concrete Technology Notes
Concrete Technology Notes
Cement
Water
Aggregates
CEMENT
It’s a greenish grey colored powder made of calcined mixture of clay and limestone when mixed
with water hardens to a building materials. Major Raw materials/ ingredient for manufacturing of
Portland cement are:-
It’s very fine powdery substance chiefly made up of limestone (calcium), sand or clay (silicon), bauxite
(aluminum) and iron ore
Dry process.
Wet process.
Mixing
Burning
Grinding
Storage and packaging
Dry process
1. Grinding and mixing
Calcareous (lime stone) and argillaceous (clay) materials are first crushed in the gyratory or
jaw crasher separately to reduce their size.
Crushed materials are grounded further to fine particles in the tube mill or ball mill, screened
using sieves then store in their respective bins.
Powdered minerals are mixed in their required proportion, water can be either be added to the
mixture depending on the moisture content which should be less than 1%. Phenomenon which
result to the mixture to behave like liquid hence being ready to be discharged in the kiln rotary.
2. Heating /burning
As the mixture enters the kiln rotary it is first heated by a current of hot wind circulating about
its center, produced from the kiln.it enables to reduce energy consumption inside the kiln
rotary.
Inside the kiln rotary, powdered mixture its heated and decomposed at abount 1400 oc - 1500oc,
which is principle stage of cement production.
During decomposition process clinkers are formed after a series of chemical reaction between
calcium and silicon dioxide compounds.
Clinkers are rapidly cooled down through pass in air from 2000oc to about 100oc- 200oc.
Additives added at this stage where there combine with clinkers to be ground in order to
ground in order to produce the desired cement. E.g gypsum regulates the setting time, gives
concrete improved compressive strength e.t.c
Cement is conveyed from grinding mill to silos where it’s packed in 50-20kg bags.
Flow chart
Mixing pulverizing
CLINKER AIR
COOLER
GYPSUM CLINCKER
PORTLAND CEMENT
Wet process
1. grinding and mixing of raw materials
Raw materials are first ground by jaw crasher or gyratory crusher in the tube mill to powder
form and then stored in silos.
The powdered mineral its then washed / mixed with water to remove adhering organic maters
presence in clay.
PREPARED BY: MR. ANTONY
KENYA INSTITUTE OF HIGHWAY AND BUILDING TECHNOLOGY
The mixture it’s then grounded further in the grinding mill/ tube mill/ ball mill for complete mixing
which leads to formation of slurry
Proper composition of slurry raw materials can be controlled effectively in wet process than in
dry process as it’s corrected periodically from the tube mill.
The mixture contains about 3-5% water content, which is then pumped to slurry tank where it is
kept in agitated condition by means of rotary arm or compressed air before being feed to the
rotary kiln.
2. Burning / heating
The slurry is feed into the upper end of the rotary kiln while the lower end its intensively heated
by means of fine grounded coal.
It slowly moves down kiln as it losses moisture content at a constant temperatures of about
1500oc hence formation of clinkers
During the process of decomposition the raw mineral materials reacts and re-combine to a
fused mass which reacts with water to form a cementation blinder.
Clinkers drops on to the rotary clinker for cooling under constant temperatures to about 100 oc –
200oc weighing 11000 – 13000 per liter.
3. grinding
Clinkers are finely ground with addition of about 3-5% gypsum into another tube mill producing
required cement.
4. packing
The fined cement it’s stored in silos then conveyed to packing plant.
BIN
ROTARY KILN
AIR
CLINKER
COOLER
PORTLAND CEMENT
It is the reaction of various component of cement with water to form a blinding materials.
Full hydration should be allowed to take place to ensure every compound reacts.
There are two ways in which compounds present in cement reacts with water
Most of the cement used are hydraulic and non-hydraulic cement hence deriver their strength
from chemical reaction between the cement and water in a process referred to as hydration
process.
In presence of water silicates (C3 S and C2S) and aluminates (C3A and C4AF) forms products
of hydration which reacts to form a firm and hard mass (hydrated mass).
Tricalcium Silicate
1. Hardens rapidly and largely responsible for initial set & early strength
2. The increase in percentage cause higher early strength but needs addition of fly ash.
3. Produces higher heat of hydration leading for faster gain in strength.
Dicalcium Silicate
Tricalcium Aluminate
1. It is the first compound to hydrate, resulting to strength development within the first few days.
2. It turns out higher heat of hydration and contributes to faster gain in strength.
PREPARED BY: MR. ANTONY
KENYA INSTITUTE OF HIGHWAY AND BUILDING TECHNOLOGY
3. But it results in poor sulfate resitance and increases the volumetric shrinkage upon drying.
4. Low percentage Tricalcium Aluminate contents usually generate less heat, develop higher strengths and
show greater resistance to sulfate attacks.
Tetracalcium Aluminoferrite
PROPERTIES OF CONCRETE
1. Fresh concrete
2. Hardened concrete
FRESH CONCRETE
Workability.
Setting.
Segregation.
Plastic Shrinkage.
Thermal Shrinkage.
Thermal Expansion.
Water Cement Ratio.
1 WORKABILITY
It is the ease with which freshly prepared concrete can be transported and placed for
the job and compacted to a dense mass.
A workable concrete should have a right balance between the plasticity and mobility for
a particular job in particular place. This is ensured by selecting the right type of
aggregates, proper proportioning of cement, sand, coarse aggregates, and water, and
thorough mixing of the constituents.
Slump test.
Compacting factor test.
V-B Consistometer test.
CONCRETE TECHNOLOGY
Concrete is a building material, obtained by mixing together definite proportion of fine aggregate, course
aggregate, water, cement and additives
Additives, admixture may be added to the concrete in very small quantities to alter properties of the concrete
mix.
Types of concrete
1. Plain/ mass concrete – not reinforced
2. Reinforced concrete – reinforced.
3. Pre-stressed concrete- pre-cast with reinforcement.
in concrete mixture, the cement and water forms a paste described as water cement paste which upon
hardening acts as a binder connecting the particles of aggregate together in a permanent mass.
The amount water mixed with cement usually determine the strength of the paste, however a balance
between enough water for workability and water for connecting must be stuck.
For a good concrete, aggregate should have the proper size, shape and grading
It is desirable that concrete in its state should be workable, free from segregation and bleeding and should
hence leading to poor quality.
Aggregates
About 75% - 80% of concrete is made up of aggregate which are the principle filler materials
The quality of aggregates used affect the quality, durability and permeability of the final concrete product.
Classification of aggregates
They can be classified in the following ways:-
1) Based on size i.e fine aggregates are those whose particles size ranges from 5mm to 0.6mm. This
includes natural sand, river sand, fine particles and crushed stones.
2) Based on source:- natural/artificial aggregates.
Natural aggregates include: course sand, granite chips e.t.c
Artificial aggregates include; blast, furnace slag, broken stones/bricks e.t.c
3) Based on mineralogical composition; examples include: silicon dioxide, calceous ( caco3)
4) Based on mode of preparation; e.g crashed aggregates, natural aggregates e.t.c
5) Based on weight; e.g normal weight with example of granite, chips, natural sand, gravel e.t.c. normal
weight aggregate produces concrete 2400kg/m2
Light weight aggregates- gives a concrete of( 350 – 1600kg/m3) and example of material making up this
aggregates include wood waste, clinkers, blast furnace slag and expanded clay
Heavy weight aggregate are used to obtain concrete of 3500kg/m3and example of such include sted
core/chippings, barron
6) An all in aggregate – this are aggregate which are made up of fine particles and course particles of
almost equal measure.
Material may either be grounded into cement or added as admixture to impact the fungicidal germicidal as
insecticidal properties to harden cement paste mortar or cement.
E. COLOURING AGENT.
Pigments are often added to produce colour in the finished concrete requirement of suitable admixtures which
include colour fastening when exposed to sunlight, chemical stability, in presence of alkalinity produced in the
cement and no adverse effect or setting time as strength development of pigment should be preferable mixed on the
ground with dry cement
1. Water content
2. Mixing proportion
3. Size of the aggregate
4. Shape of aggregate
5. Surface texture of the aggregate – rough texture shows workability while smooth texture shows good
workability.
6. Grading of aggregates – well graded aggregates have good workability.
7. Use of admixture increase workability.
Measure of workability
1. Slump test – can be employed in laboratory or site of work. Not suitable for very wet concrete or very dry
concrete.
2. Surface hardness- there is greater wear resistance, corrosion resistance.
Fresh concrete
Freshly mixed concrete material which can be moulded into any shape to enable concrete to be fully compacted; a
higher / water/ cement ratio must be calculated by theoretical consideration.
Workability – types of work, thickness of section extent and reinforcement and mode of compaction used.
Fresh concrete is consistent which is the firmness of substance is sometime taken as the degree of wetness, wet
concrete are more workable than dry concrete.
1. Water content
2. Aggregate type.
3. Cement ratio
4. Presence of admixtures
PREPARED BY: MR. ANTONY
KENYA INSTITUTE OF HIGHWAY AND BUILDING TECHNOLOGY
5. Finess of the cement.
BLEEDING
It’s a form of segregation in which some water in the mixer tends to rise to the surface of freshly placed concrete.
It is caused by inability of soil constituent to hold all of the mixing water when they settle downwards
When cement paste has hardened, sufficiently bleeding ceases/stops. If evaporation of water from the surface of
concrete is faster than bleeding rate, plastic shrinkage and cracking may occur.
Bleeding is not harmful if it is undisturbed. (water evaporates) the effective water/cement ration maybe lowered
with a resulting increase in strength.
True
shape
If it happens that one and half of the cone slides down in an included flame a shear slap is said to have taken place
and the test should be repeated. If the shear persists as may be the case in the harsh mixes this is an indication of
lack of cohesion of the mix.
PREPARED BY: MR. ANTONY
KENYA INSTITUTE OF HIGHWAY AND BUILDING TECHNOLOGY
Mixes of stiff consistence have zero slump so that if the rather dry range no variation can be detected between the
mixes of different workability.
Mixing
The mixing operation consists essentially of rotation. Stirring the objective of being to coat the surface of all
aggregate particles with cement paste and to blend all ingredient of concrete into a uniform mass.
Usual type of mixture is known as batch mixer that means one bag of concrete is mixed or discharged before any
more materials are put into the mixer.
Mixing time
It is the time required to produce uniform concrete. The mixing time is recovered from the time all the solid
materials have been put in the mixer.
The time varies with the types of mixer and depends on its size. Number of revolution of the mixer and time of
mixing are independent of each other.
When light weight aggregate is used, the mixing time should not be less than 5 min. sometimes divided two minutes
of mixing the aggregate followed by water after three minutes than you add the cement.
For mixtures of large capacity, the mixing time should be increased at rate of 20sec
Order of feeding the ingredient into the mixture depends on the properties of the mix and those of the mixer.
Generally a small amount of water should be fed first followed by all solid material, preferably fed simultaneously
into the mixture.
The choice of the mixer, depends upon the size, extend and nature of work.
Hand mixing
It’s where concrete is mixed by hands. In this case, the uniformity is hard to achieve
The aggregates should be spread in uniform layer on hard, clean non-porous base.
Cement is then spread on the aggregate and the dry material is mixed by turning it from one end of the
heap to other and cutting with a shovel until the mix appears uniform. Turning three times is usually
required.
Transportation of concrete.
Concrete from the mixer should be transported to the point where it has to be placed as rapidly as
possible. By a method which prevents segregation or loss of ingredients.
Precaution should be taken while transporting concrete to ensure the homogeneity is obtained at time of
mixing ought to be maintained.
Prevention of segregation is the most important consideration in handling and transportation of concrete.
Pumped concrete
Pumping of concrete through steel pipeline is one of the successful methods of transporting concrete.
Pumped concrete has largely been used in construction of multistoried buildings, tunnels and bridges.
A pipeline not well cleaned after previous operation may cause blockage.
1. Strength
2. Temperature
3. Slump test
4. Air content
5. Unit weight.
MIXING OF CONCRETE
Drum Mixer
The first type is the drum mixer, which can be classified as non-tilting, split drum, or titling drum mixers, as
well as truck mixers or reversing drum mixers.
A forced movement pan mixer has blades that are fixed to an assembly that agitates the concrete throughout
the pan as the vertical shaft rotates. This mixer is most common where stiff or zero slump mixes are
prevalent. "They have not gained acceptance in ready mix production because of the small size and
reputation for high blade and liner wear Pan Mixers are most commonly found in precast concrete plants.
Continuous Mixer
The final type is the continuous mixer. A free-falling continuous mixer is a gravity-fed mixer, classified by
its continuous movement.
In this process the charging of materials and discharging of the mixed concrete is released in one,
uninterrupted process. Continuous mixers utilize a continuous weigh batching system as well.
Materials are typically fed into the mixer by a conveyor system. This mixer is most suitable when large
quantities of mass concrete are required (i.e. dams, foundations, retaining walls and mass concrete filling).
1. Output capacity
2. Efficiency
3. Availability
4. Performance /Cost ratio
5. Portability of machine
6. Nature of Construction environment.
In a day of 8 hours there will be effective mixing for 7 hours. One hour being occupied in clearing drum,
chutes, etc and starting and oiling the engine.
No. of batches in one working hour = 60/3 = 20 (considering 3 minutes mixing cycle)
Considering 90% efficiency, output per batch = 200 x (90/100) = 180 litres
Output per day = 180 x 140 = 25200 litres = 25.2 cu-m (say 25 m3)
Find the working hour required to complete a concrete slab 30 m * 50 m & 0.20 m size using 200 T mixer.
The output per hour = 20 * 180 = 3600 litres i.e. 3.6 cubic meters
Compaction
It is done to remove entrapped air and set particles of fresh concrete in motion reducing friction between
them. Insufficient compaction increases the permeability of concrete resulting in easy entry for aggressive
chemicals which attack concrete and reinforcement hence reducing the durability of the concrete. In order to
achieve full compaction and maximum density with reasonable compacting effort available at site, it is
necessary to use a mix with adequate workability.
PREPARED BY: MR. ANTONY
KENYA INSTITUTE OF HIGHWAY AND BUILDING TECHNOLOGY
The mix should not be too wet for easy compaction which also reduces the strength of concrete. There are
two main methods of compacting concrete they include:-
1) Hand compaction.
2) Machine compaction.
Hand compaction
It is adopted in case of an important concrete work of small magnitude. Also applied where a large
quantity of reinforcement is, which cannot ne normally compacted by mechanical means.
It consist of rodding (poking the concrete to pack it between the reinforcement and sharp corners and
edges)
Tamping (adopted where thickness of concrete is comparatively less and surface to be finished is
required to be smooth and leveled). It consists of beating the top surface by wooded cross beam.
Ramming adopted where the reinforcement may be disturbed or formwork may fail.
Machine compaction
Its advantages include.
1) Internal vibrators
2) External vibrators
3) Table vibrators
4) Surface vibrators
Adopted where reinforcement and spacers interfere much with the internal vibrators and it provides a good
finished to the concrete surface. Though its efficiency is lower than that of internal vibrator.
Table vibrator.
The table is clamped to the table or table mounted on springs which are vibrated transforming the vibration
to the table.
Surface vibrator
It’s a vibrator placed on a screed board and mostly used in floor and slabs whose thickness is small.
Platform vibrator
It is just like the table vibrator but larger in size.
Compaction by pressure
Mostly used for compacting hollow blocks or cavity blocks where stiff concrete is used by employing great
pressure, where the ratio of water to cement is low.
Cement Dust
Hazard: Exposure to cement dust can irritate eyes, nose, throat and the upper respiratory system. Skin
contact may result in moderate irritation to thickening/cracking of skin to severe skin damage from chemical
burns. Silica exposure can lead to lung injuries including silicosis and lung cancer.
Solutions:
Rinse eyes with water if they come into contact with cement dust and consult a physician.
Use soap and water to wash off dust to avoid skin damage.
Wear a P-, N- or R-95 respirator to minimize inhalation of cement dust.
Eat and drink only in dust-free areas to avoid ingesting cement dust.
PREPARED BY: MR. ANTONY
KENYA INSTITUTE OF HIGHWAY AND BUILDING TECHNOLOGY
Wet Concrete
Hazard: Exposure to wet concrete can result in skin irritation or even first-, second- or third-degree
chemical burns. Compounds such as hexavalent chromium may also be harmful.
Solutions:
Wear alkali-resistant gloves, coveralls with long sleeves and full-length pants, waterproof boots and
eye protection.
Wash contaminated skin areas with cold, running water as soon as possible.
Rinse eyes splashed with wet concrete with water for at least 15 minutes and then go to the hospital
for further treatment.
Machine Guarding
Hazard: Unguarded machinery used in the manufacturing process can lead to worker injuries.
Solutions:
Maintain conveyor belt systems to avoid jamming and use care in clearing jams.
Ensure that guards are in place to protect workers using mixers, block makers, cubers and
metalworking machinery such as rebar benders, cutters and cage rollers.
Establish and follow effective lockout/tagout procedures when servicing equipment.
Be sure appropriate guards are in place on power tools before using them.
Falling Objects
Hazard: Workers may be hit by falling objects from conveyor belt systems, elevators or concrete block
stacking equipment.
Solutions:
Avoid working beneath cuber elevators, conveyor belts and stacker/destacker machinery.
Stack and store materials properly to limit the risk of falling objects.
Wear eye protection when chipping and cleaning forms, products or mixers.
Poor Ergonomics
PREPARED BY: MR. ANTONY
KENYA INSTITUTE OF HIGHWAY AND BUILDING TECHNOLOGY
Hazard: Improper lifting, awkward postures and repetitive motions can lead to sprains, strains and other
musculoskeletal disorders.
Solutions:
Confined Spaces
Hazard: Mixers and ready-mix trucks have confined spaces that pose safety risks for workers.
Solutions:
Follow established procedures for confined space entry and work to assure safety.
Guard against heat stress when cleaning truck mixer drums.
Wear appropriate protective equipment to avoid silica exposure when removing concrete residues
from inside truck mixer drums.
Vehicles
Hazard: Poorly maintained or improperly handled vehicles can lead to crushing injuries at the plant site or
other injuries for truck drivers.
Solutions:
General Precautions
Be sure you understand how to perform all your tasks and how to use tools and equipment safely.
Follow confined space procedures when cleaning and working in mixer drums, hoppers, tanks and
other places with potentially serious mechanical hazards, such as blades or sloping sides which may
entrap employees, or atmospheric hazards, such as oxygen deficiency.
Wear appropriate personal protective equipment to avoid being injured by flying or falling objects.
Vehicle Safety
Be sure that trucks and other vehicles are in good working order, including audible back-up warning
signals, before operating them.
Avoid overloading hoists, cranes and forklifts.
Machine Safety
Use lockout/tagout procedures to de-energize conveyors and other machinery before attempting to
free any jams.
Secure chutes and hatches to reduce injuries from swinging parts.
Make sure guards are in place to protect you from moving parts of machinery and tools before you
operate the equipment.
Overhead Hazards
Be sure that form work, casting and stressing operations are adequately braced and chocked to avoid
sudden release of materials.
Make certain that rigging is in place to protect against falling objects and materials during hoisting
and stacking procedures.
Do not walk or work under overhead loads.
A concrete plant can be a great asset in a construction site in ensuring that we get fresh and high quality
concrete. However, you need to make sure you follow the correct safety precautions
PRECAST CONCRETE
Precast concrete is a construction product produced by casting concrete in a re-usable mold/ form which is
the cured in a controlled environment (pre-cast plant) transported to the construction site and lifted into
PREPARED BY: MR. ANTONY
KENYA INSTITUTE OF HIGHWAY AND BUILDING TECHNOLOGY
place. Building component are manufactured in a central plant and later brought to the building site for
assembling.
In-situ concrete is placed where it will harden to become an integral part of the structure. Concrete is poured
into forms works at the building site to come up with the specific component. A mold is a hollowed out
block that is filled with a liquid material such as ceramic glass/metal. The liquid hardens/ sets inside the
mold adopting its shape. The process is called molding.
PRECAST COMPONENTS
1. Beams
2. Columns
3. Floors slabs i.e hollow pots waffles
4. Wall e,g single, double, sandwich cantilevers
5. Staircase.
1. Fixing sockets:-
They are used for attaching and fixing objects to pre-cast concrete such as lighting fixtures and rays.
They are mainly divided into
i) Cast in tubular sockets
It provide threaded fixing in finished concrete unit
ii) Cast in solid rod sockets
Are heavy duty fixings mostly used in architectural fixing units.
2. Ties
They connect a façade and an inner panel of a wall together.
3. Connecting loop
They connect the vertical joints of pre-cast wall panel to each other they are single wire loops which
can be applied on walled column joints.
Is a method in which compressive stress or forces are introduced to a reinforced concrete section or a plain
concrete artificially mostly used in reinforced concrete members e.g beams wall panel e.t.c. these is done by
application of predetermine forces or moment to a structural member in a such a manner that combines with
internal stresses resulting from any anticipated external loading which should be within elastic limit.
Concrete being strong in compression but very weak in tension thereby having a need to introduce stress
either by pre-tensioning or by post tensioning.
But we still get cracking, which is due to both bending and shear in pre-stressed concrete, because the pre-
stressing keeps the concrete in compression, thus no cracking occurs. This is often preferable where
durability is a concern.
Pre-tensioning
Steel tensioned before casting the concrete. Strands are tensioned, concrete is cast around the strands, and
then the strands released when concrete attains required strength. As the bond between the tendons and
concrete are resisting the shorting of the tendons the concrete is compressed. Pre-stressing force introduced
Placing of jacks
Casting of concrete
Therefore, at the ends of the member, there is a transmission length where the strand force is transferred to
the concrete through the bond: At the ends of pre-tensioned members it is sometimes necessary to de-bond
the strand from the concrete. This is to keep the stresses within allowable limits where there is little stress
induced by self with or other loads:
In this method, the concrete has already set but has ducts cast into it. The strands or tendons are fed through
the ducts (Stage 1) then tensioned (Stage 2) and then anchored to the concrete (Stage 3). The tendons are
stretched and anchored at the end of the concrete members after the member has been cast and attained
sufficient strength. Commonly a metal duct is placed along the member before concrete casting; the tendons
could be preplaced after hardening of concrete. After the concrete has attained the required strength. The
tendons are stressed using pre-stressing jacks at the end of the concrete member and anchored.
Another way
The ducts for the tendons (or strands) are placed along with the reinforcement before the casting of concrete.
The tendons are placed in the ducts after the casting of concrete. The duct prevents contact between concrete
and the tendons during the tensioning operation.
It is usually in-situ operation, used in large projects such as continuous long-span bridges.
• Use metal sheath to form a duct or use plastic duct instead.
• Use small number of large tendons as oppose to large number of strands in pre-tensioned:
Pre-tensioned rely on bond between concrete and steel thus we wish to maximize bond surface,
whereas in post-tensioned we rely on mechanical anchorage at the ends.
Fewer larger tendons results in less labor
In post-tensioned members, tendons are usually grouted after anchorage to prevent corrosion:
Cement or epoxy grout, called bonded members
Grease or no g-rout, called un-bonded members
Grout is pumped into duct under pressure to ensure it’s full. The behavior of bonded and un-bonded is the
same until before cracking, after cracking they are different.
Pre-stressing provides initial stresses controlled in magnitude and direction for counter balancing to a
desired degree stresses resulting from external loading
Three concept are applied to explain and analyze the basic behavior of pre-stressed concrete
A. Stress concept
Pre-stressed concrete is considered as a concrete structure with the tendons supplying the pre-compression
which transforms a brittle material like concrete into elastic ones. Concrete is taken as subject to two
systems of forces i.e internal pre-stressed and external load with the tensile stress is due to external load and
compressive stress due to pre-stress. The cracking of concrete due to loading which may be prevented by
pre-compression provided by the tendons as long as there is no cracks. The stress, strain and deflection due
to the two systems of forces which can be considered separately and super imposed as necessary.
B. Strength concept
Steel and concrete act together while steel taking tension and concrete taking compression so that the
materials form a resisting couple against an external moment. High tensile steel used has to be elongated to a
great deal before its strength is fully utilized. If the high strength tensile steel is embedded in concrete, as in
the case of reinforced concrete.it will crack before full strength of steel is developed; hence it is necessary to
C. Load balancing
Pre-stressing is required to balance the loads on members. Balancing gravity loads helps members under
bending stress such slabs and beams against flexural stresses under given loading conditions enabling
transformation of flexural members to members under direct stress thus simplifying both design and analysis
for complicated structures.
The concept shows the effect of pre-stressing with a parabolic draped tendon (concave upward) is to apply
an upward uniformly distributed loading on the concrete which of course counteracts to some degree. Any
downward externally applied loading.
This concept it is very effective for complicated structures such as continuous beams, rigid frames, flat and
waffle slabs and some thin shells. Therefore design concept tends to balance the external load so that there
will be no deflection taking place within member.
1. More durable since there are no tensile cracks whereas in reinforced concrete tensile cracks hence
there is greater danger of adverse environmental effect.
2. Dead weight of pre-stressed concrete is less compared to reinforced concrete members because of
high strength concrete is used
3. In pre- stressed concrete there is improved shear and tension strength
4. It prevent deflection due to reduced cracking
5. Adds protection to the steel.
CONSTRUCTION JOINT
Construction joint is the interface between concrete placements intentionally created to facilitate
construction.
PREPARED BY: MR. ANTONY
KENYA INSTITUTE OF HIGHWAY AND BUILDING TECHNOLOGY
Construction joints are the temporary joints left between subsequent concreting Operations. The joints
should be loaded where concrete is least vulnerable to maximum bending moment. It should be determined
before and after the operation by the designer when used. Joints in beams and slabs should be formed at the
point of minimum shear. It is also not desirable to have the construction joints at the point of maximum
bending moment, therefore the joints may be made at the extreme position of the middle third. Construction
joint should be properly masked when finishing the structure. Badly made and unmasked construction joint
will give an ugly appearance to the concrete construction. The groove may be incorporated at the joint to
make a feature and to hide the joint
An expansion joint: in a concrete structure is a separation provided between adjacent section to allow
movement due to dimensional increases and reductions of the adjacent sections and through which some or
all of the bonded reinforcement is interrupted.
In pavement slabs on ground it is a separation between slabs filled with a compressive filler material.
It’s a sawed, formed, tooled or grooved in a concrete slab that creates a vertical plane. Concrete undergoes
plastic shrinkage and drying shrinkage as a result of which concrete shrinks. When shrinkage is restrained,
stresses are developed which result in the formation of cracks. To avoid these cracks, contraction joints are
provided. Normally, the interval at which these joints are provided will vary from 5 to 10 meters. In it
regulates the location of cracking caused by dimensional changes in the slab. Unregulated cracks can grow
and result in an acceptable rough surface as well as the water infiltration into the base, sub base and sub
grade which can enable other types of pavement distress. They are the most common types of joint in
concrete to the pavement, thus the generic term “joints” generally referring to a contraction joint. They are
chiefly defined by their spacing and method of load transfer/they are generally between ¼-1/3 the depth of
the slab and typically spaced every 3.1 to 15m
An isolation joint. Is a separation adjacent sections of concrete structure to allow relative movement in three
dimension and through which all of the bonded reinforcement is interrupted.
These are joint that isolate the slab from a wall column or drain pipe. They have one very special purpose i.e
to isolate the slab from something else. This can be a drain pipe. Here are a few things to consider with
isolation joint.
1. Walls and columns which are on their own footings that are deeper than the slab subgrade and not
going to move the same way a slab does as it shrinks or expands from drying or temperature changes
or as the subgrade compresses a little.
2. If slabs are connected to wall or column or pipes as they contract or settle there will be restraint
which usually cracks the slab although it could also damage pipe (stand pipes or floor drains)
3. Expansion joints in concrete pavement are also rarely needed, since the contraction joint opens
enough (from drying shrinkage) to account for temperate expansion. The exception might be where a
pavement or parking lot are next to a bridge or building than we simply use a wider isolation joint
(maybe ¾ inch) instead of a ½ inch.
In this case, the area is divided into panel and each panel is casted separately, from the other. Some plastic
materials e.g bitumen, cork is filled in the joints between the panels. This allows free movement of each
panel and saves it from cracking. The edges of each panel are prevented from damage by filling enough
bitumen in the joints. In case of roads having heavy traffic, the edges are further reinforcement by providing
iron built in the slab during concreting.
Definition of terms
1. Brace- means a member placed diagonally with respect to the vertical plane of a precast component and
rigidly fixed to provide stability
2. Builder – person who is engaged to do any building works using precast concrete component
3. Competent – a person who has acquired knowledge and skill through combination of qualification,
training and experiences to perform the task required.
4. Crane – it’s a powered device that is equipped with mechanical means for raising or lowering loads
suspended by means of a hook or other load handling device.
5. Cyclic - a reversing/recurring load.
6. Dunnage – a timber (normally) material stored under or between precast concrete element to prevent
damage or instability during storage and transportation.
7. Riggers – a person who has been instructed in the proper selection of slings and the slinging of loads and
who understands the crane with which he is working
8. Element – an individual precast concrete unit e.g column, beams stairs e.t.c
9. Leveling shim – means a single or series of thin strips of suitable material that are used under elements
to assist with final positioning
10. Prop – means a member of specific design used to support a precast concrete element.
11. Strong back – means a line drawing of a precast element used in the manufacturing process to describe
details.
12. Tag line – a rope attached to the load to be used to control the load during rifting or positioning
13. Tilt slab – a concrete element normally cast in a horizontal position at or near its final location. Lifted to
the vertical position with one edge remaining on the casting floor.
i. Variation in load distribution (with time) during construction e.g variation in propping loads due to
the effect of pre-stressing.
ii. Loading on the bracing inserts, lifting inserts, lifting gear and precast elements from the dead load,
the sling angle and any extra – ordinary dynamic load or impact load applied through handling
Where element are designed to be cast offsite, the designer should consider the effect of authority limit on
length, width, height and weight. Consideration also needs to be given to the availability of suitable and
adequate transport equipment. Joint widths between adjacent precast elements should be sufficient to allow
self-alignment during erection and to accommodate tolerances.
B. Reinforcement design
Addition reinforcement may be required in the following instance for safe handling and propping of
elements
D. Lifting inserts
When choosing the number of lifting inserts to be used in elements consideration should be given to the
lifting inserts capacity. The total weight of the element, their length and height, the position of any cast out
and opening and rogging arrangement. Additional lifting inserts are often added for multiple lifts for de-
molding from the bed. Handling transportation and erection. Lifting inserts should be designed with a
minimum factor of safety of three unless they are to be used for multiple lift application e.g re-usable
manhole cover, concrete counter weights, in which case, they should be designed with a factor of safety of
five. All lifting inserts requires adequate embendement/ anchorage to function effectively.
1. Proximity to edges
2. Proximity to hole, recesses or edges rebates
3. Proximity to other lifting devices that are loaded concurrently
4. Concrete thickness
5. Embedded depth
6. The presence of cracks
7. Tension on stresses in the concrete around anchorage
8. The proximity of reinforcement/ pre-stressing tendons
Where the temporary bracing is expected to provide support extended periods (more than two weeks)
considerations must be given to a more accurate determination of wind load in accordance with appropriate
code.
Consideration should be given to the risk and consequence of failure. Awareness should be made for higher
loads due to local effect such as wind funneling
BRACE ACCESSORIES
1). Pin
A 16mm steel pin that slides through the inner and outer sleeve to hold the brace at the correct length. One end is
bent so that the pin cannot slide right through and the other end has a small hole drilled right through to take the
lock.
2). Lock
It passes through the drilled hole in the pin to prevent the pin from being removed. Designed to keep
concrete slurry out of the lock.
3). Lock key
A Key to unlock the brace pin lock.
Strength Considerations:
1. Brace strength:
A number of components contribute towards a Braces’ capacity.
i). Connection to the element
Correctly installed Braces transfer the applied load to the concrete element. Should the applied load exceed the
Brace capacity and concrete strength the connection will fail and the concrete element will fall.
Extra reinforcement or increased concrete strength may be required to prevent connection failure. The design
may still be limited by serviceability.
The WLL of the specified base support for the Brace must be sufficient to withstand the factored load on the
Brace. This could be a dead man specifically poured for the job or existing slab or footing. A design engineer
must specify the Brace anchoring system.
FW X 0.5 H
N X 0.67 H
Then force on the wall be pressure of the wind on the wall say FØ
FH
FØ
COSØ
H – Panel height
W – Panel width
i). Should have a known safe working load available. In the case of adjustable brace, the safe working load,
at zero extension and maximum extension should be available.
ii). Adjustable brace should have stops in the threads to prevent over extension.
iii).Should have a 0.5 to 2 against ultimate failure.
iv). Should be fixed to solid, flat concrete or other surface that are capable of resisting applied loads.
v). Expansion anchors for brace fixing shall be load controlled i.e an achor where an increase of loads will
result in an increasing wedging force. The permissible loads shall be limited to 65% of the load at which
the anchor exhibit first slip.
Erection platform
The builder must determine that the erection platform (floor slab) suspended slab or surrounding ground)
can carry the construction and erection loads and provide verification to the crane owner or operator prior to
the commencement of the work.
Suspended slabs are not normally designed to support cranes or transporters. If a suspended slab is used to
support the crane, the slab shall be designed for the point loads applied by the crane’s outriggers wheel loads
or any other construction loads. A temporary propping system may be required for a suspended slab.
Fixing inserts
1). Where permanent fixing or connection are to be utilized, for temporary use during construction. The
builder should verify that the fixing are suitable for the temporary use and will not compromise their
long term performance.
2). To ensure correct fitting, each component of the complete lifting system, anchorage, lifting eye or clutch
and recess formed shall be compatible with each other.
3). The strength of lifting inserts is affected by:
i) Proximity to edges.
ii) Proximity to hole, recess or edge rebates
iii) Proximity to other lifting devices that are loaded co – currently.
1). Where element are being handled flat off a casting bed or truck, the center of the lifting insert should
coincide with the center of gravity of the precast element. The lifting hook should be directly above the
center of gravity of the element. Running rigging must not be used it would permit the element to tilt in
an uncontrolled manner.
2). Whenever possible, inserts for tilt panel should be designed to suit the common rigging configuration.
The builder shall check that the configuration proposed suit the panel designs.
3). Running rigging is commonly used with tilt panel. The bottom edge must remain on the ground or
platform to maintain control of the element
4). The lifting inserts and the rigging should be so arranged that when the element is lifted, it remains stable
and the bottom edge remains horizontal.
5). Hoop of reinforcement steel shall not be used for lifting, however, the length of pre-stressing strand are
used in some circumstance for handling precast element. They may need to be used with a special lifting
mandrel. To ensure that the strang is not bent around a tight radius. Lifting loop must not be used when
complex tilting maneuvers are being carried out.
Propping
Propping of beams
1). Propping for beams should allow for possible changes to the distribution of loads during the construction
process.
2). Where beams are post – tensioned, the stressing process can change the shape of the member thereby
reducing the loads on same props and increase the loads to others. This particularly applied where the
stressing induce a camber into the beam which can lift the beam off prop at mid-span transferring all the
loads to the props at the end.
3). Pre cast shell beams are normally pre-stressed which induce a natural camber into the units. In some
cases, propping is lowest slightly at mid-span to allow the beams to deflect to a more labeled shape
during placing of the concrete core and topping to the floor. This will result to much higher than
anticipated load being carried through the temporary props at the ends.
4). The sitting for precast beams may not be suitable to transfer high loads during construction and the
beams will normally require full propping at each end.
5). If the designer of the structure requires the beams to be supported without the use of mid-span props to
reduce the end support dead loads bending (moment) then the requirement must be clearly noted on the
contract drawing and on the precast layout drawing
6). Where beams are to have floor system placed on them prior to the beams, being fully built into the
structure, allowance should be made to the fact that the beam may not be evenly loaded by the floor units
during construction. Long span floor units placed on one side only of a beam may cause the beam to roll
on the props, for this reason each edge of the beam may require temporary propping.
7). Where beams are to support floor unit, allowance must be made for the beams to carry an appropriate
proportion of the construction load from floor. Propping for floors may in some case be intended to only
even out the level of the underside of the floor units and not to take any significant floor load during
construction. This leads to higher anticipated load being carried through the beam propping unless
specifically noted otherwise all temporary propping should be in place , adjusted to the correct levels
allowing for any requires camber and fully braced prior to commencement of erection of any precast
beams.
Unless specifically noted otherwise, all temporary propping should be in place, adjusted to the correct level
allowing for any required camber and fully braced prior to commencement of erection of any floor unit.
Props should be adequately seated, leveled and capable of transferring the full loads through whatever
structure they are bearing on and into the ground without an acceptable settlement.
Props if required, should be vertical, they should also be braced to prevent side way of the whole assembly
and the buckling of individual props.
Props to floor units should have a suitable top bearer which should be located in the header of the props in
such a way as to prevent rolling of the bearer and to ensure that the loads from the bearer is transferred
concentrically into the prop. The top bearer should be over the center line of the prop otherwise, it may cause
the prop to bend leading to failure.
Floor unit such as the various hollow core systems which are normally erected without temporary props,
may require some amount of temporary propping at mid-span principally to even out natural variations in
camber of the units or for other structural or concentric reasons, with the specific approval of the floor
systems suppliers in each particular instance, it may be satisfactory to erect the temporary props after the
precast floor units are in place and for the props to take only a portion of the full construction load.
1. Accelerated Setting:-A higher temperature of fresh concrete results in more rapid hydration of cement
and leads to reduced workability, accelerated setting. This reduces the handling time of concrete hence
placing and finishing becoming difficult.
2. Reduction In Strength :-Concrete mixed , place and cured at higher temperature normally develops
higher early strength than the concrete produced and cured at normal temperature but at 28 days or later
the strength are generally lower.
3. Increased Tendency to Crack:-Rapid evaporation may cause shrinkage and cracking and subsequent
cooling of hardened concrete would introduce tensile stresses which is as a result of thermal and plastic
cracking
4. Rapid Evaporation Of Water During Curing Period (increased water demand): - It is difficult to
retain moisture for hydration and maintain reasonably uniform temperature condition during the curing
period.
In the absence of special precautions, the effect of cold weather concreting may be as follows:-
1. Delayed Setting: When the temperature is falling to about 5 degrees centigrade or below, the
development of strength of concrete is retarded compared with normal concrete.
2. Freezing of Concrete at Early Stage: The permanent damage may occur when the concrete is in fresh
stage is exposed to freeze before certain pre hardening period. Concrete may suffer irreparable loss in
properties to an extent that compressive strength may get reduced to 50% of what could be accepted for
normal temperature concrete.
3. Stresses Due to Temperature Differentials: Large temperature differentials within the concrete
member may promote cracking and affect its durability adversely. The large temperature differentials
within the concrete member may promote cracking and have a harmful effect on the durability. Such
differentials are likely to occur in cold weather at the time of removal of form insulation
4. Repeated Freezing and Thawing ( not becoming frozen):-If concrete is exposed to repeated freezing
and thawing after final set and during the hardening period, the final qualities of the concrete may also be
impaired
Assignment
Concrete curing under extreme hot and cold weather conditions
1. Moist curing of fresh concrete during the few hours after finishing operation has completed.
2. Plain gray concrete, use a white pigmented curing compounds that reflect sunshine.
3. Use a curing blanket especially a white one, either the single use or multiple use.
1. Maintain a proper water-cement ratio. The water to cement ratio should not be more than 0.40 under
freezing conditions
2. A propane heater and polyethylene enclosure could be used in cold weather climate to maintain
temperatures hot enough, to avoid freezing point.
3. Use Portland cement Type III, cement that helps in setting without reducing concrete’s quality, because
high moisture content can induce corrosion problems in steel reinforcement
Fly ash: - fine powder that Is a by-product of burning pulverized coal in electric generation power plant
Slag cement: - is hydraulic cement formed when granulated blast furnace is ground to suitable fineness and
is used to replace a portion of Portland cement.
Admixtures
Types of chemical
admixture
Problem Solving - concrete that will meet special needs for placing or performance
Durability - Ensuring that concrete fulfills its design requirements for the intended life of
the structure
Sustainability - helping to reduce the health and safety aspects of concrete during placing and
environmental impact during its life cycle
1). Retarders
These are designed to retard setting times so that the concrete worker has enough time to finish the surface
of the concrete. Retarders temporarily stop the chemical action of hydration but after the planned delay
hardening develops at an accelerated rate.
Water reducing admixtures improve important properties of concrete in both its plastic and hardened
condition. When wet the handling properties can be greatly improved without the addition of extra water. In
hardened concrete the properties of the concrete are improved because of the more effective dispersion and
hydration of cement.
1). Accelerator
Accelerating admixtures helps reduce the effects of low temperatures by increasing the rate of cement
hydration. This aids in the concrete setting time and the development of early strength in the concrete.
3). Superplaticisers
Superplasticsers are high range water reducers. These can lead to a reduction in the water content of a given
concrete mix, but with workability characteristics of a normal slump mix still retained. This is an important
factor in cold weather because if the water/cement ratio of a concrete mix is reduced the resultant concrete
will have enhanced durability and strength characteristics.
There are several methods to carry out underwater concreting such as:
1. Tremie method
2. Pumping technique
5. Skip method
Once the pipe reaches the intended position the concrete is poured and break the seal. Then concrete flow
out of the pipe and creating a seal by accumulating around the lower end of the pipe, method is convenient
for pouring large amount of high flowable concrete. The concrete is moved to the hopper by either pumping,
belt conveyer or skips.
Tremie pipe, which upper end connected to a hopper and lower end continuously submerged in fresh
concrete, is used to place concrete at the exact location from a hopper at the surface.
The reason to immerse the tremie pipe lower end is to prevent intermixing of both concrete and water.
As soon as concreting began the pipe mouth should be submerged up to 1- 1.5 m into fresh concrete to
prevent water entering the pipe. The concrete flow rate is controlled by lowering and raising the pipe and
either decrease or increase in concrete discharge indicates the loss of the seal, therefore flow of concrete
should be continuous and carefully monitored. The bulging ( discharge in round form) flow is desired
because it displaced the concrete uniformly which leads to lesser laitance deformation and flatter slopes.
1. An aluminum alloy pipe should be avoided as its affected by concrete chemicals and therefore should
have an adequate diameter to prevent blockage because of aggregate size.
2. To avoid intermixing water and concrete in the pipe, a wooden plug of plat is used to seal the end of the
pipe. This prevents entering water in to the pipe and keeps it dry.
Assignment
Advantages: If the work is executed properly, this method has the following advantages:
2. Under water concrete dos not need compaction as concrete automatically gets compacted by the
hydrostatic pressure of water.
3. The concrete is of such a high consistency which normally does not require compaction.
Disadvantage:
1. Concreting by tremie method requires high water/cement ratio for obtaining high quality concrete.
2. Reduces the strength of concrete.
N.B
But now, with the use of some plasticizer a concrete with as low w/c ratio as 0.3 or even less can be placed
by tremie method
The second type of valve is used to pour concrete at a depth of 52m without immersing end of the pipe. The
function of the valves is to permit, restrict, stop the discharge of concrete and this method is the useful
technique.
The Skip technique of underwater concreting is suitable for cases where a large mass of concrete
is required for stabilizing foundations and small amount of concrete is needed for different
locations. Shows opened and closed skips.
To prevent trapping water and air, concreting is beings from the bottom. That is why it is
necessary to position the tubes in the forms before placing the aggregate. Concrete strength of
relatively high percent 70 - 100 % can be obtained in this technique.
A caisson is a watertight retaining structure used on the foundations of a bridge pier, for the
construction of a concrete dam or for the repair of ships.
Caissons are constructed in such a way that the water can be pumped out, keeping the work
environment dry.
1.box caisson
A box caisson is a prefabricated concrete box (with sides and a bottom); it is set down on prepared
bases. Once in place, it is filled with concrete to become part of the permanent works, such as the
foundation for a bridge pier. Hollow concrete structures are usually less dense than water so a box
caisson must be ballasted or anchored to keep it from floating until it can be filled with concrete.
2.open caisson
An open caisson is similar to a box caisson, except that it does not have a bottom face. It is suitable for
use in soft clays (e.g. in some river-beds), but not for where there may be large obstructions in the
ground. An open caisson that is used in soft grounds or high water tables, where open trench
excavations are impractical, can also be used to install deep manholes, pump stations.A caisson is sunk
by self-weight, concrete or water ballast placed on top, or by hydraulic jacks. The leading edge (or
cutting shoe) of the caisson is sloped out at a sharp angle to aid sinking in a vertical manner; it is usually
made of steel. The shoe is generally wider than the caisson to reduce friction.An open caisson may fill
with water during sinking. The material is excavated by clamshell excavator bucket on crane.
3.pneumatic caisson
A pneumatic (compressed-air) caisson has the advantage of providing dry working conditions, which is
better for placing concrete. It is also well suited for foundations for which other methods might cause
settlement of adjacent structures.
4.monolith caisson.
A monolithic caisson (or just simply a monolith) is larger than the other types of caisson, but similar to
open caissons. Such caissons are often found in quay walls, where resistance to impact from ships is
required.
1.Tremie method
2.Pumping technique
5.Skip method
The underwater concreting techniques designed mostly to prevent cement washout. These methods did
not obtain the full purpose of avoiding cement wash out at early stages of using under water concreting
apart from cases where large masses of concreting were employed.