4) Work Method Statement Upper Floor Beam & Slab
4) Work Method Statement Upper Floor Beam & Slab
4) Work Method Statement Upper Floor Beam & Slab
PROJECT NAME
1. Setting out Transfers the level to every column surfaces from the TBM.
Site supervisor make sure that the level of each beam is placing to the correct level according to the construction drawing.
2. Installing Formwork Installing all of the formwork with support by timber poles or scaffolding in proper strutting.
Site supervisors make sure the formworks of each beam edge of the slab and drops are installed according to
gridline position and level according to the construction drawing.
Site supervisors to ensure that the formwork shall be sufficiently rigid to maintain the forms in the correct position, shape
and dimension.
Site supervisor to check the vertically of formwork by using spirit level.
Site supervisor to ensure the formwork strutting and bracing are adequate.
Internal surface of the formwork to be coated with non-stained from oil that shall not affect the plastering or pointing bonding at
the later stage.
3. Installing Rebar Site supervisor check the Mill certificate from the supplier during the material delivery to site.
Go through Reinforced Concrete Inspection Form Checklist to ensure compliance with QA/QC requirement.
Site supervisor to ensure the rebar are be free from dirt and rust.
14
COMPANY NAME Safe Work Method Statement
PROJECT NAME
4. Concreting Go through Reinforced Concrete Inspection Form Checklist to ensure it compliance with QA/QC requirement.
Ready mixed concrete grade 25 shall be used to the specification which is approved by Consultant Engineer.
Concreting which done by hoisting method is using 25 tons mobile crane and concrete chute.
Concreting which done by pumping method is using the mobile pump truck.
Site supervisor to ensure that concrete slump is in compliance approved Mix design.
Poker and vibrators to be carry by skilled concretor to ensure proper compaction. ( 2 in use and 2 standby with size 50mm)
Site supervisor to check construction joint are at one third of the beam length.
Site supervisor ensure the concrete floor surface is roughening by broom brush.
5. Normal Curing Site supervisor to ensure the exposed surface should be cured after 8 hours using water.
Dismantling of formwork shall be carried out as per Table 11 or obtained approval from the consultant Engineer
7. Dismantling of Formwork
Site supervisor to check any cracks or honeycombs of the concrete. If any then apply for approval of method rectification.
15