Professional Documents
Culture Documents
Spine Concrete-Type A Works-SoW - Rev 7.0
Spine Concrete-Type A Works-SoW - Rev 7.0
(Employer’s Design)
Scope of Work
10-100000-0000100854-BEC-CON-SOW-000007
Rev. 07.00
November 2022
Document history
NEOM Projects
03.00 NEOM Review 18-Sep-22
Review
Job Title Design Project Construction Director Formation Senior Manager Deputy Commercial
Manager Director
Job Title Construction Director, SPINE Engineering Director, SPINE Executive Director, SPINE
3.1. Overview.......................................................................................................................................... 8
3.2. Key Activities ................................................................................................................................... 9
3.3. Interfaces with Authorities ............................................................................................................. 11
3.4. Interfaces with Other Contractors ................................................................................................. 11
3.5. Interfaces with Third-Parties.......................................................................................................... 12
3.6. Exclusions ..................................................................................................................................... 12
List of Figures
Figure 1: Spine Concrete – Type A works Overview showing indicative contract Lot boundaries. .................. 5
List of Tables
Table 1: Table of Abbreviations and Definitions................................................................................................ 6
Table 2: Spine Concrete – Type A Works Lots ................................................................................................. 8
Table 3: Dewatering Equipment Overview ...................................................................................................... 14
Table 3: Construction Office Requirements .................................................................................................... 16
Table 4: Wadi Locations .................................................................................................................................. 19
Table 5: Precast Concrete Supply Yards ........................................................................................................ 22
1.1. Purpose
This Scope of Works (SoW) document describes the scope of the Contractor’s obligations in carrying out the
Works for Spine structural concrete cut and cover tunnels, stations, lineside facilities, and associated works.
BP Batching Plant
Wadi Riverbed
Zippering Plan A matrix showing the key personnel and points of contact, from the Employer, Contractor and
Sub-Contractors.
3.1. Overview
This scope of works is for the installation of structural concrete for the Spine rail system, comprising cut and
cover rail tunnels and stations across up to three rail systems. In addition to the concrete works, the scope
includes earthworks, roadworks, utilities work, wadi diversions, de-watering systems, earthing and bonding,
waterproofing and other activities described herein. Initial Site preparation works will have been undertaken
by Other Contractors, prior to commencement.
The below table provides key information about each Lot, identified as Lot A1 through to Lot A10.
Coastal Area
3.6. Exclusions
The following activities are excluded from the Contractor’s scope of work:
• Construction of access roads from the nearest existing arterial route to the Site boundary, shown as
existing in Schedule 3
• Permanent MEP installations, permanent fire protection systems, permanent ventilation systems, rail
systems and architectural fit out for tunnels and stations
• Design and fabrication of precast elements supplied by the Employer
• Repair of damage to precast elements caused by Other Contractors
• Replacement of precast elements required due to damage by Other Contractors
• Landscaping, installation of irrigation systems and installation of architectural hardscapes.
2 IT dedicated Server Room for 1 x 42 U Network cabinet of 800 x 1000 mm in the Server room with 2 air
EPM and NEOM conditions machines 2 ton, with light on the front and back
Network Cabinet 2 x PDU of UK Type 12-way outlet to connect UPS and direct power. 1 x
PDU should connect to UPS and 1 x PDU should connect to direct power
Contractor to supply UPS of capacity 20 KVA utilization with minimum 1-
hour backup and connect to main power.
Single phase 16 Amp power and appropriate panels for electrical and
UPS in comm room
Fire detection and suppression systems
3 Wireless Internet Connection Enough to cover all Office, Wireless heat map, with dBm value set as -70
dBm for data and snr should be 20 dBm or more
5 Plotter 1× A0 Plotter
6 Work Meeting Offices 4×80 inch 1080 p on moveable stand, Miracast enabled.
(3 of 6 m x 8 m) USB Speaker and Microphone for use with laptops. One shall be
(1 of 8 m x 8 m) executive office.
9 Office IT hardware per 2 data and 2 power sockets per every workstation
workstation CAT6A shielded twisted pair cabling with termination of patch panels inside
Network Racks
A1 5+500 183
A1 9+500 106
A1 13+500 258
A1 16+500 136
A2 19+500 190
A2 27+500 127
A2 28+500 108
A2 29+500 90
A4 72+500 913
A4 82+500 903
A5 88+000 1,554
A5 90+500 978
A5 92+500 523
A5 96+500 433
A5 102+000 1,503
A1 C-PCY-1
A2 CD-PCY-1
A3 C-PCY-1
A4 CD-PCY-4
A5 CD-PCY-2
A6 CD-PCY-2
A7 UPV-PCY-1
A8 UPV-PCY-1
A9 UPV-PCY-1
A10 CD-PCY-4
All other available Logistics Support Areas are shown within Schedule 3 and shall be available to the
Contractor in accordance with the above guidance.
5. Permits
The Contractor shall obtain all Permits required for the Works not provided by the Employer, from the
applicable stakeholders, organisations, third parties, and Authorities necessary to execute the Works.
The Contractor shall be aware that the requirements and timescales for obtaining Permits are determined by
the relevant awarding body and may vary. The Contractor shall determine the requirements and time scales
necessary for obtaining each Permit and include these durations in the Baseline Programme.
The Contractor shall plan the Works, considering the required timeframe, and shall develop and implement
necessary contingency plans to mitigate any associated delays that could impact the Contractor’s ability to
perform the Works in accordance with the Baseline Programme, or Current Programme as applicable.
If any Authority, or other applicable stakeholder require any aspect of the submission undertaken by the
Contractor to be verified by an independent party, acceptable to them for issuing the required Permit, such
services shall be obtained by the Contractor, as part of the Works.
As stated above all Permits are Contractor’s Permits unless otherwise expressly stated.
6. Logistics
6.1. Temporary Facilities Plan
The Contractor shall submit for Employer’s Representative acceptance a Temporary Facility Plan (TFP)
complying with 00-000000-0000000000-NEO-CON-EMR-000006_00 Temporary Facilities & Controls in
Schedule 4 Employer’s Requirements. The TFP shall detail all temporary offices and welfare facilities and
utilities to be installed by the Contractor.
The Contractor shall establish its facilities within the areas defined within the Site. If additional working room
is required, the Contractor shall apply in writing to the Employer’s Representative for additional areas. The
Employer is under no obligation to grant such additional space.
DOCUMENT END.