Bridges - Progress - 03.04 - 09.04

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

Volume of planned

No. Bridge Position Operation


works total
1 M1 BRIDGE km 45+208 Piles 88
2 M1 BRIDGE km 45+208 Foundations 12
3 M1 BRIDGE km 45+208 Middle piers 12
4 M4 BRIDGE km 50+816 Pedestrian walkways 4
5 M5 OVERPASS km 51+438 transverse girders 4
6 M5 OVERPASS km 51+438 Bridge deck 1
7 M6 OVERPASS km 54+014 Middle Piers 2
8 M6 OVERPASS km 54+014 Precast girders 18
9 M6 OVERPASS km 54+014 Bearing beams 4
10 M7 OVERPASS km 56+354 Pedestrian walkways 2
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
32
33
Volume of planned works in Volume of executed production from
April 3rd of April to 30th of April
20 5
3
2
2
4
1
1
1 1
2
2
Volume of executed production from 3rd of Description of executed production from 3rd of April to
April to 9th of April 9th of April
5 Concreted 5 piles.

1 Concreted 1 precast girder.