Volume of planned

No. Bridge Position Operation


works total
1 M1 BRIDGE km 45+208 Precast girders 144
2 M1 BRIDGE km 45+208 Piles 88
3 M1 BRIDGE km 45+208 Foundations 12
4 M1 BRIDGE km 45+208 Piers 12
5 M3 BRIDGE km 48+951 Foundations 8
6 M3 BRIDGE km 48+951 Piers 4
7 M3 BRIDGE km 48+951 Abutments 4
8 M4 BRIDGE km 50+816 Foundations 4
9 M4 BRIDGE km 50+816 Abutments 4
10 M5 OVERPASS km 51+438 Piers 4
11 M5 OVERPASS km 51+438 Bearing beams 4
12 M5 OVERPASS km 51+438 Precast girders 21
13 M7 OVERPASS km 56+354 Foundations 4
14 M7 OVERPASS km 56+354 Piers 4
15 M7 OVERPASS km 56+354 Bearing beams 4
16 M7 OVERPASS km 56+354 Precast girders 18
17 M8 BRIDGE km 56+773 Abutments 4
18 M9 OVERPASS km 58+170 Bearing beams 2
19 M9 OVERPASS km 58+170 Abutments 2
20 M9 OVERPASS km 58+170 Precast girders 24
21 M11 OVERPASS km 59+967 Precast girders 21
22 M13 BRIDGE km 62+350 Transition slabs 4
23 M14 OVERPAS km 62+938 Precast girders 18
24 M15 BRIDGE km63+700 Transition slabs 4

36
37
38
39
40
41
42
43
44
45
46
47
Volume of planned works in Volume of executed production in
Work done in september
October October
46 36 12
8 14 4
2 0 0
2 0 0
4 0 3
4 0 1.33
1 0 0
2 2 0
1 0 0
3 1 2.5
0 0 0
7 0 0
4 0 1
4 0 0.67
2 0 0
12 0 0
2 0 0
2 0 2
1 1 0
8 0 0
8 13 6
4 0 4
1 17 1
4 0 0
Volume of executed production from Description of executed production from 3th to 9th
3th to 9th of October of October
12 Concreted 12 girders.
4 Concreted 4 piles.
0
0
3 Concreted 3 Foundations.
1.33 Concreted 4/12 piers.
0
0
0
2.5 Concreted piers s1 and s4, and ll phase s2.
0
0
1 concreted 1 foundation.
0.67 Concreted 2/3 piers in axis s1.
0
0
0
2 Concreted 2 bearing beam.
0
0
6 Concreted 6 precast girders.
4 Concreted 4 transition slabs.
1 Concreted 1 precast girders.
0