Professional Documents
Culture Documents
Disallowed Costs - Guidance and Considerations
Disallowed Costs - Guidance and Considerations
Disallowed Costs - Guidance and Considerations
• Set clear explanations and emphasis the rationale behind the Disallowed Cost; and,
• Minimising the disputes that may arise, encouraging both parties to utilise its time
efficiently that enhances the productivity of all parties involved.
Here are the situations, outlined in the Contract, in which the Client is entitled to Disallow the
Direct Cost incurred by the Contractor:
1. Costs that the Contractor cannot prove without proper records or justification. In that
regard, the Contractor should maintain detailed site records to demonstrate incurred
costs – for example – time sheets and subcontractors’ invoices.
2. Costs incurred because Contractor did not follow a procurement procedure. The
Contractor must familiarise itself of the procurement procedures, procurement
strategies and follow the construction programs.
3. Costs incurred due to the Contractor does not give an Early Warning Notice as soon
as become aware of an event that should be within few days and not few months.
4. When the Contractor pays a subcontractor or supplier for something that is not
stipulated in its Contract with the Contractor.
5. Costs of Personnel and resources which are recovered by the Contractor under the
Management Services Work Order.
6. Costs of plant or materials that were not used for the project.
7. Costs of preparing for an adjudication.
Page 1 of 4
8. Costs for rectifying defects after Completion and the cost of correcting defects caused
by the Contractor not complying with the Contract; and
9. Clause X22.2(4) - The cost of any work that is not included in the accepted forecast
(by SW PM) is treated as a Disallowed Cost.
WHAT TO DO
The correct approach for assessing Disallowed Cost is for the Project Manager to:
The claim should be adequately particularised by the Project Manager and notified to the
Contractor through the payment process.
Page 2 of 4
D. Key Considerations
Page 3 of 4
E. Disallowed Cost vs Breach of Warranty
Disallowed Costs
When using a target cost approach under ECC option C or D, the basic principle is that a
target cost is agreed, and the Contractor is reimbursed for costs spent undertaking the work
throughout the course of the project. Payments to the Contractor are based on their
accounts and records, which the project manager must has access to inspect at any time.
Disallowed Costs steps away from the general principle – it is a cost that the Client will not
reimburse the Contractor for because the Contractor incurred the costs under one or more
of the circumstances stated in Clause 11.2(60) ECC option C.
For example, in EEC Option C's clause 20.5, it is stipulated that the Contractor is obligated
to supply materials and construct the works according to "Good Industry Standards." These
standards encompass practices, methods, and procedures in alignment with Australian
laws and regulations, along with the level of skill and care that one would reasonably expect
from a skilled and experienced Contractor.
Essentially, this means that the Contractor is inherently expected to adhere to commonly
accepted industry practices for (but not limited to) safety, durability, and quality, including
using appropriate materials, complying with building codes, and ensuring the structural
integrity of the project. Under Clause 40.3 in EEC Option C, if the Project Manager instructs
the Contractor to rectify a failure to meet quality standards, the Contractor cannot claim
costs for correcting these failures.
Page 4 of 4