SN AKMIDA HOLDING SDN BHD

PROJEK MASS RAPID TRANSIT LALUAN 2:


SUNGAI BULOH – SERDANG – PUTRAJAYA (SSP)

METHOD STATEMENT
(S208) UNDERGROUND HDPE PN10,
CORRUGATED & UPVC PIPE INSTALLATION
WORKS

Reference No. : SSP-WCTB-STP4-OVPR-MST-00014


Revision : 00

Date Issued :

Prepared by Reviewed by Approved by

Muhammad Saiful
Name: Anuar Bin Ruslan
Name: Name:
Position: E&M Engineer Position: Position:

WCT BERHAD Page 1 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

AMENDMENT HISTORY

REVISION NO. ISSUE DATE DETAILS OF AMENDMENT

00 30/11/2017 First Issue

WCT BERHAD Page 2 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

TABLE OF CONTENTS PAGE

1.0 SCOPE OF WORK 2


1.1 General Description 2
1.2 Reference 2
1.3 Materials 3
1.4 Plant and Equipment 4
1.5 Manpower 5
1.6 Construction Procedures 7

2.0 SAFETY AND HEALTH 17


2.1 Job Safety And Health Analysis (JSA) 17
2.2 Information to Personnel 18
2.3 Emergency Arrangements 18
2.4 Permit to Work 18

3.0 ENVIRONMENTAL ISSUES 18


3.1 Environmental Aspects, Impacts And Control Measures 19

4.0 QUALITY ASSURANCE & QUALITY CONTROL 20


4.1 Contractual Requirements 20
4.2 Quality Control 20
4.3 Follow Up And Evaluation 20

5.0 APPENDICES 21
5.1 Work Sequence 22
5.2 Job Safety And Health Analysis 23
5.3 Environmental Operation Control Log 24
5.4 Inspection and Test Plan 25
5.5 Quality Control Inspection Checklist 26

WCT BERHAD Page 3 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

1.0 SCOPE OF WORK

1.1 General Description


This work method statement describes the methodology and sequences that will be
carried out for the installation of underground ducting installation works which using
HDPE pipe for electrical services and UPVC pipe for telephone services.
The scope of this method statement shall include the installation of underground
ducting and cables for Project Mass Rapid Transit Laluan 2: Sungai Buloh – Serdang –
Putrajaya (Package S208) from Equine Park to Taman Putra Permai.

1.2 Reference

1.2.1 This method statement for underground cable installation used


several related documents as references:

No Description Doc. Ref. No.


.
1 Project Execution Plan SSP-WCTB-STP4-OVPR-PLN-0011
2 Project Quality Plan SSP-WCTB-STP4-OVPR-PLN-0001
3 Waste Management Plan SSP-WCTB-STP4-OVPR-PLN-0013
4 Safety and Health Plan SSP-WCTB-STP4-OVPR-PLN-0002
5 Risk Management Plan SSP-WCTB-STP4-OVPR-PLN-0010
6 Emergency Response Plan SSP-WCTB-STP4-OVPR-PLN-0003
7 Traffic Management Plan SSP-WCTB-STP4-OVPR-PLN-0012
8 Survey Quality Plan SSP-WCTB-STP4-OVPR-PLN-00013
General Specification for Civil and SSP-PDP2-GENE-OVPR-SPC-000001 (Section
9
Structural Works G6 – Damage and Interference)
SSP-PDP2-STP4-SKSA-SPC-000014 (SSP
Particular Specification for Civil Engineering Appendix K & Clause P8.3 – Special
10
Works Requirement for Protection of Utilities and
Services)
11 Material an Workmanship Specification SSP-MRTC-GENE-OVPR-SPC-03000
Cable Ducting and Manhole Standard SSP-W-SMHB-GENE-OVPR-CNS-STS-243101
12
Details SSP-W-SMHB-GENE-OVPR-CNS-STS-243102
IFC Drawing of Overall Cable Routing - SSP-W-SMHB-STP4-KULE-ELE-LAP-315130
13 Kuchai Lama Station

IFC Drawing of Overall Cable Routing - SSP-W-SMHB-STP4-TNEE-ELE-LAP-325130


14 Taman Naga Emas Station

IFC Drawing Electrical Services Standard SSP-W-OOSB-GENE-OVPR-ELE-STS-003626


15
Details
WCT BERHAD Page 4 of 20
SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

IFC Drawing of Cable Ducting and Manhole SSP-W-SMHB-GENE-OVPR-CNS-STS-243101


16
Standard Details SSP-W-SMHB-GENE-OVPR-CNS-STS-243102

1.3 Materials
No Item MSA No.
1) 100mm dia. UPVC duct (telephone cable) Will be included once approved
2) 100mm dia. HUPVC duct (telephone cable) Will be included once approved
3) 150mm dia. HDPE duct PN10 Will be included once approved
7) 150mm dia. HDPE Corrugated Double Wall Will be included once approved
8) Chequared plate Will be included once approved
10) Concrete grade 20 Will be included once approved
1.4 Plant and Equipment

1.4.1 Plants
No Equipment Purpose Unit
1 3 ton/1 ton For transporting of materials 1
2 Backhoe For excavation 1

1.4.2 Equipment and Tools


No Item Purpose Unit
2 Site Signage For work at site to warn the public of site work 1 Set
ongoing
3 Steel Plate For closing area work unable to 1 Set
complete at road/open road/open area
4 Flood Light For Night Work 1 Set
5 Ladder Site Access to Trenches 1
6 Barrier/Cone For site protection or working space 1 Set
demarcation
7 Hand Digging Tools For trenching, spreading and levelling 1
8 Shoring For trench protection 1
9 Portable Pump For dewatering 1
10 Plate Compactor For compacting 1
11 Genset For night work 1
12 Water Pump For pumping water out from trench 1

WCT BERHAD Page 5 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

1.5 Manpower

No Position Scope of work


Nos.
.
Responsible for overall commercial, contractual
1 Project Manager and technical performances associated with 1
specific projects
Planning, Coordinating, scheduling and
2 Construction Manager 1
monitoring of site activities
Responsible for overall operation including
3 Project Engineer 1
liaison with service provider
Planning, Coordinating, scheduling and
4 Site Supervisor 2
monitoring of site activities
To control and ensure the Safety, Health and
5 SHE officer 1
Environmental is adhere at site
Supervising site construction activities, Making
6 SHE Supervisor toolbox meeting and prepare all relevant permit 1
before start work
Traffic Controller and To control ingress and egress of construction 1
7
Flagmen traffic at site Team
10 General worker Conduct general works at site 2
1
11 Backhoe Operator Operate backhoe machine.
Team
13 Site Surveyor Setting out alignment and levels 1
14 Chainman Assist surveyor 2

1.6 Construction Procedure

1.6.1 Construction Procedure for Pipe Installation by Open Cut Method

1.6.1.1 Preliminaries Work


a) All existing utilities affected by the construction within the working areas shall
be identified (in size & type) and marked out as required. The setting out of
utility alignment shall be done by competent surveyor.
b) Approved shop drawing and permit approval from relevant authority need to
be obtained prior to any physical work at site.
c) Proper traffic management and safety measure shall be arranged within
working areas to prevent mishap and minimize disturbance to road traffic.
d) If work is to be carried out at night, WPC has to ensure the light for night work
is enough, proper PPEs such as high visibility vest must be worn and traffic

WCT BERHAD Page 6 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

equipment shall be installed such as blinkers, cones, signage and with adequate
traffic management.
1.6.1.2 Survey and Setting Out
a) The underground ducting route or alignment shall be pegged out in accordance
with the approved drawing issued.
b) Confirmed alignment drawings have been approved. Detection and piloting
works will be carried out to ensure that there are no other services obstructed
at the confirmed alignment stated in the confirmed drawings.

1.6.1.3 Trench Excavation


a) Prior to trench excavation, the site shall be cleared from any obstruction. The
supervisor shall ensure that all obstruction within minimum 1 m of either side
of all duct to be laid are cleared.
b) Trench excavation for laying the new ducting shall be carried out with the use
of backhoe.
c) The run of duct trench opened up ahead of duct laying operation at any one
time shall not be more than 100m.
d) The trenches shall be excavated based on the depth indicated in the
construction drawings. The number of duct ways to be laid shall be observed
such that the depth and width of the trench required shall follow the duct
formation schedule as indicated in the construction drawings.
e) The excavated trench shall be level in order for the laying of duct to be smooth.
f) The side of the trench shall be cut vertically and where necessary, shall be
protected against caving in as per JSA recommendation.
g) The good excavated materials shall be stockpiled at least 1 meter away from
the trench and has to put cover on top of it if plan not to backfill on that day.
h) De-watering with water pump shall be applied when necessary due to high
ground water or ran run-off.
i) The surplus excavated materials, earth, rubbish and waste shall be disposed off
site to approved dumping site.

1.6.1.4 Laying of Ducts


a) Care shall be taken to make the bends of pipe or duct lines as easy as
practicable.
b) Adequate provision shall be made for cables entering and leaving ducts. Draw
wires shall be provided wherever appropriate.
c) Any ducts provided for this purpose shall be adequately bushed or radius to
prevent damage to the cables.
d) All cables run in open ducts or in ducts shared with other services, shall be
adequately secured to wall of the duct by type saddles or hangers.
WCT BERHAD Page 7 of 20
SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

e) For multiple circuits laid in a common trench, 50mm spacing shall be allowed
between the ducts. This is to create space between ducts for ducts to be
arranged and function smoothly.
f) Where layers of ducts to be laid over another in the same trench, form
structure and rebar is necessary to assemble and position the ducts. The ducts
shall break joint by approximately half the duct length in alternate lines,
horizontally and vertically.
g) For HDPE ducts, socket shall be used for the process of jointing. The edges of
ducts shall be cleaned. The socket as well as the duct ends shall be wiped clean
before inserting the socket for the two ducts to be joined.
h) Pipes shall be cut when necessary at right angle to the bore only. The inside
edges shall be filed and trimmed so that they will not cause damages to the
cables.
i) The duct shall be sealed to prevent the entry of water or vermin.

1.6.1.5 Concrete Encasement


a) HDPE corrugated pipe should be encased on concrete accordingly.
b) The method used to encase ducts in concrete will be carried out by pouring
concrete onto ductbank/form structure where each duct will be completely
encased by concrete as indicated in the drawings.
c) HDPE corrugated pipe may be bent gradually to avoid obstacles.
d) The depth of the concrete for encasement depends on number of duct layers
to be installed in one trench.
e) The depth of the concrete encasement is 800mm for 4 layers duct, 800mm for
3 layers duct and 600mm for 2 layers duct as per drawings.

Diagram 1 – Typical spacing between concrete and ducts for encasement


as per standard details.

f) Concrete of grade C25/30-20 as specified in the drawing shall be placed over


the ducts to fill the spaces between the ducts.

WCT BERHAD Page 8 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

g) Approximately 50mm spacing between above and bottom layer of ducts shall
be provided.
h) Repeat the above process for the subsequent layer of ducts.
1.6.1.6 Backfilling of Trenches
a) After concrete encasement of duct is done, backfill the excavated materials to
specified levels.
b) Care shall be taken such that backfilling operation does not disturb the
completed works.
c) The trench shall be backfilled with the excavated materials in 150mm layers in
the reverse order to which they were excavated. The remaining 300mm shall
be backfilled with good quality earth and rammed. Mechanical rammer shall be
used.

Suitable Fill

Sand Compacted in 150mm


Layers

Concrete grade C25/30-20

Diagram 2 - Backfill Layer as per Standard Details of Cable Ducting


d) When consolidation of granular material is completed, premixed asphalt shall
be spread evenly over the treated stone surface and rolled until complete
consolidation has been obtained.
e) Make good of site by clearing of unwanted debris and materials. Plant and
equipment shall be removed. Grass turf shall be reinstated where require.

WCT BERHAD Page 9 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

Cable Marker

Diagram 3– Cable marker to be installed for indication


of cable location underground

1.6.1.7 Despite the protection stated in the IFC drawing indication, the needs of service
protection needed be aware for all area effected during the work take in
commence. Most of the service protection is constructed under the provisional
area such as future road area, protection for area that too close to the pier and
etc. Generally the protection for the services and type of mechanism will be
varied but generally the services will be protect as per detail below:

a) Temporary Service Protection


I. Instead of permanent service protection designed for each and every
services, there is a few event where the services might get crossed due
other site progress, for example water pipe line where place on the
road shoulder found under the area where access of the site going to
be set up, a boring work happen just a distance away from the gas pipe
and etc.
II. There is a few material such as steel sheet with suitable thickness
(chequered plate), steel case, plywood and the list of protection used
can be varies and depend to the actual site condition. Chequered plate
will be used to place on top of the ground and at the access location
where found any services beneath it. The purpose as to prevent any
overpressure and avoiding ground settlement where could eventually
damaging the underground utilities.

2.0 SAFETY AND HEALTH


2.1 Job Safety And Health Analysis (JSA)
Job Safety & Health Analysis shall be carried out on the project site. Barriers and
safety awareness signs shall be established at location of works. The potential hazards
WCT BERHAD Page 10 of 20
SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

in a particular activity and the control measures implemented shall be briefed to the
workers during safety induction, tool box talk and JSA Briefing.

2.2 Information to Personnel


All personnel shall attend and completed KVMRT SHE Passport Scheme before being
allowed working at site.

2.3 Emergency Arrangements


The emergency situations which may occur are shown in the table Appendix 5.2 for
Job Safety & Health Analysis. The level of risk or severity of the accident dictates the
emergency level.

3.0 ENVIRONMENTAL ISSUES


Environment implementation and control at site shall be complied to General
Specification GS Section G11, Detailed Environmental Impact Assessment (DEIA)
Approval Condition, Environmental Management Plan (EMP), Erosion and
Sedimentation Control Plan (ESCP), Waste Management Plan (WMP), Flood Protection
Plan and Noise and Vibration Compliance Management Plan for MRT S204.

3.1 Environmental Aspects, Impacts And Control Measures


The significant environmental impacts associated with the underground HDPE and
UPVC pipe installation works have been identified and listed in the Appendix 5.3 of
the related method of statements.

3.1.1 Air Quality


i. Air quality control to be compiled with package EMP, DEIA, Approval
condition and GS G11.21.1. All construction machineries shall be in well
maintain and in good working condition to reduce emission of soot, smoke
and noise.
ii. Water truck shall constantly spray the water to minimize the dust especially
during hot weather if any transport operation going on.
iii. Vehicles washing facilities shall be provided at site exit. Public road must be
cleaned all the time and free from dirt and soil.
iv. Open burning is prohibited at site.

3.1.2 Noise and Vibration Control


i. Noise and vibration control to be complied with MRT S204 EMP, DEIA
Approval Condition and GS G11.21.6.
ii. Movement of heavy vehicles shall be restricted to daytime working hours
and minimized during night time. Construction work during night time shall
get the approval from PDP and local authorities.
iii. Noise generating equipment and machinery shall be inspected regularly
and maintained in good working condition. Noise and vibration emitting

WCT BERHAD Page 11 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

from equipment shall be placed away from sensitive receptor or replaced


with better equipment if necessary.

3.1.3 Water Quality


i. Water pollution control to be complied with MRT S204 ESCP, EMP, DEIA
Approval Condition and GS G11.21.2
ii. Surface run-off shall be treated prior to discharge and shall not exceed 50
mg/L for TSS and 250 NTU for turbidity. If the final silt discharged level
exceeds 50 mg/L or 250 NTU, the activities can be resumed upon
rectification for control measures are done.

3.1.4 Waste Management


i. All types of wastes shall be segregated, stored and disposed of in
accordance with package EMP, DEIA Approval Condition, Waste
Management Plan and GS G.11.21.4. Waste shall be disposed of at an
approved disposal site.
ii. Waste containers and storage areas shall be sufficient capacity to contain
all waste generated.
iii. Scheduled waste from maintenance works of machineries, vehicles and
tools shall be placed in designated areas at the site. Proper oil trays shall be
placed for oil/petroleum product to prevent oil spillage at ground.
Scheduled waste shall be collected and transferred to scheduled waste
storage area. The scheduled waste shall be disposed by license contractor
registered with DOE to approved dump site. Scheduled waste storage and
disposal shall follow EQ (Scheduled Waste) Regulation 2005 accordingly.

3.1.5 Housekeeping
Housekeeping is an essential part of safety for the daily routine. Housekeeping
would include the following items:
i. Maintain the access/egress to all working area.
ii. Store and stack all construction materials in safe and orderly manner.
iii. No littering around the site and provide sufficient waste bin.

WCT BERHAD Page 12 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

4.0 QUALITY ASSURANCE AND QUALITY CONTROL

4.1 Contractual Requirements


Shall be implemented in accordance with submitted comprehensive Project Quality
Plan Ref. No. SSP-WCTB-STP4-OVPR-PLN-0001.
The quality control measures undertaken and shall be included, but not limited to:
i. Implementation & compliance with ITP.
ii. Submission, Re-submission and approval of the required documents (as
defined on ITP).
iii. Effectiveness of internal inspection via inspection checklist.
iv. Confirmation & approval of the joint inspection via RFI online for both
work inspection & testing activities.
v. Completeness & compliance of relevant forms & checklist by all relevant
parties (e.g. Relevant supervising consultant).

4.2 Quality Control Procedures


Please refer to Appendix 5.4 Inspection and Test Plan.

4.3 Follow up and Evaluation


RFIs and respective Permit to Work shall be submitted prior execution of any
construction activities. In addition to this requirement weekly walk-about will be
conducted to measure, analyze progress of works and to propose improvement
measures.

WCT BERHAD Page 13 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

5.0 APPENDICES

WCT BERHAD Page 14 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

Appendix 5.1 : WORK SEQUENCE

Start

Ensure MST, Shop Drawing, Sample Board (if


any), etc. are approved

Coordination of work process

Material delivery to site

Fail
Inspection Rectification / Corrective action

Pass

Unloading

Shifting

Positioning

Trench Excavation

Pipe Laying

A B

WCT BERHAD Page 15 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

A B

Fail
Inspectio Rectification / Corrective action
n

Pass

Concrete
Encasement

Fail
Inspectio Rectification / Corrective action
n

Pass

Backfill

Testing &
Comissioning

Fail
Inspectio Rectification / Corrective action
n

Pass

Preparation of Operation &


Maintenance Manual and as
Built Drawing

Fail
Inspectio Rectification / Corrective action
n

Pass

Final Hand Over

WCT BERHAD Page 16 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

Appendix 5.2
JOB SAFETY AND HEALTH ANALYSIS

WCT BERHAD Page 17 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

Appendix 5.3
ENVIRONMENTAL OPERATION
CONTROL LOG

WCT BERHAD Page 18 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

Appendix 5.4
INSPECTION AND TEST PLAN

WCT BERHAD Page 19 of 20


SSP-WCTB-STP4-OVPR-MST-00014
UNDERGROUND HDPE PN10, CORRUGATED & UPVC PIPE INSTALLATION WORKS
Revision:
W00

Appendix 5.5
QUALITY CONTROL INSPECTION
CHECKLIST

WCT BERHAD Page 20 of 20


SSP-WCTB-STP4-OVPR-MST-00014