METHOD STATEMENT
Mohamad Shabree
Name Hashim
Position Quality Manager
Ghazali Abdul
Name Saiful Anuar Name Zuraimyzanizam Name
Latiff
Construction
Position M&E Engineer Position Position Project Director
Manager for M&E
AMENDMENT HISTORY
Table of Contents
1 SCOPE OF WORK......................................................................................................................... 4
1.1 GENERAL DESCRIPTION............................................................................................................. 4
1.2 REFERENCES............................................................................................................................ 4
1.3 MATERIALS............................................................................................................................... 7
1.4 PLANT AND EQUIPMENT............................................................................................................. 8
1.5 MANPOWER.............................................................................................................................. 9
1.6 WORK PROCEDURES............................................................................................................... 10
2.0 SAFETY AND HEALTH............................................................................................................ 27
2.1 JOB SAFETY AND HEALTH ANALYSIS......................................................................................... 27
2.2 INFORMATION TO PERSONNEL.................................................................................................. 27
2.3 EMERGENCY ARRANGEMENTS.................................................................................................. 28
2.4 LEGAL REQUIREMENT.............................................................................................................. 28
2.5 PERMIT REQUIREMENT............................................................................................................ 28
3.0 ENVIRONMENTAL ISSUES..................................................................................................... 30
3.1 IMPLEMENTATION AND MONITORING.......................................................................................... 30
3.2 ENVIRONMENTAL ASPECTS, IMPACTS & CONTROL MEASURES...................................................30
3.3 EROSION AND SEDIMENTATION CONTROL.................................................................................30
3.4 AIR QUALITY CONTROL............................................................................................................ 30
3.5 NOISE AND VIBRATION CONTROL............................................................................................. 31
3.6 WATER QUALITY..................................................................................................................... 31
3.7 WASTE MANAGEMENT............................................................................................................. 31
3.8 HOUSEKEEPING....................................................................................................................... 32
4.0 QUALITY ASSURANCE & QUALITY CONTROL....................................................................33
4.1 CONTRACTUAL REQUIREMENTS................................................................................................ 33
4.2 INSPECTION AND TESTING........................................................................................................ 33
4.3 FOLLOW UP AND EVALUATION.................................................................................................. 33
5.0 APPENDICES........................................................................................................................... 33
1 SCOPE OF WORK
1.1.1 This statement is to outline the installation of underground services and ducting
manhole at the Package S208. This statement also to ensure the work is carried
out in controlled and systematic manner. All respective parties shall confirm to the
specified requirements, emphasizing, on the aspects of meeting quality standard,
safe working environment and compliance of safety requirements as stipulated in
the Contract during project implementation.
1.1.2 Prior to start work, identify, analyse the site situation and condition.
1.2 References
SSP-PDP2-GENE-OVPR-SPC-00001,
General Specification for Civil
3.0 Section G9 - Safety & Health
Engineering Works
Section G11 - Environmental Management
SSP-MTDC-STP8-OVPR-PLN-00003
SSP-MTDC-STP8-OVPR-PLN-00007
SSP-MTDC-STP8-OVPR-PLN-00008
SSP-MTDC-STP8-OVPR-PLN-00009
SSP-MTDC-STP8-OVPR-PLN-00010
SSP-MTDC-STP8-OVPR-PLN-00011
SSP-MTDC-STP8-OVPR-PLN-00005
SSP-MTDC-STP8-OVPR-PLN-00006
SSP-MTDC-STP8-OVPR-PLN-00002
SSP-W-KCSB-STP8-EQPS-ELE-LAP-051251
IFC Drawings
22.0 EQUINE PARK STATION SSP-W-KCSB-STP8-EQPE-ELE-LAP-051501
SSP-W-KCSB-STP8-EQPE-ELE-LAP-051521
SSP-W-KCSB-STP8-TPPS-ELE-LAP-051221
SSP-W-KCSB-STP8-TPPS-ELE-LAP-051323
SSP-W-KCSB-STP8-TPPS-ELE-LAP-051039
IFC Drawing SSP-W-KCSB-STP8-TPPS-ELE-LAP-051040
23.0 TAMAN PUTRA PERMAI STATION
SSP-W-KCSB-STP8-TPPS-ELE-LAP-051041
SSP-W-KCSB-STP8-TPPS-ELE-LAP-051042
SSP-W-KCSB-STP8-TPPE-ELE-LAP-051521
SSP-W-KCSB-STP8-TPPE-ELE-LAP-051522
1.3 Materials
1.1.3 Underground services and ducting manhole installation consisting of the following
components for the purpose of completion and functional performance of the
installed systems: -
1.1.6.1 Excavation
1.1.6.2.7 During manual digging work using man power, a careful watch
should be kept for evidence of cables, and repeat checks made
with a locator to determine more precisely the position of any cable
is positively located only when it has been safely exposed, and
even then digging should still proceed with care because there may
be others services or utilities, particularly high voltage cables,
adjacent or lower down.
1.1.6.2.8 When digging run parallel to cables, the cable should be exposed
at appropriate intervals in the immediate vicinity.
1.1.6.2.9 The located services and utilities shall be recorded in the form.
a) When lifting manhole and pipes, make sure the lifting belt length
are long enough to prevent contact with the tongue and groove
area and are kept at appropriate lifting angles. Special precaution
shall be emphasized such that it does not damage the external
coating
b) The manhole lifting apparatus must meet or exceed safe working
load capacity with respect to the lifting points. All lifting points
should be use and the product should be handled with equal
“picking” force on all lifting points.
c) All lifting machine (mobile crane & etc.) must be inspected and
approved prior to lifting.
1.1.6.5 Handling and Installing Pipe Ducting for open trench method
a) HDPE PN10, HDPE Double Wall Corrugated Pipe, and uPVC pipes
are laid at a minimum depth of 600mm to 1500mm underground.
b) HDPE PN10 will be using electrofusion joint, where HDPE double
wall corrugated pipe and uPVC will be using coupler joint for the
installation works.
c) Sand of 25mm thickness is to be used as a bedding to backfill the
bottom layers of the trench before underground piping laid.
d) After laying first layer of pipes, concrete of 25mm thickness will be
filled on top of the first layer of pipes.
e) Second layer of pipe to be laid after the concreting is done. Once
second layer of pipes laid, earth soil of 25mm thickness will be
filled.
f) Finally, earth soil of 300mm thickness to be backfilled into the
trench fully with original earth soil to original level.
g) All stages of works need to be witnessed to ensure all works are up
to specification.
h) Any excavation works below 4 metres shall be using shoring
method for protection.
1.1.6.8.2 Then, put the milling cutter in the machine frame, adjusting the
pressure of the milling cutter and cutting two pipe ends. When
received continuous cutting, the cutting pressure will be reduce and
withdrawal the cuter in order to keep the smooth of the pipe end as
in Figure below.
1.1.6.8.3 When the welding plate keep the stable temperature, put in the
machine frame and welding the pipe, following the pipe size and
environment to adjust the welding time and pressure as in figure
below.
1.1.6.8.4 After finished welding, fusion the pipe at the first time, follow the
pipe size to adjust the pressure as in figure 8.
a) Manhole components are provided with joints formed within the wall
section.
b) It is to be sealed with water proof expandable foam duct sealant
with a minimum of 300mm insertion.
c) All duct shall be used up using approved fire& water seal after
mandrel test as stated in IFC IFC : SSP-W-KCSB-STP8-TPPE-
1.1.6.12 Backfill
All site personnel must complete and attended the KVMRT SHE Passport Scheme prior to
start work at site. Only personnel who have successfully completed the training for their role
will be allowed working on site.
All workers employed in the project site must have CIDB green card.
All new workers and staff to attend the Safety Training or Safety Induction Course Before
commencing works site and attendances shall be recorded in an induction list.
All site personnel shall wear proper Personnel Protective Equipment (PPE):
o Safety helmets, Safety vest, Safety boots, Water Boot, etc.
Monthly safety meetings shall be held with all the contractors related to the works.
All workers to attend the weekly toolbox meetings conducted by the safety officer held at site and
attendances shall be recorded.
Hacking work shall be provided with proper/suitable PPE to the workers.
The organization chart, list of emergency contact person and relevant authorities with their
contact numbers shall be posted on the Notice Board. These lists can be obtained from the
Emergency Response Plan.
Manager SC
Safety officer, Construction Notify PDP/
5 Hacking Works
Manager SC
Safety officer, Construction Notify PDP/
6 Permit for Lifting
Manager SC
The control for erosion and sedimentation shall be complied with the Package ESCP, DEIA
Approval condition and GS11.21.3
Site clearing works shall be limited to construction area only. Earth stockpile area shall be
located away from the surface runoff and protective with sheeting
Temporary erosion protection for exposed slopes under construction shall be provided until such
time when the permanent measures are provided. Temporary earth slopes that are to be
exposed shall be covered with organic erosion control blanket (ECB)
Sediment control measure such as check dams/temporary earth drain, silt fences, turfing, silt
traps, wheel washing facility and sediment ponds shall be constructed prior to commencement of
work and shall be maintained.
Air quality control to be complied with Package ESCP, Package EMP, DEIA Approval Condition
and GS 11.21.1
Site clearance and earthwork shall be carried out in stages to minimize the exposed soil.
Vehicle washing facilities shall be provided at site exit. Public roads shall be kept clear of soil and
cleaned
Water truck shall constantly spray the water to minimize the dust especially during hot weather if
any transport operation going on.
Traffic control such as speed limit and traffic volume restrictions to be implemented especially at
sensitive areas
Open burning is prohibited at site
Noise and vibration control to be complied with Package ESCP, Package EMP, DEIA Approval
Condition and GS 11.21.6
Movement of heavy vehicles shall be restricted to daytime working hours 8am to 7pm and
minimized during night time, weekends and public holidays. Construction work during night shall
get approval from PDP and local authorities.
Overall noise levels arising from the movement of heavy vehicles shall be controlled by using
routes that will cause minimum disturbance in the vicinity of the site.
Noise generating equipment and machinery shall be inspected regularly and maintained in good
working condition. Noise and vibration emitting from equipment shall be placed away from
sensitive receptors.
All noise generating equipment and machinery shall be shut down when not in used
Noise level nearby sensitive receptor and human settlement shall be controlled within the limit as
stated below as referred to DEIA approval condition No. 21:
Water pollution control to be complied with Package ESCP, Package EMP, DEIA Approval
Condition and GS 11.21.2
Surface run-off shall be treated prior discharged and shall not exceeds 50mg/L for TSS and 250
NTU for turbidity
The earthworks activity shall cease if the final silt discharge level exceeds 250 NTU. The
activities can be resumed upon rectification for control measures are done.
All type of waste shall be segregated, stored and disposed of in accordance with Package EMP,
DEIA Approval Condition, Waste management Plan and GS G11.21.4
Spoil, surplus soil, hacked pavement, and demolished concrete walkway will be removed from site
regularly.
Spoil (from bore piled drilling activities) shall be stockpiled, filtered and treated before being
removed at an approved disposal site.
Waste containers and storage area shall be sufficient capacity to contain all waste generated
Waste shall be disposed of at an approved disposal site.
The approved landfill for domestic waste (municipal waste) is at Tanjung Dua Belas Sanitary
Landfill, Kuala Langat, Sepang while for inert waste is at Dengkil Inert Waste Landfill Lot 557,
Timah Dengkil Langat, Mukim Dengkil, Sepang.
The approved dumping area for USM material is at Puchong Permai.
Scheduled waste from maintenance works of machineries, vehicles and tools shall be properly
stored and disposed by DOE licensed contractors at approved facilities. Proper oil tray or drum
shall be placed to prevent the oil spillage all over the place. Subsequent waste shall be collected
and transfer to area as assigned.
Biomass waste and unsuitable material shall be disposed off at an approved disposal site
3.8 Housekeeping
Housekeeping is an essential part of environmental team for the daily routine. Housekeeping
shall include the following terms:
Maintain the access/egress road to all working area.
Store and stack all construction materials in safe and orderly manner.
Park the machineries in orderly manner.
No littering around the site.
5.0 APPENDICES
Appendix 5.1 – Construction Sequence
Appendix 5.2 – Job Safety & Health Analysis
Appendix 5.3 – Environmental Operational Control Log
Appendix 5.4 – Inspection and Test Plan
Appendix 5.5 – Quality Control Inspection Forms and Checklist
Appendix 5.1
Construction Sequence
Appendix 5.2
Job Safety and Health Analysis
Appendix 5.3
Environmental Operation Control Log
Appendix 5.4
Inspection and Test Plan
Appendix 5.5
Quality Control Inspection Forms &
Checklist